JMA-7100/9100 FieldServiceManual > 4.Replacement Procedure > 4.

3 Display Unit

3) Remove the cable connected to the radar


processing circuit board. Remove
The radar process circuit is the first board from the
left.

4) Remove the two fixing screws (M4).

5) Pull out the board to the front.

6) Remove the AIS processing board and the ARPA


processing board.

Remove

[Assembly]

1) Refer to Section 2.5.3 to check that the DIP


switch is correctly set on the new radar
processing circuit board.

2) Reinstall the AIS processing circuit board and


ARPA processing circuit board.

3) Install the radar processing circuit board to the


rack and secure it with two fixing screws (M4).

[Operation Check]

1) Check that the system starts up normally. Transfer the data stored in the CF card back
to the display unit (Refer to Section 7.4.3 of the Instruction Manual).
2) Input the cumulative operation hours (total time) to the display unit.
Hold down MENU ψ Input "91001" ψ "1. Initial Setup ψ 2. Input Total Time

4㧙 98