Professional Documents
Culture Documents
1. Define Specification.
Specification specifies or describes the nature of the work, materials to be used in the work,
workmanship etc which are very important for the execution of the work. the cost of the work
depends on the specifications.
2. Define carpet area.
Carpet area is the useful or the liveable area in a building without taking into consideration of the
wall thickness. It does not include common areas like lobby, stairs, lifts etc. usually the carpet
area for a residence is 65% approximately.
3. Write down the Specification for excavation for foundation.
Excavation of trenches, finish of trench, pumping out of water accumulated in trench, trench
filling of concrete, masonry of footings, earth filling and measurement of works in Cu.m, ex
4. What do you mean by Rough estimate?
Rough or approximate estimate is prepared to decide approximately the financial aspect, policy
and get an idea of the cost of the project.it is normal practice to work out the approximate
estimate before its detailed estimate is worked out.
5. Write a note on Specification for centering?
Centering shall be of either of hardwood plank or steel plates stiffened by angle iron.
Centering shall not be removed before 14 days in general( 4 days for RCC columns, 10 days for
roof slab and 14 days for beams)
6. What are the types of Estimate?
Approximate or rough cost estimate, detailed estimate, revised estimate, supplementary
estimate, sub-estimate, annual maintenance estimate, repair estimate, complete estimate
7. `What are the purposes of Rate analysis?
To determine the rate per unit of a particular item of work, from the cost, quantity of the
materials, labourers, other miscellaneous expenses required for the completion of project.
8. Define Bill of quantities.
It is a statement of various item of works with description, quantities and unit of rates which is
supplied to the contractor to work out the rates and amounts which is primarily part of a tender
of any work.
9. Define Contingency.
The term contingencies indicates incidental expenses of miscellaneous works which are
unforeseen expenditure, expenses to minor design changes etc. usually 3 to 5% is assumed for
contingencies.
10. What is meant by Typical bay method?
This method of estimate is mostly used for RCC structures or trussed roofs with a number of
repetitive bays ( eg. Workshop, shed, long halls etc). the total cost of the building is found out
multiplying the cost per bay by the number of bays.
PART – B
(assume suitable data wherever necessary) (5 X 16 = 80 MARKS)
11. (a) Explain the general specification of second class building.
Foundation & plinth : 1st class brickwork in lime mortar or 1:6 cement mortar over lime concrete or
1:4:8 cement concrete
Damp proof course : 2.5cm thick cement concrete 1:1.5:3, mixed with1 kg of impermo cement or
other standard water proofing materials as specified with 2 coats of bitumen.
Superstructure : 1st class brickwork with lime mortar or 1:6 cement mortar. Lintels over doors &
windows shall be of RCC
Roofing : RCC slab with insulation layer and lime concrete terracing above, supported over RS joists or
RCC beams as required. Height of rooms shall not be less than 3.7m.
Flooring : drawing and dining room shall be of mosaic(terrazzo). Bathroom and WC floors and dado
shall be of mosaic (terrazzo). Floors of bedrooms shall be colored and polished of 2.5cm cement
concrete over 7.5cm lime concrete.
Finishing : inside and outside walls shall be of 12mm cement lime plaster. Drawing, dining and
bedrooms inside shall be distempered and others inside white washed 3 coats. Outside shall be
colored snowcem washed 2 coats over 1 coat of whitewash.
Doors and windows : door frames shall be seasoned teak wood. Shutters shall be teak wood 4.3cm
thick paneled glazed or partly paneled and partly glazed as required, with additional wire gauge
shutters. All fittings shall be of brass. Doors & windows shall be varnished or painted 2 coats with high
class enamel paint over 1 coat of priming. Windows shall be provided with iron gratings or grills.
Miscellaneous : rainwater pipes of cast iron or of asbestos cement shall be provided with paint finish.
1st class sanitary, water fittings and electrical installations. 1 metre wide 7.5cm thick CC 1:3:6 apron
shall be provided all around the building
(OR)
(b) Explain the detailed specification of brick work.
Bricks : bricks shall be of 1st class of standard specifications, thoroughly burnt, deep cherry red or
copper in color. Regular in shape, edges sharp, free from cracks, chips, flaws and lumps of any kind.
Shall not absorb water more than one sixth of its weight. min crushing strength 105 kg per sq.cm
Mortar : sand shall be sharp, clean and free from organic matters. Proportion of cement, sand and
water shall be as specified. Fresh mixed mortar shall be used, old and stale mortar shall not be used.
Soaking of bricks : bricks shall be fully soaked in clean water by submerging in a tank for a period of
12 hours immediately before use. Soaking is continued till air bubbles is ceased.
Laying : bricks shall be well bonded. Wall should be in plumb. No damaged or broken bricks should be
used. Seclected best shaped bricks shall be used for face works.
Curing : the brickwork shall be kept wet for a period of atleast 10 days after laying. At the end of days
work the tops of walls shall be flooded with water by making small weak mortar edging to contain
atleast 2.5cm deep water.
Protection : the brickwork shall be protected from the effect of sun, rain, frost etc during the
construction.
Scaffolding : necessary and suitable scaffolding shall be provided to facilitate the construction of
brickwall. It shall be sound & strong supports to withstand all loads.
Measurement : brickwork shall be measured in Cu.m. different wall thickness to be taken separately.
The rate shall be for the complete work incl scaffolding and all tools & plants
12. (a) Write a detailed specification of R.C.C in roof slab and beam.
Steel : reinforcing bars shall be of mild steel or deformed steel of standard specifications shall be
free from corrosion, rust etc.
Centering and shuttering : it shall be made with timber or steel plate, with necessary props,
bracings strong and stable. Centering and shuttering should not be removed before 14 days in
general
Proportion of cement concrete : cement concrete shall be of 1:2:4 proportion by volume for
slabs,beams and lintels and 1:1,5:3 proportion for columns
Laying of concrete : before laying the concrete the shuttering shall be clean. Time between
mixing and placing of concrete shall not exceed 20 mins. Should be compacted by a mechanical
vibrating machine. Concreting shall be laid continuously, structures exceeding 45 metres in length
shall be divided by expansion joints.
Curing : the brickwork shall be kept wet for a period of atleast 10 days after laying. At the end of
days work the tops of walls shall be flooded with water by making small weak mortar edging to
contain atleast 2.5cm deep water.
Finishing : exposed surface shall be plastered with 1:3 cement sand mortar not exceeding 6mm
thickness, the plastering shall be applied immediately after removal of the centering while the
concrete is still damp or unset.
Measurement : shall be taken in Cu.m for the finished work and deduction shall be made for the
volume of steel. Steel shall be measured separately in quintal.centering and shuttering, tools and
plants charges to be added
(OR)
(b) Write detailed specification for varnishing and painting.
Painting :
- only specified brand should be used.
- Surface should be made perfectly smooth by rubbing with sand paper of required grade.
- All holes and open joints should be filled with strong putty or equivalent
- In steel work all rusts and scales shall be perfectly removed by scrapping and brushing
- One coat of priming and 2 coats of paint to be applied
- Paint should be applied evenly with brush and no brush mark should be visible
- Brushes should be cleaned and washed with turpentine at the end of days work and kept dry
- If old paint is to be removed, soda water or caustic soda can be used and scrapped by patent
remover, surface to be smoothened before paint is applied
Varnishing :
- Knots,holes, cracks etc shall be filled and covered with putty made of whiting and linseed oil
- Wood work shall be rubbed down with sand paper sufficiently smooth to remove any grain
marks and it shall be cleaned before hand
- Varnish shall be applied with brushes using strong firm strokes and spread evenly
- Specified copal varnish shall be laid on prepared surface in thin coats
- For new wood work a second coat shall be applied after the first coat of varnish has been
thoroughly dried
- Varnishing shall not be done during dry weather and should not be allowed to be undertaken
in rainy days
13. (a) Explain plinth area method and carpet area method.
plinth area method :
This method is also known as square area method. In this method, the area of the structure at
the plinth level is calculated omitting any projection at the plinth level. This area is multiplied by
the plinth area rate arrived at by studying similar types of buildings in the same locality. This
gives the total approximate estimate cost of the building
Therefore,
Cost of materials = 11,48,850/- (69%)
Cost of labour = 5,16,150/- (31%)
= 24,80,850/-
(OR)
(b) Explain the following terms (a) Abstract estimate (b) Out turn work (c) Data to be considered for
measurement of works.