Q3. An assembly is to be made from two parts A & B. Both must be turned on a lathe and B must
be polished whereas, A need not be polished. The sequence of activities together with their
predecessors is given below. Construct a network diagram
Q4. Construct the project network, write all possible paths and identify the critical path. Use AOA,
AON & Gantt Chart methods
Activity A B C D E F
Immediate
- - AB B C D
predecessor
Duration in
1 2 3 4 2 3
days
Activity A B C D E F G
Immediate - - - A C A DBE
predecessor
Duration in 4 6 2 5 2 7 4
days
1
a) Construct the project network, write all possible paths and identify the critical path.
b) Calculate total float, free float and independent float for the project activities
c) Interpret the concept of floats in Project Management
Q6. Given the following data, prepare a network and identify the critical path. Also, determine the
total float, free float and independent float for various activities
Activity 1-2 1-3 2-6 3-4 3-5 4-6 5-6 5-7 6-7
Duration 4 6 8 7 4 6 5 19 10
A - 5
B - 10
C - 11
D A 6
E B 9
F B 13
G B 7
H C 9
I DE 5
J HF 8
2
ACTIVITY IMMEDIATE PREDECESSOR NORMAL TIME IN DAYS
A - 2
B - 3
C A 5
D B 4
E C 4
F C 7
G CD 6
H FG 3
I E 3
J I 2
K H 5
Q9. Draw the Gantt chart to represent the network and find out critical path
Q10. Draw the Gantt chart to represent the network and find out critical path
Activity A B C D E F G H I J
Pred. act. - - A&B A C A&B F G G I
Time 40 20 15 25 15 25 10 15 10 15
days
3
Q11. For the given problem
1) calculate EST, EFT, LST, LFT and TF
2) Plot a Gantt Chart for resource requirements and a resource graph over time. If the available
man power is limited to 20-man days every day, find out the days of over allocation. Find out the
days of over allocation if the available man power is 25-man days/day.
Q12. A project consists of nine activities for which the relevant data is given in the table.
a) draw the network and find the project completion time.
b) calculate EST, EFT, LST, LFT and TF
c) draw the Gantt Chart for the project.
d) what is the maximum requirement of cash and on which day does it occur?
Activity Predecessor Duration Funds required Rs per day
A - 5 25
B - 5 30
C A 10 40
D B 7 28
E A 6 12
F C, D 8 24
G C, D 6 15
H E, F 5 10
I G 4 12
Q13. (MU 2018 May) Consider following data of a small project below:
Activity Preceding Duration No. of men
activity (days) per day
A - 5 4
B - 7 2
C A 3 2
4
D A 3 4
E B 2 6
F B 2 3
G DE 2 3
H FG 3 4