CS605- Software Engineering II Complete Final Term Paper 2008


FINALTERM EXAMINATION
Fall 2008
CS605- Software EngineeringII (Session - 1)
Ref No:
Time: 120 min
Question No: 1 ( Marks: 1 ) - Please choose one
The purpose of earned value analysis is to
► determine how to compensate developers based on their productivity

► provide a quantitative means of assessing software project progress

► provide a qualitative means of assessing software project progress

► set the price point for a software product based on development effort

Question No: 2 ( Marks: 1 ) - Please choose one


The RMMM plan assists the project team in developing strategy for dealing with risk. In
this context, an effective strategy must consider:
► Risk avoidance

► Risk monitoring

► Risk management and contingency plan

► All of the given choices

Question No: 3 ( Marks: 1 ) - Please choose one


The component-based development model is
► only appropriate for computer hardware design.

► not able to support the development of reusable components.

► dependent on object technologies for support.

► not cost effective by known quantifiable software metrics.

Question No: 4 ( Marks: 1 ) - Please choose one


In ___________ representation of CMMI model, consideration is given to improve all the
defined processes areas.
► Staged

WWW.VIRTUALINSPIRE.COM
Prepared byDil-E-Nadan
Campus[psmd01]Samundri
miansufyan106@gmail.com

► Continuous

Question No: 5 ( Marks: 1 ) - Please choose one


If you know the relationship between the use cases, classes, GUIs, Test cases and other
artifacts then we can say that requirements are traceable in that project.

►True

►False

Question No: 6 ( Marks: 1 ) - Please choose one


There could be multiple GUIs to satisfy one requirement

►True

►False

Question No: 7 ( Marks: 1 ) - Please choose one


Check in and Check out is actually one and the same process with two different names

►True
►False

Question No: 8 ( Marks: 1 ) - Please choose one


If a new version of a product is released by fixing the bugs in the previous release then it is
termed as _________________
►Product Update

►Product Upgrade

►Defect Removal

►Product Performance

Question No: 9 ( Marks: 1 ) - Please choose one


When an Item is baselined, it becomes frozen, here frozen means, that the item can be
changed only by creating an old version

►

WWW.VIRTUALINSPIRE.COM
Prepared byDil-E-Nadan
Campus[psmd01]Samundri
miansufyan106@gmail.com

►

Question No: 10 ( Marks: 1 ) - Please choose one


Configuration Item identification involves:

►Identifying the structure of the s/w system

►Uniquely identify individual components

►Uniquely identifying various revisions

►All of the given

Question No: 11 ( Marks: 1 ) - Please choose one


Incomplete Configuration identification documents may result in:

►Schedule Product

►all of the given choices are correct

►Defective Product

►Higher Maintenance Costs

Question No: 12 ( Marks: 1 ) - Please choose one


If Configuration item identification is not identified, it is possible to control changes and establish records.

► True
► False

Question No: 13 ( Marks: 1 ) - Please choose one


Availability and Reliability are concerned with

► Perceived quality

► Quantitatively measured quality

Question No: 14 ( Marks: 1 ) - Please choose one


Software Availability can be calculated by the following equation:

► Availability = (MTTR/MTTF) x 100

► Availability = (MTBF/MTTR) x 100

WWW.VIRTUALINSPIRE.COM
Prepared byDil-E-Nadan
Campus[psmd01]Samundri
miansufyan106@gmail.com

► Availability = (MTTF/MTBF) x 100

► Availability = (MTBF/MTTF) x 100

Question No: 15 ( Marks: 1 ) - Please choose one


Phase Index can be calculated by the help of the following formula, where
Ei – the total number of errors uncovered during the ith step in the SE process
Si – number of serious errors
Mi – number of moderate errors
Ti – number of minor errors
PSi – product size at the ith step
ws, wm, wt – weighting factors for serious, moderate, and minor errors

► PIi = ws(Si/Ei) + wm(Mi/Ei) + wt(Ti/Ei)


► PIi = ws(Si/Ei) + wm(Mi/Mi) + wt(Ti/T)

► PIi = ws(Si/Ei) + wm(Mi/Mi) + wt(Ti/Ei)

► PIi = ws(Si/S) + wm(Mi/M) + wt(Ti/E)

Question No: 16 ( Marks: 1 ) - Please choose one


The higher the Error Index, the higher will be the Defect Removal Efficiency

► True

► False

Question No: 17 ( Marks: 1 ) - Please choose one


The goal of quality assurance is to provide management with the data needed to determine which software
engineers are producing the most defects.

► true
► false

Question No: 18 ( Marks: 1 ) - Please choose one


From the following listed software development Model, which one is an object oriented model

► Classical life cycle model


► Fountain model

► Spiral model
► Waterfall model

Question No: 19 ( Marks: 1 ) - Please choose one


The prototyping model of software development is

WWW.VIRTUALINSPIRE.COM
Prepared byDil-E-Nadan
Campus[psmd01]Samundri
miansufyan106@gmail.com

► a reasonable approach when requirements are well defined.


► a useful approach when a customer cannot define requirements clearly.

► the best approach to use for projects with large development teams.

► a risky model that rarely produces a meaningful product.

Question No: 20 ( Marks: 1 ) - Please choose one


___________________is a team organization where there is no permanent leader and task coordinators are
appointed for short duration. Decisions on problems and approach are made by group consensus and
communication among team is horizontal.

► Democratic decentralized (DD)


► Controlled decentralized (CD)
► Synchronous paradigm (SP)
► Controlled centralized (CC)

Question No: 21 ( Marks: 2 )


Discuss the role of program restructuring in software reengineering?

Question No: 22 ( Marks: 2 )


Differentiate Change Control Authority (CCA) and Change Control Board (CCB)?

Question No: 23 ( Marks: 2 )


Give the uses of Time Boxing?

Question No: 24 ( Marks: 3 )


Differentiate between organizational maturity and process area capability?

Question No: 25 ( Marks: 3 )


What would you understand by the conventional numbering of the product release?

Question No: 26 ( Marks: 3 )


What would this model depict?

Question No: 27 ( Marks: 5 )


How we schedule a project with the help Critical Path Method (CPM)? Give only key points.

WWW.VIRTUALINSPIRE.COM
Prepared byDil-E-Nadan
Campus[psmd01]Samundri
miansufyan106@gmail.com

Question No: 28 ( Marks: 5 )


What problems can be caused by following bad smells in code?
· Large class
· Short gun surgery

Question No: 29 ( Marks: 5 )


Briefly explain the following graph

Question No: 30 ( Marks: 10 )


What are the difficulties in maintaining the Legacy System?

Question No: 31 ( Marks: 10 )


If we have collected the historical data of our organization, how the data related to errors help in assessing
the quality of the present project?

Cs605

1. Do you think that a long parameter list of a function/method, can be a “bad smell”? Give
reason for your answer.
2. Why prototyping is used in modeling the change in business processes before making it
part of the new system?
3. Name two techniques that can be used to schedule the project once the task network is
defined.

4. Legacy system related the aik

5.

A chat messenger is realeased and its version is 1.0.0 .it only posses chat functionality now.
after 1 year there are different major features are added lilke audio/video calls, files sharing and
data sharing. now what version number this chat messenger posses?

6.

WWW.VIRTUALINSPIRE.COM
Prepared byDil-E-Nadan
Campus[psmd01]Samundri
miansufyan106@gmail.com

For a certain applocation MTTF = 48 MTTR = 8 calculate avaibilty

7.

P1 = current annual maintenance cost for an application = 200000

P2 = current annual operation cost for an application = 50000

P3 = current annual business value of an application = 400000

L = Expected life of the system = 4years

Calculate maintenance cost of the system.

Ans:

Formula
Cmentainence = [P3-(P1 + P2)] * L

Cmentainence = [400000 – (200000 + 50000)] * 4

Cmentainence = [400000 – 250000] * 4

Cmentainence= 150000 * 4

Cmentainence = 600000

Write atleast one stretegy of Time Boxing

Write the name of technique used in Schedule

Many times we tag requirements with certain attributes e.g., Requirement


ID, requirement Status, list any
two advantages of such tags

Structure of releasing a compound number.

WWW.VIRTUALINSPIRE.COM
Prepared byDil-E-Nadan
Campus[psmd01]Samundri
miansufyan106@gmail.com

List the strategic option of legacy system assessment.

 Do you think that a long parameter list of a function/method, can be a “bad smell”? Give
reason for your answer.
 Why prototyping is used in modeling the change in business processes before making it
part of the new system?
 Name two techniques that can be used to schedule the project once the task network is
defined.

error remove efficiency ek ye tha question

Suppose for a certain project Preliminary design generated 12 defects which were passed on to
detailed design. Now at detailed design phase, 6 defects were passed on to the next stage and 6
were amplified at a ratio of 1:1.5. In addition, there were 20 new defects introduced at this
(detailed design) stage. Calculate how many defects were passed to next stage by detailed design
stage?

Suppose zero percent (0%) defect removal efficiency at each stage.

r u agreed comments are bad smell? 3

DRE formula 2 marks’

Message Chains are bad smell? How? 5

1. Why prototyping is used in modeling the change in business processes before making it
part of the new system?

5 marks

1. Why prototyping is used in modeling the change in business processes before making it
part of the new system?