Professional Documents
Culture Documents
Delft
3 June 2014
Status of the work at Daewoo
Pieter Schelte – block division plan
Pieter Schelte is constructed out of 958 blocks or 102 pre-erection blocks
Pieter Schelte – block outsourcing
Hull assembly at Daewoo shipyard in Okpo, Korea
Quay H
Dock 4
3
5
Dock 1
2
1
4
Quay E
Dock 3
Legend of numbers:
1. Erection of half hull in floating dock No. 3
2. Erection of half hull in floating dock No. 4
3. Joining of the two half hulls
4. Docking dock No. 1
5. Hull launch and mooring for final outfitting
Pieter Schelte portside hull assembly
• Transit from Daewoo to Europe will take place between 6 October and mid
November 2014.
• The stinger, stinger transition frame and topsides lift system will be installed in
Europe upon arrival of the vessel.
Painting of the hull, November 2013
Daewoo shipyard, Okpo, South Korea
Floating out Pieter Schelte from dry dock No. 1, December 2013
Daewoo shipyard, Okpo, South Korea
Cable pulling is ongoing, December 2013
Daewoo shipyard, Okpo, South Korea
Forward bridge, December 2013
Daewoo shipyard, Okpo, South Korea
Installation of the first gantry crane, January 2014
Daewoo shipyard, Okpo, South Korea
Pieter Schelte at berth, February 2014
Daewoo shipyard, Okpo, South Korea
Allseas’ Pieter Schelte alongside the D-quay, March 2014
Daewoo shipyard, Okpo, South Korea
Fitting of curtains in the cabins, March 2014
Daewoo shipyard, Okpo, South Korea
Activating the first DP console screens on the forward bridge, March 2014
Daewoo shipyard, Okpo, South Korea
Load out of the special purpose crane for transport to Daewoo, April 2014
ZPMC, Shanghai, China
Load out of the second and third pipe transfer cranes for transport to Daewoo, April 2014
ZPMC, Shanghai, China
Installation of the starboard hull stinger hinge beam, April 2014
Pieter Schelte, Okpo, South Korea
Installation of the starboard hull stinger hinge beam, April 2014
Pieter Schelte, Okpo, South Korea
Hull turn for installation of the starboard side cranes, May 2014
Daewoo shipyard, Okpo, South Korea
The second gantry crane positioned on board Pieter Schelte, May 2014
Daewoo shipyard, Okpo, South Korea
Aerial view of Pieter Schelte, May 2014
Pieter Schelte, Okpo, South Korea
Status of the owner-furnished equipment
MAN Diesel – main diesels
Scope of work:
• Delivery of 8 20V 32/44CR +1 9L
32/44CR diesel generator sets
Status:
• Delivered to Daewoo in July 2012
Imtech – high voltage equipment and DP system
Scope of work:
• Overall co-ordination and integration
of the power generation and
propulsion package
• Delivery of the high voltage
equipment
• Delivery of Kongsberg DP systems
Status:
• Delivered to Daewoo in July 2012
Rolls Royce – thrusters
Scope of work:
• Delivery of 12 thrusters plus 1 spare thruster
• Delivery of the inboard equipment
Status:
• Delivered to Daewoo in July 2012
Bosch Rexroth – central hydraulic power units
Scope of work:
• Delivery of 2 central hydraulic power units
• Delivery of 2 storage and boost oil units
• Delivery of interconnecting piping and loose components
Status:
• Delivered to Daewoo in July 2012
Bosch Rexroth – central hydraulic power units
Filter skids
SAM Electronics – communication equipment
Scope of work:
• Delivery of the communication systems
Status:
• Delivered to Daewoo in July 2012
Kongsberg – navigation equipment
Scope of work:
• Delivery of the integrated radar
• Delivery of navigation equipment and bridge
consoles
Status:
• Delivered to Daewoo in July 2012
SAM Electronics – integrated network and CCTV
Scope of work:
• Delivery of the integrated network
• Delivery of the CCTV system
• Delivery of the entertainment
systems
• Delivery of the VSAT
communication system
Status:
• Delivered to Daewoo in October
2012
Remacut contract – pipe handling equipment
Scope of work:
• Delivery of the firing line equipment
(excl. tensioners and welding equipment)
• Delivery of the double joint equipment
(excl. welding equipment)
• Delivery of the double joint elevator
Status:
• Delivered to Daewoo in July/September
2012
ZPMC – cranes
Scope of work:
• Delivery of three 50 t pipe transfer cranes
• Delivery of one 600 t special purpose crane
• Delivery of five 50 t and 100 t overhead cranes
• Delivery of two 50 t and 100 t gantry cranes
Status:
• Overhead cranes delivered to Daewoo in September 2012
• First PTC and gantry crane delivered to Daewoo in January 2014
• Last batch of cranes delivered to Daewoo in April 2014.
Load out and seafastening of the overhead cranes, October 2012
ZPMC, Shanghai, China
Stinger, stinger transition frame and related handling
systems
Upper block
Section 2
Section 3
Erndtebrücker Eisenwerke – tubulars for the stinger
Scope of work:
• Fabrication of grade 46 steel tubulars
Status:
• All tubulars delivered
Doosan – stinger forgings, castings, lower blocks
and stinger hinge beams
Scope of work:
• Fabrication of the stinger forgings, castings
and stinger hinge beams
Status:
• Lower blocks delivered in February 2014
• Stinger hinge beams delivered April 2014
Final assembly of the stinger hinge beams, April 2014
Doosan, Changwon, South Korea
Assembly of the lower blocks for the stinger, February 2014
Doosan, Gyeongsangnam, South Korea
Allseas fabrication IJmuiden/Schaap – roller boxes and
upper blocks of the stinger handling system
Scope of work:
• Fabrication of roller boxes for stinger and
stinger transition frame
Status:
• Rollerboxes construction completed;
assembly in progress
• Upper blocks stinger handling system
delivered in November 2013
Load-out of a roller box for the stinger transition frame, January 2014
Allseas Fabrication, IJmuiden, the Netherlands
CMHI – stinger transition frame
Scope of work:
• Fabrication of the stinger transition frame
Status:
• Construction in progress; delivery August
2014
Fitting stiffeners to the stinger transition frame, April 2014
China Merchants Heavy Industry Co., Shenzhen, China
Iemants – stinger
Scope of work:
• Fabrication of the stinger
Status:
• Construction in progress; delivery
November 2014
Stinger fabrication end of May 2014,
progressing section 2
Section 3 progressing end of May 2014
Section 1
coated
Transfer Section 1 to load-out location
Items:
• Cargo platform elevators
• Welding systems
• Stinger winches
• Stinger hinge cylinders/hydraulic power units
• Tensioners
• A&R winches
• Induction heating equipment
• Bevel machine cranes
• Miscellaneous equipment
Status:
• All delivered to Daewoo and installed
Fabrication of welding equipment for the double joint factory, May 2012
HAANE welding systems, Borken-Weseke, Germany
Stinger hang-off winches
Status of the construction of the
cargo barge and the stinger barge
Purpose-built cargo barge
ZPMC
Scope of work:
• Fabrication of the cargo barge (200 m x 57 m x 13 m)
Status:
• Barge launched
Purpose built transportation barge
Widening sections
The cargo barge back in dry dock for final painting of the hull, April 2014
Huarun Dadong Dockyard Company, Chongming, China
Cosco shipyard
Scope of work:
• Fabrication of the stinger barge (150 m x 36 m x 9 m)
Status:
• Barge launched
Stinger barge
Basic dimensions
Size (LBH)
Loa 150 m
Lpp 145 m
Bm 36 m
Dm 8m
Ttransit 3m
Disp_trans 13000 ton
LSW 5500 ton
Wstinger 4500 ton
Installation of stinger and STF using the stinger barge
Launching of the stinger barge, March 2014
COSCO shipyard, Zhoushan, China