Scheduling/Leveling Report - 02-Dec-19 - PM.

exe
===============================================

Default Project..................................................DHR_C1
_Rev.5A

Projects:
DHR_C1 _Rev.5A...................................................DHR_C1
Revised Schedule - Programme - Rev. 5A

Scheduling/Leveling Settings:
-----------------------------
General
-------
Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Retained
Logic
Calculate start-to-start lag from ...............................Early Start
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish Float
Calculate float based on finish date of .........................Each project
Calendar for scheduling Relationship Lag ........................Predecessor
Activity Calendar

Advanced
--------
Calculate multiple float paths...................................No

Statistics:
-----------
# Projects.......................................................1
# Activities.....................................................1736
# Not Started....................................................628
# In Progress....................................................48
# Completed......................................................1060
# Relationships..................................................4595
# Activities with Constraint.....................................3
Project: DHR_C1 _Rev.5A Activity: A1520 Contract Amendment No.1
Project: DHR_C1 _Rev.5A Activity: DD_LA_6_120 Engineering -
Employer final Approval on Al Jezah Plan
Project: DHR_C1 _Rev.5A Activity: DD_LA_6_130 Engineering -
Employer final Approval on Al Qatraneh Plan

Errors:
-------
Warnings:
---------
Activities without predecessors..................................2
Project: DHR_C1 _Rev.5A Activity: A1010 Commencement Date
Project: DHR_C1 _Rev.5A Activity: A1520 Contract Amendment No.1

Activities without successors....................................1


Project: DHR_C1 _Rev.5A Activity: A1020 Completion Date -
Updated

Out-of-sequence activities.......................................12
Project: DHR_C1 _Rev.5A Activity: BL4a_G_100 Verge Construction
Project: DHR_C1 _Rev.5A Activity: BL4a_LB_220 Wearing Course
with modified polymer bitumen
Project: DHR_C1 _Rev.5A Activity: BL4a_PR_230 IRI Wearing Course
Test
Project: DHR_C1 _Rev.5A Activity: BL4a_SI_220 Wearing Course for
Side Roads
Project: DHR_C1 _Rev.5A Activity: BL4a_UT_220 Wearing Course
with modified polymer bitumen
Project: DHR_C1 _Rev.5A Activity: BR1_DP_100 Relocation,
removal and demolishing of all utilities and obstructions including removal of
trees
Project: DHR_C1 _Rev.5A Activity: BR2_EW_110 Embankment
Construction
Project: DHR_C1 _Rev.5A Activity: BR6_HO_100 Strip H.O ,
Traffic Converting and Final Test
Project: DHR_C1 _Rev.5A Activity: BR7_HO_100 Strip H.O ,
Traffic Converting and Final Test
Project: DHR_C1 _Rev.5A Activity: BR8_EW_110 Embankment
Construction
Project: DHR_C1 _Rev.5A Activity: BR8_EW_140 Installation of
Safety & Protection Measures: New Jersey Barriers and Bollards
Project: DHR_C1 _Rev.5A Activity: CR1_M_PR_160 Binder 1
Course (7 cm)

Activities with Actual Dates > Data Date.........................0

Milestone Activities with invalid relationships..................0

Finish milestone and predecessors have different calendars.......9


Project: DHR_C1 _Rev.5A Activity: A1020 Completion Date -
Updated
Project: DHR_C1 _Rev.5A Activity: A1020 Completion Date -
Updated
Project: DHR_C1 _Rev.5A Activity: A1020 Completion Date -
Updated
Project: DHR_C1 _Rev.5A Activity: A1020 Completion Date -
Updated
Project: DHR_C1 _Rev.5A Activity: A1020 Completion Date -
Updated
Project: DHR_C1 _Rev.5A Activity: A1260 Prepare and Submit
Initial Baseline Programme
Project: DHR_C1 _Rev.5A Activity: A1270 Prepare and Submit
Health and Safety Environmental Plan
Project: DHR_C1 _Rev.5A Activity: A1280 Prepare and Submit
Quality Assurance and Control Plan (QA/QC)
Project: DHR_C1 _Rev.5A Activity: A1290 Prepare Method Statement

Scheduling/Leveling Results:
----------------------------
# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................1736
# Relationships with other projects..............................0
Data Date........................................................05-Dec-19
Earliest Early Start Date........................................05-Dec-19
Latest Early Finish Date.........................................30-Sep-20
Exceptions:
-----------
Critical Activities..............................................92
Project: DHR_C1 _Rev.5A Activity: A1020 Completion Date -
Updated
Project: DHR_C1 _Rev.5A Activity: A1111 Contract Amendment No.1
Duration
Project: DHR_C1 _Rev.5A Activity: AL1_M_PR_100 Milling
(Dismantling existing cracked asphalt concrete pavement layers)
Project: DHR_C1 _Rev.5A Activity: AL1_M_PR_110 Scarify,
Reshape and compacted the existing base layer (Consider as sub-base)
Project: DHR_C1 _Rev.5A Activity: AL1_M_PR_120 Laying new
crushed stone base course (1) 10 cm As Applicable)
Project: DHR_C1 _Rev.5A Activity: AL1_M_PR_130 Laying new
crushed stone base course (2) 10 cm (As Applicable)
Project: DHR_C1 _Rev.5A Activity: AL1_M_PR_150 Bituminous
Prime Coat MC
Project: DHR_C1 _Rev.5A Activity: AL1_M_PR_160 Binder 1
Course (7 cm)
Project: DHR_C1 _Rev.5A Activity: AL1_M_PR_180 Bituminous
Tack Coat ( RC - 1 )
Project: DHR_C1 _Rev.5A Activity: AL1_M_PR_190 Binder 2
Course (7 cm)
Project: DHR_C1 _Rev.5A Activity: AL1_M_PR_210 Bituminous
Tack Coat ( RC - 2 )
Project: DHR_C1 _Rev.5A Activity: AL1_M_PR_220 Wearing
Course with modified polymer bitumen
Project: DHR_C1 _Rev.5A Activity: B_AD_100 As Built Drawings
Section B
Project: DHR_C1 _Rev.5A Activity: BL6b_PR_160 Binder 1 Course (7
cm)
Project: DHR_C1 _Rev.5A Activity: BL6b_PR_170 IRI Binder Course
1 Test
Project: DHR_C1 _Rev.5A Activity: BL6b_PR_180 Bituminous Tack
Coat ( RC - 1 )
Project: DHR_C1 _Rev.5A Activity: BL6b_PR_190 Binder 2 Course (7
cm)
Project: DHR_C1 _Rev.5A Activity: BL6b_PR_210 Bituminous Tack
Coat ( RC - 2 )
Project: DHR_C1 _Rev.5A Activity: BL6b_PR_220 Wearing Course
with modified polymer bitumen
Project: DHR_C1 _Rev.5A Activity: BL6b_PR_250 Laying new crushed
stone base course (3) 7 cm for the outer Shoulder
Project: DHR_C1 _Rev.5A Activity: BL6b_PR_270 Bituminous Prime
Coat MC for the outer Shoulder (3rd Lane)
Project: DHR_C1 _Rev.5A Activity: BR1_PR_160 Binder 1 Course (7
cm)
Project: DHR_C1 _Rev.5A Activity: BR1_PR_170 IRI Binder Course
1 Test
Project: DHR_C1 _Rev.5A Activity: BR1_PR_180 Bituminous Tack
Coat ( RC - 1 )
Project: DHR_C1 _Rev.5A Activity: BR1_PR_190 Binder 2 Course (7
cm)
Project: DHR_C1 _Rev.5A Activity: BR1_PR_210 Bituminous Tack
Coat ( RC - 2 )
Project: DHR_C1 _Rev.5A Activity: BR1_PR_220 Wearing Course
with modified polymer bitumen
Project: DHR_C1 _Rev.5A Activity: BR2_G_100 Verge Construction
Project: DHR_C1 _Rev.5A Activity: BR2_HO_100 Strip H.O ,
Traffic Converting and Final Test
Project: DHR_C1 _Rev.5A Activity: BR2_PR_160 Binder 1 Course (7
cm)
Project: DHR_C1 _Rev.5A Activity: BR2_PR_180 Bituminous Tack
Coat ( RC - 1 )
Project: DHR_C1 _Rev.5A Activity: BR2_PR_190 Binder 2 Course (7
cm)
Project: DHR_C1 _Rev.5A Activity: BR2_PR_210 Bituminous Tack
Coat ( RC - 2 )
Project: DHR_C1 _Rev.5A Activity: BR2_PR_220 Wearing Course
with modified polymer bitumen
Project: DHR_C1 _Rev.5A Activity: BR2_RF_100 Road Furniture
Project: DHR_C1 _Rev.5A Activity: BR3_DP_110 Detour Works
(Cross Over, Entrance , Exit , Small and Large Signs ,Road Marking ,Solar Power
advance Warning Signs)
Project: DHR_C1 _Rev.5A Activity: BR3_DP_V.O_110 NJB
Transportation and Installation
Project: DHR_C1 _Rev.5A Activity: BR3_DP_V.O_130 Provide
Lighting Towers (Begining and End)
Project: DHR_C1 _Rev.5A Activity: BR3_PR_100 Milling
(Dismantling existing cracked asphalt concrete pavement layers)
Project: DHR_C1 _Rev.5A Activity: BR3_PR_110 Scarify, Reshape
and compacted the existing base layer (Consider as sub-base)
Project: DHR_C1 _Rev.5A Activity: BR3_PR_120 Laying new crushed
stone base course (1) 10 cm
Project: DHR_C1 _Rev.5A Activity: BR3_PR_130 Laying new crushed
stone base course (2) 10 cm
Project: DHR_C1 _Rev.5A Activity: BR3_PR_150 Bituminous Prime
Coat MC
Project: DHR_C1 _Rev.5A Activity: BR3_PR_160 Binder 1 Course (7
cm)
Project: DHR_C1 _Rev.5A Activity: BR3_PR_170 IRI Binder Course
1 Test
Project: DHR_C1 _Rev.5A Activity: BR3_PR_180 Bituminous Tack
Coat ( RC - 1 )
Project: DHR_C1 _Rev.5A Activity: BR3_PR_190 Binder 2 Course (7
cm)
Project: DHR_C1 _Rev.5A Activity: BR3_PR_210 Bituminous Tack
Coat ( RC - 2 )
Project: DHR_C1 _Rev.5A Activity: BR3_PR_220 Wearing Course
with modified polymer bitumen
Project: DHR_C1 _Rev.5A Activity: BR8_G_100 Verge Construction
Project: DHR_C1 _Rev.5A Activity: BR8_HO_100 Strip H.O ,
Traffic Converting and Final Test
Project: DHR_C1 _Rev.5A Activity: BR8_PR_160 Binder 1 Course (7
cm)
Project: DHR_C1 _Rev.5A Activity: BR8_PR_180 Bituminous Tack
Coat ( RC - 1 )
Project: DHR_C1 _Rev.5A Activity: BR8_PR_190 Binder 2 Course (7
cm)
Project: DHR_C1 _Rev.5A Activity: BR8_PR_210 Bituminous Tack
Coat ( RC - 2 )
Project: DHR_C1 _Rev.5A Activity: BR8_PR_220 Wearing Course
with modified polymer bitumen
Project: DHR_C1 _Rev.5A Activity: BR8_RF_100 Road Furniture
Project: DHR_C1 _Rev.5A Activity: C_AD_100 As Built Drawings
Section C
Project: DHR_C1 _Rev.5A Activity: CL1_S_BP_120 Aggregate
Base Course (20 cm)
Project: DHR_C1 _Rev.5A Activity: CL1_S_BP_130 Bituminous
Prime Coat MC
Project: DHR_C1 _Rev.5A Activity: CL1_S_BP_140 Binder
Course (7 cm)
Project: DHR_C1 _Rev.5A Activity: CL1_S_BP_160 Bituminous
Wearing Course (5 cm)
Project: DHR_C1 _Rev.5A Activity: CL1_S_DP_110 Detour Works
Project: DHR_C1 _Rev.5A Activity: CL1_S_DS_100 Utilities
Excavation
Project: DHR_C1 _Rev.5A Activity: CL1_S_DS_110 Utilities
and Manholes Installation
Project: DHR_C1 _Rev.5A Activity: CL1_S_DS_130 Utilites
Testing and Backfilling
Project: DHR_C1 _Rev.5A Activity: CL1_S_HO_100 Strip H.O ,
Traffic Converting and Final Test
Project: DHR_C1 _Rev.5A Activity: CL1_S_RF_150 Curbstone
Installation / Concrete Paving
Project: DHR_C1 _Rev.5A Activity: CL1_S_RF_160 Road Marking
Project: DHR_C1 _Rev.5A Activity: CL1_S_RF_180 Roundabout
Concrete Paving
Project: DHR_C1 _Rev.5A Activity: CR1_M_HO_100 Strip H.O ,
Traffic Converting and Final Test
Project: DHR_C1 _Rev.5A Activity: CR1_M_PR_120 Laying new
crushed stone base course (1) 10 cm
Project: DHR_C1 _Rev.5A Activity: CR1_M_PR_130 Laying new
crushed stone base course (2) 10 cm
Project: DHR_C1 _Rev.5A Activity: CR1_M_PR_150 Bituminous
Prime Coat MC
Project: DHR_C1 _Rev.5A Activity: CR1_M_PR_160 Binder 1
Course (7 cm)
Project: DHR_C1 _Rev.5A Activity: CR1_M_PR_180 Bituminous
Tack Coat ( RC - 1 )
Project: DHR_C1 _Rev.5A Activity: CR1_M_PR_190 Binder 2
Course (7 cm)
Project: DHR_C1 _Rev.5A Activity: CR1_M_PR_210 Bituminous
Tack Coat ( RC - 2 )
Project: DHR_C1 _Rev.5A Activity: CR1_M_PR_220 Wearing
Course with modified polymer bitumen
Project: DHR_C1 _Rev.5A Activity: CR1_M_RF_100 Road
Furniture
Project: DHR_C1 _Rev.5A Activity: CR1_S_BP_120 Aggregate
Base Course (20 cm)
Project: DHR_C1 _Rev.5A Activity: CR1_S_BP_130 Bituminous
Prime Coat MC
Project: DHR_C1 _Rev.5A Activity: CR1_S_BP_140 Binder
Course (7 cm)
Project: DHR_C1 _Rev.5A Activity: CR1_S_BP_160 Bituminous
Wearing Course (5 cm)
Project: DHR_C1 _Rev.5A Activity: CR1_S_DP_110 Detour Works
Project: DHR_C1 _Rev.5A Activity: CR1_S_DS_100 Utilities
Excavation
Project: DHR_C1 _Rev.5A Activity: CR1_S_DS_110 Utilities
and Manholes Installation
Project: DHR_C1 _Rev.5A Activity: CR1_S_DS_130 Utilites
Testing and Backfilling
Project: DHR_C1 _Rev.5A Activity: CR1_S_HO_100 Strip H.O ,
Traffic Converting and Final Test
Project: DHR_C1 _Rev.5A Activity: CR1_S_RF_150 Curbstone
Installation / Concrete Paving
Project: DHR_C1 _Rev.5A Activity: CR1_S_RF_160 Road Marking
Project: DHR_C1 _Rev.5A Activity: CR1_S_RF_180 Roundabout
Concrete Paving

Activities with unsatisfied constraints..........................0

Activities with unsatisfied relationships........................0

Activities with external dates...................................0