Professional Documents
Culture Documents
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Substations are important part of a power system it II. Basics of testing and commissioning
helps in transmission and distribution of electrical power system. A A. What is Testing and Commissioning?
substation receives power from generating station by transmission
Here, Testing is process to test various equipment
line and further delivers electrical power through feeder and
feeders are used to send the power in different areas. Substation according to their functions and specifications to prove its
main function is to receive energy from generating end transmit at conformity before installation for electrical system safety
high voltage for economic and reliable supply further reduce the and reliability.
voltage to a value appropriate for local distribution in distribution
substation. Commissioning is defined as a process of achieving,
verifying, and documenting that the performance of systems,
As per IS and IEC standard this paper covers the important and bring together to meet its definite objectives and criteria
equipment functions & their Testing in sub-station. Basically, sub- according to its quality.
station consists of power transformer, circuit breakers, Isolators,
Current Transformer (CT), Potential Transformer (PT), Insulators, B. What is need of Testing and Commissiong?
Lightning Arrester, etc. We have discuss different types of Testing
To check performance of equipment, specification, to
such as Power transformer testing, Current Transformer (CT)
maintain reliability of electrical system and safety. All the
testing, Potential Transformer (PT) testing, Circuit breaker testing,
tests are performed before installation.
Lightning Arrester (LA) testing and Insulator testing. The main aim After performing various tests, checking the specifications,
is to review test according to IS and IEC standards for various connections and completing the installation, we need to
equipment tests for improving reliability and to reduce faults charge the line in which the data is verified as per specific
chances in future. standards.
Key Words: Substation Equipment, Testing, IS and IEC III. Testing methods for equipment
standards.
A. Type test
I. Introduction Test carried out to prove conformity with their
Testing and commissioning of Electric substation equipment specifications these are intended to prove general qualities &
is essential to the start newly electrical system for the first design of a given type of manufactured item. Type testing is
time, considering its size, type of new installation, equipment testing to determine whether a product or system matches
used, ratings, etc. It is a very special and important for facing with the requirements which is specified. Beyond simple
some unique challenges to electrical person. Inexperience conformance other requirements for efficiency, meeting
rules or standards may apply.
and poor planning will result in delays for start newly
installation which can lead to expensively product losses. So B. Routine test
to start any project of substation installation the important Test carried out on each part or item manufactured to
thing is planning and preparation, from Engineering to check parameters which are likely to vary during production
is termed as routine test. In case of mass production, there
commissioning and start up. It provides safety by going
will be some of the test items that need to be implemented
through procedure of testing and commissioning for all the in order to make sure that the quality matches with the
Electrical system component. This paper also offers useful given samples. It is conducted on each product
guidelines on what to do when things go wrong during this manufactured to confirm proper manufacturing of each and
phase and selection of new equipment and what tests are every units. This test is essential to be performed on each
unit before dispatching the product to site. This tests are
performed before selection of equipment. intended to check the quality of the individual test unit.
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1087
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
These tests are done to ensure the reliability of test object 3. Current Distribution Test for Multi-Column – To
and consistency of the material used in their manufacture. determine the current through each column of
C. Acceptance test parallel resistor when there is no electrical
connection between columns.
Tests are carried out on samples taken at random from 4. Seal leakage test – To determine the integrity of
offered lot of manufactured items for the purpose of the arrestor seals.
acceptance of lot. Acceptance and maintenance testing is 5. Measurement of reference voltage – To measure
done for high voltage projects such as substation value within a range specified by manufacturer.
construction, transmission and distribution projects,
maintenance, labor support services, overhead and Test Performed – Acceptance test
underground system. Acceptance tests verifies the product
and actually solves the problem it was made to solve. This 1. Residual voltage test – To demonstrate the
can best be done by the user (customer), for instance protective level of arrester.
performing his/her tasks that the Equipment assists with. If 2. Measurement of power frequency voltage on
the Equipment passes all these tests, then it is accepted to complete arrestors – To measure value within a
replace the previous solution. This acceptance test can range specified by manufacturer. Short Time
sometimes only be done properly in production, especially if Withstand Current & Peak withstand Current
you have anonymous customers (e.g. ABB Circuit breaker). Test – To Prove capability of the disconnectors or
Thus a new feature will only be accepted after days or weeks earthing switches to carry the rated peak
of use. In short acceptance test is nothing but quality withstand current and the rated short time
assurance. withstand current
3. Operation Under Severe Ice – To Prove
IV. Various equipment in substation and their
satisfactory operation and mechanical
testing endurance.
4. Operation at Temperature – To Prove
A) Lightening arrester (LA)[2] satisfactory operation at minimum and maximum
Test Performed – Type Test ambient air temperature.
Standard - IS 3070 and IEC 6009-4 [See Table 1]
Test Performed – Routine test
1. Insulation withstand test – To demonstrates the
ability of the arrestor housing to withstand 1. Power Frequency Voltage Dry Withstand test of
voltage stresses under dry & wet conditions main circuit – To Verify the insulation level
2. Residual voltage test – To demonstrate the including withstand test at power frequency
protective level of arrester. voltages on auxiliary equipment.
3. Long duration current impulse withstand test – 2. Voltage test on control and auxiliary circuits – To
To Demonstrates the ability of the resistor energy Verify the insulation level of control and auxiliary
to withstand possible dielectric & energy stresses circuits.
without puncture or flashover 3. Measuring of the resistance of main circuit – To
4. Operating duty test – To demonstrate the thermal Measure resistance & confirm that it does not
stability of the arrestor under defined conditions. exceed type test value.
5. Test Arrester disconnectors – To demonstrate 4. Mechanical Operation Test – To ensure that dis-
correct operation of the disconnectors. connectors / earthing switches comply with
6. Current Distribution Test for Multi-Column – To operating conditions at rated, maximum and
determine the current through each column of minimum supply voltages.
parallel resistor when there is no electrical
connection between columns. Test Performed – Acceptance test
7. Partial discharge test – Measures the internal
partial discharge. 1. Partial Discharge Test – To Measure the internal
partial discharge.
2. Power Frequency Voltage Dry Withstand test of
Test Performed – Routine test main circuit – To Verify the insulation level
including withstand test at power frequency
1. Residual voltage test – To demonstrate the voltages on auxiliary equipment.
protective level of arrester.
2. Partial discharge test – Measures the internal Note: Table – 1 shows the maximum Withstand
partial discharge. Voltage and protection level of Lightning Arrester in
kilo-Amperes (KA).
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1088
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1089
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
1. Dielectric Tests – To Check capability and 2. Temperature rise test – To know actual
characteristics of circuit breaker with temperature rise in current transformer under
combination of voltage & the duties. loading conditions.
i. Dry, wet power frequency. 3. Lightning impulse test for current transformers
ii. Lightning impulse voltage. for service in electrically exposed – To verify
iii. Switching impulse voltage. lightning impulse voltage withstand capacity of
2. Radio interference voltage test – To Find out the installation.
radio interference voltage on pole of circuit 4. High voltage power frequency wet withstand
breaker in both close and open position. voltage test on outdoor current transformer up to
3. Measurement of resistance of the main circuit – & including 245 kV – To verify power frequency
To Record value of circuit resistance for circuit voltage withstand capacity of external insulation.
breaker for mechanical operations to be within 5. Determination of error or other characteristics
specified limits. according to requirement of designation or
4. Temperature rise test – To Ensure capability of accuracy class
the circuit breaker contents to carry rated 5.1 Current error – To measure the actual ratio
normal current within specified temperature rise against rated ratio of current transformation.
limit 5.2 Accuracy Class – To know the actual accuracy
5. Short time withstand current and peak – To against rated.
demonstrate the absolute leakage rate not 5.3 Burden – To measure the impedance of
exceeding the specified permissible value. This secondary circuit.
test can be performed on individual components
or sub individual. Test Performed – Routine test and Acceptance test.
6. Short circuit current making and breaking tests –
To Check ability of the circuit breaker to clear the 1. Determination of error or other characteristics
value of current on different tests duties in according to requirement of designation or
symmetrical and asymmetrical conditions as per accuracy class.
provisions of IEC standard. 1.1 Current error – To measure the actual ratio
against rated ratio of current transformation.
Test performed – Routine test and Acceptance test 1.2 Accuracy Class – To know the actual accuracy
against rated.
1. Dielectric Tests on main circuit – To Check the 1.3 Burden – To measure the impedance of
dielectrics withstand capability of live terminals secondary circuit.
to live terminals and to earth in both close and 2. Verification of terminal marking and polarity –
open condition of circuit breaker To ensure correct marking and function of
2. Dielectric Tests on aux. and control circuit – To current transformer.
Check the dielectrics withstand capability of 3. Power Frequency Dry withstand test on Primary
auxiliary and control circuit of circuit breaker – To verify power frequency voltage withstand
subjected to short duration (60 second) voltage capacity of primary winding (Between primary
withstand test for 2 kV. winding and earth).
3. Measurement of resistance of the main circuit – 4. Power Frequency Dry withstand test on
To Record value of circuit resistance for circuit Secondary Winding – To verify power frequency
breaker for mechanical operations to be within voltage withstand capacity of secondary winding
specified limits. (Between secondary winding and earth).
4. Tightness test – To Demonstrate the absolute 5. Over voltage inter turn test – To ensure inter turn
leakage rate not exceeding the specified insulation strength.
permissible value. This test can be performed on
individual components or sub assembly. Note: Table – 3 and 4 shows reading of rated
insulation level of Current Transformer for every
voltage Levels in kilo-volts (KV).
D) Current Transformer [5]
Test Performed – Type test
Table – 3 and 4 Standard - IS 2705 [See Table-3
and 4]
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1090
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
voltage
400 420 1175 950
4. Withstand capacity of Secondary wingding & 1300 1050
insulation. 1425 1050
5. Determination of error or other characteristics 525 525 1425 1050
according to requirement of designation or 1550 1175
accuracy class. 765 765 1800 1300
2100 1425
5.1 Current error – To measure the actual ratio 2400 1550
against rated ratio of current transformation.
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1091
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1092
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
7. Temperature Cycle Test – To check the capability of Rated Withstand Voltage For Transformer Windings With Every Voltage
Level
insulators to withstand under thermal stresses.
Highest Voltage For Rated short duration Rated Lightning
8. Test for Mechanical – To check ability to withstand Transformer power frequency Impulse Withstand
under specified falling load. KV rms withstand voltage Voltage
KV rms KV peak
9. Puncture test – To check the capability to withstand
1.1 3 -
the electrical stresses. 3.6 10 20 and 40
10. Porosity Test – To confirm non porous nature of 7.2 20 40 and 60
product.
12 28 60 and 75
11. Galvanizing Test – To determine the uniformity of 17.5 38 75 and 95
Zinc coating as well as its thickness over article. 24 50 95 and 125
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1093