You are on page 1of 8

INSTRUCTIONS

8510223 P01-A © Danfoss Commercial Compressors March 2006


Instructions

0.5% slope
4 m/s or more

max. 4 m

A B

U-trap

8 to 12 m/s
max. 4 m
0.5% slope Evaporator
4m/s or more
Fig 5
Fig. 1
Fig. 3

Fig. 2

IN

OUT

4 Cyl. Fig. 4 1 & 2 Cyl.

Suction riser dimension


C
Suction pipe selection VTZ038 VTZ054 VTZ086 VTZ121 VTZ171 VTZ215 VTZ242
A
R404A Mini riser (A) 1/2" 1/2" 5/8" 3/4" 7/8" 1"1/8 1"1/8
-10/+45°C Max riser (B) 5/8" 3/4" 7/8" 1"1/8 1"3/8 1"3/8 1"3/8 B max. 4 m
Suct. Header (C) 3/4" 7/8" 1"1/8 1"3/8 1"5/8 1"5/8 1"5/8

Fig 5

Application Envelopes
For the application envelopes of the different va- rant refer to the Danfoss Commercial Compres-
riable speed compressors and applicable refrige- sors dedicated application guidelines.

Short frequency converter recommendations

d
• Installation
Make always sure that there is no possibility of done in relation with the present drawings.
exhaust hot air by-pass from the drive. This will Generally speaking shielded cables have to be
lead to overheating thermal trip of the inverter. used all over the frequency converter and va-
riable speed compressor, except network line to
d
The wiring of a variable speed system is to be frequency converter.
done in a very professional way.
The main precautions on assembly has to be d Fig 6
175ZA786.10

 8510223 P01-A © Danfoss Commercial Compressors March 2006


Instructions

• Connection to mains and earthing:

3 Phase
91 (L1)
Power 92 (L2)
Input 93 (L3)
95 PE

Fig 7
Mains and earthing connections

• Motor connections

Fig 8

Motor cable must be screened/armoured. Use on this plate and install the screened part of the connected on both end of the cable: frequency
the accessory decoupling plate. Make sure the motor cable as shown on the above drawings. converter and compressor.
earth wire is connected to the earth terminal Earth wire and screen cable part must be earth

• Control cables
Control cables must be screened/armoured. Use the screen to the decoupling plate for control
the clamp from the accessory bag to connect cables.

Fig 9

8510223 P01-A © Danfoss Commercial Compressors March 2006 


Instructions

Example of control cables connection

Note: CD compressor Drive frequency converters are delivered with a factory preset “open loop control” for compressor speed magement.

®
Frequency converter Compressor Drive
Digital
output
Analog Analog

RS 485
output input

12 13 16 17 18 19 20 27 29 32 33 37 39 42 45 50 53 54 55 60 61 68 69 4 5 1 2 3

0/4-20 mA
0/4-20 mA

0/4-20 mA
+10 V
0 ± 10 V
COM

COM
or 4-20
Incorporate security
devices on 27 input

Bus

mA
Start
to external
Open Loop input 0-10V fault relay
between 13 55

Fig 10

Modifications to move from open loop control to process loop:

To switch from open loop to process loop cable  Reference / Ramps Parameter 3.15Reference ressource 1no
signal connections have to be done has shown Parameter 3.01 bar function
below. Parameter 3.02  -1 bar Control: Analog signal 4-20 mA for -1 / 12 bar
Parameter 3.03  +12 bar is connectected on input 54
The only parameters modifications are: Parameter 3.10  suction pressure adjus- Control Input 54: switch it on I position
 Load / motor tement required as a percentage of the sensor (switch located back to the local control panel)
 Parameter 1.00Configuration mode: Process pressure range (28% for 3.4 bar  -10°C R404A)

TM
Frequency converter CD302 Compressor Drive
Digital
output
Analogue Analogue
RS 485

output input

12 13 16 17 18 19 20 27 29 32 33 37 39 42 45 50 53 54 55 60 61 68 69 4 5 1 2 3
0/4-20 mA
0/4-20 mA

0/4-20 mA
+10 V
0 ± 10 V
0 ± 10 V
COM

COM
Incorporate security
devices on 27 input

Bus

Start
to external
fault relay

Fig 11
Process Control via an AKS32
TM
Frequency converter CD302 Compressor Drive
Digital
output
Analog Analog
RS 485

output input

12 13 16 17 18 19 20 27 29 32 33 37 39 42 45 50 53 54 55 60 61 68 69 4 5 1 2 3
0/4-20 mA
0/4-20 mA

0/4-20 mA
+10 V
0 ± 10 V
COM

COM
or 4-20
Incorporate security
devices on 27 input

Bus
mA

Start
to external
fault relay

Fig 12
Process Control via an AKS33

 8510223 P01-A © Danfoss Commercial Compressors March 2006


Instructions
Contents carried out with extreme caution to avoid any a way as to prevent free liquid refrigerant migra-
1 - Introduction shocks. Dedicated packing handles are to be used tion and drainage back to the compressor sump
2 - Transportation, storage for all required manipulation of the compressor; and discharge cylinder heads (refer to fig. 1).
3 - Safety measures prior to assembly otherwise appropriate and safe lifting equipment • Make sure the installation is equipped with high-
4 - Assembly is to be used during handling and unpacking. pressure safety components (e.g. pressure switch,
5 - Leak detection • Any damage noticed on either the packaging pressure relief valve) to prevent against the
6 - Vacuum dehydration procedure or the product itself upon reception should be bursting of pressure-containing components.
7 - Electrical connections indicated on a Customer Claim addressed to the Note that all local and regional regulations and
8 - Filling the system shipping company. The same recommendation safety standards, such as EN 378, must be taken
9 - Verification before commissioning applies to all instances when transport into account when designing, connecting and
10 - Start up instructions have not been fully respected. running the system
11 - Troublesooting • Please review the safety instructions printed on
12 - Maintenance the cardboard packaging before storage. 4 - Assembly
13 - Replacement • Verify that the compressor is never stored in an The compressor’s time of exposure to the
14 - User advisory ambient temperature of below -35°C (-31°F) or atmosphere during installation shall be held to
above 50°C (122°F). a minimum (less than 1/2 hour). The compressor
1 - Introduction • Ensure that the compressor and its packaging connection must be fast in order to avoid moisture
These Instructions pertain to Maneurop® Variable are not exposed to rain and/or a corrosive, contamination of the lubricant.
Speed hermetic compressors used for A/C and flammable atmosphere. • The grommets must be installed under the
refrigeration purposes. They are intended to compressor feet, as shown in Fig. 4. Rubber
provide necessary information regarding safety 3 - Safety measures prior to assembly grommets are to undergo compression until
features and proper handling of this product. • All installation and servicing is to be performed contact is made between the flat washer and the
Note that this is a general document for the entire by qualified personnel in compliance with all steel mounting sleeve.
range of Variable Speed hermetic compressors; pertinent practices and safety procedures. Before opening the compressor connection
certain details therefore may not be applicable to • The compressor must be located in a ventilated fittings, it is mandatory to connect a service hose to
the particular model you have purchased. Please area to ensure that the ambient temperature the Schrader fitting on the compressor shell in order
keep your manual and all relevant information never exceeds 50°C (122°F) during the off-cycle. to gradually release the nitrogen holding charge.
handy for future reference. • Make certain that the compressor can be moun- • Ensure that no material enters into the system
• Equipment description: This compressor is de- ted onto a horizontal plane with a maximum while cutting the tubing. Moreover, never drill
livered with all assembly equipment (rubber slope of 3°. holes in the pipe work after installation.
grommets + screws + washers), an electrical box • The compressor can only be supplied by a • Should additional components need to be
(cover + spring), connecting sleeves and gaskets, frequency converter. Make sure that the drive connected onto the compressor sight glass or oil
and Instructions. is the dedicated one for the compressor (power equalization ports, it is recommended that such an
• Approved list of refrigerants: size and voltage: input & output). Compressor/ operation be carried out prior to final assembly, to
- The VTZ series can be used with R404A, R507A, frequency converter/refrigerant models selection allow for compressor inclination and movement.
R407C and R134a. are listed on parameter 1.13 of the frequency • Avoid flare-type connections and exercise great
• Compressors are filled with lubricant before converter. care while brazing (use only state-of-the-art
leaving the factory: • Ensure that refrigerant-charging equipment, va- practices); apply a nitrogen gas flow to prevent
- The VTZ series with Polyolester oil (ref. 160PZ), cuum pumps, etc. for HFC refrigerant systems have oxidation inside the tubing. All brazing material is
This lubricant must not be mixed with one another. been specifically reserved for these refrigerants to contain a minimum of 5% silver. If flux additive is
• Maneurop® Variable Speed compressors must and never used with other CFC, HCFC refrigerants. used, don’t put the copper tube into the receiver of
only be used for their designed purpose(s) and • Use only clean and dehydrated refrigeration-grade flux, but put flux around the tube (i.e. with a pencil).
within their scope of application (Please refer to copper tubes as well as silver alloy brazing material. this will prevent pure flux getting inside the tube.
the Application Guidelines). • Verify that all system components are • When brazing, protect the terminal box and
Maneurop® compressors are delivered under appropriate (use of refrigerant, etc.), clean and painted surfaces of the compressor from torch
nitrogen gas pressure (between 1 and 2 bar) and dehydrated before being connected to the heat damage.
hence cannot be connected as is; please refer to completed assembly. • Remove the Teflon gaskets when brazing Rotolock
the “Assembly” section for further details. • Perform a check on the suction lines: Horizontal connectors with the solder sleeve and be aware
Compressors are not certified for mobile sections are to be sloped downwards towards that original suction and discharge gaskets must
and explosion-proof applications. Any use of the compressor. Suction gas velocity must be be replaced.
flammable refrigerant (e.g. hydrocarbons) or air is high enough to provide for an adequate oil • When installing Rotolock fittings, always use
also strictly forbidden. return. This velocity must be within 8 to 12 m/s two wrenches when tightening any fittings to
• Under all circumstances, the EN378 (or other in vertical risers. In horizontal pipes, this velocity insure that the torque is effectively cancelled on
local regulation) requirement must be fulfilled. can decrease to 4 m/s. the adjacent tubing and fittings. Do not exceed
When pressure tests are required on the • The use of U-trap and double-suction risers the maximum tightening torque for Rotolock
system, they are to be performed by qualified may be required on vertical sections, but not in connections to the compressor :
personnel, in paying close attention to potential excess of 4 m unless a second U-trap system has 1" rotolock 80 Nm
pressure-related hazards and heeding the been fitted (refer to Figs. 2, 3 and 5). Suction line 1"1/4 rotolock 90 Nm
pressure limits displayed on the compressor piping must be insulated in order to minimize 1"3/4 rotolock 110 Nm.
nameplate or in the application guidelines. the effects of superheating. • Be sure to connect the required safety and
Modifications or alterations to the compres- • Perform a check on the discharge lines: Piping to control devices onto compressor shut-off valves
sor (such as brazing on the shell) not expressly the condenser must be designed so as to prevent or fittings. In case of oil return through the Schra-
approved by the party responsible for ensuring liquid return to the compressor and adequat der fitting on the compressor shell, make sure the
compliance could invalidate the user’s authoriza- refrigerant gas velocity. The use of non-return internal valve is removed.
tion to operate the equipment. valves may prove necessary, depending on the
position of the compressor with respect to the 5 – Leak detection
2 - Transportation, storage condenser. A suitably-sized U-trap may also be Never use oxygen or dry air in order to avoid
• The compressor must be handled in the vertical po- necessary if the condenser has been placed the risk of fire or explosion.
sition (maximum offset from the vertical: 15°).Should above the compressor (refer to Fig. 1). • Perform a leak detection test on the complete
the compressor be handled in an upside-down posi- • The piping connected to the compressor must system by means of: a dry nitrogen pressure test,
tion, its performance may no longer be insured. be configured on the basis of a flexible 3-axis de- a mixture of nitrogen and the refrigerant to be
• Beware that all compressor handling must be sign to dampen vibrations and designed in such used in the system, a helium leak test and/or a
8510223 P01-A © Danfoss Commercial Compressors March 2006 
Instructions
deep vacuum test. At the time of commissioning, system moisture for line lengths (back and forth) in excess of 20 m.
• The test should be long enough in duration to content may be as high as 100 ppm. During - An additional quantity of oil might be neces-
ensure the absence of any slow leaks in the system. operation, the liquid line filter dryer must reduce sary to compensate the quantity trapped in the
• Use tools specifically designed for detecting leaks. this level to < 20 ppm. oil separator and oil reservoir when used.
• The low side test pressure must not exceed 1.1 x Ps Additional notes: - In the event additional oil is required, use only
pressure indicated on the compressor nameplate. • To improve moisture removal, the temperature an approved lubricant (refer to the “Introduction”
• For high side test pressure recommendations, of the system should not be lower than 10°C. If the section of this manual).
please refer to the Application Guidelines. evaporator coil is equipped with electrical defrost - Use the compressor oil sight glass or the sight
• Whenever the compressor is equipped with heaters, these heaters should be energized. glass from the oil level controller when used to
suction and discharge shut-off valves, these • A proper vacuum procedure is even more check the proper oil level when commissioning after
valves are to remain in the closed position while important with HFC and polyolester lubricant stabilization of the complete refrigeration system.
performing the leak test (compressor leak test than it has “traditionally” been with HCFC (R22) or For all information necessary on adding oil to the
already performed in the factory). CFC and mineral oil. compressor, refer to TI 2-025.
• Should a leak be discovered, proceed with repair • For further details, please refer to TI 2-026. • Make sure the refrigerant used to fill the system
steps and repeat the leak detection. Do not use a megohmeter or apply power to the is compatible with compressor design. Refer to
• When a deep vacuum leak detection test is compressor while it is under vacuum, as this may the “Introduction” section of this manual for an
selected, observe the following: cause motor winding damage (motor burn-out). approved list of refrigerants
1) The level to reach is 500 µm Hg. • Compressor switched off: The liquid refrigerant
2) Wait 30 min. 7 - Electrical connections is charged into the condenser and/or liquid
3) If pressure increases rapidly, the system is • Make sure the main power supply to the system receiver in the liquid phase (compulsory for
not airtight. Locate and repair leaks. Restart the has been switched off and isolated, in accordance refrigerant blends). The charge must be as close
vacuum procedure, followed by steps 1, 2, etc. with applicable regulations, before performing to the nominal system charge as possible in
4) If pressure increases slowly, the system any electrical connection. order to avoid both low pressure operations and
contains moisture inside. Break the vacuum with • Please refer to Fig 7, 8 and 9 for typical wiring excessive superheating at start-up. Throughout
nitrogen gas and restart the vacuum procedure, connections and examine the specific wiring this operation, both compressor service valves
followed by steps 1, 2, etc. diagram located in the frequency converter must remain closed.
5) Connect the compressor to the system by package. For further details, refer to the • Remember that vapor-charging is only
opening the valves. application guidelines. appropriate for pure refrigerants.
6) Repeat the vacuum procedure, followed by • Follow very closely the installation instruction • To the extent possible, maintain the refrigerant
steps 1, 2, etc. for frequency converter: charge below 2.5 kg per cylinder. Above this limit,
7) Break the vacuum with nitrogen gas. - See principal for mounting (fig 6): base frame install a system, such as a pump-down cycle or
8) Repeat the vacuum procedure, steps 1, 2; a of the frequency converter needs to very well suction line accumulator, to prevent against
vacuum of 500 µm Hg (0.67 mbar) should be rea- fixed to the support to ensure a very good conti- liquid flood-back into the compressor.
ched and maintained for 4 hours. This pressure is nuity between the earth potential of every elec- Be sure that the refrigerant charge is suitable for
to be measured in the refrigeration system, and trical panel and boxes of the system. both winter and summer operations
not at the vacuum pump gauge. - See principal for wiring (fig 7, 8 and 9): bases
Do not use a megohmeter or apply power to the are that all control wires have to be of a screee- 9 - Verification before commissioning
compressor while it is under vacuum, as this may ned design, the cable for electrical motor supply Ensure that all service valves are in the open
cause motor winding damage (motor burn-out). has to be of a shielded design too. Correct ear- position before start-up. A closed discharge or
Do not use colored leak detection fluids. thing of the shield cover has to be done using suction service valve may cause serious damage
the method shown on fig 8 and 9, every time this to the compressor and/or compromise safety
6 - Vacuum procedure one has to be earthed on each end of the cables. device operation, thereby resulting in potential
Whenever possible (if shut-off valves are present), Distinct cable tray must be used for control and injury to personnel.
the compressor must be isolated from the system. motor supply. • Check that all safety devices are operational
It is essential to connect the vacuum pump to • The frequency converter ensures direct motor and properly set (safety pressure switch set
both the LP & HP sides, in order to avoid dead- protection and the factory set parameters are de- point, mechanical relief valve if necessary, etc.).
ending system parts. signed such as it is protecting the motor over all Make sure that these devices comply with both
Recommended procedure: current malfunctions. So an external over-load is generally- and locally-applicable regulations and
1) Once leak detection has been completed, not necessary. standards (e.g. EN 378).
2) Pull down the system under a vacuum of 500 • Set the frequency converter parameters in • When using high-pressure switches or relief
µm Hg (0.67 mbar). accordance with Danfoss recommendations for valves, the setting must not exceed maximum
3) When the vacuum level of 500 µm Hg has the couple of CD 302 frequency converter and service pressure of any system component.
been reached, the system must be isolated from VTZ variable speed compressor. Refer to the Application Guidelines for relevant
the pump. • Maneurop® compressors are able to operate in compressor pressure safety limits.
4) A vacuum of 500 µm Hg (0.67 mbar) has both directions (rotation). • A low-pressure switch is recommended to
to be reached and maintained for 4 hours. This • Depending on motor size, the power supply prevent operation under vacuum. Use a minimum
pressure is to be measured in the refrigeration connection utilizes either a spade connector (1/4”- setting of 1.1 bar (absolute).
system, and not at the vacuum pump gauge. AMP-AWE) or a T-block connector (screw type 10-32 • Verify that all electrical connections are properly
If pressure increases, restart the leak-detection UNF x 9.5). For screw-type connections, be aware fastened and in compliance with local safety
procedure (refer to the “Leak detection” section that the maximum tightening torque is 3 Nm. regulations.
of this manual if necessary). • A 5-mm earth terminal screw is provided in the com- • When a crankcase heater is required (refer
Vacuum pump: pressor junction box for the grounding connection. to the Application Guidelines), ensure that it
A two-stage vacuum pump with gas ballast (1.5- All electrical components must be selected as per has been energized for a minimum of 12 hours
mbar standing vacuum) shall be used; its capacity local standards and compressor requirements. before initial start-up and/or during prolonged
is to be consistent with system volume. Never use shutdown periods.
the compressor as a vacuum pump. 8 - Filling the system
It is recommended to use large-diameter • Before charging the refrigerant, verify that the oil 10 - Start up
connection lines and to connect these lines to level is between ¼ and ¾ on the compressor oil Never start the compressor in the absence of
the shut-off valves, rather than to the Schrader sight glass (when mounted) and/or ensure that the a refrigerant charge.
connection. This recommendation allows oil charge of the original compressor is sufficient as • Do not bypass the LP or any other safety switches
avoiding excessive pressure losses. regards system dimension and piping design: during start-up.
Moisture level: - An additional quantity of oil might be necessary • Check current draw and voltage levels on the
 8510223 P01-A © Danfoss Commercial Compressors March 2006
Instructions
main. The values for the compressor electrical • The low-pressure switch trips out: Check evapo- • Make sure that the main power supply has been
motor can be directly displayed on the frequency rator operations (coil cleanliness, fan operations, switched off.
converter control panel. water flow, water filter, etc.), liquid refrigerant • Before replacement, it is necessary to determi-
• Monitor the oil sight glass for 60 min. after flow and pressure drops (solenoid valve, filter ne the cause of failure and implement remedial
system equilibrium to ensure proper oil return dryer, expansion valve, etc.), refrigerant charge. action. If such analysis and repair are not perfor-
to the compressor. This oil check has to be done • Low refrigerant charge: The correct refrigerant med, repetitive failure may occur. Note that an
over the speed range to garanty: charge is given by the liquid sight glass indica- oil acidity test always proves helpful in diagnosis
- a good oil return at low speed when gas velo- tion, the condenser delta T in relation to the re- when undertaking compressor replacement.
city is at it’s minimum, frigerant pressure tables (pressure-temperature), • Don’t forget to use the fault memory of the
- a good oil management at high speed where the superheat and the sub-cooling, etc. (if addi- frequency converter and to recover the fault
oil carry over is at it’s maximum. tional charge is deemed necessary, refer to the descriptions before initializing the system and
• Suction superheat setting: Optimal compressor “Filling the system” section). even shutting off the power
suction superheat would be around 10K, with the • Compressor short cycling: The number of cycles • Check that the new Maneurop® compressor and
maximum allowable superheat being 30K. shall never exceed 12 starts per hour. the on-site compressor to be replaced display the
• In all cases, the application limits of the same electrical and refrigeration performance
compressor must be respected; moreover, 12 - Maintenance characteristics.
high superheat values lead to high discharge • Maneurop® compressors do not necessitate any • Use the rubber grommets and gaskets supplied
temperatures and decrease compressor capacity. special maintenance procedure. However, it must with the new compressor.
The maximum discharge temperature is 130°C: be recalled that proper operations and mainte- • Whenever piping needs to be modified,
operating at a higher temperature may result in nance of the system serve to prevent against sys- please refer to the “Safety measures prior to
refrigerant decomposition. tem-related compressor problems. The following assembly” section.
• Under steady-state operating conditions, check preventive maintenance checks, to be performed • For further details on replacement steps, refer to
refrigerant piping or capillary tubes for abnormal at regular intervals, are highly recommended: the previous sections of this manual.
vibrations (refrigeration line movement in excess of 1.5 - Control operating conditions (evaporating • Danfoss recommends not to throw away a used
mm necessitates corrective actions, pipe brackets, etc.). temperature, condensing temperature, compres- compressor but to dispose of the com-
• After 2 to 4 hours of operations under sor discharge temperature, temperature differen- pressor and its oil at a specialised recycling
established conditions, check the oil level and ce on heat exchangers, superheat, sub-cooling). company site.
add oil if necessary (refer to TI 2-025). If oil return These conditions must always remain within Note: In the event of motor failure, flush and clean
continues to perform poorly, further investigation compressor operation limits. the entire circuit before replacing the compressor
of the piping design is required. - Verify that safety devices are operational and in order to remove acids and contaminants.
• Ensure that refrigerant flow through the liquid properly set. Systematically install a new filter dryer on the liquid
line sight glass (when mounted) is adequate and - Check the compressor oil level and qua- line. Prior to this step (if necessary), run the system
that operating temperatures correspond with lity; this step may include an acid test, humidity for at least 2 hours with anti-acid cartridges (in
system specifications. check, spectrometer analysis, etc. whenever the such instances, the installation of a suction filter
• When needed, refrigerant may be added in the oil becomes discolored. might also be required). After an operating period
liquid phase, carefully throttling the refrigerant - Ensure that the circuit is leak tight. of approximately 2 weeks, check the level of oil
on the low-pressure side and as far as possible - Verify the proper operation of heat exchan- acidity. If the oil acid test proves positive, drain and
from the compressor. The compressor must be gers and, if necessary, clean them. replace the oil, replace the anti-acid liquid line filter
operating during this process at a medium speed - Check the current draw on the compressor motor dryer cartridges and the suction filter previously
if possible (this can be manually hand forced at as well as proper voltage balance between phases. installed. Repeat oil and filter dryer replacements
50 Hz for exemple). - Check that all electrical connections are still until the system is clean and acid-free. When there
Do not overcharge the system. adequately fastened. is no longer any sign of acidity, replace the anti-acid
- Make sure the compressor is clean and in good cartridges by the standard model and remove the
11 – Troubleshooting working order; verify the absence of rust on the suction strainer cartridge as required.
• Compressor failure to start: Verify that the compressor shell, piping and electrical connections.
compressor is hooked up to the frequency - Make sure the refrigerant charge is suitable 14 - User advisory
converter; check the power lead connections. If for both winter and summer operations. Insist that all service operations only be
these verifications reveal no abnormality, control • Insure that periodic in-service inspections performed by qualified personnel.
the motor windings with an ohmmeter. required by local regulations are performed. The compressor and tubing surface
• Check the frequency converter control panel: • For the frequency converter check the internal temperatures may exceed 100°C (212°F) and
If any alarm is displayed check the wiring and temperature on the display and control the cause severe bodily burns. Special precaution
specially the polarity of the control cables, proper air flow for cooling. must be taken when working around the
when an alarm is shown refer to the converter • Fault are logged on the converter memory and compressor and refrigerant tubing. Moreover,
application manual and specially revue the can be displayed, this can help to revue some a compressor in operation can generate very
electrical motor parameters set in. parameter of the frequency converter or of the cold surface temperatures (as low as -45°C / -
• Compressor failure to build up pressure: Check system itself. 49°F), thereby exposing personnel to the risk of
to make sure that all bypass valves in the system freezing burns.
have not been opened. Also check that all 13 – Replacement Pressure inside the compressor can reach dange-
solenoid valves are in their proper position. Precaution must be taken when disconnec- rously high levels (e.g. abnormal operation, fire,…)
• Abnormal running noise: Ensure the absence of ting, cutting or drilling holes in the tubing to en- leading to personnel injury if suddenly released; the-
any liquid flood-back to the compressor by means sure that no refrigerant under pressure is present refore, never drill, weld or cut the compressor shell
of measuring the return gas superheat and com- in the system. and adjacent tubing (release of liquid refrigerant can
pressor sump temperature. The sump should be at The refrigerant shall not be discharged directly cause flash freezing on exposed skin).
least 10K above the saturated suction temperature into the atmosphere; rather, it must be removed Be aware that the product warranty may be
under steady-state operating conditions. using approved reclamation techniques and deemed null and void in the following cases:
• The high-pressure switch trips out: Check equipment and then safely stored, in accordance • external modifications to the compressor (ab-
condenser operations (condenser cleanliness, with applicable legislation. sence of nameplate, drilling, welding, broken
fan operations, water flow and water pressure The presence of refrigerant vapor can displace feet, shock marks),
valve, water filter, etc.). If above check out OK, air and lead to suffocation. Proper ventilation is man- • compressor opened by the customer or returned
the problem may be due to either refrigerant datory at all times when servicing the equipment. unsealed (i.e. open discharge or suction ports),
overcharging or the presence of a non- A refrigeration system component change must • presence of rust or water inside the compressor,
condensable (e.g. air, moisture) in the circuit. be carried out in compliance with local regulations. • addition of leak-detection fluid in the lubricant,
8510223 P01-A © Danfoss Commercial Compressors March 2006 
• use of a refrigerant or lubricant not approved by sion-proof ).
Danfoss Commercial Compressors,
• any deviation from recommended instructions per- The date of production of the compressor is indica-
taining to installation, application or maintenance, ted on the nameplate. Ensure that the model and
• use in mobile applications (boats, trains, trucks, serial number information are always transmitted
etc.) or under explosive atmospheric conditions with any claim filed regarding this product.
(the compressor connecting box is not explo-

Danfoss Commercial Compressors http://cc.danfoss.com


Danfoss can accept no responsibility for possible errors in catalogues, brochures and other printed material. Danfoss reserves the right to alter its products without notice. This
also applies to products already on order provided that such alterations can be made without subsequential changes being necessary in specifications already agreed. All trade-
marks in this material are property of the respective companies. Speerall®, Danfoss and the Danfoss logotype are trademarks of Danfoss A/S. All rights reserved.

8510223 P01-A

You might also like