You are on page 1of 8

1

Advanced transmission technologies in Europe:


a roadmap towards the Smart Grid evolution
A. L’Abbate, G. Migliavacca, T. Pagano, A. Vaféas

The present paper focuses on the European transmission


Abstract-- The progressive re-engineering of the European system and examines some results of the ongoing work within
power transmission system will involve a spectrum of innovative the European FP7 REALISEGRID project [2]: it aims at
technologies. Their level of application by Transmission System showing that, in Europe, transmission networks are indeed on
Operators (TSOs) will vary from one control area to the other,
the critical path to enable the Smart Grid effective
also based on past experiences and today’s operation constraints.
The present paper introduces a Technology Integration implementation and use. Furthermore, the Smart Grid
Roadmap, developed within the European research project evolution directly concerns transmission as well, which is
REALISEGRID, with the aim to analyze the evolution of expected to become ‘smarter’ than today. It is argued that this
advanced transmission technologies over the next three decades evolution is driven by two main trends:
towards their integration into the European power system. This
roadmap is based upon a systemic approach which takes into due 1. The effects of the liberalization of the European
account two knowledge elements: the transmission system electricity markets
perspective and the technological perspective. It is organized into Generators, retailers and consumers view the transmission
high level technology components based on a common long-term
vision of the European electricity network by 2030, the critical
system as a public resource to which they ask for access.
system challenges driving that vision and the overall benefits This pushes system operators towards using system assets
expected from the implementation of this spectrum of optimally. Yet, this optimization is security-limited, since
technologies. The present paper proposes an Action Agenda for large outages (blackouts) are unacceptable because of their
the next three decades, with potential integration trajectories huge economic and social costs. TSOs must therefore
including milestones as seen by TSOs and manufacturers define security limits that should be fulfilled at any time,
respectively.
which could make market stakeholders perceive them as
Index Terms — European power system, innovative constraining their activities and reducing the European
transmission technologies, smart transmission grid, technology Social Welfare. A transparent definition and periodic
integration roadmap, transmission system planning, transmission assessment of the distance to these security limits (security
system operation margins) is thus becoming of paramount importance. Also,
the increasing development of cross-border trade
exploiting different electricity price levels, generation mix
I. INTRODUCTION and load profile between national markets is stressing the

T HE Smart Grid concept [1] is often associated with the


developments needed within the electricity distribution
networks in order to enable them to efficiently integrate
existing cross-border backbones, originally planned for
providing mutual support rather than for hosting
significant electricity trade flows.
increasing shares of distributed energy resources and load
2. The massive integration of renewable (generally
control systems. However, a broader approach to the Smart variable) generation in the system
Grid evolution, at least in Europe, might be needed.
The predictability of power sources (location and levels of
power injections) decreases when a significant amount of
variable power generation is connected to the system. A
strong increase of the penetration of renewable energy
The research leading to these results has received funding from the sources (RES) is expected in Europe in the coming years in
European Community’s Seventh Framework Programme (FP7/2007-2013)
under grant agreement n° 219123 (REALISEGRID project). view of the 2020 energy and climate change policy targets
A. L’Abbate is researcher at RSE, Milan, 20134 Italy (e-mail: set by the European Union (EU). TSOs must then be more
Angelo.Labbate@rse-web.it) able to handle sudden drops or rises in electricity network
G. Migliavacca is coordinator of REALISEGRID project and head of the
Transmission Planning Research group at RSE, Milan, 20134 Italy (e-mail: injection, which were not foreseen in their usual way of
Gianluigi.Migliavacca@rse-web.it) managing electricity systems. In addition, most of the
T. Pagano is senior consultant at TECHNOFI, Sophia Antipolis, 06901 renewable electricity is not dispatchable. Moreover, large
France (e-mail: tpagano@symple.eu)
A. Vaféas is leader of the REALISEGRID technology Work Package and RES production sites may be very often located far away
senior consultant at TECHNOFI, Sophia Antipolis, 06901 France (e-mail: from electricity consumption sites: this will be even more
avafeas@symple.eu) acute upon the expected large offshore wind penetration.
2

Also, for small RES plants often connected to the expected.


distribution grid, TSOs have a poor observability of the The future decarbonisation trajectory will combine both routes
resulting power injections with no direct control over according to local specificities, with manufacturers providing
them. a wide spectrum of innovative solutions to improve on
flexibility, reliability, and robustness of the pan-European
In order to address both trends, a conventional solution transmission system.
would consist in adding transmission capacity to the system by
B. Roadmap objectives
building new overhead HVAC (High Voltage Alternating
Current) lines. This is even more necessary since a significant The Technology Integration Roadmap developed in the
amount of European transmission infrastructure assets is framework of the REALISEGRID project [5] is a TSOs’
ageing and has to be replaced. However, on the other side, it is targeted technology roadmap, which analyzes the integration
more and more difficult to build new overhead lines in of advanced power transmission technologies into the
Europe, due to environmental and socio-political constraints. European power transmission system at short/mid/long term
Then, advanced solutions may be provided by using horizons (2020/2030/2040). It leans on a systemic approach of
innovative power technologies, which, thanks to ongoing the pan-European transmission system taking into due account
developments, may impact the whole electricity system. two knowledge elements:
Storage solutions belong to this class (centralized ones like - a transmission system perspective, with a long-term
hydro pumping e.g. or decentralized ones like batteries in cars, vision of the European power transmission system,
if and when electric cars will be deployed massively). They - a technological perspective bringing in the ongoing
provide TSOs with new options to cope with variable power progress related to promising technology options, which
flows. In general, European TSOs may have four interrelated may in turn require revisiting some of current TSOs’
ways of addressing such variability, by: operating practices.
- increasingly exploiting electricity network Safe integration will require more and more collective field
interconnections (also equipped with power flow testing and intensive numerical simulations of system
controlling devices) at pan-European level; behavior, thus leading probably also to new ways of
- using fossil-fuel based generation reserves, which considering the pan- European system security limits.
however impact negatively the CO2 footprint of Overall, the present roadmap aims at clarifying the “gap to
renewable electricity production; TSO maturity” for each of the studied technology options. An
- handling demand side management programs; Action Agenda is then proposed at 10-year intervals for each
- leaning on electricity storage solutions and enhanced technology, which sequences key challenges along the
market mechanisms. estimated life cycle of technologies before reaching the TSO
maturity level. These challenges cover research and
The present paper introduces a Technology Integration development, demonstration, scaling up and replication by
Roadmap, developed within REALISEGRID [5], with the aim several TSOs. The REALISEGRID roadmap must therefore
to analyze the evolution of advanced transmission be considered as a knowledge and communication instrument
technologies over the next three decades towards their in support of the upcoming collective planning revision
integration into the European network to make it a Smart Grid. process, which will be undertaken under the ENTSO-E
(European Network of Transmission System Operators for
II. THE REALISEGRID TECHNOLOGY INTEGRATION Electricity) umbrella [3].
ROADMAP C. Components and process
A. Rationale The roadmap is made of building blocks, as shown in Fig.
1. At a higher level, contextual elements drive the long-term
Within the above described background and challenges, the
vision for the future electricity networks at 2020 [4] and 2030
electrical system decarbonisation requires a progressive re-
time horizons. It is complemented by the key benefits which
engineering of the pan-European transmission (and also
the integration of innovative technologies might bring to the
distribution) grid with technical, market and regulatory
pan-European transmission system: it is the common filter
impacts on planning, normal and emergency operations.
helping the qualitative analysis of each retained technology.
Two main non-exclusive and complementary routes can
For the set of selected technologies three questions need to be
then be envisaged for such a re-engineering:
addressed:
- a sustainable grid expansion allowing an increased power
- What are the deployment challenges for such technology
transmission capacity (larger power transfers over long-
for the next 10, 20, 30 years?
distance and more cross-border capacity): this could be - What is the qualitative benefit profile once the technology
achieved by a class of innovative and flexible technologies; is integrated in the system?
- an optimization of the existing grid assets by operating - What are the typical investment cost ranges?
them closer to their limits without impacting the system
security limits: novel ICT (Information and This roadmapping work used the available technical and
Communication Technology)-based solutions are then scientific literature and inputs from the REALISEGRID TSOs
and partners, technology experts and ongoing related FP7
3

funded projects. It took also into account well known (High Voltage Direct Current), FACTS (Flexible
boundary conditions: the EU energy policy targets for 2020; Alternating Current Transmission System) and Fault
the European Electricity Grid Initiative (EEGI) vision at a Current Limiters (FCLs).
2020 time horizon [4]; the Ten-Year Network Development 3) Real Time system monitoring equipment, based on
Plan (TYNDP) 2010-2020 of ENTSO-E [6]; the EU document advanced hardware and software components used to
on energy infrastructure priorities for 2020 and beyond [15]; sense loading and the limits of individual system
the SETIS (Strategic Energy Technologies Implementation components in real time, as well as the overall state of
System) high level roadmap for European Grids [14]. the system, while also monitoring region-wide
dynamic loadability constraints. These technologies
include WAMS (Wide Area Monitoring Systems) and
Challenges

Increasing complexity of Uncertain demand EU electricity Legal and regulatory


Critical

RTTR (Real Time Thermal Rating)-controlled


New grid architecture(s)
grid operation & planning and generation Market designs framework

lines/cables (also known as smart lines/cables), able to


dynamically increase transport capacity by controlling
By 2020 the electricity networks in Europe
2030 Vision

• Actively integrate efficient new generation and consumption models By 2030


• Coordinate planning and operations of the whole Electricity Network
• Study and propose new market rules to maximize European welfare
Same Vision as 2020 but at the levels set by
the EU energy policy at 2030 conductors temperature.
Source European Industrial Electricity Initiative on Electricity grids
4) Equipment Impacting on TSOs’ Operations, based on
some new technologies expected on the evolving
from Technologies

Increased system Increased Extended power


System Losses
Reduced
distribution systems and having an impact on TSOs’
Key benefits

Integration

Transmission flow Environmental


reliability Reduction
capacity controllability impact
operations (such as smart metering devices), and
Existing grid optimization
Sustainable grid expansion
(domestic and cross border)
electricity storage technologies. Storage covers:
REAL TIME TECHNOLOGIES
Pumped Hydroelectric Storage (PHS); Compressed Air
Energy Storage (CAES); Flywheel Energy Storage
Technologies operated by TSOs

RT1) Real-Time Thermal Monitoring (RTTR) RT2) Wide-Area Monitoring Systems (WAMS)

PASSIVE TECHNOLOGIES ACTIVE TECHNOLOGIES (FES); Superconducting Magnetic Energy Storage


P1) XLPE underground cables A1) Fault Current Limiters
(SMES); Sodium-Sulphur (Na-S) batteries.
P2) GILs (Gas Insulated Lines ) A2) PST
P3) HTC (High Temperature Conductors)
A3-4) HVDC
P4) HTS cables
A5-12) FACTS It is worth noticing that the selected technologies have been
P5) Innovative towers for HVAC lines
considered independently of each other, even though they may
Not operated
by TSOs

be introduced jointly to further enhance their impacts.


Smart metering (impact Wind powered pumped Compressed Air Energy Flywheel Energy Superconducting Sodium-Sulfur (Na-S)
of) hydro storage Storage Storage Magnetic Energy Storage batteries

Extensive power system simulations will be needed to handle


Fig. 1. Overview of the REALISEGRID roadmap
cross benefits (beyond the scope of the proposed roadmap).
Typical investment costs ranges have been then
An exhaustive list of promising technologies, with a
investigated [8][9] in close cooperation with all
rationale for discarding/selecting any of them, has been
REALISEGRID partners. This review has been complemented
proposed by REALISEGRID and debated with TSOs and
by qualitative benefit profiles [5] for each technology, when
stakeholders of the electricity system. “Core” technologies
compared to a base case (standard HVAC technology).
have been then sub-grouped into three main clusters: Passive
Finally, a set of detailed Action Agendas has been designed
equipment (P); Active equipment (A); Real Time system
for the next three decades: the aim is to provide a potential
monitoring equipment (RT). An additional class of
integration trajectory which takes into account technological
technologies has been added, the Impacting TSOs’ Operations
and transmission system challenges.
equipment (ITO). They include storage and innovative
technologies belonging to the distribution world and/or not D. Time positioning of key technology integration challenges
handled by TSOs, but which may impact future TSOs’ Time positioning of the key challenges raised by the
operations. Hence, the four clusters include: adoption of innovative transmission technologies is the central
1) Passive equipment, mainly associated with High issue of the roadmap. A preliminary positioning of a subset of
Voltage AC (HVAC) transmission devices which key milestones is presented in Fig. 2.
include: XLPE (Cross-Linked Polyethylene) They are chosen among about 400 milestones on a time
underground cables; Gas Insulated Lines (GILs); High axis leading to the 2030 vision for the European electricity
Temperature Conductors (HTCs), also known as High network. They are described in Table I, Table II, Table III and
Temperature Low Sag (HTLS) conductors, which are Table IV in Section IV.
based on advances in the area of composite materials; Fig. 2 illustrates the degree of maturity of the selected
High Temperature Superconducting (HTS) cables technologies at different time horizons1 and their contribution
operating at extreme low temperature and providing to the pan-European transmission system. The passive, active
very low resistances; HVAC lines equipped with and real-time technologies as well as the so-called impacting
innovative towers. technologies belong to future planning options which address
2) Active equipment, able to actively control the network either “sustainable grid expansion” or “existing grid asset
while increasing the transmission system capacity, optimization”:
enhancing system stability or damping possible inter-
area oscillations. These technologies include devices 1
The size of the arrow is related to the maturity of the technology (i.e.
such as Phase Shifting Transformers (PSTs), HVDC low, medium, high)
4

- It is the severity of non-technical barriers which will III. AN OVERVIEW OF THE SELECTED TECHNOLOGIES
hamper the adoption process of innovative technologies: a POTENTIAL
low level of social acceptance will favor the “existing grid
asset optimization” route (the pink oval in the bottom of A. Passive technologies
the picture) and all the related active technologies (arrows Underground and submarine XLPE cables [5][11] present
in pink in the picture) and real-time technologies (arrows a strong potential for transmission. Such cables for HVDC
in green). A higher level of social acceptance will favor applications are more and more used. For HVAC XLPE
the sustainable grid expansion route; cables, however, notwithstanding the recent technological
- Regulatory changes are implicit in the adoption of the progress, further deployment and consequent cost reduction,
“impacting technology” class (in purple color on the the cost barrier compared to conventional solutions is still high
bottom of Fig. 2). Storage could become a key facilitator and expected to remain so due to the intrinsic higher
to make RES dispatch more flexible, provided that new complexity and installation constraints of this technology. Yet,
regulations are adopted to facilitate storage expansion; the cost barrier might be reduced when all types of benefits
- In the longer run, on the right side of Fig. 2, novel stemming from this technology are considered, such as lower
network architecture, including trans-continental and losses during the whole life-time, authorization procedures
inter-continental electricity highways, will shape some of duration, visual impacts, etc.
the technical choices. Gas Insulated Line (GIL) [5][11] is a proven, yet not
It must be emphasized that the milestones related to the widespread, technology mostly used in short length
technology integration have built-in uncertainties. First, two installations (exploiting tunnels, bridges, or other existing
conflicting business attitudes prevail: the “technology push” infrastructures). It allows carrying a much higher amount of
approach of manufacturers and technology experts on one side power through a single line than conventional solutions and
and the conservative “demand pull” attitude of regulated TSOs XLPE cables. Yet, it faces strong environmental concerns in
regarding the adoption risks of innovative technologies. terms of SF6 emissions much more harmful than CO2
Secondly, the “gap to maturity” is assessed differently by emissions, with a cost ratio over conventional solutions that
different TSOs, since each control zone has its own history remains high. The current maturity level of this technology,
within bundled large energy groups. This is why the roadmap based on ex-ante analysis of its advantages and drawbacks,
has focused on three decades, leaving room to different requires further development. Its deployment is likely to
national integration paces due to distinct generation portfolios continue within niche applications valorizing existing non-
and distinct consumption patterns. electrical infrastructures: much will depend on the successful
implementation of GILs in planned projects in Europe (like in
the Brenner tunnel [6]).
Underground/submarine
bulk transport
High Temperature Conductors (HTCs) [5] are able to
withstand higher operating temperatures, thus carrying higher
x1 x2 x3 x4 x5 x6 Sustainable Grid
XLPE x7 expansion
g3

GIL g1
g2
amount of power compared to conventional conductors. They
can enhance transmission capacity without impacting the
Aerial bulk
transport
HTS s1 s3
s2
negotiated right-of-way and, in general, without modifications
c7
HTC (new) c1
c2
c3 c4
c5
c6
HTS-DC
New grid
architectures
of transmission towers. They are increasingly adopted by
d9
Innovative
Towers t1
t2 t3
d8
2030 European TSOs. HTCs encompass a broad family of very
New joint
d6
d6 Pan EU T&D system different technologies in terms of potential for transmission
HVDC CSC d3 grid vision operations
capacity and investment costs level. This explains diverging
d5

d2 d4
HVDC VSC d1
viewpoints observed between equipment manufacturers and
FACTS Shunt
f1
Coordinated
control
TSOs: the appropriate selection of a conductor will follow an
FACTS Series f2

p1 p2
f3 f4

f5
f6
Existing Grid asset
Low
maturity in-depth analysis of the power system including operational
PST
l2 l3
l4
optimisation
Medium
and climatic conditions, fatigue and safety issues as well as the
FCLs (novel
overall investment costs. Gains in capacity can reach 30% for
l1 maturity
concepts)
High

RTTR
r1 r2 r3
maturity
the most used HT Conductors, while transfer capacity could
be more than doubled with composite type conductors. HTC
w4
w3
w2 Real Time
WAMS w1
Storage facilities

σ1 σ2 σ3
in operation
Active costs are generally higher (in some cases much higher) than
STORAGE

Other Passive
conventional ACSR (Aluminium Conductor, Steel
IMPACTING
Technology
Smart metering
expansion
Impacting
Reinforced) conductors. Cost figures need to be tuned by
2010-2020 2020 - 2030 2030-2040 considering electrical losses, potential structure reinforcement,
Fig. 2. Key milestones of the technology integration roadmap installation and maintenance costs. The assessment of
performances over the life-time through a better understanding
of reconductored lines (models, endurance testing, level of
electrical losses) is essential to further extend HTC uses.
Among the studied technologies, High Temperature
Superconducting (HTS) cables [5][11] are the ones which are
5

the farthest away from commercial applications. Some concepts (High Temperature Superconducting FCL, solid-state
optimistic experts consider first applications of HTS by 2020 FCL, hybrid FCL), technology challenges still remain that
thanks to a second generation of materials (Yttrium Barium need to be faced before a commercial exploitation (especially
Copper Oxide, YBCO) and advanced deposition techniques, for High Temperature Superconducting FCL). The
starting at distribution system level. However, the majority of implementation of joint testing facilities by TSOs at EU level
manufacturers are much more prudent with regards to the use would help converging on design types and materials, cost
in transmission systems. Costs and size of the cryogenic reduction and standards.
refrigeration units will remain a major obstacle. Field tests Phase Shifting Transformers (PSTs) [5], used to control
experimentations within very specific situations (short active power by regulating the voltage phase angle difference
distance, dense urban area, DC applications) will contribute to between two nodes of the system, are a mature technology,
the further development of the HTS technology blocks. used by TSOs in Europe for power flow control through
The development of Innovative towers [5] is progressively preventive or curative strategies. In the future, the focus will
encouraged by TSOs in order to reduce the environmental be put on enabling issues: the development of shared PST
footprint of overhead lines (e.g. in terms of visual impact and models by TSOs and standards should facilitate PST
electromagnetic field level). Some common RD&D (research, integration in transmission systems. In parallel, the
development and demonstration) challenges could be development of cross-border power trade and the integration
mutualized by TSOs at EU level, such as the eco-design of of renewable generation will increase the need for such a
towers. Demonstration of new interfaces between lines and technology, possibly operated by power electronics and
towers are needed. The cost differential is expected to be enhanced by coordinated control protocols implemented
compensated, inter alia, by the advantages in terms of within inter-TSO coordination centers.
maintenance, since such structures are less prone to structural The High Voltage Direct Current (HVDC) technology
damages. [5][9] has proven its reliability and attractiveness for long
Table I presents an overview of the integration challenges distance power transmission, long submarine cable links and
for the studied Passive technologies at short and mid-term interconnection of asynchronous systems. Converters to
horizon2. convert current from AC to DC and DC to AC are critical. The
most recent technology, self-commutated Voltage Source
TABLE I Converter (VSC), is more flexible than the more conventional
KEY TECHNOLOGY INTEGRATION CHALLENGES FOR “PASSIVE” EQUIPMENT
Id Type of
line-commutated Current Source Converter (CSC), since it
Technology Key technology integration challenges

x1
challenge
allows controlling active and reactive power independently.
Environment and ageing models Modelling

x2 Insulation materials and cable architectures for improved


HVDC key benefits are in terms of increased transmission
Performances
x3
performances (reduction of junctions)
Advanced installation techniques for installation costs reduction Installation,
capacity compared to conventional HVAC, and power flow
Cross-Linked
Polyethylene
(XLPE) cables
x4
(including design of accessories)

Fast qualification techniques by TSOs and related standards


Costs
Commissioning, controllability, which in turn can enhance the stability of the
costs, standards
(underground
and submarine) x5 Integration of dynamic limits into system operation procedures and Performances, link and of its surrounding environment. Although the
tools operation
x6 Automated underground cable installation and remote sensing system Installation, investment costs of a VSC-HVDC converter station are higher
for O&M Costs
x7 Innovative cable materials (e.g. carbon nano-tube) for improved
Performances
than those of an AC substation, the overall investment costs of
performances
g1 Assessment of GILs performances in operation based on historical Performances a DC transmission link can be lower than those ones of a
data and models assessment
Gas Insulated
Lines
g2 New generation of GIL with enhanced safety in operation, longer
Performances
corresponding AC interconnection if a certain transmission
distances applications and N2/SF6 mixtures
(GIL)
g3
Environmental footprint reduction and cost reduction
Performances,
Costs
distance is reached (i.e. “break-even” distance). This break-
c1 Advanced designs and new materials for high current carrying even distance strongly depends on the specific project
capacity, reduced weight, line sags and corrosion for high Performances

c2
temperature conductors
Long-term reliability of reconductored cables with high temperature Performances
parameters (it is typically between 80 and 120 km for offshore
High c3
conductors (ageing models, endurance testing)
Improved HTC maintenance (ageing models, inspection techniques
assessment
Operation and
submarine cable connections). For onshore applications, the
Temperature
Conductors
c4
and operations)
Advanced High Temperature Conductors field tested by TSOs
maintenance
Demonstration
break-even distance is in the order of 700 km [6]. Typical
(HTC)
c5 Extension of the application field from urban areas and wind farm
connection to long distance transmission
Applications applications of VSC-HVDC include the active control of
c6 Organic composite conductors with higher transit capacity at lower
costs
Performances,
costs flows, interconnection of offshore wind farms, black start
c7
s1
Exploration of nanomaterials for conductors
Development of more efficient and affordable (costs and size)
Performances
Performances,
functionalities and multi-terminal DC applications. This
High
Temperature s2
cryogenic refrigeration system
Pilot testing of 2nd generation of HTS tapes (Yttrium Barium Copper
costs
technology is a key component of future European grid
Demonstration
Superconductive
(HTS) cables s3
Oxide and advanced deposition techniques)
Demonstration of superconducting cables for novel network
Demonstration
architectures. Meshed DC systems will appear with the advent
t1
architecture
Common TSO RD&D laboratory on modelisation issues (e.g.eco-
Inter-TSO
of commercial DC breakers.
Innovative t2
design of towers)
Modelling of eco-friendly towers
Performances
Flexible Alternating Current Transmission System
towers
t3
using new designs or composite materials
Demonstrations about technical interface problems between lines and
Demonstration
(FACTS) equipment [5][9] is a family of power electronics-
towers
based devices able to enhance AC system controllability and
stability and to increase power transfer capability. FACTS are
B. Active technologies naturally compared by TSOs with mechanical driven
Fault Current Limiters (FCLs) [5] comprise technologies equipment providing controllability features, such as PST (a
with different degrees of maturity. When addressing novel simpler, more robust, reliable and generally less costly
solution, but with limited dynamic capabilities). FACTS
2
The Id number corresponds to the reference positioned along the time devices can be classified according to their shunt, series or
axis in Fig. 2.
6

combined types of connection. Shunt type devices present Combined uses of RTTR measurements with weather forecast
relevant features for reactive power compensation and voltage might significantly increase the value of RTTR for network
control, while series devices offer key advantages for active operations: it could become an interesting option for TSOs to
power flow control and transient stability enhancement. achieve higher transmission capacity ratings safely and
Costs, complexity and reliability issues represent nowadays reliably for existing systems, at relatively low investment costs
the main barriers to the integration of these promising (when compared to the investment needed for new
technologies from the TSOs’ perspective. Up to present, shunt transmission links).
devices (like the SVC, Static VAR Compensator) have been Wide Area Monitoring System (WAMS) [5][10] is an
the most widespread and mature FACTS technologies. Further information platform with monitoring purposes. Based on
FACTS penetration will depend on the technology providers’ Phasor Measurements Units (PMUs), WAMS allow
ability to overcome these barriers, thanks to more monitoring transmission system conditions over large areas in
standardization, interoperability and economies of scale. Key view of detecting and further counteracting grid instabilities.
technology challenges are in terms of power electronic This early warning system contributes to increase system
topologies and exploration of new types of semiconductors reliability by avoiding the spreading of large area
replacing silicon. More user-friendly interfaces and proof of disturbances, and optimizing the use of assets. Yet, some
performance through field testing will contribute to improve critical R&D challenges lie in signal accuracy and reliability,
TSOs’ confidence in these new technologies. Like for other communication architectures and data processing. Standards
active equipments, FACTS, HVDC (VSC) and PST will be for data processing, large scale demonstrations, possibly in
crucial for the future integration of RES into the European combination with other active equipment, will be needed to
system, while delivering full benefits when subject to a estimate benefits brought by WAMS.
coordinated control, in combination with Wide Area Table III presents an overview of the integration challenges
Measurement Systems [10]. for Real Time technologies at short and mid-term.
Table II presents an overview of the integration challenges TABLE III
for Active technologies at short and mid-term. KEY TECHNOLOGY INTEGRATION CHALLENGES FOR “REAL TIME” EQUIPMENT
Technology Id Key technology integration challenges Type of challenge
TABLE II r1 Interoperable RTTR system combined with short-term weather forecasts for Performances,
Real Time
KEY TECHNOLOGY INTEGRATION CHALLENGES FOR “ACTIVE” EQUIPMENT Thermal
OHL monitoring operations
r2 Large scale experiments combining the use of RTTR, PST and WAMS to Demonstration,
Technology Id Key technology integration challenges Type of challenge Rating-based
control highly congested areas combined use
cables / lines
Fault Current l1 Shared testing facilities among TSOs in Europe Inter-TSO r3 Industrialization of RTTR systems for underground/submarine applications Combined use
Limiters l2 Costs and losses reduction for FCLs Costs, performances
(novel Wide Area w1 Improved WAMS signal accuracy and standards development Performances
l3 Next generation of solid state switches for Solid State FCLs (SSFCL) Performances Monitoring w2 Development of standards for WAMS algorithms Standards
concepts)
(FCLs) l4 Demonstration of relocatable FCLs Demonstration System/
w3 Evaluation of WAMS benefits based on full scale demonstrations by TSOs Coordinated use
Phasor
Phase p1 Coordinated use of PST with other active equipments Measurement w4 Large scale validation of the use of WAMS in Europe to monitor/control Demonstration,
Inter-TSO
Shifting (coordination centres in Europe) Units inter-area power oscillations combined use
Transformers p2
(PST) Standardisation of PST modelling shared by TSOs and manufacturers Standards
d1 Improved efficiency of VSC based on new switching topologies and smart
Performances
control of converters D. Impacting technologies
d2 Extended domain of use of HVDC (far-offshore, ultradeep, ultravoltage,
Applications
High Voltage
d3
high distance interconnection)
Performances,
Although not directly operated by TSOs, electricity storage
Direct Development and field tests of DC breakers
Current :
d4 Testing HVDC in highly meshed networks: coordinated control ; combined
operations solutions [5] could have a significant impact on transmission
Voltage Demonstration
Source use with WAMS, HVAC planning and operations. Storage could help maximizing
Converters, d5 Development of MTDC (Multiterminal HVDC) and exploration of meshed
Current HVDC configurations
Architecture
electricity system stability in case of any sudden drop/surge
Source d6 New types of semiconductors for a new generation of thyristors Performances
Converters d7 Test of selected options of MTDC for HVDC backbone in Europe
Architecture
due to the variability of most RES generation plants. It could
combining VSC and CSC
d8 Superconducting DC cables transmission (SCDC) Performances also support TSOs’ CO2 emissions abatement targets either
d9 Deployment of an MTDC backbone in Europe Architecture during off-peak periods, by avoiding electricity spillage, or
f1 Improved performance of FACTS based on new power electronic topologies
and semiconductors
Performances
during peak periods in the case of a generation mix that is
f2 Virtual Man-Machine interface for grid operators User-friendliness
Flexible AC f3 Development of standards for FACTS Standards highly fossil fuel dependent. Historically, storage is related to
Transmission
Systems
f4 Large scale validation of FACTS (shunt) solutions in areas where voltage
control becomes critical
Demonstration technologies like Pumped Hydro and Compressed Air Energy
f5 Large scale validation of FACTS (series) solutions in areas where fast
response line reactance control becomes critical
Demonstration Storage, whereas other storage technologies are not clearly
f6 Field testing of coordinated use with other active equipments Inter-TSO addressing large scale system issues.
Yet, there are still technical and mostly regulatory issues to
C. Real Time technologies be faced. In terms of regulatory issues, open questions are
Real Time Thermal Rating (RTTR)-monitored cables/lines related to which players (private market operators contributing
[5][17] represent a rather mature technology based on the real to system optimization or regulated operators) shall own and
time control of thermal rating of a line or a cable. It aims at manage storage facilities. Implementing large scale
maximizing the capability of a transmission line/cable while demonstrations of storage solutions at European level appears
respecting design margins, thus reducing potential congestion to be a necessary step to validate both storage benefits based
problems. Its development remains bounded by solving some on full scale studies and the potential asset ownership options
practical integration challenges: integration with other tools, for storage regulations.
interoperability with protection equipment settings, Table IV presents an overview of the short and mid-term
coordination of RTTR monitored links, communication with integration challenges for some technologies (storage)
SCADA and use of RTTR output values at a dispatch level. impacting on TSOs’ operations.
7

lines and lengthy permit procedures, the following passive


TABLE IV technology development trends are recorded:
KEY TECHNOLOGY INTEGRATION CHALLENGES FOR SOME “IMPACTING” - several technologies, like XLPE underground cables,
EQUIPMENT (STORAGE) HTCs together with new tower designs, are ready to
Technology Id Key technology integration challenges Type of challenge
σ1 Electricity storage regulation for TSOs (ownership and operation of storage Regulation respond to network expansion needs, while GILs might be
facilities)
Electricity
storage σ2 Performance improvements and cost reduction (dependent on each storage available for specific applications in a mid-term horizon;
Performances, Costs

σ3
technology)
Coordinate operation with other “active” equipments Combined use
- HTS cables, even though promising, are still a
controversial topic for which real life transmission
applications would probably occur not before 2030.
IV. ADDRESSING NON-TECHNICAL BARRIERS TO SPEED UP THE 3) Concerning active and real time technologies, several
ADOPTION PACE OF TECHNOLOGY applications already exist outside Europe (lately in countries
The power transmission technologies addressed in this like China) and in some regions of Europe. Large scale
paper show different maturity levels. Future deployment will experiments are also underway (like for TWENTIES project
depend not only on their intrinsic merits, but also on [12]) and scheduled for the coming years to validate at full
exogenous factors, such as [5]: scale critical HVDC components, PSTs and dedicated FACTS
- TSOs’ acceptance and confidence built on proven large configurations, also combined with RTTR and WAMS, for
scale demonstrations to deliver gains to the system upon a RES integration. Their replication will be decided on a case-
detailed cost-benefit analysis; by-case basis, based on coordinated investment between TSOs
- Standards and equipment interoperability driven by a few to encourage cross-border optimization on technical and
equipment manufacturers on a worldwide market3; economic standpoints.
- Scarcity of qualified power system engineers and 4) Introducing active and real time power technologies will
technicians, which is a general concern for the power inevitably make the dynamic operations of the pan-European
industry; transmission system more complex. Transients and network
- Financing, which depends on regulatory frameworks and instabilities will be considered in future short-term operational
investment incentives in place for transmission systems; planning of the electricity systems, requiring increased
- Administrative barriers, such as multi-authority numerical simulations of coupled power systems; their
authorisation procedures that are unharmonized at EU complexity will continue to grow to assess system security
level. beyond the borders of each TSO control area.
Implementing the 2030 roadmap vision will therefore 5) Three impacting technologies should ease TSOs’ operations
require extra system innovation activities over the next in the next twenty years:
decades. The following cross-cutting activities are underlined a- Smart metering at distribution level allows monitoring
in support of technology implementation: capabilities of the low voltage network: it can be coupled with
- inter-TSO large scale experimentations on active smarter substations to provide TSOs with increased
technologies including storage; observability of distributed generations and consumptions,
- inter-TSO coordinated operations at supra-national (i.e. which in turn will serve implementing demand response
regional) level; approaches to manage peak load efficiently.
- technology interoperability studies. b- The combination of PMUs, advanced computing
architectures and numerical simulation techniques will allow
V. CONCLUSIONS hierarchical state estimation of the pan-European system.
Security assessment can then be performed every five minutes,
The above roadmapping outputs [5] may serve to depict the
involving time domain simulations of the network behavior.
future prospects of the pan-European transmission grid by
Increasingly coordinated operations using such tools will then
2050. This leads to the following main conclusions.
give network operators the capability of:
1) There is evidence that the Smart Grid concept embraces
- taking into account the growing contribution of less
transmission networks as an integral part of the future
predictable and intermittent generation;
electricity networks in Europe. As a matter of fact,
- adapting more and more to the constraints of a single
transmission and distribution players will interact more and
European electricity market (more power transfers over
more with each other in order to face a paradigm shift in
long distances, operations closer to the physical limits);
electric system design:
- handling better new controllable devices;
- decentralized stochastic generation will grow;
- revisiting current operational rules and procedures to
- changes in operation rules and procedures will allow for
make demand partially controllable.
more controlled loads.
c- Massive electricity storage (centralized like hydro,
Both changes do not have to impact system security and
CAES, liquefied air or hydrogen, and decentralized like power
reliability.
flow, high temperature Na-S or car batteries) can take into
2) In a context of public opposition towards more overhead
account the change of the design paradigm of electric systems:
electricity cannot be kept and stored. From now on, wind and
3
Transmission equipments designed and developed for Asia might be of solar electricity can be produced at times where there is not
lower interest in Europe
8

enough consumption needs. Electricity storage facilities can [11] E. Zaccone, “Synthetic description of performances and benefits of
undergrounding transmission”, REALISEGRID Deliverable D1.1.1,
be optimally located close to generation centres. Large scale Dec. 2009, http://realisegrid.rse-web.it
demonstrations are needed by 2020 to prepare a massive [12] TWENTIES FP7 project http://www.twenties-project.eu/
development of electricity storage systems which would have [13] IRENE-40 FP7 project http://www.irene-40.eu/
[14] European Commission, Strategic Energy Technologies Information
benefits for the whole electric system (peak management,
System (SETIS), http://setis.ec.europa.eu/about-setis/technology-
balancing and even system services). roadmap/european-industrial-initiative-on-the-electricity-grid
6) The wealth of technologies proposed by manufacturers [15] European Commission, “Energy infrastructure priorities for 2020 and
opens new options for future transmission network beyond - A Blueprint for an integrated European energy network”,
COM(2010) 677 final, Nov. 2010.
architectures, including the ones needed to link offshore wind [16] ENTSO-E, "ENTSO-E Background Paper on a 2050 Supergrid", Jul.
farms (offshore grids). Studies initiated by ENTSO-E for the 2010, http://www.entsoe.eu
time horizon 2050 will possibly suggest new network [17] E. Zaccone, R. Gaspari, P. Maioli, “Description of the “smart” (advance
monitored) cable system and of its laboratory prototype”,
alternatives [16]. The present roadmap could provide a first REALISEGRID Deliverable D1.1.2, Feb. 2011, http://realisegrid.rse-
step in establishing timelines for new technologies adoption web.it (to be published).
and foster the fulfillment of the long-term decarbonisation
orientations of the EU. VIII. BIOGRAPHIES
7) This TSO-targeted roadmapping exercise suggests that
further fine-tuning activities would enrich the above Angelo L’Abbate graduated in Electrical Engineering at the Politecnico di
conclusions: Bari, Italy, in 1999. In 2003-2004 he received his Ph.D. in Electrical Energy
Systems at the Politecnico di Bari, Italy, in partnership with the University of
- Dynamic technology maturity models should be able to Dortmund, Germany. In 2004-2005 he was active researcher at the
address further the issues of costs and benefits of a given Mediterranean Agency for Remote Sensing (MARS), Benevento, Italy, and at
technology as a function of its network penetration level; the University of Ljubljana, Slovenia, as a CNR-NATO Fellow. In 2005-2008
- The combined use of technologies will involve he was contractual scientific agent (post-doc) at the EC - DG Joint Research
Centre - Institute for Energy. Since 2009 he has been working with CESI
intertwined effects that can only be captured through ad- RICERCA (now RSE), Milan, Italy. His fields of interest include modeling
hoc large scale demonstrations and numerical simulations and planning of power T&D systems, RES and distributed generation
of network behaviors; integration, FACTS, HVDC. He is currently deeply involved in the EC FP7
- Future quantitative cost-benefit analyses (e.g. starting REALISEGRID project. He is an IEEE Member.
from the one developed in [7]) must be based on specific
Gianluigi Migliavacca graduated in Electronic Engineering at the
business cases, relying on power system studies. Polytechnic University of Milan in 1991 and joined the Automation Research
Center of ENEL in 1994, working on mathematical modeling and dynamic
VI. ACKNOWLEDGMENT simulation of thermal power plants. In 2000 he joined CESI and then CESI
Ricerca (now: RSE), where he is head of the transmission network planning
The authors gratefully acknowledge the discussions and research group. Focus of his research activities is on mathematical modeling
contributions of the REALISEGRID partners, stakeholders and regulatory issues concerning deregulated electricity markets, cross border
and TSOs as well as manufacturers and IRENE-40 project trade issues and transmission planning. During 2005 he was consultant at the
Italian Regulator about the development of a common energy market in
[13] consortium. South-East Europe and about congestion management in Central-South
Europe. Now, he is coordinator of the European FP7 research project
VII. REFERENCES REALISEGRID.
[1] SmartGrids Technology Platform: http://www.smartgrids.eu/
[2] REALISEGRID FP7 project http://realisegrid.rse-web.it/ Tiziana Pagano is graduated from the LUISS University of Rome (Italy) and
[3] ENTSO-E “R&D plan EUROGRID 2020”, March 2010. the College of Europe in Bruges (Belgium). Her main professional experience
[4] European Electricity Grid Initiative (EEGI), Roadmap 2010-18 and includes the European Commission, the International Management Group, and
Detailed Implementation Plan 2010-12, May 2010. Technofi. Her special fields of interest include energy markets and innovation
[5] A. Vaféas, S. Galant, T. Pagano, “Final WP1 report on cost/benefit management.
analysis of innovative technologies and grid technologies roadmap
report validated by the external partners”, REALISEGRID Deliverable Athanase Vaféas, graduated from Ecole Centrale Paris in 1989, joined
D1.4.2, 2011, http://realisegrid.rse-web.it/ (to be published). Technofi in 1991. He has been in charge of management tool development
[6] ENTSO-E “Ten-Year Network Development Plan (TYNDP) 2010- and implementation in several projects, he has been coordinator or work
2020”, June 2010. http://www.entsoe.eu package leader in projects dealing with innovative technology integration in
[7] A. L’Abbate, I. Losa, G. Migliavacca, A.R. Ciupuliga, M. Gibescu, H. transmission/distribution system, distributed energy resources, renewable,
Auer, K. Zach, “Possible criteria to assess technical-economic and electricity market models.
strategic benefits of specific transmission projects”, REALISEGRID
Deliverable D3.3.1, Apr. 2010, http://realisegrid.rse-web.it
[8] A. L’Abbate, G. Migliavacca, “Review of costs of transmission
infrastructures, including cross border connections”, REALISEGRID
Deliverable D3.3.2, 2011, http://realisegrid.rse-web.it (to be published).
[9] S. Rüberg, H. Ferreira, A. L’Abbate, U. Häger, G. Fulli, Y. Li, J.
Schwippe, “Improving network controllability by Flexible Alternating
Current Transmission Systems (FACTS) and by High Voltage Direct
Current (HVDC) transmission systems”, REALISEGRID Deliverable
D1.2.1, Mar. 2010, http://realisegrid.rse-web.it
[10] U. Häger, J. Schwippe, K. Görner, “Improving network controllability
by coordinated control of HVDC and FACTS devices”, REALISEGRID
Deliverable D1.2.2, Apr. 2010, http://realisegrid.rse-web.it

You might also like