Examination Circular No. 311 of 2019 Schedule of Examinations to be held in Second Half of the Year 2019.
FACULTY OF COMMERCE AND MANAGEMENT
(A) COMMERCE
(Revised as on dated 01/10/2019)
Sr. Name of the Examination Last date for Last date with Examination fee Date of Probable Date
No accepting the late fee of Rs. ( Rs.) per Commencement of Declaration
Examination 150/- for Sem./Part/ Year/ of Examination of Result
forms without Professional & Term
late fee Non –
Professional
Courses
1. F.Y. B.Com. (Sem I) (2019 Pattern ) 03/08/2019 17/08/2019 340 31/10/2019
(Including Regular & Vocational)
Choice Based Credit System As per MPUA
2. F.Y/ S. Y./T. Y. B.Com.(2013 Pattern ) 03/08/2019 17/08/2019 340 10/10/2019 2016 Sec. 89
(Including Vocational) Regular & within 30 days
External from last day of
3. F.Y.B.B.A(I.B.) (Sem I) (2019 Pattern ) 23/08/2019 09/09/2019 1350 01/11/2019 Examination
Choice Based Credit System
4. B.B.A. (Sem. I to VI) ( 2013 Pattern) 23/08/2019 09/09/2019 1350+520 For 01/11/2019
project report
5. B.B.A. (Sem I) (2019 Pattern ) 09/09/2019 24/09/2019 1350+520 For 01/11/2019
Choice Based Credit System project report
6. B.C.A. (Sem. I to VI) (2013 Pattern ) 23/08/2019 09/09/2019 1350+520 For 01/11/2019
* B.B.A.( Computer Application ) project report

1
7. B.C.A. (Sem. I) (2019 Pattern ) 09/09/2019 24/09/2019 1350+520 For 01/11/2019
Choice Based Credit System project report
B.B.A.( Computer Application )
8. B.B.M.(I.B.) (Sem. I to VI) 23/08/2019 09/09/2019 1350+520 For 01/11/2019
( 2013 Pattern ) project report
*B.B.A. (International Business)

9. M.C.A. (Commerce) (Sem. I to VI ) 23/08/2019 09/09/2019 1350+560For 05/11/2019


( 2013 Pattern ) Including Credit project report
System ( Repeater only )
10. M.Com. (E-Commerce) 23/08/2019 09/09/2019 1350+560 For 05/11/2019
(Sem. I & III ) project report As per MPUA
2016 Sec. 89
11. M.Com.(Sem.I to IV)(Including Credit 23/08/2019 09/09/2019 520+340 Project 05/11/2019 within 30 days
System ( 2013 Pattern ) from last day of
( Regular & External ) Examination
M.Com. ( External ) (2015 Pattern )
For External only
12. M.Com.(Sem.I ) Choice Based Credit 09/09/2019 24/09/2019 520+340 Project 05/11/2019
System. ( 2019 Pattern )

Note : 1. * Academic Council Resolution No. VP B 31 PA/31/15 ( Ref. No. CB/639, SPPU Circular No.
104/2015 dt. 22 June 2015. )

2. If any revision/ change in the syllabus from the academic year 2019 will be inform accordingly.

2
SAVITRIBAI PHULE PUNE UNIVERSITY
(Formerly University of Pune)

Examination Circular No. 311 of 2019 Schedule of Examinations to be held in Second Half of the Year 2019.
( B ) MANAGEMENT
(Revised as on dated 01/10/2019)
Sr. Name of the Examination Last date Last date with Examination fee Date of Probable Date of
No. for late fee of Rs. ( Rs.) per Commencem Declaration of
accepting 150/- for Sem./Part/ ent Result
the Professional & Year/ Term Examination
Examinatio Non –
n forms Professional
without late Courses
fee

1. M.B.A. (Sem. I to IV) ( 2013 Pattern ) 17/09/2019 01/10/2019 1360+510 For 26/11/2019
M.B.A. Sem. I to IV ( 2016 Pattern ) project report
2. M.B.A. Revised Curriculum 2019 CBCGS & 17/10/2019 01/11/2019 1360 16/12/2019
OBE Pattern ( Sem. I )

3. M.P.M. (Sem. I to IV) ( 2013 Pattern) 1020+510 For


17/09/2019 01/10/2019 26/11/2019
*M.B.A. (Human Resource Development) project report

4. M.C.M. (Sem. I to IV) (2012 & 2013 17/09/2019 01/10/2019 1360+510 For 26/11/2019
Pattern) project report
*M.B.A. (Information Technology)
M.M.M. (Sem. I to IV) ( 2013 Pattern ) 1020+510 For
5. 17/09/2019 01/10/2019 26/11/2019
* M.B.A. (Marketing Management) project report

3
M.C.A. ( 2012, 2013 Pattern )
6. (Sem. I to VI ) 17/09/2019 01/10/2019 1360+510 For 26/11/2019
M.C.A .( 2015 Pattern ) (Sem. I to V ) project report
7. M. C. A. ( Part I ) ( Sem. I ) ( 2019 Pattern ) 17/09/2019 0 01/10/2019 1360+510 For 26/11/2019
project report
8. M.B.S. (Sem. I & II) ( 2013 Pattern ) 17/09/2019 01/10/2019 26/11/2019
1360+510 For
* M.M.S. project report As per MPUA
B.H.M.C.T. (Sem. I to VIII ) 2016 Sec. 89
9. 17/09/2019 01/10/2019 1275+510 For 26/11/2019 within 30 days
(2008 Pattern) project report from last day of
B.H.M.C.T. (2016 Pattern ) ( Part – I & II )
Examination
( Sem. I to VII )
B.H.M.C.T. (2019 Pattern ) ( Sem. I ) 1275
10. 17/09/2019 01/10/2019 26/11/2019
Credit System
11. B.H.M.T.T./B.Sc. (Hospitality Studies ) 17/09/2019 1275+510 For
Sem. I to VI ( Repeater Students Only ) 01/10/2019 26/11/2019
project report
Those who have admitted before the
Academic Year 2015 – 2016
* B.H.M. ( 4 Yrs. )
12. Bachelor of Management Studies 17/09/2019 01/10/2019 1360 26/11/2019
( BMS ) ( Sem. I to III )
13. P.G.D.I.E.M. (Sem. I & II) ( 2013 Pattern ) 10/09/2019 24/09/2019 850 13/11/2019
14. P.G.D.M.L.M (Sem. I & II) ( 2013 Pattern) 10/09/2019 24/09/2019 850 13/11/2019
15. P. G. Diploma in Hospital Management 10/09/2019 24/09/2019 850+510 For 13/11/2019
(Sem. I & II ) ( 2013 Pattern ) project report
16. P. G. Diploma in Hospital Management 10/09/2019 24/09/2019 850+510 For 13/11/2019
(Sem. I ) ( 2019 Pattern ) project report
17.. P.G. Diploma in Financial Service 10/09/2019 24/09/2019 850+510 For 13/11/2019
( Sem. I & II ) ( 2013 Pattern ) project report
18. P.G. D.B.M. (Sem. I to IV) (2013 Pattern) 10/09/2019 24/09/2019 850+510 For 13/11/2019
project report
19. P.G. D.M.M. (Sem. I & II) 10/09/2019 24/09/2019 850 13/11/2019
( 2013 Pattern )

4
20. P.G.D.C.M. (Sem. I & II) 10/09/2019 24/09/2019 850 13/11/2019 As per MPUA
( 2013 Pattern ) 2016 Sec. 89
within 30 days
from last day of
Examination

Note : 1. * Academic Council Resolution No. VP B 31 PA/31/15 ( Ref. No. CB/639, SPPU Circular No.
104/2015 dt. 22 June 2015. )

2. If any revision/ change in the syllabus from the academic year 2019 will be inform accordingly.

You might also like