Professional Documents
Culture Documents
Saqib imran.
Construction
Construction is the process of constructing a building or infrastructure. Construction
differs from manufacturing in that manufacturing typically involves mass production of
similar items without a designated purchaser, while construction typically takes place on
location for a known client.
Building construction
Building construction is the process of adding structure to real property. The vast
majority of building construction projects are small renovations, such as addition of a
room, or renovation of a bathroom. Often, the owner of the property acts as laborer,
paymaster, and design team for the entire project.
The key features of structural components of a confined masonry building are discussed below:
Masonry walls
Masonry walls transmit the gravity load from the slab(s) above, down to the foundation (along
with the RC tie-columns). The confined masonry walls are made up of solid clay bricks and act as
bracing panels, which resist horizontal earthquake forces acting in-plane. The walls must be
confined by RC tie-beams and tie-columns and should not be penetrated by significant openings
to ensure satisfactory earthquake performance.
Confining elements
RC tie-columns and RC tie-beams are effective in improving stability and integrity of masonry
walls for in-plane and out-of-plane earthquake effects. These elements prevent brittle seismic
response of masonry walls and protect them from complete disintegration even in major
earthquakes. Confining elements, particularly tie-columns, contribute to the overall building
stability for gravity loads.
Plinth band
Plinth band transmits the load from the walls down to the foundation. It also protects the ground
floor walls from excessive settlement in soft soil conditions and the moisture penetration into the
building.
Foundation
Foundation for confined masonry walls consist of 2" thick plain cement concrete (P.C.C), 9"
thick reinforced cement concrete (R.C.C) which supports stepped brick wall at it's base.
Foundation transmits the loads from the structure to the ground and prevents the structure from
overtopping during lateral shaking from earthquakes.
Taj Mahal is regarded as one of the eight wonders of the world, and some Western historians have
noted that its architectural beauty has never been surpassed. The Taj is the most beautiful
monument built by the Mughals, the Muslim rulers of India. Taj Mahal is built entirely of white
marble. Its stunning architectural beauty is beyond adequate description, particularly at dawn and
sunset. The Taj seems to glow in the light of the full moon. On a foggy morning, the visitors
experience the Taj as if suspended when viewed from across the Jamuna river.
Taj Mahal was built by a Muslim, Emperor Shah Jahan (died 1666 C.E.) in the memory of his
dear wife and queen Mumtaz Mahal at Agra, India. It is an "elegy in marble" or some say an
expression of a "dream." Taj Mahal (meaning Crown Palace) is a Mausoleum that houses the grave
of queen Mumtaz Mahal at the lower chamber. The grave of Shah Jahan was added to it later. The
queen’s real name was Arjumand Banu. In the tradition of the Mughals, important ladies of the
royal family were given another name at their marriage or at some other significant event in their
lives, and that new name was commonly used by the public. Shah Jahan's real name was Shahab-
ud-din, and he was known as Prince Khurram before ascending to the throne in 1628.
SAQIB IMRAN 0341-7549889 4
5|Page
Taj Mahal was constructed over a period of twenty-two years, employing twenty thousand
workers. It was completed in 1648 C.E. at a cost of 32 Million Rupees. The construction
documents show that its master architect was Ustad ‘Isa, the renowned Islamic architect of his
time. The documents contain names of those employed and the inventory of construction materials
and their origin. Expert craftsmen from Delhi, Qannauj, Lahore, and Multan were employed. In
addition, many renowned Muslim craftsmen from Baghdad, Shiraz and Bukhara worked on many
specialized tasks.
The mausoleum is a part of a vast complex comprising of a main gateway, an elaborate garden, a
mosque (to the left), a guest house (to the right), and several other palatial buildings. The Taj is at
the farthest end of this complex, with the river Jumna behind it. The large garden contains four
reflecting pools dividing it at the center. Each of these four sections is further subdivided into four
sections and then each into yet another four sections. Like the Taj, the garden elements serve
like Arabesque, standing on their own and also constituting the whole.
The minarets have an octagonal base and cylindrical body tapering to an eight-sided open
pavilion. The body of the minarets is sectioned by three balconies which create shadows and
interest in an otherwise plain design. An exquisite band of marble inlay and geometric patterns
sporting the chevron design encircle the minaret below the top balcony. The summit of the gold
gilded finial perched on the top of the dome of the Taj Mahal reaches two hundred and twenty
feet [67 meters] above the ground. At the top sits a lotus bud and under this is a water pot. This
arrangement was adapted to the Islamic domain from the 12th century. Its function is purely
decorative, accompanying the form of the dome.
Identification of stone
Quality & quantity & of stone available
It is better to confirm whether the amount and quality of stone required by you is available in the
quarry or not?
Step 1:
To assist in your stacking, sort the stone by size; setting aside the smallest pieces to use as shims
(these will help level unsteady larger stones). Prepare for this activity by stretching well and always
lift using your arms and legs, not your back Shims (shown far right), or smaller stones, help level
unsteady larger pieces.
Step 2:
Map out the design by digging a trench about 6" deep and as wide as your largest stone.
Step 3:
Pack down and level earth. Cut filter fabric at least 3 feet wider than the trench. Lay down filter
fabric inside trench so that excess is on the backside of trench. Filter fabric keeps dirt from
migrating while allowing water to drain through your wall.
Step 4:
Place a thin layer of crushed stone (1"-2") in the trench to help level stones and assist drainage.
Step 5:
Start with the largest stones first. Lay them flat from one end of the trench to the other. Continue
to stack stones, working back and forth, one level at a time.
Step 6:
As you stack your wall, make sure that it slopes back slightly to ensure stability. Position stone
tightly together, mixing small and large pieces. Stagger joints between stones to create more
stability.
Step 7:
As you build up, fill in the area behind the wall with crushed stone, and then fill dirt, compacting
as you go. Keep your filter fabric between the fill and stonewall.
Step 8:
When wall is stacked to desired height, fold the filter fabric back over the fill dirt area and finish
with your choice of top soil, mulch, gravel, etc. Run water to settle dirt behind the wall and into
its service.
First of all, in brick masonry, brick is the smallest structural unit and in stone construction stone is
the smallest structural unit.
Stone masonry is usually used in rural areas and its best kind, which is very costly can be used for
very strong construction
In brick masonry the size and shape of the brick matters a lot but not in stone masonry.
Slab:
Slabs are horizontal slab elements in building floors and roof. They may carry gravity loads as
well as lateral loads. The depth of the slab is usually very small relatively to its length and width.
Beams:
Long horizontal or inclined members with limited width and height are called beams. Their main
function is to transfer loads from the slab to the columns.
Column:
Columns are vertical members that support loads from the beam or slabs. They may be subjected
to axial loads or moments.
Frames:
Frames are structural members that consists of combination of slab, beams and columns
Footings:
Footings are pads or strips that support columns and spread their load directly to the soil.
Walls:
Walls are vertical plate elements resisting gravity as well as lateral loads e.g retaining walls,
basement walls. etc
Concrete is very versatile material. It can be cast in place with or without reinforcement. It can
also be precast or prestressed in order to achieve the required strength. In order to achieve the
required strength there is the need of proper understanding of its behavior and constituents that
are making the concrete. Any type of negligence in any of its phase like placement, design &
maintenance can lead towards its deterioration and finally it will not be able to perform its
intended functions. Some of the factors that can cause the deterioration of concrete are:
1. Accidental loading
2. Chemical reaction like sulfate attack, alkali carbonate reactions, alkali silica reactions etc
3. Corrosion of steel reinforcement
4. Poor construction detailing
5. Erosion
6. Freezing and Thawing
7. Shrinkage
8. Settlement
9. Fire and weathering
Inadequate structural design means that concrete is exposed to flexural and shearing stresses that
are greater than its design strength. All that leads towards spalling and cracking of concrete. Any
abrupt change in cross section of any member can cause the increase in stress concentration in
that member which will be ultimately resulted into cracking of concrete. Deflection is one of the
major parts in structural design. If there is any problem in its consideration during design, that
can lead towards the cracking of concrete. Inadequate provision of drainage and expansion joints
during the design also becomes the cause of deterioration and spalling of concrete.
Most of the structural problems can be avoided by proper design and planning.
It can be concluded that design and construction defects at the least can cause minor cracking or
spalling leading to concrete deterioration and may become a source of a major structural failure.
Therefore a great deal of attention and care is required in designing, detailing and construction of
concrete structure.
Factor of Safety in buildings or other construction is kept so that to compensate any uncertainty
in the design process. The uncertainty could come from anywhere in the design process
including calculations, material strengths, environmental conditions, natural phenomenons, duty
of the structure and last but not the least quality of materials used. Though there exist some
difference when viewed in technical perspective but factor of safety can also be termed as
Margin of safety or even Reserve strength.
Definition:
The ratio of Strength of material to the load it is designed for.
Composition of a Brick
Normally, brick contains the following ingredients by weight:
Classification of Bricks
SAQIB IMRAN 0341-7549889 15
16 | P a g e
Based on Quality
Based on uses
Based on Composition
Based on Manufacturing Process
Classification of Bricks Based on Quality
First Class Bricks
Second Class Bricks
Third Class Bricks
Types of Bricks Based on Uses
Facing Bricks
High Temperature Resisting Bricks (Forsterite Bricks)
Acid-Resisting Bricks (Silicon Carbide Bricks)
Light Weight Clay Bricks
Engineering Bricks
Types of Bricks Based on its Composition
There are various types of bricks used in masonry:
Common Burnt Clay Bricks
Fire Clay Bricks
Fly ash Clay Bricks
Sand Lime Bricks (Calcium Silicate Bricks)
Concrete Bricks
Based on Manufacturing Process
Sun Dried Bricks
Fired Bricks
Design of Formwork for Building Loads
Loads on Falsework<
Loads on Falsework are any combinations of the following:
Dead loads,
Imposed loads,
Environmental loads,
Incidental loads during erection and operation, and
Lateral pressure
1st Floor
It is the floor that has 1 storey height above ground.
Basement Floor
The floor of the basement of the building. It is also called cellar. The basement floor is either
completely or partially below the ground floor. A basement can be used in almost exactly the
same manner as an additional above-ground floor of a house or other building. However, the use
of basements depends largely on factors specific to a particular geographical area such as
climate, soil, seismic activity, building technology, and real estate economics.
The concrete floor in most basements is structurally not part of the foundation; only the
basement walls are. Since warm air rises, basements are typically cooler than the rest of the
house. In summer, this makes basements damp, due to the higher relative humidity.
Basement Wall
The wall surrounding the basement floor is called the basement wall. The basement walls can be
regarded structurally as part of the foundation. The basement walls are shear walls which can
resist lateral laods as well. Moreover, these walls are meant to be higly non-porous and water
resistant.
Column Bracket
Column Bracket is protrusion from the column also used for hanging or attaching lamps, bulbs or
other accessories to it like road signs.
Column Capital
Column capital is an architectural element used for aesthetic purposeswhich forms the topmost
member of a column.
Drop Panels
Drop panels are used to thicken the slab around the column in flat slabs to avoid punching shear.
Since flat slabs have no stirrups shear is resisted by thickening the slab around the column to
increase the concrete in shear. Beams can also be used, but generally drop panels are preferred to
avoid conflicts with the electro-mechanical works of the structure.
Exterior Columns
The columns supporting the main structure of the building. Usually in frame structures the
exterior columns are of extreme importance and bear the load of the building as well as resist
environmental factors like wind, rain, and other physical factors.
Flat Plate
Slabs connecting to columns directly. Flat plate system is widely adopted by engineers as it
provides many advantages . The system can reduce the height of the building, provide more
flexible spatial planning due to no beams present, and further reduce the material cost. However,
the main problem in practice is the brittle failure of flat plate under punching shear. Due to the
relatively small floor loading and the close column spacing, flat plate construction is preferred.
For heavier loading and larger column spacing, column capitals are required, and for even larger
spans to reduce the self-weight, waffle slabs are used.
Flat Slab
The flat plate is a two-way reinforced concrete framing system utilizing a slab of uniform
thickness, the simplest of structural shapes. The flat slab is a two-way reinforced structural
system that includes either drop panels or column capitals at columns to resist heavier loads and
thus permit longer spans. Construction of flat slabs is one of the quickest methods available.
Lead times are very short as this is one of the most common forms of construction.
Interior Columns
Interior columns in a frame structure support the slab and beams internally. They are not as
susceptible to buckling and environmental effects as the external ones but still are extremely
important considering the safety and stability of the building. Interior columns can also serve
aesthetic and architectural purposes.
Pedestal
An architectural support or base, as for a column or statue.
Roof
A roof is the covering on the uppermost part of a building. A roof protects the building and its
contents from the effects of weather and the invasion of animals. Structures that require roofs
range from a letter box to a cathedral or stadium, house buildings being the most numerous.
the material
the construction
the durability &
Serviceability
Spread Footing
To distribute the load of the foundation on the soil, spread footings are installed below the
building's foundation. This type of footing is continuous below the perimeter of the house walls
and may be thickened or widened at the points where concentrated loads are applied e.g.
columns. These components are constructed from concrete and are often reinforced with rebar or
steel to add additional support. Depending on the size and configuration of the building, the
footers can be buried just below ground level or several feet below the surface. In cold climates,
they are always placed below the frost line to minimize problems with concrete heaving that
occurs during freeze/thaw cycles. This type of footer design is highly beneficial to builders and
homeowners. Since they transfer the weight of the building over a large area, they have little risk
of failure
Upturned Beam
Through the use of upturned concrete T-beams, designers created a naturally ventilated work
space that employs the thermal mass of an exposed concrete ceiling. This concrete absorbs heat
during the day and is purged at night by cool breezes. The term is usually used in concrete
construction, in parking structures, but here is how it works:
The beam is above the floor it supports, or a combination. Take a parking structure, there is the
required barrier wall, so if you turn the beam up it acts as support and the barrier. Think of your
simple beam diagram with a uniform load on it. The beam supports this load, so it doesn't matter
if the load is applied at the bottom (simply, other than there are the compression/tension face)
This also works well in buildings, rather than have a large beam under the floor, the beam is cast
above and below the floors, acts as bearing and shear tension and compression face
reinforcement will be some what different, but beam cross section area will stay the same.
4. Before laying raft reinforcement, shuttering wall which is mainly brick wall should be built and
should be filled with soil on other side.
5. Check the direction of chair bars in the raft
Column Casting
On the raft the column layout is done.
Layout for starter.
The column ties and link bars are provided as per column reinforcement drawings and general
specifications.
Displacement of main bars should be provided with L bar
The plumb of formwork should be checked.
Height of cast should be calculated accurately.
Avoid caps as far as possible.
Binding Materials
Since the thermal expansion of concrete is different from that of masonry. The interface between
the concrete and the masonry is liable to crack. To avoid this crack the chicken wire mesh is used
to avoid the crack and also provides the better grip for Masonry with concrete.
Similarly when the drainage pipes are laid along with the outer wall then again the connection
between the pipe and the wall has different coefficient of temperature change hence they are joint
to the concrete by lead keys.
In the toilets and kitchen sunken portion the joints in any case are packed by water proof and non
shrinkable material.
Water Proofing
Water proofing has remained as an unsolved complex problem. Use of plasticizes, super
plasticizes, air-entraining agents helps in reducing the permeability of concrete by reducing the
requirement of mixing water, hence can be also be regarded as waterproof material.
Some of approved water-proofing compound by the company are: pidilite, cico, fosroe,
baushimine, unitile.
Different factors are used for different loadings. As dead loads can be estimated quite accurately,
their load factors are smaller than those of live loads, which have a high degree of uncertainty.
Several load factor conditions must be considered in the design to compute the maximum and
minimum design forces. Reduction factors are used for some combinations of loads to reflect the
low probability of their simultaneous occurrences. Now if the ultimate load is denoted by U, the
according to the ACI code, the ultimate required strength U, shall be the most critical of the
following:
In addition to the load factors, the ACI code specifies another factor to allow an additional reserve
in the capacity of the structural member. The nominal strength is generally calculated using
accepted, analytical procedures based on statistics and equilibrium. However, in order to account
SAQIB IMRAN 0341-7549889 25
26 | P a g e
for the degree of accuracy within which the nominal strength can be calculated and for adverse
variations in materials and dimensions, a strength reduction factor Phi should be used in the
strength design method. Values of the strength reduction factor (Phi) are:
Nominal strength
Actual strength from the material properties is called the nominal strength.
As safe design is achieved when the structural strength obtained by multiplying the nominal
strength by the reduction factor phi , exceeds or equals the strength needed to withstand the
factored loads.
Floors Definition
A floor is the bottom surface of a room or vehicle. Flooring is the general term for a permanent
covering of a floor, or for the work of installing such a floor covering.
Types of Floors
Following are some of the major types of floors:
1. Mud Floor:
Suitability:
These floors are not prepared in commercial or professional buildings but only in residential
buildings in rural areas.
2. Brick floor:
The floor whose topping is of brick. These are easy to construct and repair. but the surface resulting
from these is not smooth and is rough, hence, easily absorbs and retains moisture which may cause
dampness in the building.
For constructing a brick floor, the top surface of earth or murram filling is properly consolidated.
Over this compacted earth, a layer of clean sand about 10 cm thick is evenly spread. Then a layer
of lime concrete (1:4:8) or lean cement concrete (1:4:16) is laid, compacted and cured. Over this
base concrete well soaked bricks are laid in cement mortar (1:4) in any suitable bond. In case
pointing is to be done, the minimum thickness of joints should not exceed 2 mm and and the mortar
in joints is struck off with a trowel. When the pointing is to be done, the minimum thickness of
joints is kept 6mm and the pointing may be done.
Suitability:
3. Tile floor:
SAQIB IMRAN 0341-7549889 28
29 | P a g e
The floor whose topping is of tiles is called tile floor. The tiles used may be of any desired quality,
color, shape or thickness.
For constructing a tile floor, the base course is prepared in the same manner as in case of brick
flooring.Over the base course thus prepared, a thin layer of lime or cement mortar is spread with
the help of screed battens. Then the screeds are properly leveled and fixed at the correct height.
When the surface mortar has hardened sufficiently, the specified tiles are laid on a 6 mm thick bed
of wet cement mortar.(1:5). The surplus mortar which comes out of the joints is cleaned off. After
3 days, the joints are well rubbed a carborundum stone so as to smoothen the surface, specially the
edges.
Suitability:
These floor are used for paving courtyard of buildings. Glazed tiles floors are used in modern
buildings where a high class building is desired.
4. Flagstone floor:
The floors whose topping consists of stone slabs is called flagstone floor. The stone slabs used
here may not be of the same size but should not be more than 75 cm length and not less than 35
cm in width and 3.8 cm in thickness.
For constructing a flagstone floor, the same method is applied as in case of tile floor. The slabs are
soaked well in water at least one hour before laying. They should be evenly and firmly bedded in
mortar. The thickness of joints should not exceed 4mm and they should be struck off with a trowel
while laying.
Suitability:
These type of flooring are suitable in go-downs, motor sheds, stores, pavements etc.
Terrazzo floor
Concrete:
Concrete is a stone like substance obtained by permitting a carefully proportioned mixture of
cement, sand and gravel or other aggregate and water to harden in forms of the shape and of
dimensions of the desired structure.
The design of a structure may be regarded as the process of selecting proper materials and
proportioned elements of the structure, according to the art, engineering science and technology.
In order to fulfill its purpose, the structure must meet its conditions of safety, serviceability,
economy and functionality.
The aim of this analysis is to ensure that no limiting sate will appear in the structural member
during its service life.
Reinforced concrete's sections are heterogeneous, because they are made up of two different
materials - steel and concrete. Therefore, proportioning structural members by ultimate stress
design is based on the following assumptions:
1. Strain in concrete is the same as in reinforcing bars at the same level, provided that the
bond between the concrete and steel is adequate
2. Strain in concrete is linearly proportional to the distance from the neutral axis.
3. Modulus of elasticity for all grades of steel is taken as Es = 29 x 106 psi. The stress in the
elastic range is equal to the strain multiplied by Es.
4. Plane cross sections continue to be plane after bending.
5. Tensile strength of concrete is neglected because:
o Concrete's tensile strength is about 1/10 of its compressive strength.
6. Cracked concrete is assumed to be not effective Before cracking, the entire cross section is
effective in resisting the external moments.
7. The method of elastic analysis, assuming an ideal behavior at all levels of stress is not
valid. At high stresses, non-elastic behavior is assumed, which is in close agreement with
the actual behavior of concrete and steel.
8. At ultimate strength, the maximum strain at the extreme compression fibers is assumed to
be equal to 0.003 by the ACI code provisions. At the ultimate strength, the shape of the
compressive stress distribution may be assumed to be rectangular, parabolic or trapezoidal.
Loads
Structural members must be designed to support specific loads. Loads are those forces for which
a structure should be proportioned. Loads that act on structure can be divided into three categories.
1. Dead loads
2. Live loads
3. Environmental loads
Dead Loads:
Dead loads are those that are constant in magnitude and fixed in location throughout the lifetime
of the structure. It includes the weight of the structure and any permanent material placed on the
structure, such as roofing, tiles, walls etc. They can be determined with a high degree of accuracy
from the dimensions of the elements and the unit weight of the material.
Live loads:
Live loads are those that may vary in magnitude and may also change in location. Live loads
consists chiefly occupancy loads in buildings and traffic loads in bridges. Live loads at any given
time are uncertain, both in magnitude and distribution.
Environmental loads:
Consists mainly of snow loads, wind pressure and suction, earthquake loads (i.e inertial forces)
caused by earthquake motions. Soil pressure on subsurface portion of structures, loads from
possible ponding of rainwater on flat surfaces and forces caused by temperature differences. Like
live loads, environmental loads at any given time are uncertain both in magnitude and distribution.
Structural members must always be proportioned to resist loads greater than service or actual loads,
in order to provide proper safety against failure. In the strength design method, the member is
designed to resist the factored loads which are obtained by multiplying the factored loads with live
loads.
Different factors are used for different loadings. As dead loads can be estimated quite accurately,
their load factors are smaller than those of live loads, which have a high degree of uncertainty.
Several load factor conditions must be considered in the design to compute the maximum and
minimum design forces. Reduction factors are used for some combinations of loads to reflect the
low probability of their simultaneous occurrences. Now if the ultimate load is denoted by U, the
according to the ACI code, the ultimate required strength U, shall be the most critical of the
following
In addition to the load factors, the ACI code specifies another factor to allow an additional reserve
in the capacity of the structural member. The nominal strength is generally calculated using
accepted, analytical procedures based on statistics and equilibrium. However, in order to account
for the degree of accuracy within which the nominal strength can be calculated and for adverse
variations in materials and dimensions, a strength reduction factor (Ø) should be used in the
strength design method. Values of the strength reduction factor Ø (Phi) are:
Nominal strength
Actual strength from the material properties is called the nominal strength.
As safe design is achieved when the structural strength obtained by multiplying the nominal
strength by the reduction factor Ø, exceeds or equals the strength needed to withstand the
factored loads.
Definition:
The access and penetration of moisture content into building through its walls, floor, roof etc. is
called dampness in buildings.
Corbels
This is provided in internal side of roofs
For decoration
For preventing dampness
Rising damp is caused by capillary action drawing moisture up through the porous elements of a
building's fabric. Rising damp, and some penetrating damp, can be caused by faults to, or the
absence of a damp-proof course (DPC) or damp-proof membrane (DPM).
For internal wall we only provide horizontal DPC ( 175 kg/cm 2 standard pressure for bitumen )
Three layers of bitumen is provided
You should provide a mortar layer before DPC
Types of DPC
There are two types of DPC
1. Flexible DPC: It is DPC when load doesn’t crack e.g. Polythene and Bitumen
2. Rigid DPC: It is DPC when loaded; it cracks e.g. Rich cement concrete 1:2:4
Three layers
1. Bitumen mastic: Bitumen mix with fine sand
2. Bitumen felt: It is available in the form of rolled sheets
3. Hard laid bitumen
4. Metal sheets
SAQIB IMRAN 0341-7549889 40
41 | P a g e
Rigid DPC: It is DPC when loaded; it cracks e.g. Rich cement concrete 1:2:4
Definition:
The art of building a structure in stone with any suitable masonry is called stone masonry.
1. Rubble Masonry
2. Ashlar Masonry
Rubble Masonry:
The stone masonry in which either undressed or roughly dressed stone are laid in a suitable mortar
is called rubble masonry. In this masonry the joints are not of uniform thickness. Rubble masonry
is further sub-divided into the following three types:
Rubble masonry is the type of stone masonry in which either undressed or hammer dressed stones
are used is called random rubble masonry. Further random rubble masonry is also divided into the
following three types:
Suitability: Used for construction of walls of low height in case of ordinary buildings.
Suitability: Used for construction of residential buildings, go downs, boundary walls etc.
Suitability: Used for construction of public buildings, hospitals, schools, markets, modern
residential buildings etc and in hilly areas where good quality of stone is easily available.
Suitability: Used for construction of ordinary buildings in hilly areas where a good variety of
stones are cheaply available.
SAQIB IMRAN 0341-7549889 43
44 | P a g e
Ashlar Masonry:
It is the type of stone masonry in which finely dressed stones are laid in cement or lime mortar is
known as ashlars masonry. In this masonry are the courses are of uniform height, all the joints are
regular, thin and have uniform thickness. This type of masonry is much costly as it requires
dressing of stones.
Suitability: This masonry is used for heavy structures, architectural buildings, high piers and
abutments of bridges.
Ashlar facing:
Ashlar facing is the best type of ashlars masonry. Since this is type of masonry is very expensive,
it is not commonly used throughout the whole thickness of the wall, except in works of great
importance and strength. For economy the facing are built in ashlars and the rest in rubble.
Definition:
The pulling out of steel bars from concrete is resisted by the gripping action of concrete known as
bond and the resulting stress is called bond stress. The resistance offered to slipping of bars is due
to three factors:
Masonry structures are the oldest structures. These are structure built by using masonry units with
mortar. The masonry units may be:
Clay Bricks
Concrete Blocks
Structural Clay Tiles
Stone
Bricks
Brick is a solid unit of building having standard size and weight. Its history traces back thousand
years (almost 7500 BCE). Clay bricks made of fired clay. The composition of clay varies over a
wide range. Usually clays are composed mainly of silica (grains of sand), alumina, lime, iron,
manganese, sulfur, and phosphates, with different proportions. Clay bricks have an average
density of 125 pcf. Bricks are manufactured by grinding or crushing the clay in mills and mixing
it with water to make it plastic. The plastic clay is then molded, textured, dried, and finally fired.
Bricks are manufactured in different colors, such as dark red, dark brown, or dull brown,
depending on the fire temperature during manufacturing. The firing temperature for brick
manufacturing varies from 900°C to 1200°C (1650°F to 2200°F).
Uses of Bricks
1. As a Structural Unit
Since the clay bricks or burnt bricks are strong, hard, durable, resistive to abrasion and fire,
therefore, they are used as a structural material in different structures
Buildings
Bridges
Foundations
Arches
Pavement (Footpath, Streets)
2. As an Aesthetic Unit/Surface Finish
Bricks can be used in different colors, sizes and orientations to get different surface designs. As
an aesthetic material bricks can be used:
In Pavements
As Facing Brick
For Architectural Purposes
3. As a Fire Resistant Material
Advantages of Bricks
Economical (Raw material is easily available)
Hard and durable
Compressive strength is good enough for ordinary construction
Disadvantages of Bricks
Time consuming construction
Cannot be used in high seismic zones
Since bricks absorb water easily, therefore, it causes fluorescence when not exposed to air
Very Less tensile strength
Rough surfaces of bricks may cause mold growth if not properly cleaned
Cleaning brick surfaces is a hard job
Color of low quality brick changes when exposed to sun for a long period of time.
Constants in Building Design & Analysis
Concrete Joint Fillers, expansion joint filler, concrete expansion joint filler
Definition
Joints fillers are the strips of some compressible material which is used to fill the expansion
joints in different structure.
Uses:
Joint filling is an important process in many structures such as Buildings, Masonry Walls. A
joint filler for use in joints between structural elements comprising at least one layer of a
substantially non-compressible, moisture blocking material; at least two layers of a compressible
and resilient, moisture blocking material, each layer being in surface to surface contact with a
layer of non-compressible material; the layers of material are combined to form a strip of
interleaved compressible and non-compressible layers, and in an uncompressed state thicker than
a joint.
Expansion Joints
These are structural separation between building elements that allow independent movement
without damage to the assembly. An expansion joint is used in concrete and steel. An expansion
joint allows the concrete or steel to expand or contract with daily temperature variations. If you
don’t allow this, you may get buckling, or spalling, or total failures. They are commonly
provided in bridges, railway tracks, piping systems, and other structures.
A control joint or contraction joint is a joint that is put in the concrete to control
cracking. Control Joints (often confused with expansion joints) are cuts or grooves made in
concrete or asphalt at regular intervals. These joints are made at locations where there are
chances of cracks or where the concentration of stresses are expected, so that when a concrete
does crack, the location will be known to you. In such a way concrete will not crack randomly
but in a straight line (i.e. control joint). In other words Contraction or Control Joints are Pre-
SAQIB IMRAN 0341-7549889 51
52 | P a g e
Planned Cracks. The cracks may be due to temperature variations or drying shrinkage or other
reasons.
Joints depth should be 25% of the depth of the slab. For instance a 4" thick slab should have 1"
deep cut. Joints Interval (taken in feet) should not be more than 2 - 3 times the slab thickness (in
inches). Let say a 6" slab should have joints 2 x 6=12 to 3 x 6 = 18 feet apart. For fresh concrete
grooving tools are used while saw is used for hardened concrete.
Construction Joints
A construction joint occurs when there are multiple concrete placements. It can occur between
different days of concrete placements.
In mega projects there are starting and stopping points. The entire concrete work may not be
done at once, hence concrete pouring needs to be stopped causing a joint in element known as
Construction Joint. Construction joints are placed at points of ending and beginning of
construction for provision of a smooth transition between pours. These joints are formed between
successive building element parts during construction work, in which one part is allowed to
harden before the next is placed. These joints may be intentional or unintentional. Reasons for
intentionally providing construction joints are;
Certain time of a day i.e. Labour Hours ( e.g. 8:00 am to 6:00 pm)
Certain day of a week (e.g. Sunday, or Friday)
Certain Months of an year (e.g. extreme weather in Winter or Summer)
Religious Holidays etc (e.g. Eid or Christmas etc)
Step 1: To assist in your stacking, sort the stone by size; setting aside the smallest pieces to use as
shims (these will help level unsteady larger stones).
Prepare for this activity by stretching well and always lift using your arms and legs, not your back
Shims (shown far right), or smaller stones, help level unsteady larger pieces.
Step 2: Map out the design by digging a trench about 6" deep and as wide as your largest stone.
Step 3: Pack down and level earth. Cut filter fabric at least 3 feet wider than the trench. Lay down
filter fabric inside trench so that excess is on the backside of trench. Filter fabric keeps dirt from
migrating while allowing water to drain through your wall.
Step 4: Place a thin layer of crushed stone (1"-2") in the trench to help level stones and assist
drainage.
Step 5: Start with the largest stones first. Lay them flat from one end of the trench to the other.
Continue to stack stones, working back and forth, one level at a time.
Step 6: As you stack your wall, make sure that it slopes back slightly to ensure stability. Position
stone tightly together, mixing small and large pieces. Stagger joints between stones to create more
stability.
Step 7: As you build up, fill in the area behind the wall with crushed stone, and then fill dirt,
compacting as you go. Keep your filter fabric between the fill and stonewall.
Step 8:When wall is stacked to desired height, fold the filter fabric back over the fill dirt area and
finish with your choice of top soil, mulch, gravel, etc. Run water to settle dirt behind the wall and
into its services.
Overall, it can be stated that the improved element performed better than the traditional element
in the series of earthquake simulations. This statement is based on an assessment of the risk of
causing injury posed by each structure. The walls of the traditional corners were independent and
unstable.
Any additional force, such as another tremor or a strong wind or impact, could cause either wall
to topple over, in an inward or outward direction. This represents an unacceptable level of risk.
These buildings are one of the most deficient building systems from earthquake-resistance point
of view. The main deficiencies include excessive wall thickness, absence of any connection
between the two withes of the wall, and use of round stones.
1. Important buildings were once designed and put together by master masons who knew how
to work with stone, and understood the advantages and limitations of the material. Stone
structure should be a combination of structural firmness, technical commodity and
aesthetic delight.
2. Ensure proper wall construction. The wall thickness should not exceed 450mm.
3. Round stone boulders should not be used in the construction! Instead, the stones should be
shaped using chisels and hammers.
4. Use of mud mortar should be avoided in higher seismic zones. Instead, cement-sand mortar
should be 1:6 (or richer) and lime-sand mortar 1:3 (or richer) should be used.
5. Ensure proper bond in masonry courses: The masonry walls should be built in construction
lifts not exceeding 600 mm.
6. Through-stones (each extending over full thickness of wall) or a pair of overlapping bond-
stones (each extending over at least ¾ this thickness of wall) must be used at every 600mm
along the height and at a maximum spacing of 1.2m along the length.
7. The stone masonry dwellings must have horizontal bands roof and gable bands). These
bands can be constructed out of wood or reinforced Concrete, and chosen based on
economy. It is important to provide at least one band (either lintel band or roof band) in
stone masonry construction.
8. Care should be taken to ensure that the fixing method adopted for the construction is
appropriate to the type of stone being used.
The energy needed to collapse a structure comes from the structure itself. The high frequencies
can cause high vertical inter-stone vibrations that result in irreversible relative displacements of
the stones, which is mainly due to the non required shape of the stones, thus stone walls mainly
crumble under their own weight.
If specified lime surkhi mortar, should be mixed in 1:2 to 1:3 ratio as specified, by grinding
in mortar mill for at least three hours to use on the same day.
Lime should be fresh and should be screened.
Fresh mixed mortar should be used.
For small work, hand mixing may be allowed just as in the case of cement sand mortar.
Brickwork should be protected from the effect of sun, rain, frost etc., during the
construction.
Suitable Scaffolding should be provided to facilitate the construction of brickwork.
Scaffolding should be strong enough to withstand all the expected loads to come upon
them.
Curing of Concrete
When concrete has begun to harden after about two hours of laying, then it should be
kept wet by covering with wet gunny bags or wet sand for 24 hours. It is called curing of
concrete.Concrete is cured to complete the hydration process, and to gain strength of
concrete.
After 24 hours, concrete is cured by:
Formwork or Shuttering
Formwork or shuttering may be defined as the set of forms provided to keep the
concrete in position until it sets.
16. For example, for 2.5 meter or 10 feet. 1 cm or half inch camber should be provided
with the maximum of 4 cm or 1.5 inch.
Amalgamation of plots
Amalgamation may be defined as:
The joining of two or more adjoining plots to make a single plot for the building
purposes. Amalgamation means to combine two or more units to make one single unit.
Alteration in building
Alteration means any change in structure after the approval of building plan without
violating bylaws of concerned authority.
Alteration also includes land use change brought about after the approval of building plan.
Apartment
Apartment may be defined as:
Apartment building
Apartment building may be defined as:
A multi-storey building consists of more than two apartments with common stair case or
lifts.
Termite live in large interdependent colonies, especially in dark, moist conditions such as
soil, growing trees or rotting wooden remains in the vicinity of your home. These colonies
can vary from 2.5 lac to 6 million termites. At the center of the colony, there is a queen
whose main purpose is reproduction. The worker termites have one major role to bring
food – cellulose materials, especially wood. Thus it is important to prevent termite to enter
your home if you have not done proper anti termite proofing.
When termiticide is applied to the soil, it disorientate termites and cause them to cease
their natural grooming behavior. Grooming is very important for termites. Grooming them
against pathogenic soil fungi. When termiticide or anti termite chemical is applied, then
naturally occurring fungi in the soil attack and kill the termites. Termiticide makes fungi
10000 times more dangerous to termites.
Termites feed each other by passing food from mouth to mouth. They groom each other.
They contact each other as they forage for food. Once a termite has ingested or contacted
termiticide, it becomes carrier. Every other termite it contacts will be infected, which in
turn infects every other termite it contacts. Termiticide should work slowly letting termites
contact many other before dying themselves.
With lateral soil movement, effective concentrations of termiticide or anti termite chemical
should be distributed throughout the treated zone, even in the areas furthest from the
injection points. It should be effective for a wide range of soil conditions. Termiticide
should be non repellent. Termites should not see it, feel it. They should not know its there,
so that they forage freely in the treated area.
area of 175 square foot using anti termite chemical of good quality. This should be
applying with pressure pump.
Normal concrete
If the cement content is more than 10 and less than 15%, the concrete is called normal
concrete.
Rich concrete
If the cement content in concrete is more than about 15%, then it is known as rich
concrete.
Shoring
Shoring is the Construction of a temporary structure required to support an unsafe
existing structure. Temporary structure is known as shores.
In this method, inclined members which are called rakers, used to give temporary lateral
support to an unsafe wall. That is why it is called inclined shoring as the temporary
support is inclined.
Shallow foundation
Shallow foundation may be defined as:
1.Spread footing
Spread footings as the name suggest, spread the super imposed loads of the structure
over a large area.
Grillage foundation
When heavy structural loads of a column are required to be transferred to the soil of low
bearing capacity, the most economical foundation is grillage foundation. Depth of such a
foundation is limited to 0.9 to 1.6 meter.
2.Combined footing
The footing which is constructed for two or more columns is called combined footing.
Shape of combined footing is so proportioned that the center of gravity of the supporting
area is in line with the center of gravity of the two column loads. Its shape is either
rectangular or trapezoidal.
A combined rectangular footing is provided where both the columns carries equal load
or interior column carries greater load. A combined trapezoidal footing is provided under
any conditions of loading.
3.Strap footing
When two or more footings are connected by a beam, it is known as strap footing.
It is provided if the distance between the columns is so great that a combined
trapezoidal footing becomes quite narrow, with high bending moments.
When the soil underneath is of low bearing capacity and the building loads are
heavy.
When the combined area of individual footing is more than half of the total area of
the structure, then it is economical to use mat or raft foundation.
at various levels of entry of damp into a building. Provision of DPC prevents of entry of
moisture from walls floors and basement of a building.
Causes of dampness
Rising of moisture from the ground.
Rain travel from wall tops.
Heavy rain shower on external walls.
Poor drainage, imperfec t orientation, imperfect roof slope, defective construction
etc.
Bricks have a porous structure. The pores of bricks are interconnected to form
capillaries. That is why bricks suck dampness from soil underneath and pump it to
upper parts of the building due to capillary force.
If there is direct contact between the underneath brickwork and brickwork of the super
structure whole of the building will be affected.
D.P.C is provided on all the walls which are continuous above plinth level.
Building Demolition
Demolition Methods and Process for Building
Structures
Demolition of buildings and structures are required for various reasons.
Demolition methods and processes for buildings and other structures are
described.
There can be more reasons for demolition of a building, old structures are to be
replaced by new ones. The structure lost its stability or having any structural
damage. Small structures are demolished to build big structures etc.
Definitions
1. Surveying
2. Removal of hazardous materials
3. Preparation of plan
4. Safety measures
1. Building surveying
2. Structural surveying
1. Building Surveying
2. Structural Surveying
All the workers, site supervisors and engineers including plant and equipment
operators are briefed with the potential hazards and process of demolitions.
All goods that are flammable are removed from the site unless it is used in the
work involved. All the flammable materials like wood, timber, fuels etc. are
stored in proper storage facilities. Firefighting appliances are stationed in the
demolition site till the process is completed.
Due to the demolition of structure, many problems are faced by the workers,
such as. exposure to dust, chemical exposure, heat stress and ventilation, noise
exposure, medical and first aid facilities, sanitation and occupational diseases.
To overcome these problems suitable measures are undertaken.
1. Non-explosive demolition
2. Explosive demolition.
It means the demolition of a structure done with some equipment without the
use of any explosive. Different equipment’s used for the demolition activity are
a) Sledge hammer
It is a small handheld hammer used for the demolition of small wall or single
column.
These are big machines uses to demolish building of small sizes. They are used
for excavation of soil or transferring of debris to trucks etc.
c) Wrecking Balls
The building with the greater height up to (6-7 story) cannot be demolished
with the help of excavators or bulldozers. In such cases crane with wrecking
balls are used to perform the demolition activity. The wrecking ball crack is
crack attached with a huge steel ball hanging from a steel rope.
The steel ball is pulled and released towards the building. The steel ball with
force strikes the building and the part of the building is demolished. This
method is not recommended as the trajectory of the steel ball cannot be
controlled after it strikes the structure.
High Reach Excavator machines are used in the demolition of tall building where
demolition by explosion is not possible. The building of height up to 300ft can
be demolished by this type of machine.
High reach excavators can be used for different use by doing some attachments
such as:
Using implosion technique, the main supports of the buildings such as column’s,
beams and slab are fixed with explosives. When these explosives are detonated,
the column collapse and so is the structure.
Depending how the structure falls, there are two types of implosion:
In this type of implosion, the building is made to fall like a tree to the sideward.
This is the commonly used type of implosion. When free space is available
besides the building, this type of demolition is prescribed.
If the free space is available on the left side of the building, the explosives are
set on the lower level of the building on the left side columns. As the explosives
are detonated, the columns bursts, the building tends to falls towards the left
side. Steel cables are tied to the building to control the falling direction of the
building.
When the free spaces are not available around the building and the structure
around the building are to be protected. This type of demolition is used. In this
type of demolition, explosives are set in the floor below the middle part of the
building.
These explosives are to be heavy as the explosion must demolish the building at
once. If one part blast and followed by another. Then the building falls towards
the first blasted part. So only less companies in the world are experienced in
this type of demolition.
As the explosions are detonated, the upper part of building destroys and falls
upon the lower building. Due to the heavy load and force the lower part of the
building also collapses and falls on its own footprint.
Demolition means destruction, tearing down, breakup, removal of the whole parts
of building, normally demolition is done when the life of building is over or to
construct a new structure by replacing the older one, also it is carried out when
the structure lost its stability or having any structural damage.
Demolition techniques
Non Engineering Demolition
Manual Demolition
Engineering Demolition
Mechanical Method
Implosion
Deconstruction Method
Non Engineering Demolition
Manual Demolition: This is normally carried out by contractors using manual
tool which is portable, tools used are Sledge Hammer, Jack Hammers and Drillers.
Jack Hammer
Drill
Sledge Hammer
Engineering Demolition
Mechanical Method:
1. Wrecking Ball Method
2. Pusher Arm technique
3. Thermic Lance Technique
4. Non – Explosive Demolition
5. Concrete Sawing Method
6. Deliberate Collapse Method
7. Pressure Jetting
Wrecking Ball Method: A Steel ball anti spin device which is suspended by a
steel rope and swung by a drag rope, the weight of the ball is around 500 to 1000
Kg used with suitable fittings attached to a crane of adequate capacity, the
building is dismantled by making the steel ball to hit the structure this method is
much faster than manual method
Thermic Lace Technique: Flame is produced by having supply with pure oxygen
with a temperature of 2500 degree centigrade to melt the reinforcement.
Non- Explosive Demolition: A Number of holes is drilled along the desired line
of separation and are filled with slurry which is a special material when the slurry
is filled in the holes water is poured into the drilled holes after few hours the
slurry expands as a result cracking will appear on the structures which help in
easy demolition of structure.
Concrete Sawing Method: Using the concrete saw the structure is been
demolished which works on a high power supply helps in destruction of structure
in an easy way.
Deconstruction Method: A slow and careful process that is almost the reverse
process of construction.
Non Structural Method: Dismantling of doors, windows, flooring etc.
etc. and main explosives used are dynamites and RDX. When explosive are used
for the demolition, it is known as Implosion.
1. INTRODUCTION
We know every structure is designed for a life period. The existence of the structure after
the service life period is very dangerous to its occupants and surrounding buildings .The
building act usually contains provisions that enable local authorities to control demolition
works for the protection of public safety and to ensure adjoining premises and the site are
made good on completion of the demolition. A notice of conditions is issued that require
certain works to be undertaken to achieve these aims. Where demolition of a building
takes place, the owner must inform the council. Greenhouses, conservatories,
prefabricated garages and sheds do not require permission to be demolished. Usually if
the building to be demolished has a volume of less than 1750 cubic feet (49.56 cubic
meters), then permission is not required to knock it down.
2. DEMOLITION
Demolition is the process of tearing down or falling down of a building after its life period
with the help of some equipments or any other method. When explosives are used for
this then the demolition process are called as an implosion. Every civil engineering
structure is designed for a life period. After that the existence of a structure is very
dangerous. So removal of such structures with proper safety measures has got great
importance. There are different steps involved before and during the time of a demolition
activity. They are described as follows.
1. Surveying
3. Preparation of plan
4. Stability report
5. Safety measures
3.1 Surveying
Surveying means study of different parameters of the structure and its surroundings.
There are two types of surveying are mainly conducted. They are
A. Building surveying
B. Structural surveying
A. Building surveying
It includes,
Prior to the Building Survey, the existing record plan, including layout plan showing
adjoining properties, pedestrian walkway, roads and street, etc. shall be retrieved.
(2) The existing use and, if possible, the past uses of the building prior to demolition;
(3) The presence of wastewater, hazardous materials, matters arising from toxic
chemicals, flammable or explosive and radioactive materials, etc. and possible presence
of materials which can contribute to air pollution and soil contamination;
(4) Potential dangerous areas, e.g., abnormal layouts, presence of enclosed voids, and
non- ventilated light wells which may trap obnoxious gas at the bottom;
(5) Adjoining properties and site conditions, such as the existence of slope and retaining
wall, wall supporting ground, illegal structures, bridges, underground railway and its
above ground structures, including entrances, vent shafts, distribution substations,
traction substations, plant rooms, overhead railway structures, surface track sections,
overhead cables or guy wires, and other utility Service connections;
(6) Drainage conditions and possible problems on water pollution, flooding and erosion,
especially on sloping sites and water receiving bodies;
(7) Shared facilities with adjoining building, including common staircases, party walls, and
possible effect on it, such as self-enclosed walls to the adjoining buildings, during
demolition;
(10) Available headroom, clear spaces and distance of building from lot boundary which
may affect the loading operation and transportation of building debris during demolition;
(11) The sensitivity of neighborhood with respect to noise, dust, vibration and traffic
impact.
(12) Available site area to allow on-site sorting of building debris; and
(13) Street furniture such as fire hydrant, parking space/meters, street light, street sign
and hawkers’ stalls which could be affected by the demolition project.
(1) Unless the Building Survey reviews that no obvious hazardous material is present in
the building, the Authorized Person shall cause proper sampling and testing for the
hazardous materials;
(2) In the case when hazardous materials e.g., asbestos containing materials, or
petroleum, are present, they shall be removed and cleaned/disposed of according to the
(3) In the case when the site has previously been used to store chemicals, and other
dangerous goods, soil contamination assessment shall be required at pre-demolition
stage and/or post-demolition stage; and
(4) In the case when the site has previously been used to store explosives, special
procedures to ensure no explosives remain on site will be required.
B. Structural surveying
(a) Record Drawings
Prior to the Structural Survey, the existing record layout, structural framing
plans and structural details shall be studied. The Registered Structural Engineer shall
SAQIB IMRAN 0341-7549889 81
82 | P a g e
check the presence of unusual detailing that may cause abnormal structural behavior
during demolition, e.g., upward anchor of tensile reinforcement in cantilevered structures.
If existing record plans are available, these plans shall be used as reference and
preferably be brought along with the Structural Survey.
(5) The structural conditions of adjoining structures and its shoring which may be affected
by the proposed demolition work;
(6) The presence of continuous structures that may be truncated by the demolition;
(7) The structural system and structural conditions of basements, underground tanks or
underground vaults;
(9) The nature of walls, whether it is block wall, reinforced concrete walls, load bearing
walls or partition walls;
(2) The presence of any unconventional structural elements which may require special
attention and well-defined modification procedures;
(3) The possibilities of structural modification to enable efficient demolition traffic during
demolition; and
In the case when no structural details are available, the structural survey shall include on
site measurement and retrieve any structural framing as much as practicable, performing
tests and exposing some key structural elements to facilitate checking on existing
structure. This will allow the development of procedures that ensure the stability of the
building at all stages during demolition.
Specialists shall be employed to take samples and cause such samples to be tested for
asbestos containing material. In the case when asbestos containing material are
discovered, specialist contractor shall be employed to remove such asbestos containing
material. The asbestos waste should be handled, stored and disposed of as chemical
waste in accordance with the Waste Disposal Ordinance and Waste Disposal (Chemical
Waste) (General) Regulation.
In the case when possible soil contamination material is present, specialist shall be
employed to prepare soil contamination test proposal and submit such proposal to the
Environmental Protection Department for comment. Upon agreement by the
Environmental Protection Department, and completion of the tests, a Soil Contamination
Assessment shall be submitted to the Environmental Protection Department for
acceptance. In the case when remedial works are required, the remedial proposal shall
be submitted to the Environmental Protection Department for approval prior to
implementation of such remedial works.
(b) A detailed topography of the site and its surrounds together with ground level contours
and sections of the slopes and ground supported by the building where appropriate;
(d) The distances from the building to be demolished to its adjacent buildings, streets,
structures and significant street furniture.
(2) A layout plan of all floors of the building to be demolished, with adequate sections,
showing:
(d) The condition of the building e.g. the degree of deterioration; and
(e) The relationship of the building to be demolished with neighboring properties affected
by the demolition, which include all adjoining buildings and unauthorized structures,
shared staircases, party walls, truncating continuous frames, slopes, retaining wall,
overhead cables, guy wires and underground utility services.
(3) A plan showing the structural arrangement and construction of all unconventional
structural elements, such as prestressed concrete structures, precast concrete members,
stressed skin structures, steel framed structures, hangers, hanging ties, trusses or
Vierendeel girders, deep beams, long span beams (greater than 10m), arches, transfer
plates, transfer girders, earth retaining or basement structures, buildings which also act
as earth-retaining structures supporting adjacent ground, flat slabs, hollow block ribbed
slabs and large cantilevered structures;
(4) A plan showing the procedure for the demolition of the building; detailed sequence of
demolishing particular structural members; and the method of demolition to be adopted
including the restrictions on the use of any particular type of equipment;
(5) In the case when powered mechanical plants and equipment are used, a plan showing
the route of movement of powered mechanical plants and equipment including the
method of lifting mechanical plant, where necessary, onto the top floors of the structure;
any structural alterations required to
suit the demolition, e.g. temporary strengthening to suit early removal of any ground
floor/or cockloft structure to facilitate vehicular movement at ground floor, or strengthening
of deteriorated key structural members; and any shoring, temporary supports and/or floor
propping required;
(6) A plan showing all precautionary measures for the protection of the public including
hoardings, covered walkways, catch platforms, catch fans, scaffolding, protective screens
and safety nets;
(7) A plan showing the proposed shoring and precautionary measures for all affected
adjacent buildings, slopes, retaining structures and services at each stage of the
demolition works;
(8) A plan showing the proposed shoring and temporary support to be provided to the
building to be demolished;
(9) A plan or descriptive notes on the proposed methods for handling and disposal of
debris including
(a) The permissible temporary accumulation of building debris at upper floors and at
ground floor;
(c) The routing and movement of debris from each floor to on grade holding area prior to
leaving the site;
(f) Record scheme on the tonnage of each truck load, truck license plate, driver’s name,
trip tickets and location of dump site;
(g) The site supervisory personnel responsible for the debris management system; and
(h) A temporary parking layout for mobile machines and trucks, if necessary;
(1) A report on the stability of the building to be demolished during all stages of demolition;
(2) In the case when powered mechanical plants or equipment are used, a report on the
stability of the building with supporting calculations to demonstrate that the use of the
plants and equipment will not render inadequate the margin of safety of, or cause damage
to any building, structure, street, land and services;
(3) In the case when powered mechanical plants or equipment are used, structural
calculations for all temporary supports and bracings;
(5) In the case when temporary or permanent supports are required to these neighboring
buildings, adjoining properties, and party walls, structural calculations for these temporary
and permanent supports; and
(6) A report with calculations demonstrating that the demolition work will not render
inadequate the margin of safety of, or cause damage to any building, structure, street,
land and services.
Demolition workers, including plant or equipment operators, shall go through proper job
safety training and be informed of the potential hazards by attending training sessions as
well as on-the-job training. At present, the Construction Industry Training Authority has
organized relevant training courses for site supervisors/foremen and plant or equipment
operators.
Equipment Maintenance
All equipment shall be tested and examined before use. They shall be properly stored
and maintained. The equipment shall be inspected daily and results of the inspection shall
Electrical Safety
A properly connected power source from a local electric utility supplier or a mobile
electricity generator shall be utilized in demolition sites. The safety requirements given in
the Factories and Industrial Undertakings (Electricity) Regulations shall be adhered to.
Fire
All flammable goods shall be removed from site unless they are necessary for the works
involved. Any remaining flammable goods shall be stored in proper storage facilities. All
furniture, timber, doors, etc. shall be removed before any welding work is performed. Fire
fighting appliances shall be provided and maintained in working conditions. The
Construction Site (Safety) Regulations require the contractor to maintain in good condition
and free from defects all fire fighting appliances provided in such construction site.
Occupational Health
The health of workers on site shall be properly protected in accordance with the relevant
subsidiary regulations of the Factories and Industrial Undertakings Ordinance and the
Occupational Safety and Health Ordinance with particular attention to the following areas:
Emergency exits shall be provided during building demolition. In case of any emergency
evacuations, the emergency exit will serve as a lifeline for transportation of injured
workers. A minimum of one exit route shall be maintained and designated as the
emergency exit at all times during the demolition. Adequate lighting and fire extinguishing
SAQIB IMRAN 0341-7549889 87
88 | P a g e
Vibration
4. Vibratory cracking from ground vibration or air blast. These effects will have to be dealt
with specifically in the method statement for implosion. For other mechanical demolition
methods, the vibration effect is usually less than some other construction processes, such
as percussive piling and blasting. In some cases, the traffic vibration caused by heavy
duty tractors is more significant than that caused by mechanical demolition. In order to
identify the actual cause and effect of vibration, Registered Specialist Contractors
(Demolition) are advised to carry out vibration monitoring during demolition. As a general
guideline, the peak particle velocities at any adjoining structure shall not exceed
15mm/sec for prolonged vibration caused by mechanical demolition.
Environmental Precautions
The general requirements to minimize environmental impacts from construction sites can
also be applied to demolition processes. The following sections contain some of the
procedures to be adopted:
Concrete breaking, handling of debris and hauling process are main sources of dust from
building demolition. Dust mitigation measures complying with the Air Pollution Control
(Construction Dust). Regulations shall be adopted to minimize dust emissions. Burning
of waste shall not be allowed. Diesel fumes generated by mechanical plant or equipment
shall be subject to the control of the Air Pollution Control (Smoke) Regulations .
(b) Noise
Noise pollution arising from the demolition works including, but not limited to, the use of
specified powered mechanical equipment (SPME), powered mechanical equipment
(PME), such as pneumatic breakers, excavators and generators, etc., scaffolding,
erection of temporary works, loading and transportation of debris, etc. affects the workers,
and the sensitive receivers in the vicinity of the demolition site. Silent type PME shall be
used to reduce noise impact as much as practicable. Demolition activity shall not be
performed within the restricted hours as established by EPD. Currently under the Noise
Control Ordinance, noise from the use of SPME and PME within restricted hours is
governed by a Construction Noise Permit (CNP) system.
(c) Water
The discharge of wastewater from demolition sites requires a valid discharge license from
the EPD and the application of such a license shall be made under the Water Pollution
Control Ordinance (WPCO). Effluent shall be treated to the standards as stipulated in the
license before discharge.
4. METHODS OF DEMOLITION
2. Explosive demolition.
It means the demolition of a structure done with some equipment without the use of
any explosive. Different equipments used for the demolition activity are
a. Sledge hammer
A sledge hammer, equipment used for removing a stone wall or a single column. It
consists of a long stem with a metallic head. It is used to give impacts on the surfaces
and that cause the demolition of structure. It cannot be used for removal of large buildings.
Fig 2. Excavator
Hydraulic excavators may be used to topple one-or two-story buildings by an undermining
process. The undermining process means, erode the base or foundation, i.e., dig or
excavate beneath the foundation so as to make it collapse. The strategy of excavation is
to undermine the building while controlling the manner and direction in which it falls. The
demolition project manager will determine where under mining is necessary so that the
building is pulled into the desired manner and direction. Safety and cleanup
considerations are also taken into account in determining how the building is undermined
and ultimately demolished.
Fig 3. Bulldozer
Loaders or bulldozers may also be used to demolish a building. They are typically
equipped with “rakes” (thick pieces of steel that could be an I-beam or tube) that are used
to ram building wall. Skid loaders and Loaders will also be used to take material out and
sort steel.
c. Wrecking balls
surface. Now this method not commonly used because of this uncontrolled behavior of
wrecking balls.
The basic idea of explosive demolition is quite simple. If we remove the support
structure of a building at a certain point, the section of the building above the point will fall
down on the part of the building below that point. If this upper section is heavy enough, it
will collide with the lower part with sufficient force to cause significant damage. The
explosives are just trigger for the demolition. It’s gravity that brings the building down.
The main challenge in bringing a building down is controlling which way if falls. There are
mainly two ways to implode a building,
In this the blasting crew will be able to tumble the building over on one side, into a parking
lot other open area. This sort of blast is the easiest to execute, and it is generally the
safest way to go. Tipping a building over is something like felling a tree. For example to
topple the building to the north, the blasters detonate explosives on the north side of the
building first , in the same way you would chop into a tree from the north side if you wanted
it to fall in that direction . Blasters may also secure steel cables to support columns in the
building, so that they are pulled a certain way as they crumble.
Explosives used
Blasters use different explosives for different materials, and determine the amount of
explosives needed based on the thickness of materials. For concrete column, blasters
use traditional Dynamite or similar explosive materials. Dynamite is just absorbent stuffing
soaked in a highly combustible chemical or mixture of chemicals. When the chemical is
ignited, it burns quickly, producing a large volume of hot gas in a short amount of time.
This gas expands rapidly, applying immense outward pressure (up to 600 tons per square
inch) on whatever is around it. Blasters cram this explosive material into narrow boreholes
SAQIB IMRAN 0341-7549889 94
95 | P a g e
drilled in the concrete columns. When the explosives are ignited, the sudden outward
pressure sends a powerful shock wave busting through the column at supersonic speed,
shattering the concrete into tiny chunks.
Demolition of steel column is a bit more difficult, as the dense material is much stronger.
For buildings with a steel support structure, blasters typically used the specialized
explosive material Cyclotrimethylenetrinitramine, called RDX for short. RDX – based
explosive compounds expand at a very high rate of speed, up to 27,000 feet per second
(8,230 meters per second) . Instead of disintegrating entire column, the concentrated,
high velocity pressure slices right through the steel, splitting it in half. Additionally blasters
may ignite dynamite on one side of the column to push it over in a particular direction.
5. CONCLUSION
Type of demolition method depends upon various factors such as site condition, type of
structures, age of building, height of building and economy. Anyway controlled demolition
of building is necessary to ensure safety. Explosive demolition is the preferred method
for safely and efficiently demolishing the larger structures. Almost all major building
implosions in the world are handled by 20 well-established companies, blasting is passed
on from generation to generation.
In the case of exceeding the critical height, the stability of the soil would vary
with time due to variations in pore water pressure behind the face of the
excavation wall after release of lateral pressure.
The critical height of an open excavation is calculated by dividing four times un-
drained shear strength of soil over its density.
The use of low safety factor would be adequate unless the major slip of the
excavation wall leads to the loss of life and damaging properties at the vicinity
of the construction site.
It can stand almost vertically with small soil mass fall due to erosion and frost
damage from sandy lenses in the clay. However, if pocket lenses of water
bearing sand and gravel are present in clay or when the excavation is dug
steeply and cuts fissures in the clay, then a major risk would be highly likely
and hence the excavation is massively unstable.
It is proven that, the spread of fissures in stiff clay would pose serious issues to
the stability of slope in excavations. This is because the pore water pressure
variations cannot be anticipated when the overburden pressure is removed.
The slope slippage in stiff fissured clay is either small falls due to crumbling or
slipping along fissure plan or rotational shear slide of sizable mass of clay soil.
When the slipping does not impose server risks to the surrounding structure,
then it would acceptable to use a slope of 1:0.5.
This slope will not eliminate the risk of slippage completely but the fallen soil
mass should be smaller and clearing operation should not be difficult. If the
slipping creates serious risks to the structures close to the excavation area,
then a slope of 1:2 to 1:2.5 should be adopted or the face of excavation wall
should be supported using suitable techniques.
Finally, if the excavation is not open for long time, then it is advisable to use a
sheet layer such as polyethylene or tarpaulin to the steeply excavated face to
prevent the penetration of water into the trench wall and destabilize the
excavation.
They are cohesion less soil that able to stand at a slope equal to their angle of
repose disregard of the excavation depth.
These are partially cohesive soil that able to stand vertically for a period of less
than a month.
The slope stability in this type of soil may be kept through the use of protective
layer like cement mortar to the surface.
Factors such as erosion due to surface water and wind or degradation die to
construction works are the sources of instability of steep slopes in such soil.
As far as water bearing sand is concerned, open slope excavation in such soil is
substantially unstable specifically steep slope in which water seeps from the
excavation wall face at the toe and soil would collapse at the wall upper part till
the stable angle is realized which ranges from 15-20 degree.
The stability of water bearing sand is more problematic when thin layer of silt or
clay are present.
This is because clay or silt layer may bleed from the face and consequently
jeopardize the stability of other strong layers.
It can stand vertically and the depth of excavation of more than 15m with slight
cementing on the face can be achieved.
If such slopes are not cemented, then vibration would easily disturb their
stability. Another undesired factor that lead to destabilize slopes in silt is the
erosion due water.
So, stability of slopes in wet silt is considerably difficult because erosion due to
water lead to the collapse of the excavation until a stable angle is reached.
If the bedding plane slope is steep and toward the excavation area, then the
slope would be unstable especially in the presence of ground water that
lubricator rock planes and hence facilitate slipping.
However, if the slope of bedding plane is away from the excavation area or
horizontal, then vertical slope of the excavation wall would be stable.
With regard to shattered rocks, it could lead to the collapse of the excavation
wall. For example, of the disintegrated rock falls, then the intact rock rest on
the shattered one would fall as well and eventually total collapse are likely to
occur.
10
SAQIB IMRAN 0341-7549889
0
101 | P a g e
10
SAQIB IMRAN 0341-7549889
1
102 | P a g e
Another feature of this system is that column and beams sections should be
enlarged since bending moments, shear forces, and axial forces would get
larger at the lower storeys.
Moreover, the system is claimed to be suitable for about 20 storeys and the
joints between columns and beams should be detailed properly since it would
become a weak point of the structure during earthquake.
Finally, if the above required joint detailing is failed to obtain, then soft storey
would occur which is not desirable. Therefore, moment resisting system should
not be used if proper design especially at joints cannot be produced.
10
SAQIB IMRAN 0341-7549889
2
103 | P a g e
Due to that fact that the wall takes most of shear base when walls and columns
are used in moment resisting buildings, that is why it is named as shear wall
system.
10
SAQIB IMRAN 0341-7549889
3
104 | P a g e
Dual wall systems are the combination of shear walls with frame systems. Not
only does it offer the benefits of both systems together but also eliminate their
drawbacks.
Generally, frames are placed around the perimeter of the building and shear
walls are placed at the center of the structure around staircases or lifts.
Finally, such system has two line of defense against earthquake effects the first
one is the formation of plastic hinges at the base of the wall and the second one
is the moment resisting frames that play its role after plastic hinges has been
formed.
10
SAQIB IMRAN 0341-7549889
4
105 | P a g e
It should be known that, the flat slab column joint has low ductility and
therefore flat slab strip and column frame is suitable only for gravity loads. So,
flat slab-column frame should be used as a secondary structural member.
Finally, this structural system framework is simple and cost effective and
provides clear storey height.
10
SAQIB IMRAN 0341-7549889
5
106 | P a g e
5. Tube Systems
Mega core system consists of reinforced concrete or composite shear walls with
much cross sections that conventional shear walls extended continuously
throughout the full height of the structure.
10
SAQIB IMRAN 0341-7549889
6
107 | P a g e
Mega core structural system is able to withstand both lateral loads due to
earthquakes and wind, and vertical loads and suitable for a structure with 50
storeys.
10
SAQIB IMRAN 0341-7549889
7