This Specification covers the design of reinforced concrete foundations,

steel platform of IdU remote manifold for the Datro GAS DELIVERY
DEBOTTLENECKING PROJECT.

1.1. Project Background

COMPANY intends to develop and install a new gas pipeline of first section
4km NPS 14 conveying gas from Idu Remote Manifold to Idu Flow station
and second section 30km NPS 14 conveying gas from Datro Flow station to
Obat Gas Plant.
This scope of this Project requires the need for detailed
engineering, procurement, construction, installation, testing and
pre-commissioning, and commissioning of the Gas Pipelines
utilising the Continuous Horizontal Directional Drilling installation
method (CHDD).