requirements presented in the Contract. FLOWLINE FOR KWALE NEW 17T �PROJECT will be
constructed with the view of achieving quality delivery, structural integrity,
health, safety, security, environmental, and social performance.
Throughout the execution of the WORK, we will achieve, maintain and demonstrate its
performance excellence in each of these areas. To achieve exceptionally high
standards, we will work closely with COMPANY to achieve a the set goal in record
time.
1.1.5. DEFINITIONS
EM Engineering Manager
PM Project Manager
CM Construction Manager
LE Lead Engineer
ITP Inspection and Test Plan
QC Quality Control
QCI Quality Control Inspector
PQP Project Quality Plan
PPE Personal Protection Equipment
HSE Health Safety & Environment
PMI Positive Material Identification.
NCR Non Conformance Report.
IFR Issued for Review
AFC Approved for Construction
2. PROJECT DESCRIPTION
1. Material Handling
2. Transportation of free issued pipes to site
3. Site survey
4. Pipe fabrication and installation works
5. Hook-up at main wellhead
6. NDT
7. Coating
8. Road crossings
9. River crossing
10. Final hook-up at Kwale Gas Plant arrival manifold
11. Site restoration
3. REFERENCES