You are on page 1of 11

Tunnelling and Underground Space Technology 50 (2015) 68–78

Contents lists available at ScienceDirect

Tunnelling and Underground Space Technology


journal homepage: www.elsevier.com/locate/tust

Excavation cycle times recorded during sinking of a deep shaft in


crystalline rock – A case example at Ventilation Shaft of Mizunami URL,
Japan
H. Sanada a,⇑, T. Sato a, Y. Horiuchi a, S. Mikake a, M. Okihara b, R. Yahagi b, S. Kobayashi b
a
Japan Atomic Energy Agency, 1-64 Yamanouchi, Akiyo, Mizunami, Gifu 509-6132, Japan
b
Shimizu Corporation, 2-16-1, Kyobashi, Cyuoku, Tokyo 104-8371, Japan

a r t i c l e i n f o a b s t r a c t

Article history: Realistic and properly planned excavation cycle times developed prior to tunnel construction are an
Received 2 September 2014 important issue for dependable project management, including cost estimation and time saving.
Received in revised form 1 May 2015 Existing design studies, conducted to estimate the total cost for geological disposal, have been limited
Accepted 30 June 2015
to estimates of approximate construction total time schedules. There were no case studies which com-
pared the detailed excavation cycle time used in design studies with the actual results from an excavation
taking into account each excavation cycle operation and task. In this paper, analyses of actual cycle time
Keywords:
recorded during the sinking of the Ventilation Shaft of the Mizunami Underground Research Laboratory
Geological disposal
Mizunami URL project
and comparison with the planned cycle time developed in the design stage are intended for an evaluation
Crystalline rock of the baseline work plan and schedule and for optimization of the calculations for application to shaft
Shaft sinking construction in any future repository in Japan. Actual times to perform three operations, drill and blast,
Excavation cycle time muck removal and concrete lining emplacement were much larger than expected and represent the lar-
gest portion of the total excavation cycle time and had the largest impact on the efficiency of the exca-
vation cycles and schedules. Operating at increasingly greater depths and excavating harder, more
competent rock combined to significantly affect the shaft sinking speed. The underlying reasons for
increases in actual times for the excavation cycle operations compared to their design estimates fall into
three categories: constraints on construction; to ensure safety; and maintenance.
Ó 2015 Elsevier Ltd. All rights reserved.

1. Introduction conducted to estimate the total cost for geological disposal, have
been limited to estimates of approximate construction total time
Realistic and properly planned excavation cycle times (here- schedules. There were no case studies which compared the
after, Ect) developed prior to tunnel construction are an important detailed Ect used in design studies with the actual results from
issue for dependable project management, including cost estima- an excavation taking into account each excavation cycle operation
tion and time saving. Especially, if the design phase Ect signifi- and task as discussed in this paper. Moreover, recent examples of
cantly underestimates the actual Ect, there could potentially be a the excavation of deep shafts similar in size to those for HLW
huge, negative impact on the project, i.e., potentially, a big financial repositories are decreasing in Japan since there have not been
loss in a large tunnel project such as one for the geological disposal any new coal mines developed in Japan for over 20 years
of HLW (High-level radioactive waste), with inherently huge (Sakurai et al., 2009).
underground excavations in a rock mass. Therefore, minimizing In this paper, analyses of actual Ect recorded during the sinking
Ect differences between plan and actual are required in design of the Ventilation Shaft of the Mizunami Underground Research
studies of tunnel excavation. Laboratory (MIU) and comparison with the planned Ect developed
Existing design studies (Harmon and Lazur, 1984; Kim and Choi, in the design stage are intended for an evaluation of the baseline
2006; Kukkola and Saanio, 2005; NIREX, 2005; Read, 2011), work plan and schedule and for optimization of the Ect calculations
for application to shaft construction in any future repository in
Japan. The comparison includes not only a review of the Ect but
⇑ Corresponding author. also a review of the method and underlying assumptions used to
E-mail addresses: sanada.hiroyuki@jaea.go.jp, sanada0924@hotmail.com
(H. Sanada).

http://dx.doi.org/10.1016/j.tust.2015.06.012
0886-7798/Ó 2015 Elsevier Ltd. All rights reserved.
H. Sanada et al. / Tunnelling and Underground Space Technology 50 (2015) 68–78 69

calculate the cycle times in the design process and comparison Extensive hydrothermal alteration of the intrusive rock and in the
with the actual construction results. fault zones in the Main Shaft is evident by the abundance of clay
The Mizunami Underground Research Laboratory (MIU), an minerals. Rock strength, i.e., the uniaxial compressive strength, is
‘‘off-site’’ URL, constructed and operated by Japan Atomic Energy usually less than 3 MPa on average, in the hydrothermally altered
Agency (JAEA) at Mizunami City in Gifu Prefecture, central Japan, zones in the Main Shaft. This is much less than in the rock from
involves a comprehensive research program of investigations in a the Ventilation Shaft where it is in the order of 173 MPa (Hirano
deep underground crystalline rock environment for R & D into geo- et al., 2009; Tsuruta et al., 2009). In addition there is no soft,
logical disposal of High Level radioactive Waste (HLW). The MIU is hydrothermally-altered rock as in the Main Shaft (Fig. 1). This paper
being developed and operated in three overlapping phases: discusses Ect during sinking of the Ventilation Shaft where sound,
Surface-based Investigation phase (Phase I), Construction phase high strength granite, without hydrothermally-altered, low
(Phase II), and Operation phase (Phase III) with a total duration strength rock, is distributed.
of around 20 years. The overall project goals of the MIU Project From the pattern of structural development and spatial distri-
in Phases I through III are: (1) to establish techniques for investiga- bution of fractures, the Toki granite in the MIU is divided into
tion, analysis and assessment of the deep geological environment two domains, namely the Upper Highly Fractured Domain
and (2) to develop a range of engineering technologies applicable (UHFD) and the Lower Sparsely Fractured Domain (LSFD)
to deep underground environments in Japan (Saegusa and (Tsuruta et al., 2013b). According to Tsuruta et al. (2013b), there
Matsuoka, 2011). is a high frequency of low angle fractures in the UHFD due to pres-
The MIU consists of a circular Ventilation Shaft (4.5 m diameter) ence of sheeting joints. This is reflected in the results of well log-
and a Main Shaft (6.5 m), both with 0.4 m thick concrete lining, and ging during Phase I in which investigations indicated there is
horizontal tunnels connecting the shafts every 100 m depth high porosity in the UHFD. Fracture frequency is lower below
(Matsui et al., 2011). Excavation of the Ventilation and Main GL-460 m, the boundary between the UHFD and the LSFD in the
Shafts reached GL-500 m in FY2011. During Phase I, the design Ventilation Shaft (Fig. 2).
work for surface and underground facilities in the MIU was com-
pleted with the aim of providing a foundation for engineering tech-
nologies to safely construct and operate a deep underground 2.2. Excavation method and procedures
facility built for the purpose of data acquisition and demonstrating
disposal technologies (Saegusa and Matsuoka, 2011). The design The excavation cycle and component operations are illustrated
work incorporated development of Ect estimates prior to MIU con- in Fig. 3 and are as follows:
struction as a basis for estimating overall costs and schedule
requirements for the proper operating management of the MIU. (i) Drill and blast operations
Repositories for the geological disposal of HLW will include ver-
tical access shafts and/or ramps and disposal rooms, which are an A shaft jumbo with two hydraulic drifters is used for drilling
assemblage of disposal tunnels comprising the underground facil- blast holes. After they are drilled, rock mass blasting is done using
ities (NUMO, 2013; Svensk Kärnbränslehantering AB, 2009). non-electric detonators and water gel explosives. All equipment
Vertical access shafts will be utilized to transport the HLW, buffer (e.g. dewatering pumps) are removed from the shaft, and protec-
and backfill materials and for mucking operations during construc- tive mats are placed prior to blasting to prevent muck scattering.
tion and for access to the repository. Use of vertical shafts will be Moreover blasting is only carried out after the scaffold has been
essential from the viewpoint of ventilation and personnel access raised from 20 to 30-m above the shaft face to prevent damage
and vertical shafts make it possible to effectively excavate at from fly-rock and pressure shocks induced by blasting to the scaf-
increasing depths during the construction phase and to transport fold. After blasting, a fan at surface in the soundproof housing over
the HLW to the disposal panels during the operation phase. the Ventilation Shaft and local fans in the Sub Stages were used to
Discussion of the cycle time during shaft sinking is important for ventilate the air in the shaft. Workers are allowed to enter five
the future geological disposal project, therefore the authors under- minutes after blasting.
took the challenge of discussing, recording and validating the Ects
in the MIU with the goal of providing relevant input to shaft con- (ii) Muck removal operations
struction in a future HLW geological disposal project.
The shaft mucker attached to the bottom of the scaffold and the
kibble removes muck after each drill and blast cycle for disposal at
2. Construction of the MIU surface. A mini-backhoe is transported from the surface to the
shaft face for scaling to dislodge any loose rock from the shaft wall
2.1. Geological setting of the study site and trim rock from the walls to the design shaft diameter. And then
the kibble, filled with muck, is hoisted from the shaft face to sur-
The bedrock at the MIU site consists of the widely distributed face. Muck is deposited in a temporary yard through the chute in
Toki granite (Upper Cretaceous to Lower Paleogene) and overlying the derrick over the shaft before loading into dump trucks for
Miocene sedimentary rocks, the Toki, Akeyo and Hongo transport off-site.
Formations of the Mizunami Group. Pleistocene gravel of the Seto
Formation overlies the bedrock (Tsuruta et al., 2013a). Fig. 1 pro- (iii) Shaft wall mapping, drainage mat installation
vides a vertical cross-section of the Ventilation and Main shafts
and horizontal Sub Stages connecting both shafts in the MIU below Geologists map the shaft wall by sketching and photographing
the unconformity at GL-168 m between the Mizunami Group and fractures on the shaft wall and recording information on lithologies
the Toki granite. The general geology of the Main shaft is also shown, and structures and thus obtain data necessary for rock mass classi-
indicating the distribution of faults and fault zones. There are many fication (e.g. RMR (Bieniawski, 1989) etc.) and hydrogeological
differences in the geological conditions in the Main and Ventilation characterization. Drainage mats installed along the shaft wall help
Shafts with respect to hydrothermal alteration. Intrusive rock (lam- to remove any groundwater inflow into the shaft. Anchor bolts are
prophyre) exists along the fault plane only in the Main Shaft. installer quickly with two to secure the required piping.
70 H. Sanada et al. / Tunnelling and Underground Space Technology 50 (2015) 68–78

Fig. 1. Cross-section view of the Ventilation and Main Shafts with generalized geological map of the latter.

(iv) Concrete lining rounds, and the other activities mentioned above. First, the con-
crete formwork still in place from the previous pour is removed
Concrete lining, 2.6-m high and 0.40-m thick, is poured in place and moved up and out of the way for cleaning. Then the cleaned
against the shaft wall using slip forms after the two 1.3-m blast slip forms are moved into place using an electric winch prior to
H. Sanada et al. / Tunnelling and Underground Space Technology 50 (2015) 68–78 71

pouring the new concrete lining. Concrete, transported by truck


from the surface mixing plant is placed in the kibble for transport
to the hopper in the shaft scaffolding.

3. Excavation cycle times in design

Ect derived in planning during the design phase was based on


construction results for shafts in Japan (e. g. Ventilation Shafts in
express highways for Japan Highway Public Corporation) and
interviews with several contractors in Japan. Ect in the design
phase also took into consideration the rock mass classification
developed by the Central Research Institute of Electric Power and
referred to as the ‘‘Denken system’’ in English (Japanese
Geotechnical Society, 2004; Cai et al., 2004). According to the
‘‘Denken system’’, rock mass in the Ventilation Shaft in the MIU
is categorized as ‘‘CH class’’ between GL-200 m to GL-460 m depth
and ‘‘B class’’ between GL-460 m to GL-500 m depth. Thus ‘‘CH
class’’ and ‘‘B class’’ correspond to the UHFD and LSFD, respectively.
Fracturing in ‘‘B class’’ is less well developed than it is in ‘‘CH
class’’; in other words, the rock mass condition in ‘‘B class’’ is better
than ‘‘CH class’’.
Table 1 is a summary of the planned and actual Ect in the gran-
ite area of the Ventilation Shaft. Table 1 provides the excavation
cycle in terms of a work breakdown structure, that is, how the
work was broken down into work packages (operations) and tasks
as follows.

(a) Drill and blast: (1) preparation, (2) cleanup, (3) drilling blast
holes using shaft jumbo, (4) blasting (includes placing explo-
sives) and ventilation after blasting.
(b) Muck removal: (5) removal of fly-rock from lining, (6) prepa-
ration, (7) muck removal using shaft mucker and kibble, (8)
survey work, (9) cleanup, (10) shaping bottom wall.
(c) Shaft wall mapping: (11) clean shaft wall, (12) preparation,
(13) shaft wall mapping, (14) cleanup.
(d) Drainage mat: (15) preparation, (16) installing drainage mat,
(17) cleanup.
(e) Concrete lining: (18) clean and install formwork, (19) prepa-
ration, (20) pumped concrete, (21) cleanup.
(f) Other operations: (22) additional operations and/or tasks not
included in the above, and not done in every excavation
cycle (e.g. niche excavations) or auxiliary operations (e.g.
scheduled and unscheduled maintenance).

4. Recorded excavation cycle times

Comparison of the planned Ect and the actual excavation


results, on average, are provided in Table 1. Fig. 4 illustrates Ect
for the operations performed in each 2.6-m excavation cycle and
others at specific locations in the shaft and how the total times var-
ied with depth. The main difference in the planned cycle times
developed in the design phase compared with the actual is in
two of the main activities (#3) Drilling and (#7) Mucking opera-
tions in the UHFD and LSFD.
With respect to (#3) Drilling, since the number of blast holes
per m2 of excavated area required for effective rock breakage
was 3.0 in the UHFD and 3.2 in the LSFD per cycle, excavating in
the LSFD required more overall cycle time than in the UHFD.
With respect to mucking operations, since the volume of broken
rock to be removed (muck volume) was 109.4 m3 in the UHFD
compared to 112.7 m3 in the LSFD per cycle, mucking in the LSFD
Fig. 2. Fracture map in the Ventilation Shaft spanning the boundary between the added more to the overall cycle time than in the UHFD. The sum
UHFD and LSFD. of the average recorded actual times for all tasks in the UHFD
72 H. Sanada et al. / Tunnelling and Underground Space Technology 50 (2015) 68–78

Fig. 3. Shaft sinking procedures using the short-step method at the MIU.

and the LSFD is 3507 min and 3910 min, respectively, and the increased, and thus extended the schedule. In particular, the exca-
actual work time was twice as long as the estimate in the design vation rate below GL-460 m, was slowest of all. It was assumed that
plan of 1819 min (Table 1). In particular, the total time required both increased depth and more competent rock mass conditions
was long in special excavations such as for shaft insets, that is, contributed to reduction in excavation rates.
the locations where the shaft and horizontal sub-stages intersect, Fig. 6a presents the actual drill and blast times with depth.
and for pump niches, and for auxiliary work such as for pipework Average times in the UHFD and the LSFD are 676 min (137% of
extensions and maintenance work (Fig. 4). plan) and 871 min (172% of plan), respectively (Table 1). In the
The proportion of actual cycle times recorded, the sum of aver- Ventilation Shaft, depth increased 2.6-m every excavation cycle,
ages, is drill and blast (20%), muck removal (44%), shaft wall map- with each cycle consisting of two consecutive 1.3-m drill and blast
ping (7%), drainage mat (2%), concrete lining (15%) and other rounds. Depending on the shaft sinking progress after each excava-
operations (12%) for each of the main operations as a percent of tion cycle, adjustments could be made to the number and length of
the total Ect from GL-200 m to GL-500 m. The operations that took blast rounds and thus adjusting the excavation cycles to maintain
the longest, occupying the largest area are drill and blast, muck consistency in the shaft deepening progress. Concretely speaking, if
removal and installation of concrete lining. These three operations excavation progress in two consecutive 1.3-m blast rounds sub-
have a major influence on total Ect and hence on schedule. Almost stantially exceeded 2.6 m, the number of blast rounds was reduced
all actual operations and tasks took longer than estimated in the from two to a single blast round in the next cycle with length of the
design plan (see percent increase of result to design in Table 1). blast round increased in proportion to the extra length of the prior
Fig. 5 shows the relationship between excavation depth and excavation cycle, thus ensuring that excavation progressed in
date, and average excavation rate per month during sinking of the 2.6-m deep excavation steps. Times less than the design times
Ventilation Shaft. The average excavation rate per month shown shown in Fig. 6a correspond to single-blast cycles (purple circles
in Fig. 5 does not include special operations such as construction in Fig. 6a). Average time was 749 min for the double blasting.
of shaft insets, pump niches, and grouting. The rates between Special activities such as pump niche and shaft inset construction
GL-200 m to -300 m, GL-300 m to -400 m, GL-400 m to -460 m, required more time. The average of 871 min in the LSFD is longer
and GL-460 m to -500 m were 18.3 m/month, 19.3 m/month, in comparison to the 676 min in the UHFD (Fig. 6a). The reasons
17.0 m/month, and 13.6 m/month, respectively (Fig. 5). Therefore, could be due to a combination of excavating in more competent,
the excavation rates deeper than GL-300 m decreased as depth intact rock due to decreased fracture frequency below GL-460 m
H. Sanada et al. / Tunnelling and Underground Space Technology 50 (2015) 68–78 73

Table 1
Summary of design estimates and average actual work time in minutes for each task in an excavation cycle. Average time calculated does not include time for special operations
such as construction of shaft insets, pump niches and extension of pipe work.

Design Result
GL 200 m to 460 m GL 460 m to 500 m GL 200 m to GL460 m GL 460 m to 500 m
(CH class; UHFD) (B class; LSFD)
Design Design Result Increase rate of Result Increase rate of
(avg.) result to design (avg.) result to design
Drill and blast (1) Preparation 80 80 142 178% 150 188%
(2) Cleanup
(3) Drilling blast holes 222 236 311 140% 403 171%
(4) Blasting and ventilation 190 190 223 117% 318 167%
Subtotal 492 506 676 137% 871 172%
Muck removal (5) Removal of fly-rock from lining – – 156 – 190 –
(6) Preparation 60 60 72 120% 74 123%
(7) Muck removal by shaft mucker and 662 686 1215 184% 1272 185%
kibble
(8) Survey work 50 50 16 32% 60 120%
(9) Cleanup – – 57 – 72 –
(10) Shaping bottom wall 30 30 26 87% 21 70%
Subtotal 802 826 1542 192% 1689 204%
Shaft wall (11) Clean shaft wall – – 13 – 19 –
mapping (12) Preparation 180 180 20 23 127%
(13) Shaft wall mapping 188 127% 185
(14) Cleanup 20 20
Subtotal 180 180 241 134% 247 137%
Drainage mat (15) Preparation 7 7 15 214% 16 229%
(16) Installing drainage mat 28 28 52 186% 33 118%
(17) Cleanup – – 14 – 15 –
Subtotal 35 35 81 231% 64 183%
Concrete lining (18) Clean and install formwork 70 70 153 219% 122 174%
(19) Preparation 41 41 65 159% 51 124%
(20) Pumped concrete 109 109 227 208% 226 207%
(21) Cleanup 30 30 115 383% 126 420%
Subtotal 250 250 560 224% 525 210%
Other operations (22) Additional operations and/or tasks not 60 60 407 678% 514 857%
included in the above
Subtotal 60 60 407 678% 514 857%
Total 1819 1857 3507 193% 3910 211%

and the increased travel time with depth. The actual drill and blast average of 551 min exceeds the design estimate of 250 min. Note
times per cycle, for (#3) Drilling and (#4) Blasting and ventilation, that special activities such as niche and shaft inset construction
shown in Table 1 are due to the differences in the fracture domains. required additional form work and concrete than for the standard
Fig. 6b shows actual muck removal times per cycle with depth. 2.6-m excavation cycle and thus increased the Ect and conse-
Average muck removal times in the UHFD and in the LSFD were quently, extended the schedule. The concrete lining operation
1542 min and 1689 min, respectively, and approximately twice proved to be the least accurately estimated operation in the plan-
as long as the design estimates (Table 1). It can be seen in ning stage, having actual times, on average, exceeding the planned
Table 1 that ‘‘(#7) Muck removal by shaft mucker and kibble duration by more than 200%.
required the most time, 1215 min and 1272 min in the UHFD and
the LSFD, respectively, of all the tasks in all operations identified
in Table 1. 5. Discussion – differences between design and actual
The variations in the actual durations of shaft wall mapping per excavation cycle times
cycle, with depth, are shown on Fig. 6c. The average of the actual
times, 243 min exceeded the design estimate of 180 min between 5.1. Excavation
GL-200 m to GL-500 m. The actual shaft wall mapping times per
cycle are the closest to the design estimates in the total excavation The average number of blast holes and actual explosive charge
cycle (subtotal: 134% in UHFD, 137% in LSFD). volumes used in the UHFD per excavation cycle were 168 holes
Fig. 6d shows drainage mat installation times per excavation and 2.11 kg/m3, respectively. In the LSFD, 212 blast holes and explo-
cycle vs depth. The average actual time per cycle of 77 min is more sive charge volumes of 2.90 kg/m3 were required per excavation
than twice the design estimate of 35 min for installations between cycle, somewhat more than in the UHFD. Although the planned
GL-200 m to GL-500 m. The average time for the drainage mat blast hole length was 1.6 m, the actual blast hole lengths were mod-
installation task is the shortest of all the operations in the shaft ified from 1.6 m to 1.8 m during the actual construction due to blast
excavation cycles. efficiency considerations. These factors caused an increase in work
Fig. 6e shows the actual and design estimates for the concrete with respect to drilling requirements and placing explosives; there-
lining operation expressed in terms of time vs depth. Similar to fore, considerable additional time was required for drill and blast
the other excavation cycle operations, the actual times and their activity in this cycle representing a significant increase in time in
74 H. Sanada et al. / Tunnelling and Underground Space Technology 50 (2015) 68–78

shown in Fig. 7, if a line is drawn orthogonally from the bottom of


the blast hole (V-cut), it would intersect the shaft wall at point
‘‘a’’ below the shaft face as shown in Fig 7. A short drill length of
1130 mm was generally, just achieved. In other words, drilling
and blasting in the constricted conditions in the Ventilation Shaft
reduced workability. Therefore, more blast holes, larger explosive
charge volumes and blast hole length were required.

(2) Loading muck bucket

The capacity of the muck bucket (the kibble) used in the


Ventilation Shaft is only 0.2 m3. It is therefore necessary that the
muck be finely comminuted to ensure efficient use of the small size
kibble. Therefore the number of blast holes and explosive charge
volumes were increased and thus the size of the muck was reduced
to enhance the loading efficiency. The larger number of blast holes,
increased explosive charge volumes and blast hole length due to
(1) and (2) above lengthened the timeline for the drill and blast
operation, thus increasing the shaft Ect.

5.2. Muck removal operation

The number trips made by the kibble and the rock volume con-
version rate (the bulking factor), L, will be described with depth. As
a rule, rock volumes will increase compared to in situ rock volumes
due to blasting and fragmentation of the rock and generation of
loose rock conditions in the muck. In this paper, rock volume con-
version rate of normalized value was used to estimate the muck
removal volume. Volume of mucked rock and rock volume conver-
sion rate were calculated as follows:

T ¼ M  Vk ð1Þ

where T is total volume of muck (m3), M is number of kibble trips,


and Vk is volume of muck in the kibble (m3).

T
L¼ ð2Þ
C þ Asi  l
where L is rock volume conversion rate, C is designed concrete
placement volume (m3), Asi is designed cross-sectional area of the
shaft (m2), and l is designed progress length of shaft (m).
In design, the assigned Vk for estimating was 2.0 m3 but the
Fig. 4. Depth distribution of excavation cycle times in the Ventilation Shaft with
actual Vk was reduced to 1.6 m3 (80% of design) for work safety
excavation cycle operation represented by colored squares. Times for special and
auxiliary operations (e.g. construction of pump niches and shaft insets every 100-m considerations, that is to minimize kibble overloading and the risk
depth, maintenance) that caused an increase in total cycle time are included in this of muck falling from the kibble while being hoisted. Therefore, the
graph. number of actual trips for the kibble was expected to increase by
about 20%. However, the actual average number of trips to remove
muck using the kibble in the UHFD and in the LSFD was 54 and 53,
respectively. These are less than the design estimate of 53 in the
comparison with the planned drill and blast activity in the excava-
UHFD and 58 in the LSFD. This is not what was expected.
tion cycle. The reason why the number of blast holes, explosive
The explanation lies in the rock volume conversion rate. The
charge volumes and blast hole lengths increased in excess of the
actual results, on average, were 1.33 and 1.38 in the respective
design, as mentioned above, are summarized as follows:
fracture domains, representing a decrease of about 20% compared
to design. The reason is that the large blast energy released due
(1) High drill angle for blast holes in the confined area of the
to increase in the number and length of blast holes and explosive
Ventilation Shaft
charge volumes greater than the design, as described in
Since the range of movement and the workability of the shaft Section 5.1, resulted in improved fragmentation efficiency. Thus,
jumbo were substantially restricted due to the presence of the con- the drill and blasting operation is the factor resulting in an
crete lining and the forms, resulting in the small diameter of the improved rock volume conversion rate and suppression of the
Ventilation Shaft, a drill angle of 70° is the shallowest angle possible number of kibble trips to a level lower level than design, despite
for the center-cut (V-cut) around the middle of the shaft excavation the decreased volume of muck in a kibble, Vk. From the reason
(Fig. 7). In contrast, a standard drill angle of 60° is preferred for sink- mentioned above, the factor causing a major difference between
ing shafts. For example, the shaft diameter of 6.5 m in the Main actual working time and design estimate is not related to increas-
Shaft at the MIU, being larger than the Ventilation Shaft diameter, ing muck removal volume and limitation of loading volume in
allowed a drill angle of 60° to be utilized for the Main Shaft. As kibble.
H. Sanada et al. / Tunnelling and Underground Space Technology 50 (2015) 68–78 75

Fig. 5. Excavation progress through time and average excavation rate per month in the Ventilation Shaft.

Fig. 6a. Depth distribution of cycle time for each operation with estimated cycle
Fig. 6b. Depth distribution of cycle time for each operation with estimated cycle
times from design and actual total cycle time averages. Drill and blast time vs depth
times from design and actual total cycle time averages. Muck removal time vs.
for each excavation cycle.
depth for each excavation cycle.

Differences between actual and planned work in design are (2) Use of mini-backhoe with a hydraulic breaker for scaling the
described as follows: shaft wall

(1) Limitation of kibble volume To maintain stability of the shaft wall after blasting, removal of
loose rock from the shaft wall is required. This was conducted
Although the maximum kibble volume is 2.0 m3, muck loads in using a mini-backhoe with a hydraulic breaker for safety reasons.
the kibble were limited to 1.6 m3 during the actual construction for This is a change from the design plan, in which scaling would be
safety considerations as mentioned above. done manually using a pick hammer. Therefore, extra time was
76 H. Sanada et al. / Tunnelling and Underground Space Technology 50 (2015) 68–78

Fig. 6c. Depth distribution of cycle time for each operation with estimated cycle Fig. 6e. Depth distribution of cycle time for each operation with estimated cycle
times from design and actual total cycle time averages. Shaft wall mapping time vs. times from design and actual total cycle time averages. Concrete lining installation
depth for each excavation cycle. time vs. depth for each excavation cycle.

required for moving the mini-backhoe in the shaft, attachment of


the hydraulic breaker, in addition to scaling of loose rock from
the shaft wall.

(3) Limitation on maximum winch hoisting speed

Although design maximum winch hoisting speed was


300 m/min, the speed limit was reduced to 200 m/min for safety.

(4) Supplement for removing blast rock


Before muck removal could be done, fly-rock ejected onto the
concrete lining was removed. The work time for this was over
150 min on average. This work was necessary from a safety per-
spective to mitigate falling rock hazard.

(5) Muck removal from the shaft outer periphery under the con-
crete lining

The removal of muck from the shaft outer periphery under the
concrete lining proved too difficult using the shaft mucker.
Therefore, the mini-backhoe was used for removing the muck from
that region. This required extra time not included in the design
plan to move the backhoe to the shaft face to perform this work.
The five items mentioned above are reasons for significant dif-
ferences between the design and the actual work. With the excep-
tion of (1), these could be the main reason for differences between
Ect derived in design compared to the actual excavation.

5.3. Shaft wall mapping

Actual shaft wall mapping time in almost all excavation cycles


Fig. 6d. Depth distribution of cycle time for each operation with estimated cycle
was longer than allowed for in design. The reason is that although
times from design and actual total cycle time averages. Drainage water pipe shaft wall mapping time of 180 min was considered in design plan-
installation time vs. depth for each excavation cycle. ning, work for tasks ‘‘(#11) Clean shaft wall’’, ‘‘(#12) Preparation’’,
H. Sanada et al. / Tunnelling and Underground Space Technology 50 (2015) 68–78 77

Total drilling time for blast holes Td can be calculated by follow-


ing equation.

Dl  Dn
Td ¼ ð3Þ
Dv
where Dl is drill length of blast hole (m), Dn is number of blast holes
per drifter and Dv is drilling rate (m/min).
Number of blast holes per drifter, Dn, can be defined by the fol-
lowing equation.

As  Dnr
Dn ¼ ð4Þ
J
Fig. 7. Cross-section of the excavation face in the Ventilation Shaft showing blast where As is design shaft excavation area (m2), Dnr is number of blast
hole angle at center V-cut on the shaft face.
holes per m2 and J is number of drifters.
‘‘(#14) Cleanup’’ in Table 1 required more effort than expected,
that is, about 50 min extra in addition to shaft wall mapping. The T m ¼ 1:5  Dn ð5Þ
average time of about 187 min for actual shaft wall mapping in where Tm is the time required for drifter moves between holes. 1.5
each excavation cycle was almost the same as the design time of (min./hole number) means drifter move time between holes.
180 min. Time allocation for shaft wall mapping should include ‘‘(#3) Drilling’’ in Table 1 is the sum of Td and Tm. Since Td and Tm
more than 50 min for any auxiliary tasks, such as mentioned above, are time per excavation length of 1.3 m, the sum should be doubled
in addition to shaft wall mapping, in any future scheduling of Ect. to be representative of a 2.6 m long excavation cycle. The drilling
component of Ect in design for the UHFD and the LSFD were
5.4. Drainage mat installation 222 min and 236 min, respectively. The recalculated estimate is
294 min and 372 min in the UHFD and the LSFD. The actual drilling
Iron plates were installed on the shaft wall with anchor bolts to took 311 min in the UHFD and 403 min in the LSFD, fairly close to
fasten drainage mats. The effort to install the anchor bolts the recalculated estimates based on more realistic actual values for
exceeded the estimated effort due to the greater than expected the drilling.
hardness of the rock. Now, consider the following with regard to ‘‘(#4) Blasting and
ventilation’’ in Table 1
5.5. Concrete lining operation
Dnr Dlr
T br ¼ T bd   ð6Þ
The design concrete volume for the concrete lining per excava- Dnd Dld
tion cycle is 25.0 m3, which took into consideration the possibility
where Tbr is recalculated explosive charge and wire connection, Tbd
of over-break at the periphery after blasting. The average concrete
is explosive charge and wire connection in design, Dnr is number of
placement volume of 23.3 m3, with the exception of the shaft
blast holes (actual), Dnd is number of blast holes (design), Dlr is
insets and pump niches, is almost the same as the design specifica-
length of blast holes (actual) and Dld is length of blast holes (design).
tion of 25.0 m3. Therefore, the basis for the design estimates,
The design estimate was 190 min (blasting and ventilation of
including likely overbreak estimates, were fundamentally correct.
80 min, and others of 110 min) for this task in the drill and blast
The reason why concrete lining work was more time consuming
operation. Recalculation of the estimate yields effort of 233 min
than was allowed for in design is because of the difference between
and 263 min in the UHFD and the LSFD. Actual work time was
the construction method proposed in design and the actual method
223 min and 318 min in the UHFD and the LSFD. Thus, recalcula-
employed, since the actual concrete placement volume is lower
tion using actual values is much closer to the actual blasting and
than the design estimate.
ventilation times in the excavation cycle.
(1) Maximum hoisting speed

7. Concluding remarks
Although maximum hoisting speed was 300 m/min in design, as
noted for the mucking operations, the winch speed was limited to
This paper describes the results of the analysis of Ect and a
200 m/min for safety reasons.
breakdown of excavation cycle time by task during the sinking of
the Ventilation Shaft in the MIU and discusses differences between
(2) Cleanup
design and actual times. The results obtained are summarized as
Removal of slip forms for concrete lining actually required sig- follows:
nificantly more time than estimated in the design. As shown in
Table 1, the actual time required is around 400% more than in (1) Average cycle time for all excavation cycles in the UHFD
the design. required about 3500 min, which is twice as long as the
design estimate. Actual times to perform three operations,
6. Recalculation of cycle time for drill and blast considering drill & blast, muck removal and concrete lining were much
actual blasting conditions larger than expected and represent the largest portion of
the total excavation cycle time and had the largest impact
In Section 5, the difference between design and actual effort are on the efficiency of the excavation cycles and schedules.
described. With respect to blasting efficiency, actual drill and blast- (2) Excavation rate declined with increasing depth below
ing has been modified. This chapter provides a description of the GL-300 m. In particular, large decreases in excavation rate
recalculation using the actual blasting circumstances. Consider occurred at depths greater than GL-460 m, the boundary
the following with regard to (#3) Drilling blast holes in Table 1: between the UHFD and the LSFD where there is a substantial
78 H. Sanada et al. / Tunnelling and Underground Space Technology 50 (2015) 68–78

decrease in fracture frequency. It is apparent that the Acknowledgements


increase in depth and in rock strength had a significant role
in the decline in excavation speed. The authors thank Glen McCrank, ex-JAEA International Fellow,
(3) For the drill and blast timeline, recalculation of the estimate and anonymous reviewers for improving the manuscript.
using the actual number of blast holes and their length
yields much more realistic estimates, that is, times that are References
closer to the actual times expended in the excavation cycles.
It is suggested that realistic operation times can be esti- Bieniawski, Z.T., 1989. Engineering Rock Mass Classifications. Wiley, New York.
Cai, M., Kaiser, P.K., Uno, H., Tasaka, Y., Minami, M., 2004. Estimation of rock mass
mated by evaluation of accurate drill and blast work vol- deformation modulus and strength of jointed hard rock masses using the GSI
umes and methods prior to the actual excavation. system. Int. J. Rock Mech. Min. Sci. 41, 3–19.
(4) The underlying reasons for increase in actual times for the Harmon, L.M., Lazur, E.G., 1984. Testing a predictive model for repository cost – the
waste isolation pilot plant experience. In: Proc. of WM1984, pp. 345–351.
excavation cycle operations compared to their design esti- Hirano, T., Nakama, S., Yamada, A., Seno, T., Sato, T., 2009. Mizunami underground
mates can be ascribed to three categories: constraints on research laboratory project (rock mechanical investigations) – MIZ-1 borehole
construction; safety assurance; and maintenance. investigations. Technical Report JAEA, JAEA-Research 2009-031, 58 p.
Japanese Geotechnical Society, 2004. Method for Engineering Classification of Rock
(a) Constraints on construction;
Mass (JGS: 3811-2004). Japanese Geotechnical Society, 36 p.
– Decrease in blasting efficiency because blast hole Kim, S., Choi, J., 2006. Assessment of the cost of underground facilities of a high-
angles were steep due to restricted work area for level waste repository in Korea. Nucl. Eng. Technol. 38 (6), 561–574.
the drill jumbo. Therefore, the number of blast holes Kukkola, T., Saanio, T. 2005. Cost estimate of Olkiluoto disposal facility for spent
nuclear fuel. Posiva Working Report, Working Report 2005-10, 65 p.
and explosive charge volumes had to be increased Matsui, H., Noda, M., Nobuto, J., 2011. Status of the Mizunami URL construction and
over and above the original design plan. study on engineering technology. In: Proceedings of ITA-AITES 2011 World
– Difficulty removing muck from just below the con- Tunnel Congress/37th General Assembly, pp. 1248–1255.
NIREX, 2005. Cost estimate for a reference repository concept for UK high-level
crete liner. An additional task, the removal and rein- waste/spent nuclear fuel. NIREX Technical Report, 484281, 22 p.
stallation of the backhoe from the Shaft mucker was NUMO, 2013. Safety of the geological disposal project 2010 – safe geological
required to improve mucking efficiency. disposal based on reliable technologies. Technical Report NUMO, NUMO-TR-13-
05, 125 p.
Read, J., 2011. APM conceptual design and cost estimate update. SNC Lavalin
(b) Safety assurance; Nuclear Report, 020606-6100-REPT-0001, 159 p.
– To ensure safety, the hoisting velocity of the winch Saegusa, H., Matsuoka, T., 2011. Final report on the surface-based investigation
(Phase I) at the Mizunami Underground Research Laboratory Project. Technical
was self-regulated and lower than the design plan; Report JAEA, JAEA-Research 2010-067, 377 p.
therefore time required for muck removal and con- Sakurai, S., Shimizu, N., Akutagawa, S., Yoshida, H., Matsui, H., Sato, T., Yamachi, H.,
crete placement for the liner increased. 2009. Investigation on collapse mechanism of super-deep vertical shafts in
Japan. In: Proceedings of the 7th International Symposium on Rockburst and
– Scaling operations entailed substitution of the back-
Seismicity in Mines, August 21–23, Dalian, pp. 1314–1324.
hoe with a hydraulic breaker for trimming the shaft Svensk Kärnbränslehantering AB, 2009. Underground design Forsmark Layout D2.
wall. Removal and reinstallation of the backhoe and SKB Technical Report, R-08-116, 128 p.
set up of the hydraulic breaker increased mucking Tsuruta, T., Takeuchi, S., Takeuchi, R., Mizuno, T., Oyama, T., 2009. Results of the
pilot borehole investigations conducted from bottom of shafts at the Mizunami
time. Underground Research Laboratory. Technical Report JAEA, JAEA-Research 2008-
– To ensure water inflow reduction, unplanned drilling 098, 116 p.
of pilot boreholes for pre-excavation grouting was Tsuruta, T., Sasao, E., Kawamoto, K., Kuboshima, K., Ishibashi, M., 2013. Study on
geology on the Mizunami Underground Research Laboratory Project – geology
required. and geological structure from G.L.-300 m to G.L.-500 m. Technical Report JAEA,
JAEA-Research 2013-014, 78 p.
(c) Maintenance; Tsuruta, T., Tagami, T., Amano, K., Matsuoka, T., Kurihara, A., Yamada, Y., Koike, K.,
2013b. Geological investigations for geological model of deep underground
– Routine equipment maintenance services (e.g. for geoenvironment at the Mizunami Underground Research Laboratory (MIU). J.
Shaft mucker, Pumps etc.) increased as construction Geol. Soc. Jpn. 119, 59–74.
progressed.

You might also like