ESTABLISHMENT OF WASTE
MANAGEMENT AT PEOPLES MEDICAL
COLLEGE HOSPITAL NAWABSHAH,
SHAHEED BENAZIR ABAD
2. Location
Name of District/Province PEOPLES MEDICAL COLLEGE HOSPITAL
Indicate project location NAWABSHAH SHAHEED BENAZIR ABAD
a) Plan provision
Total bloc provision Amount already Amount proposed for/ this Balance available
committed project
--
2
5. Project objectives and its relationship
with sectoral objectives:
The objectives of the sector / sub sector as To examine & determine detailed and comprehensive
indicated in the medium term / five year plan Hospital Waste Management Program including
be reproduced Indicate objectives of the collection storage, segregation, transportation and
project and develop a linkage between the disposal by utilizing advance and environmental
proposed project and sectoral objectives. friendly technology.
3
6. Description, justification and technical DESCRIPTION OF THE PROJECT
Parameters :
Procurement of new high tech equipment and the
Describe the project and indicate replacement of the old one is imperative for quality
Existing facilities in the area and justify management of hospital infectious waste. Induction of
The establishment of the project.
trained, operational and maintenance staff for efficient
and competent use of equipment also cannot be over
looked.
JUSTIFICATION
4
environmental (Health) safety standards resulting in
professional handicaps. Hence new high tech
equipment is mandatory for safe collection and
disposal of the health waste.
There is acute shortage of staff for efficient
collection and preparation of hospital waste. Further,
mere procurement & installation of high tech
equipment will not suffice without properly trained
staff. Dedicated hospital waste management staff is
required for proper collection /segregation/disposal of
hospital waste & operation / maintenance of the
equipment’s.
5
Cost estimates:
6
10. Financial Plan and mode of financing:
Health Department, Government of Sindh
Sources of financing
2 Cost of Equipment (Oxygen Rs. 49.2 Million N/A Rs. 49.2 Million
Generation Plant.
Total Capital
Total Revenue Rs. 49.2 Million
Grand Total Rs. 49.2 Million
b) In case of revised Projects,
Provide:
7
Justification for revision N/A
of PC-I and variation in
scope of the project if
applicable.
7. Annual operating and Total recurring cost for five years after completion of project is
maintenance cost after details at annexure-
completion of the Project
Operational and maintenance cost of the hospital after completion
of the project
11. Project benefits and
analysis:
----------------
i) Financial To eliminate the need for hazardous storage.
ii) Social benefits with Hospitals solely independent with continuous duty/24 hour-
indicators per-day operation
By reducing moving parts to an absolute minimum and by
applying high quality components, maintenance costs will
stay at low levels during the entire generator’s lifetime.
12. Implementation schedule: Completion period of the scheme is designed for one year it shall
Indicate starting and be completed in all respects by the end of financial year 2019-
completion date 2020.
of the project Implementation plan is depicted below:
8
IMPLEMENTATION PLAN:
Time line
S.N Budgeting
# Scope of Work July-Sep Oct-Dec Jan-Mar April-Jun Requirement
2019-20 2019-20 2020-21 2020-21
CIVIL WORKS:
Advertisement
Tender Receipt
Bids Evaluation
N/A.
1 Work order
Payment to Contractor
REVENUE COMPONENT:
Advertisement
Tender Receipt
Bids Evaluation
2 Order
Purchase of Equipment
Payment to Contractor
9
If required so far, skill of existing manpower
shall be utilized till the SNE is sanctioned by the
Manpower requirements during execution finance Department.
and operation of the project be provided
by skills / profession.
10