OFFICE OF THE SUPERINTENDING ENGINEER (R&B)

CIRCLE ,KADAPA
T S Memo No: /RR Plan PH-II/SE-KDP/DSE-KDP/AEE-2/2018, Dt: -12-2018.
1 Head of Account 5054 - Capital out lay on Roads & Bridges
04 - District and Other Roads MH - 337 other
Expenditure GH -07 - Rural Infrastructure
Development of Road works under RIDF-SH -17 -
Rural Roads -530- Major Works -531 - Other
Expenditure.

2 Name of the Work Improvements to Khajipeta-Kamalapuram road


to Sambaturu (via) Gangavaram, Vibharapuram
and Molakavari palli from Km 0/0 to 4/355 in
Y.S.R district ( Working stretch from Km 2/290
to 4/355)

3 Sub-Head of Work Improvements to Khajipeta-Kamalapuram road


to Sambaturu (via) Gangavaram, Vibharapuram
and Molakavari palli from Km 0/0 to 4/355 in
Y.S.R district ( Working stretch from Km 2/290
to 4/355)

4 Name of work as given in the estimate Improvements to Khajipeta-Kamalapuram road


to Sambaturu (via) Gangavaram, Vibharapuram
and Molakavari palli from Km 0/0 to 4/355 in
Y.S.R district ( Working stretch from Km 2/290
to 4/355)

5 Amount of estimate
Rs.200.00 Lakhs.
6 Administative sanction Administrative sanction accorded for Rs. 200.00
lakhs vide GO Rt No.515, dated 17.12.2018 of T
R&B (R.I) department

7 Technical Sanction Technical sanction accorded for Rs. 200.00


Lakhs (Rupees Two Hundred Lakhs only) based
on S.S.R 2018-19 under Rural Roads Plan
(Phase-II).

AEE-II Dy.S.E S.E(R&B) Kadapa

To
The Executive Engineer(R&B)
Proddatur
c
DATA WITH SSR 2018-19

Name of Work ::- Improvements to Khajipeta-Kamalapuram road to Sambaturu (via) Gangavaram,


Vibharapuram and Molakavari palli from Km 0/0 to 4/355 in Y.S.R district ( Working
stretch from Km 2/290 to 4/355)
Quantity Description of Item Rate per Amount
1 Forming embankment with borrowed useful earth from outside road boundary by mechanical means upto SDR with all
leads and lifts including pre-watering of soil at borrow area, removal of top soil, excavation of soils at borrowed area,
conveyance of soil, depositing the soil on the embankment, spreading soil, breaking clods, sectioning, grading and
consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet requirement of table 300-2 of MoRT&H,
including all hire and operational charges of T&P , complete for finished item of work as per MoRT&H specification
305 (5th revision) (Payment will be made based on level for finished item of work).

Unit : Cum
Taking out put = 100 Cum Page 68,69 of MoRT&H SDB
(A) Labour
0.04 day Mate 451.00 day 18.04
1.00 day Mazdoor unskilled 400.00 day 400.00
418.04
(B) Machinery
1.67 hr Hydraulic Excavator 1 cum bucket capacity @ 60 cum 2791.60 hr 4661.97
per hour
2880.00 t.km Tipper (for 1 Km ) 160 18 7.44 t.km 21427.20
Add 10% of cost of carriage to cover cost of loading 2142.72
and unloading
0.50 hr Dozer 80 HP for spreading @ 200 cum per hour 2454.60 hr 1227.30
1.00 hr Motor Grador for Grading @ 100 cum per hour 3020.40 hr 3020.40
4.00 hr Water tanker 6 KL 655.20 hr 2620.80
1.00 hr Vibratory roller 8T 2736.20 hr 2736.20
37836.59
(D) OH charges @ 4.615% on (A) + (B)+( C) 1765.45
(E) Total of (A) + (B)+( C)+(D) 40020.08
(F) Add Contractors Profit at 10% on (E) 4002.01
Cost per 100 cum (E) + (F) 44022.09
Rate per Cum 440.22
Rate per 1 cum 440.00
1 Cum
2 Construction of Granular sub-base by providing HBD material confirming to Grading - V of MoRT&H Table 400-1
including cost and conveyance of all materials to work site and spreading in uniform layers with motor grader or by
approved means, on prepared surface mixing by mix in place method with Rotavator / approved means at OMC and
compacting with vibratory roller to achieve the desired density etc., complete for finished item of work as per MoRT&H
Specification 401 (5th revision) and as directed by the Engineer-in-charge. ( Payment will be made based on levels
for finished item of work ).

Unit = cum
Taking output = 300 cum Page 95 of MoRT&H SDB
(A) Labour
0.40 day Mate 451.00 day 180.40
2.00 day Mazdoor skilled 455.00 day 910.00
8.00 day Mazdoor unskilled 400.00 day 3200.00
Total 4290.40
(B) Machinery
6.00 hr Motor grader 3.35M Blade @50 cum/Hr 3020.40 hr 18122.40
12.00 hr Tractor with Rotavator 423.60 hr 5083.20
6.00 hr Vibratory roller 8T 2736.20 hr 16417.20
3.00 hr Water tanker 6 KL 655.20 hr 1965.60
Total 41588.40
(C) Material
Granular sub-base material as per Table 400-1 of
MORT&H
192.00 cum 53 mm to 9.5 mm @ 50% 1283.83 cum 246494.40
(Av. rate of 50 - 55 mm, 40-45 mm, 25 - 27 mm, 19
- 22 mm, 12 to 14 mm, 9.5-11.2mm HBD M/C
metal)
9.5 mm to 2.36 mm @ 35% 991.76 cum 133292.99
134.40 cum (Av. rate of 9.5-11.2mm , 5-7mm & 2.36 - 5mm HBD
M/C metal)
2.36mm and below @15% 672.22 cum 38719.87
57.60 cum
(Rate of 2.36mm & below HBD metal)
Total 418507.26
(D) Over head charges @ 4.615%
4.615 % Add for Over head charges @ 4.615% on (A)+(B)+( C) 21431.42
(E) Total of (A) + (B)+( C)+(D) 485817.48
(F) Add Contractors Profit at 10% on (E) 48581.75
Cost per 300 cum (E) + (F) 534399.23
Rate per 1 cum 1781.33
Rate to be adopted 1781.00
1 Cum
3 Providing, Laying, Spreading and compacting graded HBD crushed stone aggregate to Wet Mix macadem specification
( 5th Revision) as per Table 400-13, including cost of all materials and including premixing the material with water at
OMC in Mechanical mix plant carriage of mixed material by tipper to site , laying in uniform layers with paver in base
courses on well prepared surface and compacting with Vibratory roller to acheive the desired density etc., as directed
by the Engineer-in-Charge and as per MoRT&H specification.406 (5th revision) for finished item of work.

Unit = cum Page 110,111 of MoRT&H SDB


Taking output = 225 cum
(A) Labour
0.48 nos. Mate 451.00 day 216.48
2.00 nos. Mazdoor skilled 455.00 day 910.00
10.00 nos. Mazdoor 400.00 day 4000.00
Total 5126.48
(B) Machinery
6.60 hr Wet mix plant of 60 tonne hr. capacity 1679.70 hr 11086.02
6.00 hr Electric generating set 125 KVA 1543.10 hr 9258.60
6.00 hr front end loader 1 cum capacity 1594.70 hr 9568.20
6.00 hr Mechanical Paver finisher 100 TPH 2290.60 hr 13743.60
3.90 hr Vibratory roller 8-10 T 2736.20 hr 10671.18
3.00 hr Water tanker 655.20 hr 1965.60
Total 56293.20
(C) Material

Page 4
Quantity Description of Item Rate per Amount
89.10 cum 45 to 22.40mm IRC&MoRT&H HBD M/C metal@ 30% 1407.64 cum 125420.43

(Av. Of 40-45, 25-27, 19-22mm )


118.80 cum 22.4 to 2.36 mm IRC&MoRT&H HBD M/C metal@40% 1178.75 cum 140035.02
(Av. Of 19-22mm, 12-14mm, 9.5-11.2mm, 5-7mm,
2.36 to 5 mm)
89.10 cum 2.36 - 5mm
2.36 mm ) micron @ 30% (2.36mm & below)
to 75 672.22 cum 59894.80
Total 325350.25
(D) Over head charges @ 4.615%
4.615 % Add for Over head charges @ 4.615% on (A)+(B)+( C) 17849.43
(E) Total of (A) + (B)+( C)+(D) 404619.36
(F) Add Contractors Profit at 10% on (E) 40461.94
Cost per 225 cum (E) + (F) 445081.30
Rate per 1 cum 1978.14
Rate to be adopted per 1 cum 1978.00
Cum
4 Providing and applying prime coat with bitumen emulsion (SS1) Bulk using emulsion pressure distributor on
prepared surface of granular base including clearing of road surface and spraying emulsion at the rate of 0.70
kg/sqm using emulsion pressure distributor for finished item of work etc., complete as per MoRT&H Specification
502 (5th revision) and as directed by the Engineer-in-charge

Unit = sqm
Taking output = 3500 sqm
a) Labour
0.080 day Mate 451.00 day 36.08
2.000 day Mazdoor 400.00 day 800.00
836.08
b) Machinery
2.800 hr Mechanical broom @ 1250 sqm 381.80 hour 1069.04
2.800 hr Air compressor 250 cfm 556.50 hour 1558.20
2.000 hr Emulsion pressure distributor @ 875.60 hour 1751.20
1.000 hr Water tanker 6 KL capacity @ 1 655.20 hour 655.20
5033.64
c) Material
2.450 MT Bitumen emulsion @ 0.7 kg per sqm 45746.40 MT 112078.68
a+b+c 117948.40
4.615 % d) OH Charges on (a+b+c) 5443.32
a+b+c+d 123391.72
e) Contractor's profit @ 10 % input on
12339.17
(a+b+c+d)
Cost for 3500 sqm = 135730.89
Rate per sqm = 38.78
38.80
1 Sqm
5 Providing and applying tack coat with bitumen VG-10 (Bulk) using Bitumen pressure distributor at the rate of 0.20
kgs per sqm on the prepared bituminous surface cleaned with mechanical broom for finished item of work as per
MoRT&H Specification 503 (5th revision) and as directed by the Engineer-in-Charge.

unit = sqm Page 124 of MoRT&H SDB


Taking output = 3500 sqm
(A) Labour
0.08 nos Mate 451.00 day 36.08
2.00 nos Mazdoor 400.00 day 800.00
Total 836.08
(B) Machinery
2.80 hr Mechanical broom Hydraulic @ 1250 sqm/hr. 381.80 hr 1069.04
2.80 hr Air compressor 250 cfm 556.50 hr 1558.20
2.00 hr Bitumen pressure distributor @1750 sqm/hr 1527.10 hr 3054.20
Total 5681.44
(C) Material

Page 5
Quantity Description of Item Rate per Amount
0.70 MT Bitumen VG-10 (Bulk) @ 0.20 Kgs/sqm 32706.40 MT 22894.48
Total 22894.48
(D) Over head charges @ 4.615%
4.615 % Add for Over head charges @ 4.615% on (A)+(B)+( C) 1357.36
(E) Total of (A) + (B)+( C)+(D) 30769.36
(F) Add Contractors Profit at 10% on (E) 3076.94
Cost per 3500 sqm (E) + (F) 33846.30
Rate per 1 sqm 9.67
Rate to be adopted 9.70
1 Sqm
6 Providing and applying tack coat with bitumen VG-10 (Bulk) using Bitumen pressure distributor at the rate of 0.25
kgs per sqm on the prepared Granular surface treated with primer cleaned with mechanical broom for finished
item of work as per MoRT&H Specification 503 (5th revision) and as directed by the Engineer-in-Charge.

unit = sqm Page 124 of MoRT&H SDB


Taking output = 3500 sqm
(A) Labour
0.08 nos Mate 451.00 day 36.08
2.00 nos Mazdoor 400.00 day 800.00
Total 836.08
(B) Machinery
2.80 hr Mechanical broom Hydraulic @ 1250 sqm/hr. 381.80 hr 1069.04
2.80 hr Air compressor 250 cfm 556.50 hr 1558.20
2.00 hr Bitumen pressure distributor @1750 sqm/hr 1527.10 hr 3054.20
Total 5681.44
(C) Material
0.875 MT Bitumen VG-10 (Bulk) @ 0.25 Kgs/sqm 32706.40 MT 28618.10
Total 28618.10
(D) Over head charges @ 4.615%
4.615 % Add for Over head charges @ 4.615% on (A)+(B)+( C) 1621.51
(E) Total of (A) + (B)+( C)+(D) 36757.13
(F) Add Contractors Profit at 10% on (E) 3675.71
Cost per 3500 sqm (E) + (F) 40432.84
Rate per 1 sqm 11.55
Rate to be adopted 11.60
1 Sqm
7 Providing and laying of 50mm thick Bituminous Macadam with 100 -120 TPH hot mix plant producing an average
output of 75 tonnes per hour using hard blasted granite crushed aggregates of Grading - II as per table 500-7 of
MoRT&H specificaion 504 (5th Revision) premixed with bituminous binder of VG-30 grade @ 3.4 % by weight of
total mixture, transported to site, laid over a previously prepared surface with Hydrostatic paver finisher with sensor
control to the required grade, level and alignment and rolled as per Clauses 501.6 and 501.7 to achieve the desired
compaction for finished item of work as directed by the Engineer-in-Charge including hire and opeational charges all
T&P and all other contingent charges necessary , complete and as per MoRTH specification No. 504 (5th Revision) .

Unit = cum
Taking out put = 205 cum (450 tonne) Page 125,126,127 of MoRT&H SDB
(A) Labour
0.84 nos. Mate 451.00 nos. 378.84
14.00 nos. Mazdoor working with HMP, mechanical broom, 400.00 nos. 5600.00
paver, roller, asphalt cutter and assistance for setting
out lines, levels and layout of construction

5.00 nos. Mazdoor skilled 455.00 nos. 2275.00


Total 8253.84
(B) Machinery
6.00 hr Batch mix Hot mix plant @ 100 - 120 TPH 24636.00 hr 147816.00
2.20 hr Air Compressor 250 cfm 556.50 hr 1224.30
6.00 hr Hydrostatic Paver finisher with sensor control 3115.20 hr 18691.20
6.00 hr Generator 250 KVA 2162.60 hr 12975.60
6.00 hr Front end loader 1 cum bucket capacity 1594.70 hr 9568.20
3.90 hr Smooth wheeled roller 8-10 tonnes for initial break 1329.90 hr 5186.61
down rolling
3.90 hr Vibratory roller 8 tonnes for intermediate rolling 2736.20 hr 10671.18

3.90 hr Finish rolling with 6-8 tonnes smooth wheeled 1856.50 hr 7240.35
tandem roller.
Total 213373.44
(C) Material
15.30 MT Bitumen 60/70 @ 3.4 % of weight of mix = 33506.40 MT 512647.92
205x2.2=450 tonne

ii) Aggregate
Total weight of mix = 450 tonnes 15.3
weight of bitumen - 15.3 tonnes
Weight of aggregate = 450-15.3 = 434.7 tonnes
Taking density of aggregate = 1.5 tonne/cum 289.8
Volume of aggregate = 289.8 cum 1.41366
Grading - II (19 mm nominal size)
116.04 Cum of 25-10mm @ 40%
115.92 cum IRC & MORT&H HBD M/C chips 25 to 10mm @ 40% 1410.41 cum 163494.44

Average rate of IRC&MoRT&H HBD M/C metal of


sizes 25-27mm, 19-22mm, 12-14mm, 9.5-11.2mm

115.92 cum IRC &MORT&H HBD M/C chips 10 to 5mm @ 40% 1099.69 cum 127476.06

Average rate of IRC&MoRT&H HBD M/C metal of


sizes 9.5-11.2mm, 5 to 7mm
57.96 cum IRC &MORT&H HBD M/C chips 5mm and below @ 724.07 cum 41966.81
20%
Average rate of IRC&MoRT&H HBD M/C metal of
sizes 2.36 to 5mm and 2.36mm& below
Total 845585.23
(D) Over head charges @ 4.615%
4.615 % Add for Over head charges @ 4.615% on (A)+(B)+( C) 49251.86
(E) Total of (A) + (B)+( C)+(D) 1116464.37
(F) Add Contractors Profit at 10% on (E) 111646.44
Cost per 205 cum (E) + (F) 1228110.81
Rate per 1 cum 5990.78
Rate to be adopted 5991.00

Page 6
Quantity Description of Item Rate per Amount
1 Cum

Page 7
Quantity Description of Item Rate per Amount
8 Providing , laying of close graded premix surfacing material ( Mixed seal surfacing) of 20 mm thickness by hot mix
plant using hard blasted granite crushed aggregates of 13.2 mm to 0.09 mm (Type 'B') as per table 500-19 of
specification 508 of MoRT&H (5th Revision), premixed with bituminous binder VG-30 (60/70) grade @ 19.00 Kg
per 10 Sqm area, including cost of all materials and transporting the hot mix to work site, laying with mechanical
paver finisher to the required grade, level and alignment, rolling with smooth wheeled roller 8 to 10 Tonnes as per
MoRT&H (5th Revision) Specification No. 508 complete for finished item of work in all respects as directed by
Engineer-in-charge.

Unit = sqm Page 146,147 of MoRT&H SDB


Taking output = 10250 sqm (205 cum)
(A) Labour
0.84 nos. Mate 451.00 day 378.84
Mazdoor working with HMP, road sweeper, paver and
14.00 nos. 400.00 day 5600.00
roller
5.00 nos. Skilled Mazdoor for checking line and levels. 455.00 day 2275.00
Total 8253.84
(B) Machinary
12.00 hr Hot mix plant 40 to 60 TPH 19546.00 hr 234552.00
6.00 hr Generator 250 KVA 2162.60 hr 12975.60
6.00 hr Front end loader 1 cum capacity 1594.70 hr 9568.20
6.00 hr Paver finisher hydrostatic with sensor control 3115.20 hr 18691.20
6.00 hr Smooth wheeled roller 8-10 Tonnes 1329.90 hr 7979.40
Total 283766.40
(C) Material
19.475 M.T (i) Bitumen VG-30 Grade @ 19.00 kg per 10 sqm 33506.40 MT 652537.14
(ii) Aggregate
For Type 'B'
HBD M/C aggregates 13.2mm to 0.09mm @ 0.27
cum per 10 sqm
Average rate of IRC&MoRT&H HBD M/C metal of
276.75 cum sizes 12-14, 9.5-11.2, 5-7mm,2.36 - 5mm and 997.06 cum 275935.80
HBD 2.36 mm & below
Total 928472.94
(D) Over head charges @ 4.615 % on (A) + (B)+( C)
4.615 % Add for Over head charges @ 6% on (A)+(B)+( C) 56325.76
(E) Total of (A) + (B)+( C)+(D) 1276818.94
(F) Add Contractors Profit at 10% on (E) 127681.89
Cost per 10250 Sqm (E) + (F) 1404500.83
Rate per 1 sqm 137.02
Rate to be adopted 137.00
1 sqm
9 Providing Vibrated Cement Concrete (1:4:8) mix using 40mm size HBD crushed stone aggregate and fine aggregate
conforming to table 1000-2 of MoRT&H including cost, conveyance of all materials to site and labour charges,
centering, machine mixing, laying, Vibrating, curing etc., including all other incidental and operational charges of all
T&P etc., complete for finished item of work as per MoRT&H specification 1500,1700, 2100 (5th Revision) and as
directed by the Engineer-in-Charge for base coarse below CC Pavement

Unit = cum
Taking output = 15 cum
(A) Labour
0.64 nos Mate 451.00 day 288.64
1.00 nos Mason 455.00 day 455.00
15.00 nos Mazdoor 400.00 day 6000.00
Total 6743.64
(B) Material
13.50 cum Cost of 40mm SS-5 HBD M/C metal 1147.22 cum 15487.47
6.75 cum Sand at site 290.47 cum 1960.67
2.43 MT Cement at site 3900.00 MT 9477.00
Total 26925.14
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 525.50 hr 3153.00
6.00 hr Generator set 35 KVA 1032.00 hr 6192.00
2.00 hr Water tanker 6 KL 655.20 hr 1310.40
Total 10655.40
(D) Over head charges @ 4.615%
4.615 % Add for Over head charges @ 4.615% on (A)+(B)+( C) 2045.56
(E) Total of (A) + (B)+( C)+(D) 46369.74
(F) Add Contractors Profit at 10% on (E) 4636.97
Cost per 15 cum (E) + (F) 51006.71
Rate for 1 cum 3400.45
Rate to be adopted 3400.00
1 Cum
10 Vibrated cement concrete M 35 grade using 20mm & 10mm HBD crushed stone aggregate (Coarse aggregate
conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, conveyance of all
materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc., including all other
incidental and operational charges of all T&P etc., complete for finished item of work as per MoRT&H specification
1500, 1700, 2100 & 2702 (5th Revision) and as directed by the Engineer-in-Charge for C.C Pavement.

Unit = cum Page 345,346 of MoRT&H SDB


Taking output = 15 cum
(A) Labour
0.86 nos Mate 451.00 day 387.86
1.50 nos Mason 455.00 day 682.50
20.00 nos Mazdoor 400.00 day 8000.00
Total 9070.36

(B) Material
8.10 cum Cost of 20mm SS-5 HBD M/C metal 1642.22 cum 13301.98
5.40 cum Cost of 10mm SS-5 HBD M/C metal 1233.22 cum 6659.39
6.75 cum Sand at site 290.47 cum 1960.67
6.33 MT Cement at site 3900.00 MT 24687
Total 46609.04
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 525.50 hr 3153.00
6.00 hr Generator set 35 KVA 1032.00 hr 6192.00
9345.00
(D) Form work
3.50 % Form work @ 3.50% on (A)+(B)+( C) 65024.40 Cum 2275.85
(E) Over head charges @ 4.615%
4.615 % Add for Over head charges @ 4.615% on (A)+(B)+( C)+(D) 3105.91
(F) Total of (A) + (B)+( C)+(D)+(E) 70406.16
(G) Add Contractors Profit at 10% on (F) 7040.62

Page 8
Quantity Description of Item Rate per Amount
Cost per 15 cum (F)+(G) 77446.78
Rate for 1 cum 5163.12
Rate to be adopted 5163.00
1 Cum
11 Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing and
technical specification including setting out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing sides of bottom, back filling the excavation earth to the extent required etc., complete
for finished item of work, excluding seigniorage charges, as per MoRT&H specification 304 (5th Revision) and as
directed by the Engineer-in-Charge

Unit : Cum Page 323 of MoRT&H SDB


Taking out put = 240 Cum
(A) Labour
0.32 day Mate 451.00 day 144.32
8.00 day Mazdoor unskilled 400.00 day 3200.00
3344.32
(B) Machinery
6.00 hr Hydraulic Excavator 1 cum bucket capacity @ 60 cum 2791.60 hr 16749.60
per hour
(C) Over head charges @ 4.615% on (A) + (B) 927.33
(D) Total of (A) + (B)+( C) 21021.25
(E) Add Contractors Profit at 10% on (D) 2102.13
Cost per 240 cum (D)+(E) 23123.38
Rate for 1 cum 96.35
Rate to be adopted 96.30
1 Cum
12 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBD crushed stone aggregate and fine aggregate
conforming to table 1000-2 of MoRT&H including cost, conveyance of all materials to site and labour charges,
centering, machine mixing, laying, Vibrating, curing etc., including all other incidental and operational charges of all
T&P etc., complete for finished item of work as per MoRT&H specification 1500,1700, 2100 (5th Revision) and as
directed by the Engineer-in-Charge for foundation.

Unit = cum Page 331 of MoRT&H SDB


Taking output = 15 cum
(A) Labour
0.64 nos Mate 451.00 day 288.64
1.00 nos Mason 455.00 day 455.00
15.00 nos Mazdoor 400.00 day 6000.00
Total 6743.64
(B) Material
13.50 cum Cost of 40mm SS-5 HBD M/C metal 1147.22 cum 15487.47
6.75 cum Sand at site 290.47 cum 1960.67
3.45 MT Cement at site 3900.00 MT 13455.00
Total 30903.14
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 525.50 hr 3153.00
6.00 hr Generator set 35 KVA 1032.00 hr 6192.00
2.00 hr Water tanker 6 KL capacity 655.20 hr 1310.40
Total 10655.40
(D) Over head charges @ 4.615%
4.615 % Add for Over head charges @ 4.615% on (A)+(B)+( C) 2229.15
(E) Total of (A) + (B)+( C)+(D) 50531.33
(F) Add Contractors Profit at 10% on (E) 5053.13
Cost per 15 cum (E)+(F) 55584.46
Rate for 1 cum 3705.63
Rate to be adopted 3706.00
1 Cum
13 Providing, laying Reinforced cement concrete Hume pipes of 1000 mm Dia., NP-4 class for pipe culverts including
cost and conveyance of Pipes etc., complete and Labour charges for laying, jointing of 1000 mm dia. R.C.C Hume
pipes in position including lifting, aligning, lowering and hoisting etc., as per drawing and as per MoRT&H Specification
2900, 2905 and 2906 (5th Revision) and IRC Special Publication No: 13 and as directed by the Engineer-in-Charge
for finished item of work.

Unit = metre Page 272,273 of MoRT&H SDB


Taking output = 12.5 metre
1000 mm Dia.
(A) Labour
0.18 nos Mate 451.00 day 81.18
0.50 nos Mason 455.00 day 227.50
4.00 nos Mazdoor 400.00 day 1600.00
Total 1908.68
(B) Material
12.50 RM Cost of 1000mm Dia., pipes 7708.18 RM 96352.30
Total 96352.30
(C) Over head charges @ 4.615%
4.62 % Add for Over head charges @ 4.615% on (A)+(B) 4534.74
(D) Total of (A) + (B)+( C) 102795.72
(E) Add Contractors Profit at 10% on (D) 10279.57
Cost per 12.5 metre (D)+(E) 113075.29
Rate for 1 RM 9046.02
Rate to be adopted 9046.00
1 RM
14 Filling in between body walls with gravel including cost and conveyance of all materials to site etc., complete as
per Clause 710.1.4 of IRC : 78 and as per MoRT&H Specification No. 2200 & 2907 (5th Revision) and as per
Drawing and technical specifications for finished item of work.

Unit = cum Page 462 of MoRT&H SDB


Taking output = 10 cum
(A) Labour
0.28 nos Mate 451.00 day 126.28
7.00 nos Mazdoor 400.00 day 2800.00
Total 2926.28
(B) Material

Page 9
Quantity Description of Item Rate per Amount
12.00 cum Cost of Gravel 334.79 cum 4017.48
Total 4017.48
© Machinery
2.50 hr Plate compactor/Power rammer/road roller 59.10 hr 147.75
0.05 hr Water tanker 6 KL capacity 655.20 hr 32.76
Total 180.51
(D) Over head charges @ 4.615%
4.615 % Add for Over head charges @ 4.615 % on (A)+(B)+(C) 328.79
(E) Total of (A) + (B)+( C)+(D) 7453.06
(F) Add Contractors Profit at 10% on (E) 745.31
Cost per 10 cum (E)+(F) 8198.37
Rate for 1 cum 819.84
Rate to be adopted 820.00
1 Cum
15 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBD crushed stone aggregate
(Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost and
conveyance of all materials to site and all labour charges for machine mixing,laying in position, Compacting ,
Vibrating and curing including all other incidental and all other operational charges of T&P required etc., complete as
per MoRT&H Specification 1500,1700, 2100 (5th Revision) for footings and Raft foundation .
Unit = cum Page 335 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate 451.00 day 387.86
1.50 nos Mason 455.00 day 682.50
20.00 nos Mazdoor 400.00 day 8000.00
Total 9070.36
(B) Material
8.10 cum Cost of 40mm SS-5 HBD M/C metal 1147.22 cum 9292.48
4.05 cum Cost of 20mm SS-5 HBD M/C metal 1642.22 cum 6650.99
1.35 cum Cost of 10mm SS-5 HBD M/C metal 1233.22 cum 1664.85
6.75 cum Sand at site 290.47 cum 1960.67
4.13 MT Cement at site 3900.00 MT 16107.00
Total 35675.99
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 525.50 hr 3153.00
6.00 hr Generator set 35 KVA 1032.00 hr 6192.00
9345.00
(D) Form work
4.00 % Form work @ 4% on (A)+(B)+( C) 54091.35 Cum 2163.65
(E) Over head charges @ 4.615%
4.615 % Add for Over head charges @ 4.615% on (A)+(B)+( C)+(D) 2596.17
(F) Total of (A) + (B)+( C)+(D)+(E) 58851.17
(G) Add Contractors Profit at 10% on (F) 5885.12
Cost per 15 cum (F)+(G) 64736.29
Rate for 1 cum 4315.75
Rate to be adopted 4316.00
1 Cum
16 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBD crushed stone aggregate
(Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost and
conveyance of all materials to site and all labour charges for machine mixing, laying in position,Compacting,
Vibrating and curing including all other incidental and all other operational charges of T&P required etc., complete as
per MoRT&H Specification 1500,1700, 2200 (5th Revision) for Sub structure .

Unit = cum Page 335,455 of MoRT&H SDB


Taking output = 15 cum
(A) Labour
0.86 nos Mate 451.00 day 387.86
1.50 nos Mason 455.00 day 682.50
20.00 nos Mazdoor 400.00 day 8000.00
Total 9070.36
(B) Material
8.10 cum Cost of 40mm SS-5 HBD M/C metal 1147.22 cum 9292.48
4.05 cum Cost of 20mm SS-5 HBD M/C metal 1642.22 cum 6650.99
1.35 cum Cost of 10mm SS-5 HBD M/C metal 1233.22 cum 1664.85
6.75 cum Sand at site 290.47 cum 1960.67
4.13 MT Cement at site 3900.00 MT 16107.00
Total 35675.99
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 525.50 hr 3153.00
6.00 hr Generator set 35 KVA 1032.00 hr 6192.00
9345.00
(D) Form work
10.00 % Form work @ 10% on (A)+(B)+( C) 54091.35 Cum 5409.14
(E) Over head charges @ 4.615%
4.615 % Add for Over head charges @ 4.615% on (A)+(B)+( C)+(D) 2745.95
(F) Total of (A) + (B)+( C)+(D)+(E) 62246.44
(G) Add Contractors Profit at 10% on (F) 6224.64
Cost per 15 cum (F)+(G) 68471.08
Rate for 1 cum 4564.74
Rate to be adopted 4565.00
1 Cum

Page 10
Quantity Description of Item Rate per Amount
17 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters including cost and
conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting, bending, binding
rods, tying grills, placing them in position etc., complete including cost and conveyance of binding wire and all
handling charges and operational charges etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the directions of the Engineer-in-Charge and as
per MoRT&H specification 1600 & 2300 (5th revision) and as per I.S.1786 of 1985 for Super structure of R.C.C
items.

Unit = MT Page 489,490 of MoRT&H SDB


Taking output = 1 MT
(A) Labour
0.44 nos Mate 451.00 day 198.44
3.00 nos Black smith 475.00 day 1425.00
8.00 nos Mazdoor 400.00 day 3200.00
Total 4823.44
(B) Material
1.05 MT HYSD bars including overlaps 41300.00 MT 43365.00
6.00 Kg Binding wire 53.00 MT 318.00
Total 43683.00
(C) Over head charges @ 4.615%
4.615 % Add for Over head charges @ 4.615% on (A)+(B) 2238.57
(D) Total of (A) + (B)+( C) 50745.01
(E) Add Contractors Profit at 10% on (D) 5074.50
Rate for 1 MT (D)+(E) 55819.51
Rate to be adopted 55820.00
1 MT
18 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters including cost and
conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting, bending, binding
rods, tying grills, placing them in position etc., complete including cost and conveyance of binding wire and all
handling charges and operational charges etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the directions of the Engineer-in-Charge and as
per MoRT&H specification 1600 & 2100 (5th revision) and as per I.S.1786 of 1985 for foundations of R.C.C
items.

Unit = MT Page 448 of MoRT&H SDB


Taking output = 1 MT
(A) Labour
0.40 nos Mate 451.00 day 180.40
2.00 nos Black smith 475.00 day 950.00
6.00 nos Mazdoor 400.00 day 2400.00
Total 3530.40
(B) Material
1.05 MT HYSD bars including overlaps 41300.00 MT 43365.00
6.00 Kg Binding wire 53.00 Kg 318.00
Total 43683.00
(C) Over head charges @ 4.615%
4.615 % Add for Over head charges @ 4.615% on (A)+(B) 2178.90
(D) Total of (A) + (B)+( C) 49392.30
(E) Add Contractors Profit at 10% on (D) 4939.23
Rate for 1 MT (D)+(E) 54331.53
Rate to be adopted 54332.00
1 MT
19 Providing Uncoated Mild Steel bars ( Fe-250 ) of different diameters, wrought and put up bars of all diameters
including cost and conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting,
bending, binding rods, tying grills, placing them in position etc., complete including cost and conveyance of binding
wire and all handling charges and operational charges etc., and including over lapping welding if required etc.,
complete for all R.C.C items for finished item of work as per standard drawings, as per the directions of the Engineer-
in-Charge and as per MoRT&H specification 1600 & 2200 (5th revision) and as per I.S.1786 of 1985 .

Unit = MT Page 460 of MoRT&H SDB


Taking output = 1 MT
(A) Labour
0.28 nos Mate 451.00 day 126.28
1.50 nos Black smith 475.00 day 712.50
5.50 nos Mazdoor 400.00 day 2200.00
Total 3038.78
(B) Material
1.05 MT Mild steel bars including overlaps 41500.00 MT 43575.00
6.00 Kg Binding wire 53.00 Kg 318.00
Total 43893.00
(C) Over head charges @ 4.615%
4.615 % Add for Over head charges @ 4.615% on (A)+(B) 2165.90
(D) Total of (A) + (B)+( C) 49097.68
(E) Add Contractors Profit at 10% on (D) 4909.77
Rate for 1 MT 54007.45
Rate to be adopted 54007.00
1 MT
20 Providing 25.4 mm thick Mastic pads for Expansion joints etc., complete for finished item of work.

Rate as per Buildings SSR 2017-18 (BMS - W .20) 839.000


1Sqm

21 Supplying and laying of seperation membrane 125 micron and as per ISI standard specification duly fixing over DLCC
including cost, conveyance of all materials etc., complete and as directed by the Engineer-in-Charge during execution
of work.
Rate as per SoR 2017-18 15.25
1Sqm

Page 11
657 1.28

1.28

1791

1.32

25

6.6 1.32

Page 12
2450

23.3

Page 13
0.875 875

1.413658537

451

434.7

115.92

57.96

Page 14
19475

Page 15
0.45

Page 16
4

Page 17
Page 18
Page 19
Page 20
COST OF BITUMEN / MT WITH LEADS

N.W:- Improvements to Khajipeta-Kamalapuram road to Sambaturu (via) Gangavaram,


Vibharapuram and Molakavari palli from Km 0/0 to 4/355 in Y.S.R district ( Working
stretch from Km 2/290 to 4/355)
Ref ::- For Emulsion (Bulk) , IOCL Price List with effect from Dt. 16.12.2018
For Bulk Bitumen VG-30 & VG-10 IOCL Price List With effect from Dt. 16.12.2018

Bulk VG-30 Grade Emulsion (SS1) Bulk VG-10 Grade


Chennai Chennai Chennai

Basic Price 32490.00 44730.00 31690.00

Total 32490.00 44730.00 31690.00

Lead from Chennai

308.00 Kms 1016.40 1016.40 1016.40


Lead charges for Bulk @
1.65 per KM

33506.40 45746.40 32706.40


ROAD METAL RATES (SoR 2018-19)

Improvements to Khajipeta-Kamalapuram road to Sambaturu (via)


NAME OF WORK ::- Gangavaram, Vibharapuram and Molakavari palli from Km 0/0 to 4/355 in
Y.S.R district ( Working stretch from Km 2/290 to 4/355)
Machine
Sl. Lead in Blasting Toal Cost
Description of Material Source of Supply Conveyance Initial cost crushing
No Kms charges per Cum
charges
A) FOR ROAD WORKS
60 to 63 mm IRC and MoRTH
1 28 339.22 399.05 70.00 808.27
HBD metal
40 to 45 mm IRC and MoRTH
2 28 339.22 560.00 70.00 969.22
HBD metal

3 SS Revetment work 300mm 28 339.22 156.00 70.00 565.22


Quarry spall(Field picked
4 metal) 28 339.22 47.15 386.37
Av. Of rate 25mm & 40mm
150 mm soling stone
5 28 339.22 90.50 70.00 499.72
HBD metal
Jeddy Stone 450 mm to 600
6 28 339.22 196.20 70.00 605.42
mm thick
50 to 55 mm IRC and MoRTH
7 28 339.22 434.30 70.00 108.58 952.10
HBD metal

40 to 45 mm IRC and MoRTH


8 28 339.22 560.00 70.00 140.00 1109.22
HBD M/C metal

25 to 27 mm IRC and MoRTH


9 28 339.22 899.05 70.00 224.76 1533.03
HBD M/C metal

19 to 22 mm IRC and MoRTH


10 28 339.22 937.15 70.00 234.29 1580.66
HBD M/C metal
12 to 14 mm IRC and MoRTH
11 28 339.22 742.85 70.00 185.71 1337.78
HBD M/C metal
9.5 to 11.20 mm IRC and
12 MoRTH 28 339.22 624.75 70.00 156.19 1190.16
HBD M/C metal
5 to 7 mm IRC and MoRTH
13 28 339.22 480.00 70.00 120.00 1009.22
HBD M/C metal
2.36 to 5 mm IRC and MoRTH
14 28 339.22 293.35 70.00 73.34 775.91
HBD M/C metal
HBD Stone chips 2.36mm
15 28 339.22 333.00 672.22
and below
16 Filler material 28 339.22 84.75 423.97
17 Gravel 18 224.79 110.00 334.79
B) FOR C.D. WORKS
18 40 mm SS-5 HBD M/C metal 28 339.22 590.40 70.00 147.60 1147.22
19 25 mm SS-5 HBD M/C metal 28 339.22 947.20 70.00 236.80 1593.22
20 20 mm SS-5 HBD M/C metal 28 339.22 986.40 70.00 246.60 1642.22
21 12 mm SS-5 HBD M/C metal 28 339.22 782.40 70.00 195.60 1387.22
22 10 mm SS-5 HBD M/C metal 28 339.22 659.20 70.00 164.80 1233.22
23 6 mm SS-5 HBD M/C metal 28 339.22 506.40 70.00 126.60 1042.22
24 Sand for Concrete 15 190.47 100.00 290.47
25 Sand for Filling 15 190.47 100.00 290.47
26 Sand for Mortar 15 190.47 182.00 372.47
27 HYSD Steel 41300.00 41300.00
GO RT No. 158 T,
28 6mm Mild Steel R&B (R-I) Dept. dt. 41500.00 41500.00
9.5.2018
29 Mild Steel 40000.00 40000.00
30 Cement 3900.00 3900.00

31 Hume Pipes 300 mm Dia., NP4 27 79.37 842.35 921.72

32 Hume Pipes 450 mm Dia., NP4 27 120.39 1250.00 1370.39

33 Hume pipes 600mm Dia., NP4 27 228.12 2405.48 2633.60

34 Hume pipes 800mm Dia., NP4 27 284.64 4205.16 4489.80

35 Hume pipes 900mm Dia., NP4 27 450.35 5256.55 5706.90

36 Hume pipes 1000mm Dia., NP4 27 490.92 7217.26 7708.18

37 Hume pipes 1200mm Dia., NP4 27 563.86 9782.03 10345.89


Cement for NP3 & NP4 As per 1S 458 2003

barrel Volume of Wt. of


thick concrete cement

300 40 0.04274286 19.234


450 75 0.12375 55.688
600 85 0.18299286 82.347
800 95 0.26722143 120.250
900 100 0.31428571 141.429
1000 115 0.40299286 181.347
1200 120 0.49782857 224.023
Steel for NP 4
300 3.815
450 5.126
600 13.126
800 27.184
900 33.826
1000 45.778
1200 65.478
Steel for NP3
300 2.796
450 5.025
600 9.031
800 17.265
900 23.156
1000 26.762
1200 41.148
LEAD CHARGES Cost of Materials, Labour
Earth/Gravel/ Metal
Sand
1 28.52 27.73 Material Rates
2 39.87 38.82 60 to 63 mm IRC & MoRTH HBG metal 399.05
3 53.25 53.25 50 to 55 mm IRC & MoRTH HBG metal 434.30
4 64.60 64.60 40 to 45 mm IRC & MoRTH HBG metal 560.00
5 76.05 76.05 Quarry Rubbish 84.75
6 87.49 87.49 Roughstone 300mm (HBG)for revetment 163.80
7 98.93 98.93 Roughstone 225mm (HBG)for revetment 168.55
8 110.37 110.37 SS Revetment work 225mm 138.00
9 121.81 121.81 SS Revetment work 300mm 156.00
10 133.26 133.26 SS Revetment work 450mm 148.55
11 144.70 144.70 Laterite for Revetment 225mm 129.50
12 156.14 156.14 Laterite for Revetment 300mm 151.43
13 167.58 167.58 Jeddy stone above 450mm to 600mm 196.20
Quarry spall(Field picked metal)
47.15
14 179.03 179.03 Av. Of rate 25mm & 40mm
15 190.47 190.47 150 mm soling stone HBG metal 90.50
16 201.91 201.91 40 to 45 mm IRC & MoRTH HBG M/C metal 560.00
17 213.35 213.35 25 to 27 mm IRC & MoRTH HBG M/C metal 899.05
18 224.79 224.79 19 to 22 mm IRC & MoRTH HBG M/C metal 937.15
19 236.24 236.24 12 to 14 mm IRC & MoRTH HBG M/C metal 742.85
20 247.68 247.68 9.5 to 11.20 mm IRC & MoRTH HBG M/C metal 624.75
21 259.12 259.12 5 to 7 mm IRC & MoRTH HBG M/C metal 480.00
22 270.56 270.56 2.36 to 5 mm IRC & MoRTH HBG M/C metal 293.35
23 282.01 282.01 HBG Stone chips 2.36mm and below 333.00
24 293.45 293.45 Gravel 110.00
25 304.89 304.89 40 mm SS-5 m/c HBG metal 590.40
26 316.33 316.33 25 mm SS-5 m/c HBG metal 947.20
27 327.77 327.77 20 mm SS-5 m/c HBG metal 986.40
28 339.22 339.22 12 mm SS-5 m/c HBG metal 782.40
29 350.66 350.66 10 mm SS-5 m/c HBG metal 659.20
30 362.10 362.10 6 mm SS-5 m/c HBG metal 506.40
31 371.61 371.61 Sand for concrete 100.00
32 381.11 381.11 Sand for Filling 100.00
33 390.62 390.62
34 400.12 400.12
35 409.63 409.63
36 419.13 419.13
37 428.64 428.64 Blasting charges
38 438.15 438.15 Blasting charges 70.00
39 447.65 447.65 Blasting charges for rough stone 70.00
40 457.16 457.16 Seigniorage charges
41 466.66 466.66 Metal 75.00
42 476.17 476.17 Gravel/earth 30.00
43 485.68 485.68 Sand 50.00
44 495.18 495.18 Labour Rates
45 504.69 504.69 Mate 451.00
46 514.19 514.19 Mazdoor skilled 455.00
47 523.70 523.70 Mazdoor unskilled 400.00
48 533.20 533.20 Machinery Rates
49 542.71 542.71 Dozer 80 HP for spreading @ 200 cum per hour 2454.60
50 552.22 552.22 Motor grader 3.35M Blade @50 cum/Hr 3020.40
51 561.72 561.72 Hydralic excavator 2791.60
52 571.23 571.23 Front end loader 1 cum capacity 1594.70
53 580.73 580.73 Tipper 5.5 cum 950.30
54 590.24 590.24 Vibratory roller 8T 2736.20
55 599.74 599.74 Smooth wheeled roller 8 Ton 1329.90
56 609.25 609.25 Water tanker 6 KL 655.20
57 618.76 618.76 Tractor 413.60
58 628.26 628.26 Tractor with Rotavator 423.60
59 637.77 637.77 Tractor with ripper attachment @ 60 cum per hour 423.60
60 647.27 647.27 Air compressor 250 cfm 556.50
61 656.78 656.78 Wet mix plant of 60 tonne hr. capacity 1679.70
62 666.29 666.29 Mechanical broom @ 1250 sqm/hr. 381.80
63 675.79 675.79 Bitumen pressure distributor @1750 sqm/hr 1527.10
64 685.30 685.30 Emulsion pressure distributor @1750 sqm/hr 875.60
65 694.80 694.80 Hot mix plant 40 to 60 TPH 19546.00
66 704.31 704.31 Mechanical Paver finisher 100 TPH 2290.60
67 713.81 713.81 Hydraulic self propelled chip spreader @ 1500 sqm/hr. 2743.70
68 723.32 723.32 Finish rolling with 6-8 tonne smooth wheeled tandem roller. 1856.50
69 732.83 732.83 Pneumatic road Roller 1515.60
70 742.33 742.33 GSB Plant 50 Cum 1279.70
71 751.84 751.84 Generator 250 KVA 2162.60
72 761.34 761.34 Generator set 125 KVA 1543.10
73 770.85 770.85 Generator set 35 KVA 1032.00
74 780.35 780.35 Concrete mixer 0.4/0.28 cum 525.50
75 789.86 789.86 Tipper 5.50 cum capacity per Tonne per km 7.44
76 799.37 799.37 Tipper 5.50 cum per km 74.40
77 808.87 808.87 Plate compactor/Power rammer 59.10
78 818.38 818.38 Sand for Mortar 182.00
79 827.88 827.88 Blacksmith 475.00
80 837.39 837.39 Driller 550.00
81 846.90 846.90 Blaster 550.00
82 856.40 856.40 Hot mix Plant 100 to 120 TPH 24636.00
83 865.91 865.91 Paver finisher hydrostatic with sensor control 3115.20
84 875.41 875.41 C C Batch mix plant @ 50 cum per hour 1343.30
85 884.92 884.92 Generator 100 KVA 1316.30
Concrete paver finisher with 40 HP motor for 3247.20
86 894.42 894.42 paving of Concrete surface
87 903.93 903.93 Curing Compound / liter (irrigation) - M-090 101.00
88 913.44 913.44 Sealant Primer / Kg - M146 - Irrigation 148.00
Plastic sheath,1.25 mm thick for dowel bars per 47.00
89 922.94 922.94 sqm - M138 - Irrigation
90 932.45 932.45 Joint sealant / irrigation / local (M-120) 58.00
Super Plastisizer Admixure (irri / M180 ) & 43.00
91 941.95 941.95 Irrigation materials Si. No. 70
Pre moulded Joint filler, 25 mm thick for expansion 262.00
92 951.46 951.46 joint / sqm (iiri. rate)/ M-141
93 960.96 960.96 Concrete joint cutting macine / hr for CC Pvmt 220.00
94 970.47 970.47 Texturing Machine / hour for CC Pavement 450.00
Separation Membrane of impermeable plastic
95 979.98 979.98 sheeting 125 micron thick / sqm 15.25
96 989.48 989.48 Gelatine per kg 57.00
97 998.99 998.99 Electric Detonators / each 9.00
Credit for excavated rock found suitable for use 194
98 1008.49 1008.49 per cum / Irrigatiion item/ M 089
99 1018.00 1018.00 Binding Wire 53.00
100 1027.51 1027.51 Kerb casting machine / hr 671.9
Synthetic enamel paint Si. No. 71 of material /
Irrigation SoR 222
101 1037.01 1037.01
102 1046.52 1046.52 100 mm dia A C Pipe (PH - Table 8) 253
103 1056.02 1056.02 Galvanised MS Flat Camp (Irrigation M-101) 165
104 1065.53 1065.53 Mastic Pad 25.4 mm thickness 839
105 1075.03 1075.03 Mastic Pad 12.7 mm thickness 481
106 1084.54 1084.54
107 1094.05 1094.05
108 1103.55 1103.55
109 1113.06 1113.06
110 1122.56 1122.56
111 1132.07 1132.07
112 1141.57 1141.57
113 1151.08 1151.08 Tipper 10Tonne capacity for carriage of stone
114 1160.59 1160.59 chips from stock pile on road side to chip
115 1170.09 1170.09 spreader
116 1179.60 1179.60
117 1189.10 1189.10
118 1198.61 1198.61
119 1208.12 1208.12
120 1217.62 1217.62
121 1227.13 1227.13
122 1236.63 1236.63
123 1246.14 1246.14
124 1255.64 1255.64
125 1265.15 1265.15
126 1274.66 1274.66
127 1284.16 1284.16
128 1293.67 1293.67
129 1303.17 1303.17
130 1312.68 1312.68
131 1322.18 1322.18
132 1331.69 1331.69
133 1341.20 1341.20
134 1350.70 1350.70
135 1360.21 1360.21
136 1369.71 1369.71
137 1379.22 1379.22
138 1388.73 1388.73
139 1398.23 1398.23
140 1407.74 1407.74
141 1417.24 1417.24
142 1426.75 1426.75
143 1436.25 1436.25
144 1445.76 1445.76
145 1455.27 1455.27
146 1464.77 1464.77
147 1474.28 1474.28
148 1483.78 1483.78
149 1493.29 1493.29
150 1502.79 1502.79
151 1512.30 1512.30
152 1521.81 1521.81
153 1531.31 1531.31
154 1540.82 1540.82
155 1550.32 1550.32
156 1559.83 1559.83
157 1569.34 1569.34
158 1578.84 1578.84
159 1588.35 1588.35
160 1597.85 1597.85
161 1607.36 1607.36
162 1616.86 1616.86
163 1626.37 1626.37
164 1635.88 1635.88
165 1645.38 1645.38
166 1654.89 1654.89
167 1664.39 1664.39
168 1673.90 1673.90
169 1683.40 1683.40
170 1692.91 1692.91
171 1702.42 1702.42
172 1711.92 1711.92
173 1721.43 1721.43
174 1730.93 1730.93
175 1740.44 1740.44
176 1749.94 1749.94
177 1759.45 1759.45
178 1768.96 1768.96
179 1778.46 1778.46
180 1787.97 1787.97
5 86.40 76.05
6 13.00 99.40 87.49
7 13.00 112.40 98.93
8 13.00 125.40 110.37
9 13.00 138.40 121.81
10 13.00 151.40 133.26
11 13.00 164.40 144.7
12 13.00 177.40 156.14
13 13.00 190.40 167.58
14 13.00 203.40 179.03
15 13.00 216.40 190.47
16 13.00 229.40 201.91

17 13.00 242.40 213.35


18 13.00 255.40 224.79
19 13.00 268.40 236.24
20 13.00 281.40 247.68
21 13.00 294.40 259.12
22 13.00 307.40 270.56
23 13.00 320.40 282.01
24 13.00 333.40 293.45
25 13.00 346.40 304.89
26 13.00 359.40 316.33
27 13.00 372.40 327.77
28 13.00 385.40 339.22
29 13.00 398.40 350.66
30 13.00 411.40 362.1
31 10.80 422.20 371.61
32 10.80 433.00 381.11
33 10.80 443.80 390.62
34 10.80 454.60 400.12
35 10.80 465.40 409.63
36 10.80 476.20 419.13
37 10.80 487.00 428.64
38 10.80 497.80 438.15
39 10.80 508.60 447.65
40 10.80 519.40 457.16
41 10.80 530.20 466.66
42 10.80 541.00 476.17
43 10.80 551.80 485.68
44 10.80 562.60 495.18
45 10.80 573.40 504.69
46 10.80 584.20 514.19
47 10.80 595.00 523.7
48 10.80 605.80 533.2
49 10.80 616.60 542.71
50 10.80 627.40 552.22
51 10.80 638.20 561.72
52 10.80 649.00 571.23
53 10.80 659.80 580.73
54 10.80 670.60 590.24
55 10.80 681.40 599.74
56 10.80 692.20 609.25
57 10.80 703.00 618.76
58 10.80 713.80 628.26
59 10.80 724.60 637.77
60 10.80 735.40 647.27
61 10.80 746.20 656.78
62 10.80 757.00 666.29
63 10.80 767.80 675.79
64 10.80 778.60 685.3
65 10.80 789.40 694.8
66 10.80 800.20 704.31
67 10.80 811.00 713.81
68 10.80 821.80 723.32
69 10.80 832.60 732.83
70 10.80 843.40 742.33
71 10.80 854.20 751.84
72 10.80 865.00 761.34
73 10.80 875.80 770.85
74 10.80 886.60 780.35
75 10.80 897.40 789.86
76 10.80 908.20 799.37
77 10.80 919.00 808.87
78 10.80 929.80 818.38
79 10.80 940.60 827.88
80 10.80 951.40 837.39
81 10.80 962.20 846.9
82 10.80 973.00 856.4
83 10.80 983.80 865.91
84 10.80 994.60 875.41
85 10.80 1005.40 884.92
86 10.80 1016.20 894.42
87 10.80 1027.00 903.93
88 10.80 1037.80 913.44

89 10.80 1048.60 922.94


90 10.80 1059.40 932.45
91 10.80 1070.20 941.95

92 10.80 1081.00 951.46


93 10.80 1091.80 960.96

94 10.80 1102.60 970.47

95 10.80 1113.40 979.98


96 10.80 1124.20 989.48
97 10.80 1135.00 998.99

98 10.80 1145.80 1008.49


99 10.80 1156.60 1018
100 10.80 1167.40 1027.51

101 10.80 1178.20 1037.01


102 10.80 1189.00 1046.52
103 10.80 1199.80 1056.02
104 10.80 1210.60 1065.53
105 10.80 1221.40 1075.03
106 10.80 1232.20 1084.54
107 10.80 1243.00 1094.05
108 10.80 1253.80 1103.55
109 10.80 1264.60 1113.06
110 10.80 1275.40 1122.56
111 10.80 1286.20 1132.07
112 10.80 1297.00 1141.57
113 10.80 1307.80 1151.08
114 10.80 1318.60 1160.59
115 10.80 1329.40 1170.09
116 10.80 1340.20 1179.6
117 10.80 1351.00 1189.1
118 10.80 1361.80 1198.61
119 10.80 1372.60 1208.12
120 10.80 1383.40 1217.62
121 10.80 1394.20 1227.13
122 10.80 1405.00 1236.63
123 10.80 1415.80 1246.14
124 10.80 1426.60 1255.64
125 10.80 1437.40 1265.15
126 10.80 1448.20 1274.66
127 10.80 1459.00 1284.16
128 10.80 1469.80 1293.67
129 10.80 1480.60 1303.17
130 10.80 1491.40 1312.68
131 10.80 1502.20 1322.18
132 10.80 1513.00 1331.69
133 10.80 1523.80 1341.2
134 10.80 1534.60 1350.7
135 10.80 1545.40 1360.21
136 10.80 1556.20 1369.71
137 10.80 1567.00 1379.22
138 10.80 1577.80 1388.73
139 10.80 1588.60 1398.23
140 10.80 1599.40 1407.74
141 10.80 1610.20 1417.24
142 10.80 1621.00 1426.75
143 10.80 1631.80 1436.25
144 10.80 1642.60 1445.76
145 10.80 1653.40 1455.27
146 10.80 1664.20 1464.77
147 10.80 1675.00 1474.28
148 10.80 1685.80 1483.78
149 10.80 1696.60 1493.29
150 10.80 1707.40 1502.79
151 10.80 1718.20 1512.3
152 10.80 1729.00 1521.81
153 10.80 1739.80 1531.31
154 10.80 1750.60 1540.82
155 10.80 1761.40 1550.32
156 10.80 1772.20 1559.83
157 10.80 1783.00 1569.34
158 10.80 1793.80 1578.84
159 10.80 1804.60 1588.35
160 10.80 1815.40 1597.85
161 10.80 1826.20 1607.36
162 10.80 1837.00 1616.86
163 10.80 1847.80 1626.37
164 10.80 1858.60 1635.88
165 10.80 1869.40 1645.38
166 10.80 1880.20 1654.89
167 10.80 1891.00 1664.39
168 10.80 1901.80 1673.9
169 10.80 1912.60 1683.4
170 10.80 1923.40 1692.91
171 10.80 1934.20 1702.42
172 10.80 1945.00 1711.92
173 10.80 1955.80 1721.43
174 10.80 1966.60 1730.93
175 10.80 1977.40 1740.44
176 10.80 1988.20 1749.94
177 10.80 1999.00 1759.45
178 10.80 2009.80 1768.96
179 10.80 2020.60 1778.46
180 10.80 2031.40 1787.97