You are on page 1of 9

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/325570251

Design and Construction of the Billy Bishop City Airport Pedestrian Tunnel,
Toronto, Canada

Conference Paper · October 2014

CITATIONS READS

0 147

1 author:

Andrew Cushing
Arup
25 PUBLICATIONS   15 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Geotechnical Engineering for the Autoroute 30 - Montreal Quebec Canada View project

Tunnels View project

All content following this page was uploaded by Andrew Cushing on 05 June 2018.

The user has requested enhancement of the downloaded file.


Design and Construction of the Billy
Bishop City Airport Pedestrian Tunnel,
Toronto, Canada

Andrew Cushing, Jon Hurt, Robert Talby


Arup, Toronto, Ontario CANADA

Tony DiMillo, Mike MacFarlane


Technicore Underground, Inc., Toronto, Ontario CANADA

ABSTRACT
The Billy Bishop City Airport Pedestrian Tunnel in Toronto is the first known underwater pedestrian tunnel to an airport
facility in the world. It was constructed in the thinly horizontally bedded Georgian Bay Shale formation characteristic of
Southern Ontario, and employed a unique pre-support technique comprised of seven 1.85m diameter interlocking
horizontal secant drift bores, each sequentially drilled by tunnel boring machines and backfilled with mass concrete. This
paper summarizes the key aspects of the design and construction associated with this groundbreaking tunnel project.

RÉSUMÉ
La sous-marin tunnel piétonnier à Billy Bishop de Toronto City Airport est le premier de son genre dans le monde. Il a été
construit dans la formation de la baie Georgienne de schiste de la sud de l'Ontario, qui se caractérise par de minces
literie horizontal, et utilisé une technique de pré-support constitué de sept 1,85 m verrouillage horizontales alésages,
chaque séquence de forage remblayé avec du béton. Ce document résume les aspects clés de la conception et de la
construction associés à ce projet révolutionnaire.

1 INTRODUCTION potential, tunnel construction issues, including TBM drift


bore drilling and concrete backfilling operations, the use of
The Billy Bishop City Airport is located on an island in prefabricated steel rebar cages and steel fiber reinforced
Lake Ontario, and is separated from the downtown concrete in the permanent tunnel lining, and tunnel
Toronto mainland by a 120 meter wide shipping channel. performance monitoring results.
At present, the only access to the airport is by ferry.
However, an airport upgrade project which includes a new 2 PROJECT HISTORY AND PARTICIPANTS
pedestrian tunnel is currently under construction. When it
opens to the public next year, it will provide the first fixed In early 2010, the Toronto Port Authority (TPA)
connection to island airport since its initial opening in announced that it was seeking a private partner to
1939. construct a pedestrian tunnel at the Billy Bishop City
The tunnel, along with two vertical access shafts, has Airport. In July 2011, an agreement involving an exchange
already been excavated through the Georgian Bay Shale of land between the TPA and the City of Toronto
formation, which is characteristic of Southern Ontario and permitted the tunnel project to go forward. Three consortia
the Greater Toronto Area (GTA). The rock is thinly were invited to respond to the Request for Proposal (RFP)
horizontally bedded, under a high in-situ horizontal stress for the project, with bids being submitted in October 2011.
state, and when excavated leads to time-dependent In January 2012, a Public Private Partnership (P3) was
swelling deformation. The 10 meter cut diameter of this formed between the TPA and Forum Infrastructure
tunnel makes it one of the largest excavated in the GTA to Partners, a consortium consisting of Forum Equity
date. Considering the potential for tunnel crown instability Partners (Developer and Equity Partner), PCL
within the bedded shale for this rather large span below Constructors, Inc. (General Contractor), Technicore
Lake Ontario, the tunnel contractor (Technicore Underground (Shaft and Tunneling Contractor and TBM
Underground) proposed a novel construction technique by Manufacturer), Johnson Controls (Facilities Manager),
sequentially drilling a series of seven 1.85m diameter Arup Canada, Inc. (Lead Designer – Structures and
interlocking (secant) drift bores with tunnel boring Tunneling), ZAS (Architect), and EXP (Geotechnical
machines and backfilling them with unreinforced mass Engineer of Record), with groundbreaking for the project
concrete, thereby resulting in an arched roof pre-support. taking place in March 2012.
Conventional excavation methods were used to advance
the main tunnel profile, which consisted of a continuous 3 TUNNEL DESIGN ISSUES AND METHODS
central cut, incremental sidewall excavation and bolting,
and mass invert excavation. 3.1 Introduction
This paper will address the design and construction
aspects of the Billy Bishop City Airport Pedestrian Tunnel, There are two distinctive features of the shale in the
including the analysis methods employed to evaluate the Toronto region. One is a high horizontal stress regime,
tunnel crown stability and tunnel rockwall swelling and the second is long-term time dependent swelling
behavior which occurs upon stress relief of the rock mass cut (no. 1) between main tunnel springline and invert level
and availability of fresh water. and left open to provide both a void for the rockbreaker
excavating the central cut to break into and a temporary
3.2 Horizontal Bedding of Rock Mass ventilation duct for dust control during excavation.
Temporary support within each drift bore consisted of
The short term kinematic stability of the backfilled TBM- 1.2m x 2.4m sheets of 10mm thick plywood placed
driven secant bore arch was assessed on the basis of lengthwise along the crown of each drift bore and
numerical modeling using the discrete (distinct) element expanded into place with circular steel ribs placed at 1.1m
program UDEC by Itasca Consulting Group, which offers spacing immediately behind the tail shield of the TBM
the advantage of modeling the entire construction (Figure 3). This temporary support was provided to
sequence of excavating and backfilling each individual prevent pieces of shale from falling from the crown of the
drift bore, followed by the main tunnel excavation and drift bore. The center-to-center spacing of the four
support as well as the potential to identify kinematic failure primary drift bores allowed for all to be left open
mechanisms. The UDEC analysis also considers stress simultaneously prior to concrete backfilling, with the
and jointing anisotropy of the rock mass and models the vertical load of the rock above being transmitted
progressive stress re-distribution following each temporarily through the rock pillars between adjacent
construction stage. primary drift bores. The steel sets were typically
UDEC uses a constitutive Mohr-Coulomb failure recovered during the retreat from each drift bore just prior
criterion model which does not address the time to backfilling.
dependent deformation (TDD) behavior of the Georgian The structural compression integrity of the secant bore
Bay shale. However, potential kinematic failure arch was paramount to the stability of the main tunnel
mechanisms would be expected regardless of TDD excavation cavity, as it provided vertical support to the
effects. Therefore, the use of UDEC was deemed crown rock load from above. During the excavation of
appropriate to evaluate these kinematic failure each drift bore, some of the rock chips within the
mechanisms. cutterhead were pulverized and subsequently
compressed by the weight of the TBM shield as it
3.3 Time-dependent Deformation (TDD) advanced against the wall of the bore at and below
springline level into the equivalent of a stiff to hard clay of
Hawlader, Lee, and Lo (2003) studied the impact of approximate 25mm thickness. As the presence of any
applied load on the swelling potential of different shale soft layers within the secant bore arch could compromise
samples. They concluded that the applied stress in one its compressive stiffness and hence overall structural
principal stress direction reduces swelling strain not only integrity, the rock abutment wall of each end primary bore
in that direction but also in the perpendicular directions. (3 and 4) and the sidewalls of each of three secondary
Arup contracted the Itasca Consulting Group to implement bores (5, 6, and 7) were cleaned of the aforementioned
the numerical forumulations of Hawlader, Lee, and Lo deleterious materials prior to concrete backfilling
(2003) into the “Swello” module in the FLAC 2D finite operations.
difference progam to evaluate time-dependent swelling Upon completion of drilling each of the three
behavior of the shale rock mass. The results of these secondary crown drift bores (5, 6, and 7), the sidewalls of
analyses, and a comparison to measured values, are these bores were also inspected to ensure sufficient
presented later in the paper. overlap with the concrete backfill of the adjacent primary
drift bores. The design called for a minimum secant
dimension of 300mm, which was governed primarily by
4 TUNNEL CONSTRUCTION DETAILS the minimum concrete shear area required to support the
selfweight of the drift bore arch in the event that it was not
4.1 Drift Bore Drilling and Temporary Support fully engaged in compression. Despite a slight mis-
alignment of the first drift bore, this overlap was achieved.
The tunnel design concept proposed by Technicore
Underground involved the drilling and backfilling of seven 4.2 Drift Bore Backfilling
1.85m diameter drift bores (1 to 7) within the crown of the
main tunnel profile, two lower unfilled drift bores (8 and 9), To avoid having to use the airport ferry to transport
and three main tunnel excavations – center (cut 1), concrete trucks to the island shaft, all drift bore concrete
sidewalls (cut 2), and invert (cut 3) – as shown in Figure backfilling (with a 15 MPa compressive strength) was
1. The drift bores were sequentially drilled using two advanced from within the mainland shaft. Since the
1.85m diameter tunnel boring machines, one of which is vertical position of each drift bore is 5m lower at the
shown in Figure 2, constructed by Technicore mainland portal relative to its position at the island portal,
Underground. Each TBM was fitted with a total of 16 drift bore backfilling operations had to be advanced
300mm diameter disc cutters. through a 3m long concrete bulkhead cast within each
Each of the seven bores followed the same inclination drift bore at the mainland end. To prevent the buildup of
profile of the main tunnel, namely a 1% incline from the drainage water behind the bulkhead prior to concreting, a
mainland portal to approximate mid-length, followed by a small drainage hole was provided within the bulkhead
4% incline leading to the island portal. Lower bores 8 and invert, and the concreting tube was placed within the
9 were drilled at a constant inclination within the central bulkhead crown, terminating just behind its interior end.
As the backfill concrete had to be pumped “uphill” to
overcome a 5m elevation increase over a portal-to-portal
distance of 187m, it had to remain in a fluid state for the
entire backfilling operation of each drift bore - potentially
3
over an 8 hour duration for each 500 m volume.
Technicore Underground’s affiliate Tec-Mix developed a
proprietary concrete mix for the drifts which allowed for
long duration fluid properties for pumping uphill, but did
not use traditional high cement content that would have
made the backfilled drifts difficult to mine through.
For the very first backfilling operation, a second
concreting pipe was placed within the bulkhead crown
which extended along the entire 1% grade and through
the transition zone to the start of the 4% grade segment.
This secondary pipe was installed in case the fluid
concrete could not be pushed along the entire 187m
length of the bore, either due to premature setting or
difficulties in overcoming the 5m elevation difference. As
it turned out, this second concreting pipe was not
required, and it was subsequently deleted from all
remaining six drift bore backfilling operations.
Figure 1. Tunnel profile – drifts and main excavation In an effort to ensure complete filling, a tube-á-
manchette (TAM) was installed within the crown of the
first backfilled bore along its entire length to permit
remedial grouting (if necessary), while truncated TAM
tubes were used at the higher (island) end of all
subsequent bores. In fact, during the drilling of the central
secondary bore, a tapered void (400mm maximum depth
at the island portal) was encountered along the final 10m
length of each adjacent backfilled primary bore.
Additional temporary support – in the form of intermittent
wooden wedge blocks, plywood, and shotcrete – was
applied within the sidewalls of the central bore to
accommodate a temporary span width more than double
that of a single bore.
The cumulative duration of drift bore drilling and
backfilling took approximately 6 months, from December
2012 to May 2013.

4.3 Main Tunnel Excavation


Figure 2. One of two 1.85m diameter TBM’s for drift bores Central Cut 1 Excavation

Once drilling and backfilling of the series of seven


interlocking crown drift bores was completed (Figure 4),
excavation of the main tunnel central cut (no. 1)
commenced. This work was advanced from mainland to
island portal over a two month period using a Liebherr 934
excavator with rockbreaker attachment (Figure 5). As a
means of dust control, a positive air stream was induced
toward the island portal through one of the two open drift
bores at/below the main tunnel springline with fans
installed at both the mainland and island portals.
The rock sidewalls were inspected by Arup staff on a
regular basis, and the locations of vertical joints and water
seeps were noted. The primary vertical joint set
(coincident with the major horizontal stress direction) was
oriented transverse to the tunnel axis. During the
excavation of the tunnel, vertical slices of rock typically fell
from the tunnel face, so care was taken not to approach
Figure 3. 1.85m diameter drift bore temporary support the working face too closely.
standardize the geometric profile of the main tunnel
sidewalls, a template was fabricated and hung by a single
sliding, rotating pivot from temporary overhead rails
affixed to the underside of the crown drift bores (Figure 7).
The template was rotated into place against the final (cut
2) sidewall and checked for proper horizontal and vertical
alignment. When the template was not in use, it was
rotated 90 degrees about its vertical axis, slid
longitudinally, and stored against the temporary cut 1
sidewall.
Cut 2 was advanced in 3m increments. After each
incremental excavation, the final tunnel sidewall
excavation was bolted using an upper row of 3.5m long
polyester resin encapsulated steel dowels (32mm bar
diameter) at 1.25m longitudinal spacing, followed by six
rows of 3.5m long Swellex MN24 bolts (installed on a
1.5m staggered grid pattern). After cut 2 had advanced
Figure 4. Completion of secant drift bore backfilling some distance, the heads of the Swellex bolts were cut
and a 50mm thick non-structural sealing layer of
polypropylene fiber reinforced shotcrete was applied to
the exposed shale surface to prevent it from slaking
deterioration.
Invert (cut 3) excavation was advanced using a
backhoe with mini-roadheader attachment (Figure 8), and
took approximately two weeks to complete.

4.4 Tunnel Waterproofing

The waterproofing system for the tunnel is comprised of a


2.5mm thick PVC membrane which is separated from the
shotcreted sidewalls by a layer of geotextile. Ribbed
waterbars were thermally welded to the PVC membrane
around the entire tunnel profile perimeter at 12m intervals,
coinciding with the construction joint locations of the
permanent tunnel arch lining. As the tunnel invert was
poured separately from the tunnel arch, longitudinal
Figure 5. Main tunnel excavation with rockbreaker waterbars were also installed along the entire tunnel
length at the invert-arch interface.
Inspection of the underside of the crown drift bores A gap grouting tube was installed within the crown
indicated regular instances of transverse cracking, most along the entire tunnel length, and remedial grouting
likely resulting from shrinkage of the unreinforced backfill tubes were installed at either side of the ribbed waterbars
concrete. These transverse shrinkage cracks were easily and in the tunnel invert. It should be noted that the shaft
identified, as they were always accompanied by a nominal waterproofing was comprised of an HDPE membrane,
amount of water seepage. As the drift bore crown arch hence a transition detail had to be developed between the
was intended to act solely in compression within the PVC and HDPE membranes. This transition was
transverse plane, the transverse cracks were not of great achieved using an intermediate Dilatec membrane and
concern. Nevertheless, locations where a transverse epoxy paste adhesive. In addition, a remedial grouting
crack intersected multiple bores were instrumented with tube was also installed on the PVC-side of the transition,
additional survey prisms and monitored for relative which can be injected with a polyurethane grout (if
displacement across the crack. No such displacement necessary).
was observed.
4.5 Permanent Tunnel Lining
Sidewall (Cut 2) and Invert (Cut 3) Excavation
The permanent tunnel lining was constructed in two
After the central cut was complete, the main tunnel was general phases. First, the invert was cast in 18m
widened by the removal of the rock sidewalls, indicated as maximum lengths, followed by the tunnel arch, which was
“cut 2.” cast in 12m maximum lengths. The invert and arch pours
Cut 2 sidewall excavation was advanced primarily by a are connected by a shear key. While there is continuity of
reconditioned DOSCO roadheader (Figure 6) as well as rebar over the invert construction joints, there is no
an X-centric rock ripper, and took approximately 2 months continuity between the invert and arch pours or across the
to complete. The final sidewall excavation was achieved arch construction joints. As a means of secondary
with a small grinder attachment on an excavator arm. To
Figure 6. DOSCO Roadheader Figure 8. Tunnel invert excavation

travelling crane with an extendable boom capable of lifting


the rebar mats and cages over a freshly poured section
and placing it on the invert waterproofing membrane
without damaging it. Invert construction, which took
approximately three months to complete, would have
taken several weeks longer if the steel cages had been
tied in the tunnel.
The relatively short tunnel length (187m) did not justify
the purchase of new formwork for the tunnel arch.
Instead, the formwork used for the “Devil’s Slide” Highway
Tunnels (San Mateo County, California, USA) was
purchased and modified by Technicore to suit the profile
of this tunnel. The formwork ran along a pair of rails laid
on the invert (Figure 11).
The tunnel invert and arch were poured to very tight
tolerances, with variations of only a few millimetres
relative to theoretical, as measured by a Faro Focus 3D
High Resolution LiDAR Scan.

5 TUNNEL CONSTRUCTION MONITORING

5.1 Drift Bore Crown Stability during Main Tunnel


Excavation

As the central cut was advanced, a series of three optical


survey prisms were installed within the underside of the
backfilled crown drift bores, along with one in each
temporary cut 1 sidewall, at 20m intervals along the
tunnel. Regular monitoring of these survey prisms during
sidewall (cut 2) and invert (cut 3) excavations indicated a
Figure 7. Tunnel sidewall (cut 2) profile template stable rock mass during the works, as shown by sample
survey results at Station 0+060m in Figure 13. Survey
waterproofing, a bentonite strip was installed at all results were generally within ±3mm of the initial baseline
permanent tunnel lining construction joints. measurements, the variation attributed primarily to the
The invert is comprised of normal concrete, with a precision of the surveying method. Unfortunately, the
minimum 28-day compressive strength of 35 MPa, while initial elastic movement of the drift bore arch crown was
the arch is comprised of steel fiber reinforced concrete (30 not captured during the initial excavation of central cut 1,
3
kg/m fiber dosage) with the same compressive strength. although it is presumed to be significantly lower than the
The invert concrete pour was advanced efficiently predicted value.
using rebar mats and cages pre-fabricated by Technicore
affiliate Ewing Fabricators, which were placed with a
Figure 9. Tunnel invert rebar placement Figure 12. Completed permanent tunnel lining (June
2014)

Figure 10. Tunnel invert concreting

Figure 13. Optical survey data for crown and sidewalls

was with the use of a steel convergence tape. A hole was


drilled into each of the optical survey prism points installed
within the tunnel sidewalls (at approximate springline
level), which was then used to secure each end of the
convergence tape. The tape was manually tightened to a
standard tension using a steel turnbuckle to obtain the
horizontal chord convergence reading.
The change in the horizontal chord dimension as a
function of time (days) after the central (cut 1) main tunnel
excavation is reported in Figure 14. With the exception of
the station 0+060m readings, the horizontal chord
dimension had reduced (converged) by only 1.5mm (or
less) up to 56 days after excavation. The single outlying
reading at 0+060m is believed to result from the west wall
prism point not being fully fixed, as a consequence of a
Figure 11. Tunnel arch formwork and concreting vertical fracture oriented parallel to the tunnel axis behind
the prism point. It should be noted that as the initial
5.2 Main Tunnel Excavation Sidewall Convergence convergence readings were taken anywhere between 7
and 22 days after the cut 1 excavation was advanced at
Manual Convergence Tape any given tunnel station, the initial elastic sidewall
convergence was not captured in these convergence
One method of measuring the horizontal convergence of readings.
the tunnel sidewalls during the main tunnel excavation
Upon excavation of the tunnel sidewalls (cut 2), the
optical prisms installed within the cut 1 sidewalls were
sequentially removed, reinstalled within the cut 2
sidewalls, and rebaselined. Once again, the incremental
horizontal chord convergence of cut 2 sidewalls at
springline level were recorded with time (days after cut 2
excavation), as reported in Figure 15. With the exception
of the data recorded at station 0+020m, the incremental
shortening of the horizontal chord up to 84 days after cut
2 sidewall excavation was 0.75mm or less.
While the manual convergence tape readings reported
in Figures 14 and 15 demonstrate a general trend in the
shortening of the horizontal chord with time, the data are
also characterized by a significant degree of day-to-day
variability, which is attributed to the combined effect of
ambient temperature fluctuations within the tunnel, along
with standard operational errors. The relative effects of
these error sources on the convergence measurements
are more pronounced because of the very small absolute Figure 14. Horizontal convergence tape measurements
values which were recorded. after central (cut 1) tunnel excavation

MPBXs

In an effort to obtain more reliable tunnel sidewall


convergence measurements, two multi-point borehole
extensometers (MPBXs) were installed at station 0+020m
(two tunnel diameters from the mainland portal), one in
each sidewall, in mid-July of 2013. The MPBXs were
installed within 3m long alcoves excavated from the
central cut 1 sidewall to the final main tunnel sidewall (cut
2) profile.
The MPBX data for the eastern wall has previously
been reported by Hurt, et al. (2014), and is updated in
Figure 16. The overall MPBX was 12m in length, with
values of inward deformation (convergence) measured at
the tunnel sidewall and at 2m, 5m, and 8m behind the
wall, all measured relative to a presumed point of fixity
12m behind the wall. Very little wall movement
(~0.05mm) was recorded until the east sidewall cut 2
excavation work was completed both up-station and Figure 15. Horizontal convergence tape measurements
down-station from the 3m long alcove (centered at station after tunnel sidewall (cut 2) excavation
th th
0+020m) between August 29 and September 6 , 2013,
which resulted in approximately 0.1mm of immediate
elastic sidewall movement followed by a nominal degree
of time-dependent movement. A second discrete jump in
the tunnel sidewall movement (~0.2mm) was observed
when the invert (cut 3) was excavated between October
18-19, 2013, which was again followed by time-dependent
movement. The tunnel sidewall was pushed back slightly
during the concreting of the permanent tunnel arch in mid-
March, 2014, but recovered rather quickly;the MPBX
points within the rock mass have since experienced a
nominal residual effect.
After nearly one year of MPBX measurements, the
total inward movement of the eastern wall was only
0.6mm, with about half of this movement being attributed
to elastic movements induced by the sidewall (cut 2) and
invert (cut 3) excavations. The remaining time-dependent
inward movement of the eastern wall (after completion of
the cut 2 sidewall excavation) of approximately 0.25mm is
generally consistent with the typical post-cut2 shortening Figure 16. Updated eastern wall MPBX readings
The numerical procedure of Hawlader, Lee, and Lo
(2003), which was implemented by Arup using the FLAC
2D Swello module, should be viewed as a major
improvement over the older closed-form solution (Lo and
Yuen, 1981), as it considers the non-linear time- and
stress-dependency of the key swelling parameters,
typically resulting in less conservative (but more realistic)
predictions of tunnel sidewall convergence deformation.
Figure 18 shows the large discrepancy in the closed-form
prediction compared to that of the numerical analysis.
After a period of 100 days, the closed-form method had
predicted sidewall convergence values of between 40 and
140mm (a function of the range of input parameters),
Figure 17. Time-dependent tunnel sidewall swell which was far in excess of the refined numerical
deformations - MPBX readings compared to predicted prediction (and MPBX observation) of approximately
values (Hurt, et. al., 2014) 0.25mm after a similar length of time.

of the horizontal chord of less than 0.75mm as indicated 6 SUMMARY


by the manual convergence tape readings (Figure 15).
Figure 17 shows the time-dependent horizontal tunnel This paper has presented several design and construction
sidewall swell deformations (i.e., total deformation minus aspects associated with the Billy Bishop City Airport
elastic deformation) compared to a FLAC 2D Swello Pedestrian Tunnel in Toronto, Canada. The tunnel was
module prediction using the numerical analysis procedure constructed in shale bedrock using a unique system of
of Hawlader, Lee, and Lo (2003). It should be noted that pre-support consisting of seven interlocking secant drift
the tunnel sidewall swelling prediction presented in Figure bores drilled by tunnel boring machines and backfilled
17 was made with the aid of a back-analysis of time- with mass concrete. The construction monitoring results
dependent horizontal free swell measurements obtained demonstrated that the main tunnel cavity excavated
from borehole inclinometers installed in the rock walls of underneath the tunnel arch pre-support was stable. While
the mainland shaft, which suggested a horizontal free the tunnel convergence measurements were far less than
swell potential of between 0.3% to 0.4% (per log cycle those predicted by a closed form solution for rock swell,
time), an in-situ horizontal stress of approximately 5 MPa, they agreed reasonably well with a non-linear time-step
and a critical (swell suppression stress) of about 3 MPa. numerical procedure, with input parameters calibrated
The data in Figure 17 show generally good agreement, with the observed time-dependent vertical shaft wall
with the measured time-dependent MPBX convergence movements.
being somewhat lower than that predicted from the
numerical model. One reason for this is that the ACKNOWLEDGEMENTS
excavated rock walls inside the tunnel were relatively dry,
as there was very little induced damage to the rock mass The writers would like to acknowledge the contribution of
from the roadheader excavation (relative to a drill-and- a number of individuals to the paper, including Seth
blast excavation, for instance), although the mainland Pollak, Sean Lee, and Amirreza Ghasemi (Arup), as well
shaft sidewalls on which the back-analyzed input as Gary Benner, David Marsland, and Joey DiMillo
parameters were based did have adequate access to (Technicore).
freshwater to facilitate swelling.
REFERENCES

Hawlader, B.C, Lee, Y.N., and Lo, K.Y. 2003. Three-


Dimensional Stress Effects on Time-Dependent
Swelling Behavior of Shaly Rock, Canadian
Geotechnical Journal, Vol. 40, pp. 501-511.

Hurt, J., Lee, S., Ghasemi, A., Pollak, S., and Cushing, A.
2014. Time Dependent Movements on the Billy Bishop
Toronto City Airport Pedestrian Tunnel, Ontario,
Canada. North American Tunneling Conference, Los
Angeles, CA, USA.

Lo, K.Y. and Yuen, C.M.K. 1981. Design of Tunnel Lining


in Rock for Long Term Time Effects. Canadian
Geotechnical Journal, Vol. 18, pp. 24-39.
Figure 18. Comparison of tunnel sidewall swell
deformation predictions – closed form solution versus
numerical analysis (Hurt, et. al., 2014)

View publication stats

You might also like