Professional Documents
Culture Documents
Dr.
Eng.
Ahme
d
Elshah
at ,
PhD,
PMP
PMP
#
1607
907
Project Management Professional
Sessions Interests
PMP Exam
Practice
PM
Practice
PMP Study Roadmap
5.Conclude 8.Process
2.Solve
Key - words Assembly
9.Test
3.Read 4.Summarize environment
preparation.
Guidelines
Focus on one source of knowledge.
Continuous reading ( Every day reading is better than
one day a week)
Logic thinking is the core competency.
PM is a life style more than knowledge.
Raise your benchmark when solving exams ( let your
passing score 90%)
PM key – words is the most important key for the
exam.
What is a project?
Project
Project is a temporary endeavor undertaken to create a
unique product, service or result.
The temporary nature indicates definite beginning and end
and not mean short duration.
The end is reached when the objectives had been
achieved, or the project is terminated because its
objectives will not or cannot be met, or the need for the
project no longer exist.
Projects can have also social, economic and environmental
impacts.
Why Establishing a project?
Market Demand
An Organizational Need.
Customer Request.
Technological Advance.
Legal Requirement.
Exercise 1
?
Project Life Cycle
Cost & Staffing Level
Time
Scope
Quality Cost
Project Knowledge Areas
vs. Process Groups
Initiation Planning Execution Monitoring & Closing
Control
Integration Scope Quality Scope Integration
Cost Stakeholder Schedule
Schedule Communication Cost
Stakeholders Quality Resources Quality
Resources Integration Communication
Communication Procurement Risk
Risk Risk Procurement
Procurement Stakeholder
Integration Integration
Stakeholder Resources
Project Office
A formal structure that supports project management within an
organization and usually takes one of three forms (or
combinations):
Providing the policies, methodologies and templates for managing
projects.
Providing support, guidance, tools and training on how to manage
projects.
Providing project managers for different projects and being
responsible for the results of the projects.
Main Role : Supportive, Controlling, Directive.
Relationship Between the Product and
the Project Life Cycles
Upgrade
Idea Product
Staff Staff
Project Oriented Organization
Project CEO
Coordination
PM PM PM
Staff Staff
Matrix Organization
This form is an attempt to maximize the strengths and
weaknesses of both the functional and project forms.
In a strong matrix, power rests with the project
manager.
In a weak matrix, power rests with the functional
manager.
In a balanced matrix, the power is shared between the
functional manager and the project manager.
Matrix Organization
Advantages Disadvantages
Visible objectives More than one boss
Efficient utilization of Complex structure to control
resources Differing priorities of PM
Better co-ordination and FM
Better information flow Duplication of effort
Retention of home after Conflict
project
Weak Matrix
CEO
Staff Staff
Project Coordination
Balanced Matrix
CEO
PM Staff Project
Coordination
Strong Matrix
CEO
Functional Functional Manager of
Manager Manager PMs
Staff Staff PM
Project
Coordination
Influences on Project Management
Functional Weak Balanced Strong Hybrid,
Matrix Matrix Matrix composite
Project Part - Time Part - Time Part - Time Full - Time Full - Time
Admin staff
Exercise
Question: You are managing the release of a new drug in the market. Your role
is that of a:
1. Functional Manager, because you have good functional knowledge of
the pharmaceutical industry
2. Project Manager, because you are creating a unique product within
specific time schedules
3. Operations Manager, because you have to do several repetitive tasks
4. Program Manager, because you have to manage several projects to
do your job effectively
Exercise
Question: Your company is responsible for developing an anti-virus software.
You are responsible for managing both the individual product releases and the
coordination of multiple releases. Your role is that of a:
1. Program manager
2. Project manager
3. Functional manager
4. Operations manager
Exercise
Question: You have reached the end of the design phase of your project. You
decide to call a "phase end review" for obtaining authorization to close the
design phase and initiate the next phase (i.e., execution phase) of your project.
Your manager disagrees with your suggestion. He wants a "kill point" to
formally end the design phase of the project. In this context, you should:
1. Disagree with your manager because you know that phase end reviews
should be used at the end of each phase of the project
2. Agree with your manager
3. Escalate this issue to the project sponsor
4. Take advice from a senior project manager about what should actually
be done at the end of each phase of the project
Exercise
Question: You are working in the Project Management Office
(PMO) of your organization. Your job responsibility is to:
1. Manage the operational activities in the company
2. Manage human resource and risk management issues for
individual projects
3. Provide support functions to project managers in the form of
training, providing software, standardizing policies, etc.
4. Provide subject matter expertise in the functional areas of
the project
Exercise
Question: You are the project manager in a company where you
have maximum authority. To which organizational structure does
your company belong?
1. Functional
2. Weak Matrix
3. Strong Matrix
4. Projectized
Changes in sixth Edition
Changes in sixth Edition
Project Scope Management
Dr. Eng. Ahmed Elshahat, Ph.D, PMP
Project Scope Process group
1. Plan Scope Management (New in fifth edition)
2. Collect Requirement
3. Define Scope
4. Create WBS ( Work Breakdown Structure)
5. Validate Scope ( New in fifth edition)
6. Control Scope.
Product / Project Scope
Product Scope: The features and functions that
characterize a product, service or result.
Process of developing a
detailed description of the
project and the product.
Project Scope
3. Define Scope:
The process of developing a detailed description of the project and
product.
During planning, the project scope is defined and described with
greater specificity as more information about the project is known.
Existing risks, assumptions, and constraints are analyzed for
completeness, additional risks, assumptions and constraints are added
as necessary.
Main output of define scope process is “ Project Scope statement”
Project scope statement : describes, in detail, the project’s
deliverables and the work required to create those deliverables.
3. Define Scope Process
Define Scope T&T
1. Expert Judgment
2. Product Analysis :
Product breakdown, System analysis, system
engineering, value engineering, value analysis and
functional analysis.
Value analysis and value engineering help to know
how to complete the project at a lower budget
without any change in the scope.
Define Scope T&T
3. Alternative identification :
Technique used to generate different approaches to
execute and perform the work of the project.
The most common approaches are : lateral thinking (
solving problem through an indirect & creative
approach using reasoning that is not immediately
obvious),
Brainstorming.
Define Scope Outputs
1. Project scope statement.
2. Project documents update:
Stakeholder register.
Requirement documentation
Requirement traceability matrix.
Project Scope
1. Plan Scope Management (New in fifth edition)
2. Collect Requirement
3. Define Scope
4. Create WBS ( Work Breakdown Structure)
5. Validate Scope ( New in fifth edition)
6. Control Scope.
4. Create WBS
4. Control Thresholds.
5. Reporting Formats
Project Time Management
1. Plan Schedule Management
2. Define Activities
3. Sequence Activities
4. Estimate Activity Durations
5. Develop Schedule
6. Control Schedule
2. Define Activities
contract.
Milestone has zero duration.
Project Time Management
1. Plan Schedule Management
2. Define Activities
3. Sequence Activities
4. Estimate Activity Durations
5. Develop Schedule
6. Control Schedule
3. Sequence Activities
6. Reserve Analysis:
Duration estimates may include contingency reserves, sometimes
referred to as time reserves or buffers, into the project schedule to
account for schedule uncertainty. Contingency reserves are the
estimated duration within the schedule baseline, which is allocated for
identified risks that are accepted and for which contingent or
mitigation responses are developed. Contingency reserves are
associated with the “known-unknowns,” which may be estimated to
account for this unknown amount of rework.
Estimate Activity Durations: Outputs
1. Activity Duration Estimates:
Activity duration estimates are quantitative assessments
of the likely number of time periods that are required to
complete an activity, For example:
2 weeks +/― 2 days, which indicates that the activity
will take at least eight days and not more than twelve
(assuming a five-day workweek).
15 % probability of exceeding three weeks, which
indicates a high probability—85 %—that the activity
will take three weeks or less.
2. Project document update.
Project Time Management
1. Plan Schedule Management
2. Define Activities
3. Sequence Activities
4. Estimate Activity Durations
5. Develop Schedule
6. Control Schedule
6. Develop Schedule
Forward
Pass
A B
Backward
Pass
Immediate
Activity Description Predecessor(s) Activity Time (Wks)
A – 12 A F K
B – 9
C A 10
D B 10 Start C G Finish
E B 24
F A 10
G C 35 B D H J
H D 40
I A 15
J E,G,H 4 E
K F,I,J 6
St. Adolf’s Hospital
Activity Paths
I
Paths are sequences of activities
between a project’s start and finish.
A F K
A-I-K 33
A-F-K 28
B D H J
A-C-G-J-K 67
B-D-H-J-K 69
B-E-J-K 43
E
St. Adolf’s Critical Path
The longest path is the critical path!
I
A-I-K 33
A-F-K 28 Start C G Finish
A-C-G-J-K 67
B-D-H-J-K 69
B-E-J-K 43 B D H J
Project Expected
Time is 69 wks. E
Earliest Start and Earliest Finish Times
12
I 27
A 12 K
0 12 F 22 63 69
12 10 6
12
C 22 22
G 57
Start Finish
10 35
0
B 9 9
D 19 19
H 59 59
J 63
9 10 40 4
9 E 33
24
Earliest Start and Earliest Finish Times
Path Time (wks)
12
I 27 The Critical Path takes
A-I-K33 15 69 weeks
A-F-K28
A-C-G-J-K 67
A K
B-D-H-J-K 69 0 12 12 F 22 63 69
B-E-J-K 43 12 10 6
12
C 22 22
G 57
Start Finish
10 35
0
B 9 9
D 19 19
H 59 59
J 63
Critical Path
9 10 40 4
9 E 33
24
Latest Start and Latest Finish Times
(You start with the last activity and work toward the first activity)
12
I 27
48 15 63
A K
0 12 12 F 22 Latest 63 69 Latest
2 12 14 53 10 63 start 63 6 69
finish
time time
C
12 22 22 G 57
Start Finish
14 10 24 24 59
35
0
B 9 9
D 19 19
H 59 59
J 63
0 9 9 9 10 19 19 40 59 59 4 63
9 E 33
35 24 59
0
B 9 9
D 19 19
H 59 59
J 63
Activity Slack 0 9 9 9 10 19 19 40 59 59 4 63
Analysis
9 E 33
35 24 59
Tools & Techniques
3. Critical Chain Method : CCM
The critical chain method (CCM) is a schedule method
that allows the project team to place buffers on any
project schedule path to account for limited resources
and project uncertainties.
The critical chain method uses activities with durations
that do not include safety margins, logical
relationships.
The resource-constrained critical path is known as the
critical chain.
CCM
Project buffer: One buffer, placed at the end of the
critical chain protects the target finish date from
slippage along the critical chain.
Feeding buffers: are placed at each point where a
chain of dependent activities that are not on the
critical chain feeds into the critical chain.
The size of each buffer should account for the
uncertainty in the duration of the chain of dependent
activities leading up to that buffer
CCM
Tools & Techniques
4. Resource Optimization Techniques:
A) Resource Leveling:
A technique in which start and finish dates are
adjusted based on resource constraints with the goal
of balancing demand for resources with the available
supply
Resource leveling can be used when shared or
critically required resources are only available at
certain times, or in limited quantities.
Resource Leveling
Tools & Techniques
4. Resource Optimization Techniques:
B) Resource Smoothing:
A technique that adjusts the activities of a schedule
model such that the requirements for resources on the
project do not exceed certain predefined resource
limits.
Differences between Leveling &
Smoothing
Leveling Smoothing
Mainly for availability of Mainly for resource usage
critical resources.
Allocation of critical skills Allocation of number of
among activities workers.
Qualitative Quantitative
Complicated technical Regular performed projects
projects
Tools & Techniques
5. Modeling Techniques:
A) What if scenario Analysis:
This is an analysis of the question, “What if the
situation represented by scenario ‘X’ happens?”
A schedule network analysis is performed using the
schedule to compute the different scenarios, such as
delaying a major component delivery, extending
specific engineering durations, or introducing external
factors, such as a strike or a change in the permitting
process.
Tools & Techniques
5. Modeling Techniques:
B) Simulation:
Simulation involves calculating multiple project
durations with different sets of activity assumptions,
usually using probability distributions constructed
from the three-point estimates.
Tools & Techniques
6. Leads & Lags:
7. Schedule Compression:
A) Crashing : A technique used to shorten the
schedule duration for the least incremental cost by
adding resources.
Examples of crashing include approving overtime,
bringing in additional resources, or paying to
expedite delivery to activities on the critical path
Crashing works only for activities on the critical path
Crashing Steps
Step 1 – Calculate the critical path and list all critical
activities and the float of other paths. Calculate
direct and indirect costs.
Step 2 – Exclude critical activities, which can not be
crashed due to technical reasons.
Step 3 – Rank the list of critical activities according
to its cost slope ( cost of crashing unit time)
Crashing Steps
Step 4 – Crash the activity with the least cost slope (
from the list in step 3) until the total float of any of
the parallel paths first consumed. Calculate direct and
indirect costs for this case.
Step 5 – Recalculate the critical path and apply step
1 to step 4 until all possible crashing is done.
Step 6 – Plot the different project durations and the
associated costs and determine the optimum crashed
project duration.
Crashing Quiz
Activity Dependency Normal Crash Normal Crash Cost
Duration Duration cost $ $
Days days
A ------ 6 4 6000 8000
B A 4 3 5000 5750
C ----- 8 7 8000 8500
D B&C 6 5 6000 8000
Which activity would you crash if your project budget was only $27000? What is
the new project duration?
Normal Time & Cost
Normal:
1 Duration = 16
1 6 7
0 days
A B Cost = 25,000$
du=6 du=4
1 1
6 7
0
Start
1 1
1 8
1 6
C D
Finish
du=8 6
1 1
3
0 6
First Run
Activity Dependency Normal Crash Normal Crash Cost Cost slope Rank
Duration Duration cost $ $
Days days
A ------ 6 4 6000 8000 1000/d 2
• (B) reduced 1
1 5 6 8 day at 750 $
• (A) reduced 1
A B day at
du=5 Du=3 1000$
1 6 7 8 • Crashed (1):
• Duration =
Start
1 14 days
1 8 9 • Cost =
4
C D 26750
Finish
du=8 6
1 1
3 9
0 4
Tools & Techniques
7. Schedule Compression:
B) Fast Tracking:
A schedule compression technique in which activities or
phases normally done in sequence are performed in
parallel for at least a portion of their duration.
An example is constructing the foundation for a building
before completing all of the architectural drawings.
Fast tracking may result in rework and increased risk.
Fast tracking only works if activities can be overlapped to
shorten the project duration.
Outputs
1. Schedule Baseline:
A schedule baseline is the approved version of a
schedule model that can be changed only through
formal change control procedures and is used as a
basis for comparison to actual results.
It is accepted and approved by the appropriate
stakeholders as the schedule baseline with baseline
start dates and baseline finish dates.
Outputs
2. Project Schedule:
The project schedule presentation may be presented in
summary form, sometimes referred to as the master
schedule or milestone schedule, or presented in detail.
Examples:
A) Bar Charts
B) Milestone Charts
C) Schedule network diagram.
Milestone chart
for high level presentation
Bar Chart
For Management Presentation
Detailed Schedule for Project Team
Outputs
3. Schedule Data:
Resource requirements by time period, often in the
form of a resource histogram;
Alternative schedules, such as best-case or worst-case,
not resource-leveled, or resource-leveled, with or
without imposed dates; and
Scheduling of contingency reserves.
outputs
4. Project Calendars:
A project calendar identifies working days and shifts
that are available for scheduled activities.
5. Project Management Plan Updates
6. Project Documents Updates
Project Time Management
1. Plan Schedule Management
2. Define Activities
3. Sequence Activities
4. Estimate Activity Durations
5. Develop Schedule
6. Control Schedule
7. Control Schedule
Control Schedule is the process of monitoring the
status of project activities to update project progress
and manage changes to the schedule baseline to
achieve the plan.
Schedule control is concerned with:
Determining the current status of the project
schedule.
Influencing the factors that create schedule changes.
Managing the actual changes as they occur.
Control Schedule ITTO
Control Schedule Inputs
Source Inputs
Develop PM Plan ( PM plan
Integration)
Develop Schedule Project Schedule
Direct and manage project Work performance data
execution ( Integration)
Develop schedule Project calendars
Develop schedule Schedule data
OPA OPA
Control Schedule outputs’ Targets
Output Target
1. Work performance information 1. Perform quality control (
Quality)
2. Report performance (
Communication)
2. Change requests 2. Perform integrated change
control ( Integration)
3. Schedule forecast 3. Monitor and control project
work ( Integration)
4. Project documents 4. Project documents update
5. OPA 5. OPA
Project cost Management
Dr. Eng. Ahmed Elshahat, Ph.D, PMP
Project Cost Management
Project Cost Management includes the processes
involved in planning, estimating, budgeting, financing,
funding, managing, and controlling costs so that the
project can be completed within the approved budget.
Project Cost Management should consider the
stakeholder requirements for managing costs.
Different stakeholders will measure project costs in
different ways and at different times
Project Cost Management
Project Cost Management is primarily concerned
with the cost of the resources needed to
complete project activities.
In many organizations, predicting and analyzing
the prospective financial performance of the
project’s product is performed outside of the
project.
Project Cost Management vs. process groups
Estimate costs
Determine Budget
Project Cost Management
3. Determine Budget
4. Control Costs
Plan Cost Management
6. Reserve analysis
7. Cost of Quality
3. Determine Budget
4. Control Costs
Determine Budget
Outputs Sources to
1. Cost baseline 1. Develop PM plan.
2. Project funding 2. Control costs
requirements
1. Cost Aggregation
Determine Budget T & T
2.Reserve Analysis.
Contingency reserves : are allowances for unplanned
but potentially required changes that can result from
realized risks identified in the risk register as ( “
Known unknown”) part of cost baseline.
Management reserves : are budget reserved for
unplanned changes to project scope and cost ( “
unknown - unknown”).
Determine Budget T & T
3. Expert Judgment
4. Historical relationships.
5. Funding limit reconciliation:
The expenditure of funds should be reconciled with any
funding limits on the commitment of funds for the project.
A variance between the funding limits and the planned
expenditures will sometimes necessitate the rescheduling
of work to level out the rate of expenditures.
This is accomplished by placing imposed date constraints
for work into the project schedule.
Determine Budget Outputs
Cost Performance Baseline:
Is an authorized time – phased budget used to
measure, monitor, and control overall cost
performance on the project. ( called S curve)
Funding
Cumulative Costs
Requirement
Cost
Baseline
Expenditure
Time
Variance
Project Budget Components
Determine budget - outputs
2. Project Funding Requirements:
The cost baseline will include projected expenditures
plus anticipated liabilities.
Funding often occurs in incremental amounts that are
not continuous, which appear as steps.
The total funds required are those included in the cost
baseline, plus management reserves.
Control Costs
EV
Formulas & Descriptions
200
BAC
150
100 AC =
90
90 PV = 75
75
50 EV = 50
J A S O N D J F
Financial Indicators Guiding
Performanc SV & SPI
e Measures
> 0 & > 1.0 = 0 & = 1.0 < 0 & < 1.0
>0 Ahead of Schedule On Schedule Behind
& >1 Under Budget Under Budget Schedule,
Under Budget
CV =0 Ahead of Schedule On Schedule Behind
& =1 On Budget On Budget Schedule
CPI On Budget
<0 Ahead of Schedule On Schedule Behind
& < Over Budget Over Budget Schedule
1 Over Budget
New Approach. ( Earned Schedule)
Project Selection financial basis
5. Payback Period.
Project Selection
1. Life cycle costing:
The direct & indirect costs + periodic or continuing
costs of operations and maintenance.
Direct costs : Raw material, manpower.
Indirect costs : Renting, management overhead.
Committee will recommend the lower life cycle cost
project.
Project Selection
2. Present Value:
Present value : Today’s value of future money.
Future Value : Future value of today’s money
Net present value (NPV) = (Present value of all cash inflows) –
( Present value of cash outflaws).
PV = Fv / (1+i)n
Where n : the number of years.
I : Interest rate.
Committee will recommend projects with high NPV.
Project Selection
3. Benefit / Cost Ratio (BCR):
Expected revenue / estimated cost.
Committee will recommend projects with high BCR.
4. IRR ( Internal rate of return)
The discount rate at which the project cost and
outcome are the same.
The discount rate : the interest rate.
Committee will recommend the project with high IRR.
Project Selection
5. Payback Period:
The number of time units it takes to
recover your investment in the project
before you start accumulating the profit.
Committee will recommend the shorter
payback period.
Quiz
In your project, if the benefit cost ratio is greater than 1, it means that
3. You should select this project from all other competing alternatives.
4. You should not select this project from all other competing alternatives.
Quiz
There are two projects:
Investment in project A is $ 1,000,000 and its NPV is $ 100,000
Investment in project B is $ 1,200,000, its net cash inflows are $ 2,000,000, and net cash
outflows are $ 1,900,000
Which project should be selected if net present value(NPV) criterion is used for selection?
1. Project A
2. Project B
following statements related to benefit cost ratio (BCR) are correct EXCEPT:
3. If two projects have positive BCR, select the project with higher BCR
“ Quality is fitness
for use”
The Quality Trilogy:
• 1. Quality
improvement.
• 2. Quality planning.
• 3. Quality control.
Quality and Grade
Quality is “the degree to which a set of inherent
characteristics fulfill requirements”.
Grade is a category assigned to products or services
having the same functional use but different technical
characteristics.
Low quality is always a problem; low grade may not
be.
Precision and Accuracy الدقة و المقاربة
You are involved in manufacturing ball bearings using lathe machines. The
ball
bearings should have a diameter of 5.0 cms - allowable control limits are
4.95 cms to
5.05 cms. Measurements made after the end of the process for the bearings
produced
are: 4.96, 4.98, 5.01, 5.03, 5.02, 5.01,5.03,5.04, 5.02, 4.96, 4.98, 5.00.
What is your conclusion about the process?
Process is out of control and needs to be investigated
Process is in control and adjustments are not required
The tool needs to be changed or re-calibrated
Process should be further measured using a run chart
Control Charts
Group Exercise
From the last slide, determine the following:
1. Upper Control Limit
2. Lower Control Limit
3. Upper specification Limit
4. Lower specification limit
5. Assignable cause / special cause.
6. The process is out of control
7. Rule of seven
8. Normal distribution curve.
Flowcharting
Flowcharting helps to analyze how problems occur.
A flowchart is a graphical representation of a process.
Process flowcharts show activities, decision points, and the
order of processing. Flowcharts show how various elements of
a system interrelate.
Flowcharting can help the project team anticipate what and
where quality problems might occur and, thus, can help develop
approaches for dealing with them.
Pareto Chart
A Pareto chart is a specific type of histogram, ordered
by frequency of occurrence, which shows how many
defects were generated by type or category of
identified cause.
• The Pareto technique is used primarily to identify
and evaluate nonconformities and guide corrective
action.
Pareto’s Law – A relatively small number of causes
will typically produce a large majority of the
problems or defects (80/20 rule)
Plan Quality Management: Outputs
1 Quality Management Plan:
The quality management plan is a component of the
project management plan that describes how the
organization’s quality policies will be implemented.
It describes how the project management team plans
to meet the quality requirements set for the project.
Plan Quality Management: Outputs
2 Process Improvement Plan
The process improvement plan details the steps for analyzing project
management and product development processes to identify activities
that enhance their value. Areas to consider include:
Process boundaries. Describe the purpose of the process, the start and
end of the process, its inputs and outputs, the process owner, and the
stakeholders of the process.
Process configuration. Provides a graphic depiction of processes, with
interfaces identified, used to facilitate analysis.
Process metrics. Along with control limits, allows analysis of process
efficiency.
Targets for improved performance. Guide the process improvement
activities.
Plan Quality Management: Outputs
3 Quality Metrics:
A quality metric specifically describes a project or product
attribute and how the control quality process will measure
it.
A measurement is an actual value. The tolerance defines
the allowable variations to the metric.
For example, if the quality objective is to stay within the
approved budget by ― 10%, the specific quality metric
is used to measure the cost of every deliverable and
determine the percent variance from the approved budget
for that deliverable.
Plan Quality Management: Outputs
4 Quality Checklists:
A checklist is a structured tool, usually component-
specific, used to verify that a set of required steps has
been performed. Based on the project’s requirements and
practices, checklists may be simple or complex.
Many organizations have standardized checklists
available to ensure consistency in frequently performed
tasks.
Quality checklists should incorporate the acceptance
criteria included in the scope baseline.
5 Project Documents Updates
2 Perform Quality Assurance
Perform Quality Assurance is the process of auditing
the quality requirements and the results from quality
control measurements to ensure that appropriate
quality standards and operational definitions are
used.
In project management, the prevention and inspection
aspects of quality assurance should have a
demonstrable influence on the project. Quality
assurance work will fall under the conformance work
category in the cost of quality framework.
2 Manage Quality
Source / Inputs
Source Inputs
Plan quality .1 Quality management plan
3 Process analysis
QM Tools
Quality Audits
2 Quality Audits
A quality audit is a structured, independent process to determine if project
activities comply with organizational and project policies, processes, and
procedures. The objectives of a quality audit may include:
Identify all good and best practices being implemented;
Identify all nonconformity, gaps, and shortcomings;
Share good practices introduced or implemented in similar projects in the
organization and/or industry;
Proactively offer assistance in a positive manner to improve implementation of
processes to help the team raise productivity; and
Highlight contributions of each audit in the lessons learned repository of the
organization.
3 Process Analysis
3 Process Analysis
Process analysis follows the steps outlined in the process
improvement plan to identify needed improvements.
This analysis also examines problems experienced,
constraints experienced, and non-value-added activities
identified during process operation. Process analysis
includes root cause analysis—a specific technique used to
identify a problem, discover the underlying causes that
lead to it, and develop preventive actions.
Control Quality
Control Quality is the process of monitoring and
recording results of executing the quality activities to
assess performance and recommend necessary
changes. The key benefits of this process include:
(1) Identifying the causes of poor process or product
quality and recommending and/or taking action to
eliminate them;
(2) Validating that project deliverables and work
meet the requirements specified by key stakeholders
necessary for final acceptance.
Control Quality
Source / Inputs
Source Inputs
1. Plan Quality .1 Project management plan
2. Plan Quality .2 Quality metrics
3. Plan Quality .3 Quality checklists
4. Direct and manage project execution ( .4 Work performance data
Integration) .5 Approved change
5. Perform integrated change control ( requests
Integration) .6 Deliverables
6. Direct and manage project execution ( .7 Project documents
Integration) .8 Organizational process
assets
Outputs / Targets
Outputs Targets
.1 Quality control measurements 1. Perform quality assurance
Control Chart
Ishikawa Diagrams
Pareto Diagrams
Inspection
Quiz
Question 2Relevance: PMP Exam only
You are managing the tools/spare parts section for an aircraft manufacturing company. Your
team members have discovered some defective tools/spare parts. The probable cause for
these could be materials used, defective measurement systems, inaccurate tolerances in the
machines, or other factors. To determine what caused the defect, you will:
Create a flowchart
Flowchart
Quality Checklist
Pareto Chart
Histogram
Quiz
Question 5Relevance: PMP Exam / CAPM Exam
The project team has added some functionalities to the product that are not required as part
of the project. However, the customer is satisfied with the product. From a quality perspective,
the action of the team is:
Not acceptable, because it constitutes gold plating, which is not a good practice.
Conflict Resolution
Maslow’s Hierarchy of Needs
According to Maslow’s theory:
Once a level of need is satisfied, it is no longer a
motivational factor
One cannot ascend to the next level until the levels
below are fulfilled
People do not perform for security or money, but
rather to get a chance to contribute (self-
actualization)
McGregor’s Theory
Theory X
Traditional view of management; top-down
Theory Y
responsibility
Managers: Create environment that aids workers in
achieving goals
Herzberg’s Theory
Motivating Agents: Motivators are mostly
intrinsic to the job and serve as motivators
De-motivators (Hygiene Factors) Are mostly
self-actualization
Workers have a sense of personal growth and
responsibility
Power versus Influence
Power
Is the ability to make what you want even
if your subordinate do not want to do it.
Influence
Penalty (Coercive)
Noise
Message
Sender Encoding Decoding Receiver
Medium
Feedback
What is Effective Communication
Receiver
Sender
Medium
Decoding
Encoding
Are events that take your mind away from communication and
make you less understanding of other people’s problems.
Internal Noise
External Noise.
T&T
1 Communication Requirements Analysis:
The analysis of the communication requirements
determines the information needs of the project
stakeholders.
The total number of potential communication channels
is n(n – 1)/2, where n represents the number of
stakeholders.
For example, a project with 10 stakeholders has
10(10 – 1)/2 = 45 potentiel communication
channels.
T&T
2 Communication Technology:
Factors that can affect the choice of communication
technology include:
Urgency of the need for information.
Availability of technology.
Ease of Use.
Project environment.
Sensitivity and confidentiality of the information.
T&T
Communication Model
T&T
4 Communication Methods:
Interactive communication. Between two or more parties performing a
multidirectional exchange of information. It is the most efficient way to ensure
a common understanding by all participants on specified topics, and includes
meetings, phone calls, instant messaging, video conferencing, etc.
Push communication. Sent to specific recipients who need to receive the
information. This ensures that the information is distributed but does not ensure
that it actually reached or was understood by the intended audience. Push
communications include letters, memos, reports, emails, faxes, voice mails,
blogs, press releases, etc.
Pull communication. Used for very large volumes of information, or for very
large audiences, and requires the recipients to access the communication
content at their own discretion. These methods include intranet sites, e-learning,
lessons learned databases, knowledge repositories, etc.
T&T
5 Meetings:
The Plan Communications Management process requires
discussion and dialogue with the project team to
determine the most appropriate way to update and
communicate project information, and to respond to
requests from various stakeholders for that information.
These discussions and dialogue are commonly facilitated
through meetings, which may be conducted face to face
or online and in different locations, such as the project site
or the customer’s site.
2. Manage Communication
Types
Known known = Total certainty
• Interviewing.
Outputs
Opportunities
Strategy for Both Threats and
Opportunities
Contingent Response Strategy
Strategies for Negative Risks or Threats
3 Control Procurements
Procurement vs. Process Group
Contract-type
Fixed-price or lump-sum contracts.
Cost-reimbursable contracts.
Make-or-Buy Analysis is
a general management
technique that can be used to determine
whether a particular product or service can
be produced by the project team or can be
purchased.
The analysis includes both indirect as well
as direct costs.
Make-or-Buy Analysis
Cost versus Benefit
PROJECT PROCUREMENT
MANAGEMENT
1 Plan Procurement Management
2 Conduct Procurements
3 Control Procurements
Conduct Procurement
3 Control Procurements
3. Control Procurement
4 Performance Reporting:
Work performance data and reports
supplied by sellers are evaluated against
the agreement requirements.
Work performance information from this
evaluation is then reported as appropriate.
T&T
6 Claims Administration:
Contested changes and potential constructive changes are those
requested changes where the buyer and seller cannot reach an
agreement on compensation for the change or cannot agree that a
change has occurred.
These contested changes are variously called claims, disputes, or
appeals.
Claims are documented, processed, monitored, and managed
throughout the contract life cycle, usually in accordance with the terms
of the contract. If the parties themselves do not resolve a claim.
it may have to be handled in accordance with alternative dispute
resolution (ADR) typically following procedures established in the
contract. Settlement of all claims and disputes through negotiation is
the preferred method.
T&T
7 Records Management System:
A records management system is used by the project
manager to manage contract and procurement
documentation and records.
It consists of a specific set of processes, related
control functions, and automation tools that are
consolidated and combined as part of the project
management information system
Project Manager Role In Procurement
Know the procurement process
Understand contract terms and conditions
Make sure the contract contains all the project management requirements Such
as attendance at meetings. Reports, actions and communications deemed
necessary
Identify risks and incorporate mitigation and allocation of risks into the contact
Help tailor the contract to the unique of the project
Fit the schedule for completion of the Procurement process into the schedule
for the project
Be involved during contract negotiation to protect the relationship with the
seller
Protect the integrity of the project and the ability to get the work done
Work with the contract manager to manage changes to the contract
Quiz
D. Purchase order
Quiz
A new project manager is about to begin creating the procurement
statement of work. One stakeholder wants to add many items to the
procurement statement of work. Another stakeholder only wants to
describe the functional requirements. The project is important for the
project manager's company, but a seller will do the work. How would you
advise the project manager?
A. The procurement statement of work should be general to allow the
seller to make their own decisions.
B. The procurement statement of work should be general to allow for
clarification later.
C. The procurement statement of work should be detailed to allow for
clarification later.
D., The procurement statement of work should be as detailed as
necessary for the type of project.
Quiz
What type of contract do you NOT want to use if you
do not have enough labor to audit invoices?
A. Cost plus fixed fee (CPFF)
Project
Stakeholders : Any Team
individual or
organization may
positively or Users Project Environment
negatively impact
by the project.
Contractors
Identify Stakeholders ITTO
T & T stakeholder analysis
Outputs
Stakeholder Register:
This contains all details related to the identified
stakeholders including, but not limited to:
Identification information. Name, organizational position,
location, role in the project, contact information;
Assessment information. Major requirements, main
expectations, potential influence in the project, phase in
the life cycle with the most interest; and
Stakeholder classification. Internal/external,
supporter/neutral/resistor, etc.
Project Stakeholder mgmt processes
2. Plan Stakeholder Management
Resolving conflict,
and
Modify organizational behavior to accept the project
outcomes.
4. Control Stakeholder Engagement