You are on page 1of 3

CHANCELLOR HOTEL BORACAY

CONTRACT#20180021

Section Original Provision KPI 1st Comments Remarks (by the OWNER) KPI 2nd Comments Revised Provision proposed by KPI

For other projects we agree to bear


responsibility for safekeeping. However, Unloading of materials from the delivery truck,
Unloading of materials from the delivery truck, rental rental of lifting equipment, moving-in to the
the owner should provide storage. Also,
of lifting equipment, moving-in to the designated designated area, storage and safekeeping of
the owner should be responsible for
area, storage and safekeeping of equipment and equipment and parts, provided that the OWNER is
safekeeping if the project is delayed due responsible at its cost for safekeeping of materials,
parts. Charges incurred due to delayed unloading of
The Owner should provide storage Safekeeping of parts should to the owner. As a compromise please equipment and parts if and to the extent the Works
equipment shall be for the account of the
Sec 2.1.3 space at the site and be responsible be shouldered by the amend the clause by deleting “storage” are delayed by any act or omission of the OWNER.
ELEVATOR CONTRACTOR. Required Permits and
for site security. Elevator Contractor. and add at the end of the first sentence: Charges incurred due to delayed unloading of
Fees for temporary parking of delivery trucks and equipment shall be for the account of the
“, provided that the OWNER is
preparation of access of delivered materials shall be ELEVATOR CONTRACTOR. Required Permits
responsible at its cost for safekeeping of
secured and its expenses shall be borne by and Fees for temporary parking of delivery trucks
materials, equipment and parts if and to
ELEVATOR CONTRACTOR. and preparation of access of delivered materials
the extent the Works are delayed by any shall be secured and its expenses shall be borne
act or omission of the OWNER”. by ELEVATOR CONTRACTOR.

Accelerating completion date should


The OWNER reserves the right to appoint at least be agreed mutually noting the
one (1) elevator for fast track completion to be increased costs for KONE. If For other contracts the clause should be
This scope of work is
temporary use is required, a deleted as proposed by KONE due to the
commissioned and used as temporary service for included in the instruction to “Please remove as proposed by KONE”
separate construction time use reasons we have commented earlier.
Sec 2.1.11 hauling of workers and materials. bidders before awarding
agreement based on KONE’s
template should be signed to govern
such use in detail.
The ELEVATOR CONTRACTOR shall provide at its
own expense an emergency generator sufficient to For other projects, KONE agrees The ELEVATOR CONTRACTOR shall provide at
Temporary utilities such as
meet the temporary power requirement for otherwise to provide an emergency its own expense an emergency generator sufficient
electric power and water
uninterrupted Installation, Testing and generator but not to take into account to meet the temporary power requirement for
Owner should provide such should be shouldered by
Sec 10.4.2 any interruptions by AKELCO. Please uninterrupted Installation and Testing &
Commissioning operation in case of emergency & facilities. Elevator Contractor, starting
delete the words “ operation in case of Commissioning operation in case of emergency &
brown outs or delay in provision of temporary power from the mobilization to final
emergency & brown outs or delay in brown outs or delay in provision of temporary
from AKELCO. testing and commissioning
provision of temporary power from power from AKELCO.
AKELCO”.
The ELEVATOR CONTRACTOR shall be deemed in 14.1. The ELEVATOR CONTRACTOR shall be
default if it becomes bankrupt, or receives an Order deemed in default if it becomes bankrupt, or
or judgment made against it, or shall present its receives an Order or judgment made against it, or
shall present its petition in bankruptcy or shall
petition in bankruptcy or shall make an arrangement
make an arrangement with or assignment in favor
with or assignment in favor or its creditors or shall or its creditors or shall agree to carry out the
agree to carry out the liquidation of the Agreement liquidation of the Agreement (other than voluntary
(other than voluntary liquidation for the purpose of liquidation for the purpose of amalgamation or
amalgamation or reconstruction) or if the Provisions already stated on For other contracts the clause should be reconstruction) or if the ELEVATOR
SVB Contract and was based amended as proposed by KONE due to CONTRACTOR shall assign the Agreement,
Sec 14.1 ELEVATOR CONTRACTOR shall assign the
on the previous agreement the reasons explained in our comments without first obtaining the written consent of the
Agreement, without first obtaining the written with the Elevator Contractor. previously. OWNER or shall have an execution levied on its
consent of the OWNER or shall have an execution
goods, or if the Project Manager shall certify in
levied on its goods, or if the Project Manager shall writing to the OWNER that in his opinion, the
certify in writing to the OWNER that in his opinion, ELEVATOR CONTRACTOR:
the ELEVATOR CONTRACTOR:
a) Has abandoned the Agreement; or
a) Has abandoned the Agreement; or
b) Without reasonable excuse has failed to b) Without reasonable excuse has failed to
commence the works; or commence the works; or

c) Has suspended the progress of the works for c) Has suspended the progress of the works for
c) Suspension caused by others
Seven (7) calendar days; or Seven (7) calendar days unless such suspension
should not be grounds for
termination. is caused by the OWNER or others; or
d) In case of materials or workmanship rejected by
the OWNER, the ELEVATOR CONTACTOR fails to d) In case of materials or workmanship rejected by
undertake the corresponding corrective measures the OWNER, the ELEVATOR CONTACTOR fails
within Fifteen (15) calendar days (or such other to undertake the corresponding corrective
measures within Fifteen (15) calendar days (or
period as may be specified by the OWNER) from the
such other period as may be specified by the
OWNER's written order that the said materials or OWNER) from the OWNER's written order that
works had been condemned and rejected by the the said materials or works had been condemned
OWNER under these conditions; or and rejected by the OWNER under these
conditions; or
e) Despite previous demand by the OWNER in
writing, the ELEVATOR CONTRACTOR fails or e) Despite previous demand by the OWNER in
refuses to execute the Works in accordance with this writing, the ELEVATOR CONTRACTOR fails or
Agreement, or persistently or flagrantly neglects or refuses to execute the Works in accordance with
this Agreement, or persistently or flagrantly
refuses to carry out its obligations under the
neglects or refuses to carry out its obligations
Agreement such as, but not limited to, the provision under the Agreement such as, but not limited to,
of the required bonds and insurances and the the provision of the required bonds and
correction of defects; or insurances and the correction of defects; or

f) Failed to complete the Works including approved


f) Termination due to any delay
f) not applicable (please remove as proposed by
alterations within the Completion Period or duly KONE)
would be unreasonable.
adjusted period.
g) Without reasonable excuse has caused the delay
g) Without reasonable excuse has caused the delay g) The delay should be significant to of Works by more than Fifty Percent (50%) of the
of Works by more than Ten Percent (10%) of the allow termination. Completion Period; or
Completion Period; or
Absent the OWNER's consent or in defiance of the
Owner's instruction to the contrary, the ELEVATOR
h) Absent the OWNER's consent or in defiance of CONTRACTOR subcontracted the whole or part of
the Owner's instruction to the contrary, the the Works
ELEVATOR CONTRACTOR subcontracted the
whole or part of the Works.

Without prejudice to the rights of the OWNER under


this Agreement, the OWNER shall have the right to
extra-judicially rescind this Agreement in case of
substantial delay in the completion of the Works or
for non-compliance by the ELEVATOR Rescinding the agreement due to For other contracts please delete the
Provisions already stated on
CONTRACTOR with any of its terms. any delay would be unreasonable. clause as proposed by KONE.
SVB Contract and was based
Sec 21.1 The other termination clauses Rescinding the agreement due to any “Please remove as proposed by KONE”
on the previous agreement
provide sufficient protection for the delay would be unreasonable. The other
Such rescission shall take effect upon the lapse of with the Elevator Contractor.
owner. termination clauses provide sufficient
Seven (7) calendar days from receipt by the protection for the owner.
ELEVATOR CONTRACTOR of the OWNER's
written notice. The OWNER's rescission shall be
without prejudice to any of the OWNER's existing
rights provided in this Agreement or by operation of
law.

In case the OWNER exercises its right to rescind


this Agreement, the OWNER shall pay for the work
rendered or accomplished by the ELEVATOR
CONTRACTOR at the time of the rescission subject
to deductions allowed to OWNER under this
Agreement.

You might also like