Project :
Summary :
PSSR Team
Name Position Signature Date PSSR Team Approval
Reviewer
Reviewer
Reviewer
Reviewer Sign :
Reviewer Name :
Reviewer Title :
PSSR Facilitator
PSSR Facilitator
Scriber
Signatures of the PSSR Team above indicate acceptance that the equipment or project is safe and satisfactory to start-up with the exceptions note, after the Category A actions are completed.
Guidance :
These supplemental questions are provided to assist the PSSR team in ensuring that the objectives of the PSSR are met. Complete each applicable section by marking “Yes”, “No” or “N/A” to the questions in that section. If an entire section is non-
applicable, mark through the entire section with an “X”. If the answer to any question is “No”, start-up cannot proceed until the issue has been resolved.
When the answer is "NO", resolve the issue by assigning action. The category will be "A" for actions to be closed before the startup, and will be "B" for actions that can be closed after the startup.
1.02 Does the Work Pack or MOC Dossier clearly ALL Yes
show/outline what the change is or should
look like?
4.08 Have flange and manway nuts and stud bolts Cons Yes
been field checked to verify tightness?
(Flange Management)
4.09 Are flange bolts long enough? (2 threads min. Cons Yes
showing outside the nut) Is spacing
adequate for bolt removal?
4.13 Is there a high point vent to remove air and a Cons Yes
low point drain to remove water during start-
up and/ or to properly prepare equipment for
maintenance?
4.14 Are all drain and vent plugs in place? Cons Yes
5.05 Do guy wires have equal tension and are free Cons Yes
from sagging?
6.09 Are vents and drains for normal operation Eng Yes
visible, easily accessible and safely located?
6.11 Are all drain and vent plugs in place? Have Eng Yes
all normally closed drain and vent valves
been appropriately plugged or capped?
6.13 Has new piping been designed and installed Eng Yes
as avoid the creation of dead legs?
6.14 Has piping been painted/ coated for external Eng Yes
corrosion protection as per design?
6.15 Are lines and valves heat traced and Eng Yes
insulated where applicable and has the
insulation been installed to be watertight?
6.17 Are valve boxes/ pits properly guarded and Eng Yes
avoiding hazards rising out of the ground?
6.20 Have flanges been checked for proper bolting Eng Yes
and gasketing materials?
6.21 Are flange bolts tight and long enough? (2 Eng Yes
threads min. showing outside the nut)? Is
spacing adequate for bolt removal?
6.28 Have all valves and orifice plates been Eng Yes
installed in the correct flow direction?
7.03 Have PSVs been bench tested and installed Eng Yes
correctly? Are they code stamped?
7.06 Does the inlet line appear adequate to avoid Eng Yes
restricting flow to the PSV?
7.08 Is the PSV inlet and outlet piping properly Eng Yes
supported to avoid undue stresses on the
PSV?
7.10 Are all PSVs readily accessible for visual Eng Yes
inspection of tags and seals or necessary
maintenance?
7.14 Are all relief valve paths properly flare locked Eng Yes
and documented?
7.15 Are inlet and outlet isolation valves properly Eng Yes
oriented to avoid a potential dropped gate
into the line (i.e. installed with stem in
horizontal position so gate cannot fall off and
block venting)?
8.06 Where turbine casings are not designed for Cons N/A
full line steam pressure are exhaust valves
locked open?
8.07 Have flanges been checked for proper bolting Cons Yes
and gasketing materials?
8.08 Are flange bolts long enough (threads do not Cons Yes
extend outside the nuts)? Is spacing
adequate for bolt removal?
8.15 Have all valves and orifice plates been Cons Yes
installed in the correct flow direction?
8.18 Has the unit/ equipment lubrication list been Eng Yes
updated to reflect any changes/ additions for
rotating equipment?
8.19 Are MSDSs available for lubricants and seal Eng Yes
fluids?
9.04 Have all motors been tested and vibration Eng Yes
checked? Has motor rotation been checked?
9.14 Are bulbs and vapor globes in place; are Eng Yes
guards functional?
9.16 Are junction and pull boxes bolted closed? Eng Yes
Revie
10 Instrumentation/ Controls Yes No N/A Yes No N/A Reviewer Comments Actions Responsible Category
wer
10.01 Have all instruments been installed according Eng Yes
to specifications (P&IDs, drawings,
manufacturer’s recommendations)?
10.04 Has all computer control logic and software Eng Yes
been thoroughly tested?
10.06 Have safety systems (ISS, PES, EPS, and Eng Yes
Critical Alarms, etc.) been checked and are
they functioning as designed? Are SCE list,
performance standard and function test
report available?
10.07 Has heat tracing been turned on and working Eng Yes
for outside instrumentation?
Revie
11 Utilities
wer
11.01 Are utility systems isolated from process Oper Yes
systems per regulatory standards? Do
double blocks, bleeder, and check valve exist
for all applications where required?
11.03 Are all utility connections clearly labeled (e.g., Oper Yes
steam, water, air, nitrogen)?
Revie
12 Blowdown, Flare & Pump Out Systems
wer
12.01 Has the pump out system been designed for Eng N/A
emergency as well as routine shutdown
conditions?
12.02 Has unit relief capacity been checked for the Eng Yes
impact of this project?
13.02 Have ramps and steps been provided over HSE Yes
firewalls/ dikes?
13.03 Are firewall drain valves provided along with HSE Yes
safe access to drain valve?
14.02
14.04
15.10 Have fire protection systems including but not HSE Yes
limited to sprinkler, deluge and foam systems
been functionally tested and properly
identified?
16.02 Is there more than one route of escape from HSE Yes
any sizable area or platform?
16.08 Are handrails, ladder rails, etc. free of any HSE Yes
abrupt finger catchers?
18.02 Have provisions been made for disposal of all HSE Yes
wastes including construction waste, startup
wastes, off spec product, excavated dirt/
gravel etc.?
18.08 Are all Oily Water Sewer (OWS) drain hubs HSE Yes
filled with water?
18.09 Has the Oily Water Sewer/ Storm Sewer Plot HSE Yes
Plan been redlined for “as-built” changes?
19.05 Has the area been cleared of litter such as HSE Yes
bottles, cans or other trash? (a general
housekeeping inspection should be
performed)
19.08 Have all gas cylinders either been removed HSE Yes
or properly stored and secured, and properly
capped if not in use?
19.16 Are personnel protected from contact with hot HSE Yes
surfaces?
19.21 Are there any other safety concerns with this ALL N/A
change?
20
Remarks/ Reference
Others: Yes No N/A Yes No N/A Reviewer Comments Actions Responsible Category Status/Target
Documents
A HSE Yes
B Oper Yes
Are personnel for phase-1 startup available,
adequate, and qualified?
C Oper Yes
Are phase-1 operations personnel available,
adequate, and qualified?
D Oper Yes
Is Phase-1 Startup Organization Chart
available?
E Oper Yes
Are personnel for phase-2 startup available,
adequate, and qualified?
F Oper Yes
Are phase-2 operations personnel available,
adequate, and qualified?
G Oper Yes
Is Phase-2 Startup Organization Chart
available?
J Are battery limits for first gas in, transition, Oper Yes
and phase-2 start up available and
approved?
M Flowline: N/A
AR Well to Manifold Pipeline
N Pipeline: N/A
Manifold Pipeline to CPP
O Trunkline: N/A
CPP to Metering JBL