ID progress WorkOrder # TAG Location Shutdown Enact Hydrotest Task Name Start Finish Inspection Type Resource Names

Start Finish Inspection Type Resource Names Predecesso


Code Required Y/N
Y/N
2 0% REG TAR 2013 31 May 08:00 04 Jul 12:00 REG TAR 2013

3 0% REG TRAIN 1 SHUTDOWN ( 10 DAYS) 31 May 08:00 10 Jun 17:00 REG TRAIN 1 SHUTDOWN
( 10 DAYS)
12 0% REG TRAIN 2 SHUTDOWN (10 DAYS) 11 Jun 08:00 20 Jun 12:00 REG TRAIN 2 SHUTDOWN
(10 DAYS)
21 0% REG FF SHUTDOWN (15 DAYS) 21 Jun 08:00 04 Jul 12:00 REG FF SHUTDOWN (15
DAYS)
73 56% REG ILI 2013 01 Jan 08:00 31 Dec 18:00 REG ILI 2013

94 28% 2nd QUARTER(APR-MAY-JUNE) 01 Apr 08:00 30 May 17:00 2nd


QUARTER(APR-MAY-JUNE)
95 0% 454231 K-VK-063101A OL Y Y VESSEL - DRYER ADSORBER ( SN: S21753A/1A) 13 May 08:00 25 May 17:00 Enact/Hydrotest+DMI Enact/Hydrotest+DMI

96 0% 454232 K-VK-063101B OL Y Y VESSEL - DRYER ADSORBER ( SN: S21753A/1B) 13 May 08:00 25 May 17:00 Enact/Hydrotest+DMI Enact/Hydrotest+DMI

97 0% 454233 K-VK-063201A OL Y Y VESSEL - DRYER ADSORBER ( SN: S21753B/1A) 13 May 08:00 25 May 17:00 Enact/Hydrotest+DMI Enact/Hydrotest+DMI

98 0% 454234 K-VK-063201B OL Y Y VESSEL - DRYER ADSORBER ( SN: S21753B/1B) 13 May 08:00 25 May 17:00 Enact/Hydrotest+DMI Enact/Hydrotest+DMI

99 0% 454236 K-VL-091001 OL Y Y REG WORKSHOP AIR RECEIVER Fab Num: 67039 203753H 13 May 08:00 25 May 17:00 Enact/Hydrotest+DMI Enact/Hydrotest+DMI

Page 1