You are on page 1of 9

1

PROJECT TITLE : PROGRAMMABLE LAWN MOWER WITH AUTOMATIC DISPOSAL SYSTEM: A Microcontroller and GPS Aided Device
Group Leader: Fajardo, April Joy D.
Group Member:
1 Bautista, Rhealyn Anne D. 4 Serandon, Patrick Gerard A.
2 Esteban, Erickson R. 5. Torrequimada, Sharmaine B.
3 Santos, Adrian B.
Course Year and Section: ECE-5C
Duration of the Project Sudy: 9 months
Schedule of Activities
Activity # Major Activities Detailed description of the activities Expected Outcput
Sept Oct Nov Dec Jan Feb Mar April May
1 Research and Data Gathering W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W1 W2 W3 W4 W5 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2
Customer/Client/ Target User Identify the target user/ customer or Statistical data; Type of
1.1 Validation client/ project beneficiaries respondents
Location/ Research Setting Identify the location / research Statistics; report on
1.2 Validation setting location
List of Materials/
equipment with
appropriate technical
Identify/Determine the Project specifications according
Requirements and Technical to the project needs/
Project Requirements and Technical Specifications and Review Related design/ List of References
1.3 Specification Analysis Literature and Studies and Past Studies related

2 System Designing and Programming


Identify the software/programming Programing
language to be used and develop the language/Sotware; Flow
2.1 Software Design(If Applicable) flow chart and algorithm chart; algorithm
Identify and draw the process flow, process flow; block
block diagram and schematic diagram diagram. Schematic
2.2 Hardware Design of the project. diagram; pcb design
Assembly and System
3 Implementation
Software Implementation(If
3.1 Applicable) Develop the source code or program Source Code / Progarm

Create the working prototype and working prototype and


3.2 Hardware Implementation construt the miniature of the project miniature
Integrate the hardware and software
part to become a system and conduct
the testing to determine the testing results, data
effectiveness/quality performance interpretation and
4 Integration and System Testing of the project analysis
5 Documentation Record all documents. records; documents 2
3
4
5
6
7
8
9