Date- 07/11/2019, 4.

30 PM

Minutes of meeting at SCPL 2X50 MW PP


Meeting Purpose – Discussion on Unit-1,2- utilization & condition monitoring reports & month
wise costing, Vacuum problem in U#2 .

Chaired by- Mr.Ashok .k. Malik (V.P)

Plant Head- Mr.Sanjay azad

Venue: Conference Room

Name Dept. Meeting arrival time


Hemant MECH. 4.30
Vjay Khare MECH. 4.30
Viresh Tiwari WTP 4.30
Akhil Malik ELECT. 4.30
JP Tiwari ELECT. 4.30
Sunil singh ELECT. 4.30
Sainit bhavasar C&I 4.30
Suresh Kumar C&I 4.30
Shisupal CHP 4.30
Kulbir Goyat C&I 4.30

The Following are discussed during the meeting –


•For unit-1, Proper De-metering of water & steam circuit in furnace & 3 rd pass zone
to be done in opportunity shut-down to avoid frequent leakages .
• Utilization reports are checked & high breakdown percentage points are discussed
along its remedial action.

• For unit-2, complete vacuum circuit of Air cooled condenser to be checked for air
ingression problem with all possible approaches like expansion bellows, rupture disks,
welding joints of tubes, . External agency is finalized for helium leak test on ACC to
find out any air leaks in system.

Attachment:

 Utilization report.
 APH data
Date- 07/11/2019, 4.30 PM