JOB HAZARD ANALYSIS (JHA)

JHA Preparation Instructions: JHAs are to be prepared by the Supervisor or Group Manager in
charge of the work, with work group member participation. The goal of preparing a JHA is for those responsible
for or performing any work to review the risks and possible complications of that work and to consider ways of
mitigating those risks and complications. A JHA shall be completed for all work executed. The JHA## is to be
incremented when a procedure requires more than one JHA form. “Standing” should be marked if job or task is
performed regularly and work group members are always the same individuals. Supervisors are responsible for
getting the work group members sign off completed and a copy sent to the safety officer for each JHA.
JHA Change Instructions: If changes to the content of this JHA are required, follow the KPNO ETS Engineering
Change Process. The master copy of the document must be checked out of the Document Vault, an Engineering
Change form must be completed, and the Revision Table (see last page) must be updated. Note that periodic
reviews of this JHA that do not result in content changes require only entry of the review date and the name of
the reviewer in the Revision Table; the document revision should not be advanced in this case.

Tammie Lavoie 8 March 2017


Tammie Lavoie, Safety Manager Date

JHA Number: 1000-AD-015-0059-JHA01 Rev: - Standing: X


Date Completed: 3 March 2017
Title of Job or Task: Installation and Removal of Zenith Stay Bar
Location/Facility: KPNO 4 Meter
Supervisor or Person
Miranda Saucedo
Completing this JHA:
Person(s) Assisting
Tammie Lavoie
with this JHA:

Recommended Personal Protective Equipment (PPE): select area above line to make entry
Head Protection X Eye Protection Hand and body Protection Fall Protection X
Foot Protection X Hearing Protection Respiratory Protection

Special PPE: N/A


Notes:
*Hard hats must be used whenever someone is working above you or at your head height, or when working with suspended
loads.
** Safety Shoes are mandatory in the area during construction, maintenance, heavy or complex work.

Equipment or tools needed to perform the job: tab or select to make entry in next location, only use if not listed
in procedure.

INSTALLATION AND REMOVAL OF ZENITH STAY BAR Page 1 of 6


1000-AD-015-0059-JHA
PRINT DATE: 2017-03-08
HAZARD ANALYSIS

Hazard Analysis Instructions: Complete the table below with the basic job steps, stating the hazards present and safe
procedures or precautions to control the hazards for each step. Tab will move to next column; to add rows place cursor
outside table on the right, and press ENTER.
Basic Job Steps: Review the activity and divide it into basic steps.
Hazards Present in Each Job Step: Identify the hazards or the possible danger present for each basic job step.
Correct and Safe Procedures and Precautions: Decide what actions or procedures are necessary to control and minimize the
hazards present.

Things to consider: Use designations in the “Hazards Present” column:


Do employees know how to do the job? AX – Asphyxiation HS – Heat stress
What are the hazards? Include people and equipment. BR – Burn Hazard R – Repetitive Motion
How can injuries or accidents occur? CB – Caught Between SA – Struck Against
How can injuries or accidents be prevented? CBY – Contacted By SB – Struck By
Are there obvious unsafe conditions? CI – Caught In SE – Stored Energy
Are special tools needed? CO – Caught On SL – Suspended Load
Do people need personal protective equipment? CW – Contact With TH – Trip Hazard
E – Exposure to Chemicals,
How would we rescue people if something went wrong?
Noise, Vibration, Radiation
Do we have the equipment to rescue? EL – Electrical
ER – Ergonomics
FB – Fall to Below
FH – Fire Hazard

Item HAZARDS PRESENT CORRECT AND SAFE PROCEDURES


BASIC JOB STEPS
No. IN EACH JOB STEP AND PRECAUTIONS
1.1 Ensure the telescope drives and hydraulic
pumps are off and tagged out according to EL, SE
the Lockout/Tagout Standard Operating
Policy (1000-AD-015-0001) and the Note: These procedures must be
Lockout/Tagout Standard Operating reviewed prior to starting the process
1
Procedure (2100-AD-015-0065). CB, CI, CO, ER, FB, SB of installing and removing the Zenith
1.2 Refer to the Fall Protection Plan SOP stay bars.
(1000-AD-015-0003). CB, CI, CO, ER, FB, SB
1.3 Refer to the Rescue Plan SOP (1000-AD-
015-0004).
-Electrical equipment must be
handled with care to prevent shocks,
burns and other injuries from
Ensure the telescope is at Zenith position.
occurring.
2 Note: Place a “Maintenance in Work” placard EL, SE
-Workers must always review the
in the Control Room.
Lockout Tagout SOPs (1000-AD-015-
0001 and 2100-AD-015-0065) before
handling electrical equipment.

INSTALLATION AND REMOVAL OF ZENITH STAY BAR Page 2 of 6


1000-AD-015-0059-JHA
PRINT DATE: 2017-03-08
Item HAZARDS PRESENT CORRECT AND SAFE PROCEDURES
BASIC JOB STEPS
No. IN EACH JOB STEP AND PRECAUTIONS
Install the “Hour Angle” (lower stay bar) to its
corresponding attachment points using the -Inspect push pins for rust and wear
3 attached push pins. CO, FB, SB to ensure a proper fit in the
Note: A minimum of two workers is required equipment.
to complete this step.
Position the 5-ton dome crane to a
predetermined spot to attach the “Man -Use caution when walking around
4 Basket” to the crane hook. CO, FB, SB the crane hook, as there may be a
Note: A minimum of two workers is required low head clearance.
to complete this step.
-Examine the lifting cables for
Connect the 4-point lifting cables to the “Man
abnormal wear.
Basket.”
5 CI, CO, FB, SB -Use caution when walking around
Note: Connecting the lifting cables incorrectly
lifting cables on the equipment, as
will cause the basket to lift unevenly.
there may be a low head clearance.
-Examine the web sling assembly and
its lifting ring for abnormal wear.
Connect the “Declination” (upper stay bar) to
-Use caution when walking around
6 the “Man Basket” using the attached web sling CI, CO, FB, SB
the web sling assembly and its lifting
assembly and its lifting ring.
ring, as there may be a low head
clearance.
-Fall protection must always be worn
and secured properly before any
Lift the “Man Basket” slowly and move it
movement of the basket occurs.
towards the North end of the telescope, as
-All radio communication must be
needed.
7 CI, CO, FB, SB isolated between the crane operator
Note: Begin from floor position. Only one
and the person inside of the basket.
person is able to use the “Man Basket” at a
-Confirm no workers are standing
time.
under the “Man Basket” as it is being
elevated.
Install and secure the lower attachment point
of the stay bar using the attached push pins.
-Inspect push pins for rust and wear
Note: Ensure the upper attachment point has
8 CO, FB, SB to ensure a proper fit in the
been installed and the individual in the “Man
equipment.
Basket” has been cleared before completing
this step.
-Confirm no workers are standing
Lower worker in the “Man Basket” to the Main
9 CI, CO, FB, SB underneath the “Man Basket” as it is
Floor.
being lowered.
-Use caution when walking around
10 Unhook the basket from the crane hook. FB, SB the crane hook, as there may be a
low head clearance.

INSTALLATION AND REMOVAL OF ZENITH STAY BAR Page 3 of 6


1000-AD-015-0059-JHA
PRINT DATE: 2017-03-08
Item HAZARDS PRESENT CORRECT AND SAFE PROCEDURES
BASIC JOB STEPS
No. IN EACH JOB STEP AND PRECAUTIONS
-Examine the web sling assembly and
Removing the “Declination” stay bar: After
its lifting ring for abnormal wear.
personnel are cleared, reposition the crane
-Use caution when walking around
11 and the “Man Basket” to the upper attachment CI, CO, FB, SB
the web sling assembly and its lifting
point and reconnect the stay bar to the web
ring, as there may be a low head
sling on the “Man Basket.”
clearance.
Removing the “Hour Angle” stay bar: Remove
-Inspect push pins for rust and wear
the lower pin from the attachment point,
12 CI, CO, FB, SB to ensure a proper fit in the
remove the upper pin from the attachment
equipment.
point, and securely store the stay bar.

INSTALLATION AND REMOVAL OF ZENITH STAY BAR Page 4 of 6


1000-AD-015-0059-JHA
PRINT DATE: 2017-03-08
REVISION TABLE
Date Remarks and/or Change Details
Rev Approved Reason for Change Name
- Feb. 17, 2015 Initiated

INSTALLATION AND REMOVAL OF ZENITH STAY BAR Page 5 of 6


1000-AD-015-0059-JHA
PRINT DATE: 2017-03-08
WORK GROUP MEMBERS FOR THIS JHA
I understand & will adhere to the steps, hazards & controls as described in this JHA. I understand that performing steps out
of sequence may pose hazards that have not been evaluated, nor authorized. I will contact my supervisor prior to continuing
work, if the scope of work changes or new hazards are introduced. I understand I have the authority and responsibility to
stop work if I believe it to be unsafe.

N° NAME (print) SIGNATURE DATE


1

3
4

6
7

9
10

SUPERVISOR IN CHARGE
I have reviewed the steps, hazards & controls described in this JHA with all workers listed above and authorize them to
perform the work. Workers are qualified (i.e. licensed or certified, as appropriate, & in full compliance with NOAO training
requirement(s) to perform this activity.

N° NAME SIGNATURE DATE


1

INSTALLATION AND REMOVAL OF ZENITH STAY BAR Page 6 of 6