Sales Budgeted
For Quartal 2 2018
Schedule 1 Sales Budgeted
April Mei Juni Q2
Sales 8000 9000 10000 27000
Cost/unit Rp 5,000 Rp 5,000 Rp 5,000 Rp 5,000
total Rp 40,000,000 Rp 45,000,000 Rp 50,000,000 Rp 135,000,000
cost move
jan 8000
feb 9000
maret 10000
Schedule 2
Toko Fajar
Production Budget
For Quartal 2 2018
Schedule 2 Production Budgeted
April Mei Juni Q2
Sales 8000 9000 10000 27000
Desired Ending Inventory 240 192 144 144
Total Needs 8240 9192 10144 27144
Less: Beginning Inventory 288 240 192 288
Units to be Produced 7952 8952 9952 26856
Schedule 3
Toko Fajar
Direct Material Purchased Budget
For Quartal 2 2018
Schedule 3 Direct Material Purchased Budget
Dompet Jadi April Mei Juni Q2
Units to be Produced 7952 8952 9952 26856
DM per unit 1 1 1 1
Production Needs 7952 8952 9952 26856
Ending Inventory 192 120 96 96
Total Needs 8144 9072 10048 26952
less: beg Inventory 240 192 120 240
Dm to purchased 7904 8880 9928 26712
cost DM Rp 2,700 Rp 2,700 Rp 2,700 Rp 2,700
Total purchased Dm Rp 21,340,800 Rp 23,976,000 Rp 26,805,600 Rp 72,122,400
24,500,000
Rp 2,265,600.00
Rp 320,000.00
Rp 8,820,000.00
Rp 11,405,600.00
Rp 16,993,600.00
Schedule 9
Toko Fajar
Budgeted Income Statment
For Quartal 2 2018
Schedule 9 Income Statment
sales Rp 135,000,000
Cogs Rp 108,994,471.85
gross profit Rp 26,005,528.15
selling&adm exp Rp 16,993,600.00
net icome Rp 9,011,928.15
Schedule 1
Toko Fajar
Sales Budgeted
For Quartal 2 2018
Schedule 2
Toko Fajar
Production Budget
For Quartal 2 2018
Schedule 2 Production Budgeted
April Mei Juni
Sales 8000 9000 10000
Desired Ending Inventory 240 192 144
Total Needs 8240 9192 10144
Less: Beginning Inventory 288 240 192
Units to be Produced 7952 8952 9952
Toko Fajar
Direct Material Purchased Budget
For Quartal 2 2018
Schedule 3 Direct Material Purchased Budget
Dompet Jadi April Mei Juni
Units to be Produced 7952 8952 9952
DM per unit 1 1 1
Production Needs 7952 8952 9952
Ending Inventory 192 120 96
Total Needs 8144 9072 10048
less: beg Inventory 240 192 120
Dm to purchased 7904 8880 9928
cost DM Rp 2,700 Rp 2,700 Rp 2,700
Total purchased Dm Rp 21,340,800 Rp 23,976,000 Rp 26,805,600
Schedule 4
Toko Fajar
Direct Labor Budget
For Quartal 2 2018
Schedule 4 Direct Labor Budget
April Mei Juni
Units to be Produced 7952 8952 9952
wages per unit Rp 250 Rp 250 Rp 250
total DL Rp 1,988,000 Rp 2,238,000 Rp 2,488,000
Schedule 5
Toko Fajar
Overhead Budget
For Quartal 2 2018
Schedule 5 Overhead Budget
April Mei Juni
Direct labor hour 2783.2 3133.2 3483.2
variable OH rate Rp 11.703 Rp 11.703 Rp 11.703
Budgeted Variable Overhead Rp 32,570.75 Rp 36,666.67 Rp 40,762.59
budgeted Fix Overhead Rp 490,000.00 Rp 490,000.00 Rp 490,000.00
Total Overhead Rp 522,570.75 Rp 526,666.67 Rp 530,762.59
Schedule 7
Toko Fajar
Cost of Goods Sold Budget
For Quartal 2 2018
Schedule 7 COGS Budget
DM Rp 100,119,168
DL Rp 6,714,000
OH Rp 1,580,000.00
manufacturing cost budget Rp 108,413,168
B. Finished goods] Rp 1,162,607.70
goods availbale for sale Rp 109,575,775.70
E. Finished goods Rp 581,303.85
COGS budget Rp 108,994,471.85
Schedule 8
Toko Fajar
Selling and Administrarive Expenses Budget
For Quartal 2 2018
Schedule 8 Selling and Administrarive Expenses Budget
April Mei Juni
budget sales 8000 9000 10000
variable rate Rp 206.96 Rp 206.96 Rp 206.96
total variable selling & adm exp Rp 1,655,703.70 Rp 1,862,666.67 Rp 2,069,629.63
fix selling &adm exp
Salaries Rp 755,200.00 Rp 755,200.00 Rp 755,200.00
Depreciation Rp 106,666.67 Rp 106,666.67 Rp 106,666.67
Rent Rp 2,940,000.00 Rp 2,940,000.00 Rp 2,940,000.00
total fix Exp Rp 3,801,866.67 Rp 3,801,866.67 Rp 3,801,866.67
total selling & adm exp Rp 5,457,570.37 Rp 5,664,533.33 Rp 5,871,496.30
Schedule 9
Toko Fajar
Budgeted Income Statment
For Quartal 2 2018
Schedule 9 Income Statment
sales Rp 135,000,000
Cogs Rp 108,994,471.85
gross profit Rp 26,005,528.15
selling&adm exp Rp 16,993,600.00
net icome Rp 9,011,928.15
Q2
27000
Rp 5,000
Rp 135,000,000
Q2
27000
144
27144
288
26856
Q2
26856
1
26856
96
26952
240
26712
Rp 2,700
Rp 72,122,400
Q2
26856
1
26856
110
26966
250
26716
Rp 700
Rp 18,701,200
Q2
26856
1
26856
95
26951
247
26704
Rp 184
Rp 4,913,536
Q2
26856
2
53712
220
53932
500
53432
Rp 72
Rp 3,847,104
Q2
26856
Rp 250
Rp 6,714,000
Q2
9399.6
Rp 11.703
Rp 110,000.00
Rp 1,470,000.00
Rp 1,580,000.00
Q2
27000
Rp 206.96
Rp 5,588,000.00
Rp 2,265,600.00
Rp 320,000.00
Rp 8,820,000.00
Rp 11,405,600.00