S. Percentage For a 1000 sq ft No. Item of work of total work house House Area in Sq ft Construction Rate per Sq ft 800 1,000 2,000
1 Excavation in 3% 24,000 48,000 1
2 ordinary Foundation soil and 5% 40,000 80,000 2 3 Construction upto 5% 40,000 80,000 3 4 plinth Superstructure in 25% 200,000 400,000 4 5 brickwork Roofing including 17% 136,000 272,000 5 6 waterproofing Flooring 6% 48,000 96,000 6 7 Wood work i.e. 13% 104,000 208,000 7 8 Joinery, Internal doors and finishes 6% 48,000 96,000 9 External finishes 3% 24,000 48,000 10 Water supply 4% 32,000 64,000 11 Sanitary work 8% 64,000 128,000 12 Electrification 5% 40,000 80,000 13 Total 100% 800,000 1,600,000 rea in Sq ft in Red Color Cell Approx Approx Requirement Unit of Quantity Qyt for Qyt for of Materia measurement sq ft sq ft
Area of Construction in Sq ft 1000 2,000
Cement Bags/sqft 0.4 400 800
Sand (cu ft) Cut/sqft 1.81 1,810 3,620 Aggregate (cu Cut/sqft 1.14 1140 2280 ft) Bricks Nos/Sqft 34 34000 68000 Size Stone Nos/Sq ft 11 11000 22000 Steel Kg/Sqft 2.1 2100 4200 Wood CuF/Sqft 0.077 77 154