TIPPL-GRD (JV)

RFI SUMMARY SHEET


Name of the Project :- Development of NH-31 to 4 lane configuration from km 551.360 to km 563.260 (Ghoshpukur to Bihar More, Bagdogra) in Darjeeling District,West Bengal under EPC Mode''
(Project length-11.90 km.)
RFI SUMMARY DATE :
Submission Chainage Chainage Proposed Proposed
Sl No. RFI No. Side Description of Work Submitted By Status
Date (Km) (Km) Inspection Inspection
5711 TIPPLGRDJV/NH-31/HW/ 5916 6-Dec-19 LHS HIGHWAY BC Tack Coat MR. SATYAKI SARKAR 7-Dec-19 11:30
5712 TIPPLGRDJV/NH-31/HW/ 5917 6-Dec-19 LHS HIGHWAY BC BC MR. SATYAKI SARKAR 7-Dec-19 12:30
5713 TIPPLGRDJV/NH-31/HW/ 5918 6-Dec-19 LHS HIGHWAY MEDIAN Kerb Laying MR. SATYAKI SARKAR 7-Dec-19 12:30
5714 TIPPLGRDJV/NH-31/HW/ 5919 6-Dec-19 RHS HIGHWAY BUS BYE Laying 1st MR. SATYAKI SARKAR 7-Dec-19 01:30
5715 TIPPLGRDJV/NH-31/HW/ 5920 6-Dec-19 RHS HIGHWAY BUS BYE wmm 1st MR. SATYAKI SARKAR 7-Dec-19 02:30
5719 TIPPLGRDJV/NH-31/STR/ 5921 6-Dec-19 552+480 LHS Reinforcement checking of RE Pannel STRUCTURE RE PANNEL concreting of RE Pannel MR. ARINDAM SINHA 7-Dec-19 12:30
5720 TIPPLGRDJV/NH-31/STR/ 5922 6-Dec-19 552+480 LHS Concreting of RE Pannel STRUCTURE RE PANNEL PCC MR. ARINDAM SINHA 7-Dec-19 01:30
Reinforcement and shuttering RETAINING
5722 TIPPLGRDJV/NH-31/STR/ 5923 6-Dec-19 553+870 553+940 70 RHS STRUCTURE reinf. Of raft of ret. Wall MR. ARINDAM SINHA 7-Dec-19 02:30
checking of raft of ret. Wall WALL
RETAINING concreting of raft of ret.
5723 TIPPLGRDJV/NH-31/STR/ 5924 6-Dec-19 553+870 553+940 70 RHS Concreting of raft of ret. Wall STRUCTURE MR. ARINDAM SINHA 7-Dec-19 02:45
WALL Wall
Excavation for foundation A-2 of
5724 TIPPLGRDJV/NH-31/STR/ 5925 6-Dec-19 559+982 LHS STRUCTURE Minor Bridge Excavation MR. ARINDAM SINHA 7-Dec-19 03:00
MNB
Reinforcement checking of wall 1st lift
5725 TIPPLGRDJV/NH-31/STR/ 5926 6-Dec-19 560+654 LHS STRUCTURE CULVERT reinf. Of ret. wall 1st lift MR. ARINDAM SINHA 7-Dec-19 03:15
of ret. Wall
concreting of ret. wall 1st
5731 TIPPLGRDJV/NH-31/STR/ 5927 6-Dec-19 560+654 LHS Concreting of wall 1st lift of ret. Wall STRUCTURE CULVERT MR. ARINDAM SINHA 7-Dec-19 04:15
lift
5733 TIPPLGRDJV/NH-31/STR/ 5928 6-Dec-19 562+020 562+030 10 LHS Excavation for PCC of Side drain STRUCTURE CULVERT Excavation MR. ARINDAM SINHA 7-Dec-19 04:20
Level Checking of Earthen Bed for
5731 TIPPLGRDJV/NH-31/STR/ 5929 6-Dec-19 562+020 562+030 10 LHS STRUCTURE CULVERT Level checking MR. ARINDAM SINHA 7-Dec-19 04:15
PCC of Side Drain
5733 TIPPLGRDJV/NH-31/STR/ 5930 6-Dec-19 562+020 562+030 10 LHS PCC OF SIDE DRAIN STRUCTURE CULVERT PCC MR. ARINDAM SINHA 7-Dec-19 04:20