You are on page 1of 9

CADE/CAODC DRILLING CONFERENCE

October 20 & 22, 2003


Calgary, Alberta, Canada

TITLE: Wellbore Stability (Geomechanics) Modelling and Drilling Optimization PAPER NO.
Practices Reduce Drilling Cost – Terra Nova Project 2003 - 005
AUTHOR(S): Page 1 of 9
Jason Evans, SPE, Petro-Canada
David Folmer, SPE, Baker Hughes OASIS
Seehong Ong, SPE, Baker Atlas/GeoScience

COPYRIGHT NOTATION: This paper was selected for presentation by the CADE/CAODC Drilling Conference Technical Committee, following a review of
information contained in an abstract submitted by the author(s). Contents of the paper have not been reviewed by the Technical Committee and do not necessarily
reflect the position of any or all of the Conference sponsors. Permission to copy is restricted to just this abstract page. Illustrations may not be copied. The abstract
should contain conspicuous acknowledgement of where and by whom the paper was presented. Further permission to copy may be requested from the
CADE/CAODC Technical Chairman, 800, 540 - 5 Avenue SW, Calgary, Alberta, Canada T2P 0M2.

calculated and actual trends are explained and that any


required remedies are put in place immediately.
ABSTRACT: The most significant accumulation of non-
productive time (NPT) due to wellbore instability on a
Wellbore instability has resulted in elevated single well to date is 36 days. Since implementing the
operations time and costs on 11 of 18 current development geomechanics model and focused engineering approach,
wells in the Terra Nova Field, offshore Eastern Canada. The four wells have been successfully drilled, including a twin
non-productive time associated with wellbore instability to the problem well mentioned above, with no wellbore
related issues has varied from 2 to 860 hours. In some cases, instability related non-productive time.
multiple sidetracks have been performed to regain a stable The successful merger of theory and application
wellbore. The typical problems encountered included has saved time and money at Terra Nova. It has also given
washing/reaming/overpull, stuck bottom hole assemblies an improved focus and integration between planning and
(BHA), fluid losses, sidetracks and casing not going to execution of the well, and the people performing the
bottom. In order to reduce the risk and associated costs of activities.
problems related to wellbore instability, Petro-Canada
partnered with Baker Hughes OASIS and Baker Atlas to
develop a plan incorporating the use of a geomechanics INTRODUCTION
model and optimized drilling practices during the planning
and drilling phase. A set of well specific guidelines were Drilling the deviated development oil wells in the
then compiled which included measurements to ensure the Terra Nova Field (Figure 1), offshore Eastern Canada, has
effective implementation of the geomechanics model. proven challenging. The Fortune Bay shale, located directly
The geomechanics model is derived from logging above the reservoir sands, has been identified as one of the
and leak-off data. It is designed to provide formation most critical zones from an instability perspective for many
mechanical properties, characterization of in-situ stresses of the wells drilled in the field. Instability in this and other
(orientation and magnitude), identification of wellbore zones (Figure 2) has lead to the occurrence of NPT on more
failure mechanisms and appropriate mud weight windows than one third of the wells drilled in the field. The issue
for safe drilling operations. The model is based on the surrounding wellbore instability in this formation is one
theory of “Controlled Breakout”® (CB), which allows some which originates from physical instability. A mud weight
amount of hole breakout to occur. The hole breakout is program is designed to control instability and minimize the
limited so that the wellbore will stabilize and be stronger in negative effects on rate of penetration (ROP) thus allow
its breakout geometry than it would be in a perfectly round drilling operations to proceed without the significant
geometry. occurrence of NPT while reducing the risk of reservoir
Once the geomechanics model has been created damage in the formations below. To add to the challenge,
and calibrated, it is imperative that the model is applied in a the appropriate mud weight window varies with the
formal drilling implementation process to ensure that the inclination and azimuth of each well drilled in the field.
guidelines controlling breakout are implemented. If To address the issues of wellbore instability, Petro-
breakout is occurring, operations must be altered to allow Canada partnered with Baker Hughes Drilling Optimization
the excess cuttings/cavings to be circulated out of the Services and Geomechanical Services to develop a plan
wellbore. Additionally, multiple parameters like torque, which incorporated the use of a geomechanics model and
drag, Equivalent Circulating Density (ECD) etc. must be optimized drilling practices for future wells.
monitored real-time to ensure that any deviation from
TITLE: Wellbore Stability (Geomechanics) Modelling and Drilling Optimization PAPER NO.
Practices Reduce Drilling Cost – Terra Nova Project 2003-005
AUTHOR(S): Page 2 of 9
Jason Evans, SPE, Petro-Canada
David Folmer, SPE, Baker Hughes OASIS
Seehong Ong, SPE, Baker Atlas/GeoScience

BENCHMARKING PAST PERFORMANCE h). The magnitude of the stresses is determined from
The first step in improving drilling performance is density logs, the synthetic rock properties, leak-off tests (or
measuring current performance and evaluating the entire extended leak-off tests where available) and borehole
sequence of events that has lead to any non-productive time. acoustic image log (if breakout is present). The stress
Once this step has been completed, recommendations can be RULHQWDWLRQV IRU HDQG h) can be determined from caliper,
made to plan for the identified improvement opportunities borehole image and acoustic anisotropy logs.
and the ultimate implementation process to be applied to
upcoming wells.
On the eight wells which exhibited more than 1 day CONTROLLED BREAKOUT®
NPT due to wellbore instability, a total of 1922 hours were Beyond the full assessment of the mechanical
spent trying to overcome related operational issues. The properties of the rocks and the stresses within the rocks, an
approximate costs due to wellbore instability related NPT is important part of the success on the Terra Nova Project can
$ 28.8 million CDN. The NPT can be broken down into: be attributed to the use of the theory of Controlled Breakout
washing/reaming/overpull, stuck BHA, fluid loss, ® (CB). CB is a theory which has been established and well
sidetracking due to instability (either around a stuck BHA or documented (Zheng, 1998). CB is the process of allowing
inability to re-enter an existing wellbore) and casing not some of the wellbore to cave in, thereby changing the
going to bottom. geometry of the remaining hole. An example of a wellbore
Typical remedies applied in the past to alleviate with breakout can be seen in Figure 3. This new wellbore
these problems include randomly increasing mud density, shape, which now more closely resembles an oval rather
additional wiper trips, longer connections to work the hole than a circle, is stronger and will require less mud density to
clean, extra circulating time for mud conditioning and help support it. In fact, a hole with breakout will be at least
density increases, and additional time to clean the hole. 33% stronger than a circular hole (Zheng, 1998). There are
many advantages to drilling wells using the CB theory:
¾ The primary advantage is the use of a lower density
GEOMECHANICS MODEL mud. Since some of the wellbore is allowed to cave in,
With regards to understanding and controlling a lower mud density is required than if the hole were to
wellbore instability, the first step is to create a be maintained in its perfectly round geometry.
geomechanical model. A proper geomechanical model ¾ Lower mud density reduces the ROP penalty that is
requires numerous inputs to accurately depict the static associated with higher mud density.
mechanical properties of the rock being drilled and the in- ¾ The lower mud density also reduces the chances of
situ stress tensor of the field. The logging and petrophysical formation damage in the reservoir and fluid losses
data required to perform the assessment includes: relative throughout the well.
volumes of sand, shale and fluids, acoustic wave CB can also accommodate more challenging well
(compression and shear) and bulk density. From this suite of path trajectories1 and will manage tight tolerance issues with
logging and petrophysical data, a number of other variables respect to mud weight, pore pressure, and fracture pressure
can be calculated, including: Young’s modulus, Poisson’s considerations. This is accomplished by enlarging the mud
ratio, compressive & tensile strengths, internal friction weight window between the fracture gradient and the mud
angle, Biot’s constant and cohesive strength. In the absence density required to maintain wellbore stability, applying the
of any petrophysical data (particularly in the overburden CB concept.
section), correlations will be used to estimate the required
rock mechanical parameters for the wellbore stability
analysis (Jaeger, and Cook, 1979). Pore pressure is also MODEL CALIBRATION/VALIDATION
determined using the offset logging data. Once a geomechanics model has been created, it
An important part of the model used in the Terra must be calibrated by matching predicted breakout with the
Nova Field is the fact that the static mechanical properties actual data evaluated using the original rock properties from
are all generated from logging data, and not from actual the initial model. The validation typically is achieved by
measurement of rock samples. This model is the only one in evaluating critical breakout areas observed in offset wells
current commercial use that applies this method to obtain and a well in which the CB concept has been applied.
rock mechanical properties. Predicted versus actual geometry of the breakout is
Next, the in-situ stresses and orientation within the evaluated with the mud density used and compared to the
rock are determined. This evaluation is qualified from a
thorough understanding of the faulting environment within 1
A challenging well path can be defined by its combination
the area, whether the faults are normal, thrust or strike slip. of vertical section, inclination, and azimuth in relation to the
7KH7HUUD 1RYD )LHOG LV D QRUPDO IDXOWLQJ DUHD v ! H > orientation of the field wide rock stresses.
TITLE: Wellbore Stability (Geomechanics) Modelling and Drilling Optimization PAPER NO.
Practices Reduce Drilling Cost – Terra Nova Project 2003-005
AUTHOR(S): Page 3 of 9
Jason Evans, SPE, Petro-Canada
David Folmer, SPE, Baker Hughes OASIS
Seehong Ong, SPE, Baker Atlas/GeoScience

output of actual caliper and borehole image logs. Any and cavings being removed from the hole must be
differences are noted and the model is revised accordingly. accurately estimated. This is to be compared to the expected
The rock mechanics model is then used to simulate the new volume of cavings which is based on a combination of the
expected response and is calibrated for modeling future inclination and azimuth, in relation to the far-field stress
wells. orientations and from offset wells with wellbore image logs.
There are two primary forward modeling outputs of The combination of the original hole, plus the planned
the rock mechanics model that are used for drilling future breakout, over the expected section of hole interval where
wells. The first is the mud density requirement versus depth breakout will occur, give the planned estimated rock volume
for a specific planned well trajectory and a given amount of to be removed from the hole.
breakout (Figure 4). This graphical presentation of data ECD is also estimated prior to drilling the well.
provides an overall picture of the mud weight requirements ECD measurements while drilling will give indications of
at known problem intervals and is used to determine the possible cuttings / cavings build-up in the wellbore
depths of casing seats required to successfully drill the well. (Hutchinson, Rezmer-Cooper, 1998). ECD is particularly
The second output is a set of contour plots defined for a important to track, as it can give one of the most obvious
specific breakout angle and created for the critical intervals and earliest indications of breakout occurring. Additionally,
identified (Figure 5). Both outputs are used in the planning ECD may reduce if breakout has occurred, as the annular
phase of a well and are often referenced during wellpath formation volume will have increased.
trajectory changes as required. A contour plot shows, for a Real-time Downhole Pressure Measurement
specific depth (typically a depth of instability), the mud (DPM) technology is required to capture the ECD data
density required for a set amount of breakout at various during the drilling phase. Part of the planning process is to
inclination and azimuth combinations. ensure that the proper tool is selected and evaluation criteria
are in place. The DPM tool used in the Terra Nova drilling
project captures data while drilling and stores data when the
FOCUSED ENGINEERING pumps are off. This is important for capturing downhole
The geomechanical model provides the basis for pressures from tripping in (surge) or while pulling out of the
improving drilling performance in areas where wellbore hole (swab), when circulation does not take place.
instability is a problem. The application of the modeling Torque and drag estimates and sensitivity studies
results by the drilling optimization services during the are prepared while planning for a well. The loading and
drilling operation is just as critical in providing the overall cleaning of cuttings / cavings from the wellbore will give
solution to wellbore instability. variations to the measured pick-up, slack-off and rotating
weights while drilling (Reiber, Vos, Eide, 1999). Knowing
what these variations mean in terms of cuttings / cavings
PLANNING volumes in the hole is essential when drilling operations
Controlled Breakout ® is the premise for the model begin.
and engineering solution, and as such there is a volume of Fluid volume trends (calculated and actual) in the
cavings, in addition to the cuttings generated, which must be active system are also tracked and changes are accounted for
accounted for in the planning and drilling phases. For this while drilling commences. This is based on a gauge hole,
reason, a series of parameters are benchmarked and trend plus the expected breakout volume through the intervals
analysis performed to monitor wellbore stability and to where breakout is expected. Variations from this number
ensure NPT is minimized. The additional volumes of can provide indications that breakout is worse or less than
cavings will have an impact on hole cleaning, equivalent expected.
circulating density (ECD), torque/drag and fluid Fluid properties are evaluated to ensure
volumes/properties used while drilling. To evaluate if the compatibility with expected operations. Specifically, fluid
amount of breakout occurring is as planned, excessive or properties are designed to maximize cuttings / cavings
lower than planned, it is important to know expected levels carrying potential. This is particularly important as the
first. This can prove challenging, since the exact geometry primary problem zones exist near the bottom of the well.
of the hole breakout is difficult to estimate in advance. For Thus fluid properties require a predictable carrying capacity
this reason, exact values are not typically used, but trends of given longer distances for cuttings transport and can be seen
key parameters are tracked as changes to the parameter as being more critical with large transport distances at high
trends may signify a potential instability issue. inclination sections of the wellpath.
Hole cleaning is one of the primary parameters Surge and swab calculations are performed for
requiring calculated and actual trend analysis. Whether or two different scenarios. The first is for operations when
not the hole is clean has an impact on nearly every other pulling out of the hole, whether tripping or working a stand
parameter being observed. The actual volume of cuttings during a connection. The geomechanical model provides a
TITLE: Wellbore Stability (Geomechanics) Modelling and Drilling Optimization PAPER NO.
Practices Reduce Drilling Cost – Terra Nova Project 2003-005
AUTHOR(S): Page 4 of 9
Jason Evans, SPE, Petro-Canada
David Folmer, SPE, Baker Hughes OASIS
Seehong Ong, SPE, Baker Atlas/GeoScience

required downhole pressure to ensure breakout does not quantify the angle of breakout which exists. This is due to
exceed an expected amount. Additional mud density is used the fact that the shape of a breakout can change
to give a safety factor (swab margin) to allow for operations considerably, based on the wellbore trajectory in relation to
which will lower the downhole pressure, such as pulling out the orientation and anisotropy of the far-field stresses.
of the hole. This safety factor must be matched with the Additionally, the other logs listed previously as input for the
geometry of the BHA and the pulling speed when tripping geomechanics model should also be collected so they may
through the critical sections of the well. Since reducing mud be added to the model for calibration purposes.
density below the minimum required mud weight for a
stable wellbore is a concern, swab pressures prove to be a
key control parameter while ensuring breakout does not IMPLEMENTATION
exceed the planned values. The planning process ensures the Once the planning phase is completed and the
proper tools will be available to measure the required values required detail is included in the design files for the well,
while drilling. The DPM technology is used to capture the drilling commences. The focus is then totally on the
actual surge / swab pressures which are compared to the engineering program that has been prepared. In an ideal
planned values and benchmarked for the planning of future service situation, there will be two “drilling optimization
wells. service engineers” on the rig site to monitor the previously
The ideal scenario is to drill the wells with the mentioned values and trends2. This way, all deviations are
lowest possible mud density to maximize rate of penetration noted as they occur and remedies can be implemented
(ROP), however in reality it is the wellbore instability that immediately. Another engineer will be in town with the
dictates the required mud densities. Another issue to drilling team, to interpret and share the plots generated
consider is the potential for lost circulation when running offshore as the well is drilled.
casing in higher mud density. Therefore surge pressures are The importance of the implementation phase
analyzed to give appropriate running speeds for running cannot be overemphasized. While many of the real-time
casing (casing strings are typically tapered in the Terra measurements on the rig can be observed by others on the
Nova Field, so running speeds will vary throughout the well site, it is the sole focus of the optimization engineers on
process of running casing). controlling wellbore instability which is essential to the
All of these items are planned for and monitored success of the project. It is easy enough for the driller to
while the well is ongoing with the goal of maximizing ROP. notice that torque and drag values are erratic over the course
Due to the highly interbedded nature of the Terra Nova of a well and for the mud engineer to notice a slow increase
Field, ROP will vary significantly throughout a well. in pit volume above the normal active mud system.
However, the goal is to maximize ROP in each section of However, with someone on the rig focused on wellbore
the well and still control any possible wellbore instability instability, trends are analyzed to see if there is a
issues. relationship between these items.
The logging program is the final issue that Since surge and swab pressures are so important to
requires considerable attention in the planning phase. The the end result of this process, the engineers will be on the
primary focus at this point is to run the appropriate rig floor during trips in and out of the hole with BHA’s and
“advanced technology hole image logging” and other casing strings. The engineer will also spend a significant
pertinent logging technology to characterize the CB amount of time in the shaker room, analyzing cuttings and
concept. Since the geomechanics model is only as good as cavings, and the geometry and volume of each, being
the data used in the model, ensuring that complete, accurate removed from the hole. The rest of the pertinent data is
and relevant data sets are added is important to the constantly uploaded from the mud logging database as the
continued integrity of the model. For this reason, part of the well is being drilled.
planning process is ensuring the proper logging data will be Once drilling is completed, and the BHA is pulled
collected over the appropriate intervals of the well. The out of the hole, the engineer remains heavily involved
most important log to ensure the proper characterization of during the logging program in order to analyze the results as
the wellbore is an acoustic borehole image log (Figures 6 soon as they are available. Significant deviation from
and 7). The geomechanical model is designed to produce a expected values, particularly with the caliper and wellbore
fixed amount of breakout in the least stable section of the image log, can instigate a clean-out run or the need to
well. The only way to determine the degree of conservatism increase mud density, prior to running casing.
of the model is to have an actual measurement of the
breakout, which occurred when drilling the well. The only
decisive way to quantify the existence of breakout is with a 2
Due to the complete buy-in and support from the rig-based
hole image log. The existence of breakout can be qualified personnel, currently only one “drilling optimization service
by caliper data, but it is impossible to use that data to engineer” is required during the implementation phase.
TITLE: Wellbore Stability (Geomechanics) Modelling and Drilling Optimization PAPER NO.
Practices Reduce Drilling Cost – Terra Nova Project 2003-005
AUTHOR(S): Page 5 of 9
Jason Evans, SPE, Petro-Canada
David Folmer, SPE, Baker Hughes OASIS
Seehong Ong, SPE, Baker Atlas/GeoScience

POST WELL block within the field, the original geomechanics model was
After casing has been successfully run it is time to not directly applicable. However, with no model available
compare all of the planning and actual values from the well. specific to this fault block, key information (sonic, pore
If all trends and results are reflecting the planned values, the pressures etc.) for both areas were evaluated and provided
model is verified and carried forward to the next well. sufficient initial justification to apply the original
If there are variations from the expected and actual geomechanics model to these two wells. Both wells were
values seen on the well, detailed analysis of the two values drilled successfully with no indication of wellbore
is performed. All of the assumptions made during the instability and no NPT related to instability was experienced
planning phase are addressed and either supported or during the drilling phase. One additional wiper trip was
revised. If the assumptions are correct, but there is still required before running casing on the fourth well due to
variation between the model and the actual wellbore some minor instability during logging in a zone not
geometry seen, then these differences are captured and identified as critical by the original geomechanics model.
entered into the database which forms the model. The model As a result, an additional geomechanics model, specific to
is updated, and again verified against the existing actual this fault block, will be developed as subtle differences
data to be used on forward well planning. between the different parts of the field exist.

RESULTS FUTURE PLANS


Since implementing the process of combining With the successful implementation of this new
geomechanics modeling and a focused engineering service, Petro-Canada has decided to apply it to future
approach, four wells have been drilled in the Terra Nova drilling in all fault blocks within the Terra Nova Field. As
field. The first well was very similar to the typical wells mentioned, this will initially include one possibly two
drilled in the field, with inclination up to 38q and a drop additional geomechanics studies to determine the rock
section to 25q prior to reaching the critical problem properties and stresses in the different fault blocks.
formations. There was no intermediate casing on this well, This commitment to the future focus of the
so the critical risk section was open for a longer period of wellbore stability concerns has also introduced changes
time. There was no amount of NPT related to wellbore during the well planning phase. There is more
instability on this well. Analysis of fluid and cuttings communication and a better understanding about items
volumes actually indicated less breakout than expected. related to wellbore stability, which has affected the drilling,
However, due to logistical problems, no hole image log was geology and reservoir departments.
run and the amount of breakout could not be definitively There is also a potential to introduce three-
quantified. dimensional presentation/visualisation as part of the service
A second well was drilled utilizing the new depending upon future drilling plans. This progressive step
wellbore stability approach. This well was a twin to the will allow a better translation of the existing geomechanics
offset well with the most NPT related to wellbore instability models and actual field results in the planning of future
in the Terra Nova field. The offset well had two sidetracks wells. This will be done by capturing the far-field stress
and the tapered production casing string had to be pulled as regimes, assessing the faults in the field and their affects on
it would not go to bottom, due to wellbore instability. The wellbore stability, and the magnitude of breakout with
new well was designed to build to an inclination of 49.8q relation to wellbore trajectory and mud density on existing
followed by a tangent section and a drop to 25q prior to the wells.
critical formation. The reduced hole angle through the
critical zone was done purposely in order to avoid excessive
mud weight requirements for wellbore stability. Due to the CONCLUSIONS
historical instability problems and the proximity to a ƒ The assimilation of rock mechanics modeling with
delineation well that provided reasonable geological specific drilling procedures has been important to the
certainty, intermediate casing was planned for this particular overall success of the Terra Nova project. Either
well. The offset well experienced a total of 36 days of NPT component of the wellbore stability approach may add
due to wellbore instability. The twin well did not suffer any value and savings to the Terra Nova project, however in
wellbore instability related NPT in this intermediate section. combination it has shortened the learning curve and
Drilling cost savings on this well when comparing to its increased the savings by reducing NPT.
‘sister-well’ are in the order of several million dollars CDN. ƒ Running the “advanced technology hole image log” is
The third and fourth wells both were sidetracks (re-entry) vital to calibrating the rock mechanics model versus
from an existing well. As these wells are in a different fault actual field results. Otherwise, only qualitative
learnings will be captured.
TITLE: Wellbore Stability (Geomechanics) Modelling and Drilling Optimization PAPER NO.
Practices Reduce Drilling Cost – Terra Nova Project 2003-005
AUTHOR(S): Page 6 of 9
Jason Evans, SPE, Petro-Canada
David Folmer, SPE, Baker Hughes OASIS
Seehong Ong, SPE, Baker Atlas/GeoScience

ƒ Rig-site “drilling optimization service engineers”


provide round the clock observation, significantly
improving response time to deviations from planned
trends. With complete buy-in and support from rig
based personnel, only one drilling optimization
engineer is required for the implementation phase.
ƒ Preparation and use of specific required mud density
versus depth plots remove ambiguity that can
accompany the use of contour plots alone. This has lead
to improved results and reduced NPT.
ƒ Observing and analyzing the rig-captured data real-
time, as it relates to wellbore stability, does lead to
improve measurement quality and reporting of drilling
parameters.
ƒ Teamwork is a vital component of the process
presented and has resulted in the success of the project
to date. Engineers in the office review the benefits of
this approach to overall well planning, while operations
also need to be included to ensure that implementation
goes as planned.

ACKNOWLEDGEMENTS
The authors would like to thank Petro-Canada and Baker
Hughes for permission to publish this paper. Thanks are also
extended to Roger Dugal of Petro-Canada and Greg Szutiak
of Baker Hughes OASIS for their contributions to this
paper.

REFERENCES
1. Jaeger, J. and Cook, N.G.W. Fundamentals of
Rock Mechanics, 3rd edition, Chapman and Hall, London,
1979.
2. Zheng, Z.: “Integrated Wellbore Stability Analysis
– Against Tradition”, SPE 47282, Proc. Eurock ’98,
SPE/ISRM joint conference, 8-10 July 1998, Trontheim,
Norway,
3. Hutchinson, M. and Rezmer-Cooper, I.: “Using
Downhole Annular Pressure Measurements to Anticipate
Drilling Problems”, SPE 49114, 1998 SPE Annual
Technical Conference and Exhibition, 27-30 September
1998, New Orleans, USA
4. Reiber, F., Vos, B.E. and Eide, S.E.: On-line
Torque & Drag: A Real-Time Drilling Performance
Optimization Tool”, SPE/IADC 52836, 1999SPE/IADC
Drilling Conference, 9-11 March 1999, Amsterdam,
Holland
TITLE: Wellbore Stability (Geomechanics) Modelling and Drilling Optimization PAPER NO.
Practices Reduce Drilling Cost – Terra Nova Project 2003-005
AUTHOR(S): Page 7 of 9
Jason Evans, SPE, Petro-Canada
David Folmer, SPE, Baker Hughes OASIS
Seehong Ong, SPE, Baker Atlas/GeoScience
Figure 1 – Field Map Terra Nova

Area covered by Original


Geomechanics Model

Figure 2 – Stratigraphic Cross-Section Terra Nova

Critical zones:

¾
¾
Middle/Lower Hibernia
Fortune Bay
TITLE: Wellbore Stability (Geomechanics) Modelling and Drilling Optimization PAPER NO.
Practices Reduce Drilling Cost – Terra Nova Project 2003-005
AUTHOR(S): Page 2 of 9
Jason Evans, SPE, Petro-Canada
David Folmer, SPE, Baker Hughes OASIS
Seehong Ong, SPE, Baker Atlas/GeoScience
Figure 3 – Borehole Breakout – Oval Wellbore

Figure 4 – Mud Weight Program – Based on 0 / 60 / 90 degree


breakout, fracture gradient and wellbore inclination

Mud weight program to


control breakout
TITLE: Wellbore Stability (Geomechanics) Modelling and Drilling Optimization PAPER NO.
Practices Reduce Drilling Cost – Terra Nova Project 2003-005
AUTHOR(S): Page 3 of 9
Jason Evans, SPE, Petro-Canada
David Folmer, SPE, Baker Hughes OASIS
Seehong Ong, SPE, Baker Atlas/GeoScience
Figure 5 – Contour Plot - For 75º breakout in critical Fortune Bay
Marker

Well-X
Inclination / Azimuth
@ Fortune Bay Marker

Figure 6 – Acoustic Wellbore Image Offset Well Figure 7 – Acoustic Wellbore Image – Offset Well
60-90 degree breakout 80 – 100 degree breakout

You might also like