Professional Documents
Culture Documents
SUBMITTED BY
BATCH II
BATCH
MEMBERS
K.S.KALAIVANI (310817103034)
F.LALITHA (310817103040)
V.MAHALAKSHMI (310817103041)
S.KEERTHANA (310817103701)
DEPARTMENT OF CIVIL
ENGINEERING JEPPIAAR ENGINEERING
COLLEGE, CHENNAI – 600 119.
OCTOBER 2019
JEPPIAAR ENGINEERING
COLLEGE
EXAMINERS:
Date: Internal:
External:
JEPPIAAR ENGINEERING COLLEGE
BONAFIDE CERTIFICATE
I would also like to thank Mrs. T.Pauline M.E., (Assistant professor) for
selecting the site of Manamathi village for the phase II of our camp.
I thank all the staff members of our Department for their kind support and
encouragement to make this camp a success.
Last but not the least; I thank all my team members for their enormous
effort and co- operation during the entire period.
Above all, I thank the Almighty for his grace, without which our endeavor
would not have been a success.
SURVEY CAMP
2. TRILATERATION METHOD
3. TRIGNOMETRIC LEVELLING
4. RADIAL CONTOURING
5. GRID CONTOURING
7. RECIPROCAL LEVELLING
8. RECONNAISSANCE SURVEY
TABLE OF CONTENTS
EXP. PAGE
NO. DATE DESCRIPTION OF SURVEY WORK NO.
FIGURE PAGE
DESCRIPTION OF FIGURES
NO. NO.
1 TRIANGULATION SYSTEM 19
2 TRILATERATION 27
3 TRIGONOMETRIC LEVELING 32
4 RECIPROCAL LEVELING 45
6 58
RECONAISSANCE SURVEY
INTRODUCTION
SURVEYING:
Surveying is the science and art of determining the relative positions of
various points above or below the surface of the earth. The relative positions can be
determined by measuring the horizontal distances, vertical distances, horizontal
angles and vertical angles accurately using various surveying instruments. After
taking the measurements in the field, computations are done and the plans and maps
are prepared in the office. These plans and maps are used for planning of engineering
works, marking of boundaries, computations of area and volume and other purposes.
OBJECTS OF SURVEYING:
To take measurements to determine the relative positions of
existing features on or near the ground.
To layout or mark the position of proposed structures on the ground.
To determine the areas, volumes and related qualities.
PRINCIPLES OF SURVEYING:
Always work from whole to part.
Always choose the method of survey that is most suitable.
Always make provisions for adequate checks.
Always record field observation carefully.
PLANE SURVEYING:
It is used for relatively small area.
The curved line on earth’s surface is considered as straight.
The direction of plumb lines at various points are assumed to be
parallel to one another.
The spherical angles are considered as plane angles.
The standard of accuracy is lower than geodetic surveying.
GEODETIC SURVEY:
It is used for large areas.
It is used for establishing precise points of reference control points.
The surface of the earth is considered as curved.
The direction of plumb lines at various points is different. The
earth’s mean sea level is perpendicular to direction of gravity.
The standard of accuracy is very high.
Control surveying,
Land surveying,
City surveys,
Topographical surveys,
Route surveys,
Mine surveys,
Hydrographic surveys,
Astronomic surveys,
Geological surveys,
Construction surveys,
METHOD OF TRAVERSING:
Depending upon the types of instruments used for measurements of angles,
the method of traversing is classified as follows:
Chain traverse: In a chain traverse, the direction of the traverse line is fixed
by taking suitable ties near the traverse station. A chain traverse is not very accurate
and is rarely used in practice.
Plane table survey: A plane table can be for plotting a traverse directly in the
field.
Stadia traverse: In stadia traverse the length of the traverse lines, the angle
between the traverse line and elevation of traverse station are measured with
tachometer.
TYPES OF TRAVERSE:
A traverse may be classified as follows:
1. Closed traverse.
2. Open traverse.
Closed traverse: A closed traverse starts from one station and closes on the
same station whose location is already know. The closed traverse is also called as
link traverse or connecting traverse.
Open traverse: An open traverse starts from one station and closes at
another station whose location is neither known nor located. An open traverse is
generally done for a long strip of area.
2. Setup the table at a level slightly lower than your elbow height.
COMPUTATION OF AREAS:
In surveying the areas means the area of tract of land as projected upon a
horizontal plane and not the actual area of the tract for steep tract the actual area is
much more than in the projected area. The area of the land is computed from its
plan. The methods selected for computation of the area depend upon the shape of
the tract and the accuracy required. When the plane is enclosed by straight
boundaries it can be subdivided into simple geometric shapes such as triangles,
trapezoid, rectangles etc.
UNITS:
Where;
S= (a +b +c)/2
TRAPEZOIDAL RULE:
This rule is based on the assumption that the figures are trapezoids. Add the
average of the end offsets to the sum of the intermediate offsets multiply the total
sum thus obtained by the common distance between the ordinates to get the required
area.
MULTI-LEVEL SECTION:
In this method, the co-ordinate system provides the most general method of
calculating area. The cross section nodes provided with X and Y co-ordinates for
each vertex of the section, the origin being at central point H. The X co-ordinates
are measured positive to the right and negative to the left of the H. The Y co-
ordinates are measured positive for cuts and negative for fills.
TRIANGULATION
Date: 01/07/2019
AIM:
APPARATUS USED:
2. Tripod stand
3. Ranging rods
4. Metallic tape
5. Dumpy level
6. Levelling staff
LOCATION:
SITE CONDITIONS:
The survey was carried out starting from 8.00 A.M to 2.00
P.M on 01/07/2019 which was a clear sunny day.
DESCRIPTION:
Triangulation Survey:
PROCEDURE:
2. The leveling instrument has been set up at the given station A and it
is leveled by making temporary adjustments.
3. The horizontal angles are taken between the given stations by using
Method of Repetition combined with Method of Reiteration.
0
‘ “ ‘ “ 0
‘ “ 0
‘ “
A B 0 0 0 0 0 0 0 0 81 30 40 28.95
B 46 55 20 55 20 46 55 20
B C 0 0 0 0 0 0 0 0 31 31 0 15.38
D 31 31 0 31 0 31 31 0 35.88 206.61
BCD C B 0 0 0 0 0 0 0 0 68 44 40 27.42
D 68 44 40 44 40 68 44 40
D B 0 0 0 0 0 0 0 0 79 44 20 28.95
C 79 44 20 44 20 79 44 20
C D 0 0 0 0 0 0 0 0 44 20 0 12.33
51*34 B
21.83m
28.93 m A
81*30’40”
22.93m
C
By Sine rule,
(AB/Sin C) = (AC/Sin B) =
(BC/Sin A) 21.83/Sin
AC = 22.93 m
C = 28.93m.
S=
(22.93+28.93
+21.83)/2
=36.61m
=242.03m2
RESULT:
The complete area of the land surveyed using triangulation has been calculated as
642.13 m2
and it has been presented in the form of the figure
TRILATERATION
Date: 01/07/2019
AIM:
To find out the area of the given site by using a network of triangles by
Trilateration
method.
APPARATUS USED:
2. Tripod
3. Ranging rod
4. Metallic tape
LOCATION:
SITE CONDITIONS:
The survey was carried out starting from 8.00 A.M to 2.00 P.M on
01/07/2019 which was a clear sunny day.
DEFINITION:
2. The leveling instrument has been set up at the given station A and it is
leveled by making temporary adjustments.
3. The horizontal angles are taken between the given stations by using Theodolite
Traversing.
I SI
G SIDE
N H VERNIER VERNIER MEAN STAFF OPPOSITE S(m) AREA
S T A B ANGLE STATION (m) (sq.m.)
T T
A O
T
0 ‘ “ ‘ “ 0 ‘ “
B 9 21 40 21 40 9 21 40 2.600 18.85
A 24.54 104.99
10 33 20 33 20 10 33 20 3.005
2 20 0 20 0 2 20 0 2.950 11.97
C
5 40 0 40 0 5 40 0 3.650
1 52 20 52 20 1 52 20 1.350 18.26 24.53 67.69
B C
3 0 0 0 0 3 0 0 1.710
D 2 25 20 25 20 2 25 20 2.600 22.72
3 19 40 19 40 3 19 40 2.960
D 1 10 0 10 0 1 10 0 2.850 8.07 17.34 50.63
C 2 5 20 5 20 2 5 20 2.980
E 3 24 40 24 40 3 24 40 3.070 13.91
5 10 20 10 20 5 10 20 3.500
E 1 44 0 44 0 1 44 0 0.450 12.69
D
4 26 0 26 0 4 26 0 1.050 19.87 71.83
F 1 20 33 20 33 1 20 33 1.410 11.48
3 0 0 0 0 3 0 0 1.700
E F 1 4 20 4 20 1 4 20 1.200 15.56
2 26 0 26 0 2 26 0 1.570
MODEL CALCULATION:
18.26m
18.85 m C
11.97m
∆ABC,
AB= S / (tanα1-tanα2)
= (3.005-2.600) /
(tan10033’20”-tan9021’40”)
AB=18.85m
AC= S / (tanα1-tanα2)
= (3.650-2.950) /
(tan5040’-tan2020’)
AC= 11.97m
BC= S / (tanα1-tanα2)
= (1.710-1.350) /
(tan30-tan1052’20”)
BC=18.26m
=104.990m2.
RESULT:
The complete area of the land surveyed using trilateration has been calculated as
295.14 m2
and it has been presented in the form of the figure.
TRIGONOMETRICAL LEVELLING
Day: Tuesday
EX.NO: 3
Date: 02/07/2019
AIM:
APPARATUS REQUIRED:
1. Theodolite
2. Tape
3. Leveling staff
4. Plumb bob
FORMULA:
h1 = dtan Ө1
h2 = (d+D)tan Ө2
LOCATION:
The site is located at Manamathi village in the hillock located near the Madurandagam
lake.
SITE CONDITION:
The survey was carried out starting from 8.00 A.M to 2.00 P.M on 02/07/2019
which was a clear sunny day.
PROCEDURE:
1. Set up the theodolite at P and level it accurately with respect to the altitude
bubble.
2. Direct the telescope towards Q and bisect it accurately. Clamp both the
plates. Read the vertical angle Ө1.
3. Transit the telescope so that the line of sight is reversed. Mark the second
instrument station R on the ground. Measure the distance RP accurately.
4. Repeat steps (2) and (3) for both face observations. The mean values should be
adopted.
5. With the vertical vernier set to zero reading, and the altitude bubble in the
center of its run, take the reading on the staff kept at the nearby B.M.
6. Shift the instrument to R and set up the theodolite there. Measure the
vertical angle Ө2 to Q with both face observations.
7. With the vertical vernier set to zero reading, and the altitude bubble in the
center of its run. Take the reading on the staff kept at the nearby B.M.
When the instrument axes are at different levels. If S1 and S2 are the
corresponding staff readings on the staff kept at B.M., the difference in levels of the
instrument axes will be either (S2-S1) if the axis at B is higher or (S1-S2) if the axis
at A is higher. It has been derived from, when S2 is greater than S1
h1= D tanØ1
h2 = (d+D) tan Ø2
OBSERVATION AND TABULATION:
CALCULATION:
Ø = 10045’00”
tan Ø1 =h2/D
1=D tan Ø1
tan Ø2
=h2/(d+D)
h2=(d+D)tan
Ø2
subtracting(2)fr
om(1),we get
h1-h2=D tan
Ø2
tan Ø2
D = (S+d tan
Ø2)/(tan Ø1-tan
Ø2) S =1.165m.
h1=143.35 * tan10045’00”
=27.22m.
=100.000+1.615+27.22
=128.835m.
=128.835-100.000
=28.835m.
RESULT:
1) The elevation of the proposed level with respect to the staff station was found
as
28.835m.
2) The corresponding horizontal distance between the staff station and proposed
level is
153.350m.
3) The R.L of the proposed level on the hill with respect to B.M was found to be
128.835m.
RADIAL
CONTOURING
Day: Wednesday
EX.NO: 4
Date: 03/07/2019
AIM:
To study the concept of contour surveying and to plot the contour lines of the
given area by radial contouring method. From which the volume of cutting and
filling has to be determined for the proposed R.L.
APPARATUS REQUIRED:
2. Leveling staff
FORMULA:
V .D = K × S × Sin2θ (C × Cosθ )
Vertical Distance 2
H .D = K × S × Cos 2θ + (C × Sinθ )
Horizontal Distance
SITE CONDITION:
The survey was carried out starting from 8.00 A.M to 2.00 P.M on
03/07/2019 which was a clear sunny day.
PROCEDURE:
1. The instrument station ‘O’ was chosen such that almost all the points on
the hillock were seen from it.
2. The instrument was fixed at ‘O’ and the temporary adjustments were made.
3. The instrument was set 0°00’00” at both horizontal & vertical plane on facing
north.
4. The staff was placed along this line of sight at various control
points
were three stadia hair readings were taken.
5. Necessary angle of elevation & depression are taken to locate the specific
control points which are not visible with horizontal line of collimation with
the leveling staff fully extended.
6. Similarly various feasible line of sights were chosen and step 4&5 were repeated
V .D = K × S × Sin2θ (C × Cosθ )
Vertical 2
Distance
Check:
0.625 = 0.625
Hence checked.
RESULT:
Thus the R.L of the different points on the radial contour are determined.
GRID CONTOURING
EX.NO: 5 Day:
Wednesday
Date: 03/07/2019
AIM:
To study the concept of contour surveying and to plot the contour plan of the
given area by grid contouring method. From which the volume of cutting and filling
has to be determined for the proposed R.L.
INSTRUMENTS USED:
3. Leveling staff
4. Ranging rods
5. Tape
6. Arrows
SITE CONDITION:
The survey was carried out starting from 8.00 A.M to 2.00 P.M on
03/07/2019 which was a clear sunny day.
FORMULA USED:
– Proposed R.L
ARITHMETIC CHECK:
DESCRIPTION:
Contour:
Contour Interval:
Characteristics of Contour:
1. The contour lines are closer near the top of a hill or high ground and wide
apart near the foot. This indicates steep slope towards the peak and flatter
slopes towards the foot.
3. The contour lines are closer near the bank of a pond or depression and
wide apart towards the center.
4. Contour lines always form a close circuit, but these lines may be within or
outside the limits of the map.
5. Contour lines cannot cross one another except in the case of an
overhanging cliff. But overlapping portion must be shown by a dotted
line.
In direct method the reduced levels are determined in the known coordinates.
This method is applicable to recheck the reduced level in the existing site.
In indirect method the reduced levels are determined randomly in the area to
be surveyed. From which contour lines are plotted. This method is generally
applicable to determine the R.L for the newly constructing site.
PROCEDURE:
1. Base line of the given area is marked along the longitudinal direction at
midway.
2. Grids of size 24m x 24m are marked on both sides of base line by
running parallels and perpendicular survey lines.
7. If other stations are not visible, the instrument might be shifted and
the above procedures (3 to 6) are repeated.
8. Using the observations the reduced level of all the points of grids is
determined. Then the contour lines of the spillway profile are plotted
on graph sheet at same convenient contour intervals.
TABULATION:
CHECK:
1.48-3.42 = 100-98.06
1.94 = 1.94
S
H
RESULT:
The reduced levels of ground near the hill are determined and contour lines
are plotted
in graph.
LONGITUDINAL AND CROSS SECTION
SURVEY
Day: Thursday
EX.NO:6
Date: 04/07/2019
AIM:
APPARATUS USED:
2. Levelling staff
4. Tape
FORMULA USED:
Horizontal distance
‘HD’= KS + C When
inclined
Horizontal distance ‘HD’= KS
cos2ɵ + C cosɵ
B.M + H.I +V + h
Where, K is
additive constant
C is multiplying constant
LOCATION:
SITE CONDITIONS:
The distance covered was 120m starting from 8.00 A.M to 2.00 P.M on
04/07/2019 which was a clear sunny day.
The level of the site is somewhat lower than the adjoining areas. It is
understood from the locals that the selected road stretch is frequently flooded during
heavy rains.
THEORY:
Cross Section: Cross section has been taken at right angles to longitudinal
profile and on either side of the road stretch to study the profile of ground surface.
PROCEDURE:
2. The width of the road is measured and the centre line of the road is marked with
chain.
3. The levelling staff is held at the temporary bench mark and at every
required point along the longitudinal direction. The level readings must be
noted accurately.
4. The levels of cross section is taken along the width of the road,
perpendicular to longitudinal profile ay an interval of 20m and the readings
are recorded.
5. From the readings, reduced level of all points is determined and the cross
section is plotted on the graph.
6. From the graph, the quantity of earth work involved in filling and cutting
can be calculated.
REMARK
B.S I.S F.S H.I R.L
L C R
1.150 101.150 100
1.570 99.58 2.5
1.560 99.59 1.5
1.555 99.595 0
1.550 99.6
1.560 99.59
1.685 99.465 2.5
1.665 99.485 1.5
1.645 99.505 5
1.630 99.52
1.610 99.54
1.765 99.385 2.5
1.770 99.38 1.5
1.745 99.41 10
1.730 99.42
1.730 99.32
1.830 99.3 2.5
1.850 99.325 1.5
1.825 99.33 15
1.795 99.355 1.5
1.800 99.35 2.5
1.995 101.150 99.15 2.5
1.880 99.27 1.5
1.870 99.28 20
1.865 99.285
1.880 99.27
1.840 99.31 2.5
1.835 99.315 1.5
1.830 99.32 25
1.815 99.335 1.5
1.825 99.325 2.5
CHECK:
∑B.S. - ∑F.S. = Last R.L. – First R.L.
1.150-1.825 = 99.325-100
0.675 = 0.675
n
c
RESULT:
The required longitudinal and cross section profile of the existing
pathway has been drawn and the proposed pathway is also been identified.
RECIPROCAL LEVELLING
Date: 04/07/2019
AIM:
APPARATUS REQUIRED:
1. Dumpy level
2. Levelling staff
3. Plumb bob
FORMULA:
D2
LOCATION:
The site is located Manamathi village in the abandoned quarry located near the
Madurandagam lake.
SITE CONDITION:
The survey was carried out starting from 8.00 A.M to 2.00 P.M on 04/07/2019
which was a clear sunny day.
PROCEDURE:
1. The instrument is set at near A and staff readings are taken on A and B
with the bubble at the centre of its run.
3. Then the instrument is then shifted to the other bank, on a point very
near to B.M. B, and the readings are taken on staff held at B and A.
5. The staff readings taken near A and at B from the instrument station A
are noted as ha and hb and the staff readings taken near B and at A from
the instrument station B are noted as ha' and hb' The difference in R.L.
between the stations A and B are found using the formula
1
given below: H = [ (ha – hb) + (ha` - hb`) ]
2
OBSERVATION AND TABULATION:
R.L of the Instrument Station (E) with respect to B.M. @ 100.000 m:
INSTRUMENT SIGHT TO
STAFF READING
AT
TOP MIDDLE BOTTOM
CALCULATION:
H=1/2[(A-B) +
(Al-Bl)]
H=1/2[(3.10-
0.65) + (4.50-
2.15)] H=4.8/2
H=2.4m
= 100.000-2.4
= 97.6m.
RESULT:
The difference in level between two points are found by reciprocal
levelling .The point A is at the height of 2.4m above point B. The R.L of B is
found to be 98.825m.
RECONNAISSANCE SURVEY
Date: 05/07/2019
AIM:
APPARATUS USED:
3. Offset rod
4. Cross staff
5. Arrow
6. Prismatic Compass
7. Tape
LOCATION:
SITE CONDITIONS:
2. Total station was used to find the length of breakwaters and the water spread
area.
4. Total station was switched on and the temporary adjustments are done.
5. The parameters of the instrument are set using the function keys.
6. The bubble in the spirit level is used for levelling the instrument.
7. Before measuring, the horizontal and vertical angles are set to zero
using function keys F1 and F4.
9. Total station was placed at a point in such a way that maximum area is
covered.
10. The prism in prism rod is placed at various points and horizontal
distance and respective angles are noted.
12. Using the angles and distances the water spread area was calculated.
14. A base line was selected so that the whole area is covered.
15. At regular known intervals offsets are taken and the offset distances are noted.
16. In similar manner the whole area is covered and the land area is calculated.
RESULT:
The complete area of the Jeppiaar engineering college has been surveyed
and the layout of the college has been drawn.