Professional Documents
Culture Documents
Formwork Design Guidelines PDF
Formwork Design Guidelines PDF
LOADS
Formwork for concrete must support all vertical and lateral loads that may be applied
until such time as these loads can be carried by the concrete structure itself.
VERTICAL LOADS
The effect of high frequency vibration on freshly placed concrete within formwork is
to keep it in a fluid state so that it behaves almost as a liquid. However, full hydrostatic
pressure may or may not be developed depending on whether stiffening of arching of
concrete occurs before the lift is finished.
For pressure calculation of concrete the following factors are taken into consideration:
For structures concrete placed at controlled rates ACI committee 347 has developed
the formulae below for the maximum lateral pressure on the form for prescribed conditions
of temperature, rate of placement, vibration, weight-of concrete and slump. They are all
empirical formulae based on experiments and should not be considered theoretically precise.
Then,
3. For walls, rate of placement ranging from 2.0 m/h to 3.0 m/h
HORIZONTAL LOADS
Bracings and props should be designed for all foreseeable horizontal loads due to
wind, inclined supports, dumping of concrete and equipment. However, in no case this
horizontal load acting in any direction at each floor line should be less than 150 kg per linear
meter of floor edge or 2 % of total dead load on the form distributed as a uniform load per
linear meter of slab edge, whichever is greater. Wall forms should be designed to meet wind
load requirements of the local building code. Bracing for wall forms should be designed for a
horizontal load of at least 150 kg per linear meter of wall, applied at top.
If special methods of placing concrete using equipment like pumps are adopted the
formwork including staging should be designed for additional loads. In the case of pumping,
if the transport pipes are anchored on to the staging, the bends in the pipes will transmit very
high lateral and vertical loads to the staging.
It is also necessary to take into account the effects of starting and stopping of heavy
equipment on the deck. They can be estimated using the expression
F = Wa/g
When large concreting buckets are used, it may be necessary to unload the concrete
in one place for distribution. This can cause impact due to dropping, uplift and unbalanced
loading on the formwork and staging.
In the case of special structures like shells and domes there are additional factors to
be considered. Due regard should be given to unsymmetrical of eccentric loading which may
occur in the formwork during placement. Stress occurring during erection and decent ring of
the false work should also be considered. Since a three dimensional analysis of these
complex shapes is required, a competent an experienced engineer should do the structural
analysis. It is also essential to consider the necessity on back forms and the load flow from
concrete pressures on inclined form surfaces.
DESIGN CRITERIA
Although there is a need for greater accuracy than is frequently used in formwork
design, excessive refinement wastes time. Absolute precision is unwarranted when so many
assumptions have to be made as to loads, lateral pressures, and quality of materials,
workmanship at site and other factors.
• Beam supported over three or more spans are regarded as continuous and
approximate formulae are used.
In the absence of job specification to the contrary acceptable and frequently used
values of permissible deflections are:
• for members spanning more than 1.5m is 6.0 mm or span/360, whichever is less
DESIGN METHOD
load have an insignificant effect on the lateral pressure. Therefore the maximum lateral
pressure is generally below the fluid head and it is controlled by this change of stricture
(which can take from a few minutes to a few hours).
The following factors affect the change of state (and hence the maximum formwork
pressure):
Concrete
Admixtures
Cementations materials
Mix proportions
Temperature at placing
Weight density
Workability
Formwork
Permeability/water tightness
Vibration
The complex inter-relationships of these factors are not described in this Report. A
rationalized design equation is presented, together with a description of how the variables
should be treated under design conditions.
Using concepts developed at the Cement and Concrete Association and during recent
research on the mechanisms creating formwork pressures. The data for OPC concrete were
analyzed to quantify the relationships between maximum pressure, vertical from height, rate
of rise and concrete temperature at placing. Modifications to these basic relationships were
then developed for concrete containing admixtures. This analysis led to the following
expression for the maximum concrete pressure on formwork:
Where
C1 - coefficient dependent on the size and shape of from work (see Table I for
values). √ (mh)
C2 - coefficient dependent on the constituent materials of the converts (see Table I for
values). √m
D - Weight density of concrete kN/m3
H - Vertical form height in m.
h - Vertical pour height in m.
K - Temperature coefficient taken as (36/ (T+16)) 2
R - The rate a: which the concrete raises vertically up the form. m/h
T - concrete temperature at placing. ˚C
When C1 √R > H, the fluid pressure (Dh) should be taken as the design pressure.
The term C1 √ R incorporates the effects of vibration and workability, because these
factors are largely dependant on size, shape and rate of rise. All the effects of the height of
discharge, cement type, admixtures, and concrete temperature at placing are incorporated in
the term:
C2 K√ (H-C1 √R)
The design chart. Table 2. quantifies these equations for normal UK conditions
where the concrete placing temperature is between 5 and 15º C. Pressure values shown in
bold on the chart are for placing conditions broadly covered by pressure measurements on
site, where the highest recorded pressures were 90 kN/m2 for walls and 166 kN/m2 for
columns. Values not in bold are outside recorded experience. They are in accord with the
general trend, but may be somewhat conservative.
No change is proposed in the design pressure envelope from that given in the CIRJA
Report I design method. The envelope (Figure 1) comprises fluid pressure to the depth where
the maximum pressure obtained from the design equation or chart occurs and then remains at
this value.
Concrete Value of C2
Coefficient C2 (see Table 1) takes into account the effects of different cementitious
materials and admixtures. The term ‘admixture’ in Table I covers the range of products
commercially available in 1985: Within the grouping ‘retarder’ fall readers, retarding water-
reducers and retarding superplasticisers, also any admixture which is used above the
recommended dosage such that it effectively acts as a retarder.
Aggregates
While quantifying the design equation, the effects of the aggregate shape and grading
could not be isolated from the other mix parameters, so these factors are not included in the
design method. With the exception of no-fines concrete the formula apply to all graded
natural aggregates.
The design equations apply to concrete mixes containing maximum aggregate sizes
up to 40 mm. Pressures with larger maximum sized aggregates are likely to be controlled by
the impact on discharge and the heavy vibration required..
MIX PROPORTIONS
The formula and design tables apply to the whole range of normal mix proportions.
No-Fines Concrete
Because no - fines concrete has a particle structure from the moment of placing. It
results in a low formwork pressure. Typical design values are of the order of 2 to 2.5 kN/m2
so that handling stresses are likely to control the design of the form.
Workability
Slump is not included as a variable in the design chart for the following reasons:
1. The problems with placing low workability concrete around reinforcement lead to
prolonged vibration and formwork pressures similar to those obtained with more
workable concretes.
2. The site data show no consistent difference in formwork pressure between low,
medium and high slump concretes.
3. Slump is not a good measure of the factors which affect formwork pressure.
K = (36/ (T + 16)) 2
Although this only strictly applies to OPC and RHPC concretes, it is sufficiently
accurate for all types of concrete when used in conjunction with coefficient C2. The K factor
represents a ratio of stiffening effects, which are dependent on temperature at placing. Data
for concrete temperatures at placing in excess of 30ْ C or below 5ْ C are rare, and it is prudent
not to extrapolate the design equation beyond these values.
1. It limits the potential maximum pressure which can develop (in general, the
maximum design pressure is not greater than Dh ).
Both these factors affect the maximum formwork pressure, and they have been
incorporated in the design equation as a function of the form height.
Sometimes, the form can be substantially higher than the height of section cast (see
Figure 3). In these cases, the limiting pressure might be the fluid pressure (which is obtained
from the weight density times the actual pour height). This should be checked with a separate
calculation.
In a section of small plan area, vibration can be sufficient to mobilize all the concrete
in a layer and to transmit a relatively high amount of energy to the form. This has the effect
of increasing the depth over which vibration is effective, and consequently the pressure on
the form.
In a larger section, all the concrete in a layer is not mobilized at the same time, and
less energy is transmitted into the formwork. The point of concrete discharge and vibration is
normally moved along the section, which allows the concrete a period of rest before the next
layer is placed. The net effect is that in ‘walls’ the maximum pressures are lower than in
‘columns’. In fundamental terms, a wall is where the concrete placed in layers with the point
of discharge and vibration moving along the wall, while, for columns, the point of discharge
and vibration is raised vertically. These conditions can be conservatively defined using the
following simple definitions:
Column - section where both the width and breadth are 2 m or less.
The few size data recorded for small, single- storey columns indicated a fluid
pressure distribution. The formula generally predicts fluid head for small columns. This is
reasonable, because small columns can be placed very quickly and vibrated such that the full
fluid head is mobilized. However, an analysis of the forces on column camps indicates that
they would fail if concrete in columns develops full fluid pressure. It is therefore widespread
practice to design small ply and timber column forms assuming less than the fluid head. The
possible explanation of this anomaly has not been experimentally verified.
Formwork Permeability
Study of the data suggests that the use of stiffer forms results in high pressures.
Conversely, independent research work shows that the formwork pressure decreases
substantially if a stiff form is moved slightly outwards. In most practical situations, the
stiltness of a form varies from point to point, and it is difficult to quantify. Formwork
stiffness was not, therefore, included in the design equation.
While the concrete is acting as a fluid, the formwork roughness is immaterial, until a
particle structure forms and the concrete starts to develop internal friction. Compared with
other factors, its influence on the maximum pressure is small, and it has not been isolated in
the design equation.
The pressure on sloping forms was not specifically examined in the research, and
only a few experimental results were available. However, the CIRIA method described in
this Report can be used conservatively with non-parallel sided walls with and without a
uniform rate of rise. If the volume supply rate is varied so that the rate of vertical rise is
constant, the equation of tables can be directly used. The pressure at any level in the pour is
the same on both faces, and the direction of action is perpendicular to the form (see Figure
4).
Figure 4 Pressure envelopes on the Formwork of a wall with sloping face where the fluid head is fully
developed
The following method is suggested for calculating the pressure envelope with a
constant volume supply rate:
1. Split the pour into horizontal levels with the vertical distance between each level 1m or
less.
4. Calculate the pressure at each level using the full height of the form H either from the
equation or tables.
5. Produce the design pressure envelope acting at right angles to the form.
Placing Method
The design equations do not apply to conditions where the concrete is being pumped
from below of where pre-placed large aggregate is grouted from below. In both these cased,
the formwork pressures are likely to be higher than these given in the Report.
Rate of Rise
The rate at which the concrete rises vertically up the formwork is an important factor,
and it is included in the design equation. In practice, this is never constant, but, the use of an
average rate of rise is normally adequate for vertical formwork. The average rate of rose
might not be applicable when a considerable lift is placed rapidly, followed by a long delay
before the subsequent lift.
As the rate of rise increased, the maximum pressure increased, but the relationship is
not linear. At high rates of rise, changes in the rate of rise have less effect on the maximum
pressure than changes at lower rates of rise (see Figure 5).
General
The formwork shall be designed and constructed so as to remain sufficiently rigid during
placing and compaction of concrete and shall be such as to prevent loss of slurry from the
concrete. The tolerances on the shapes, lines and dimensions shown in the drawing shall be
within the limits given below:
1. Deviation from specified dimension of
Cross-section of columns and beams - + 12 mm / - 6 mm
2. Deviation from dimension of footings
1. Dimension in plan - + 50 mm / - 12 mm
2. Eccentricity - 0.02 times the width of the footing
in the direction of deviation but
not more than 50 mm.
3. Thickness - +/- 0.05 times the specified
thickness
These tolerances apply to concrete dimensions only and not to positioning of vertical
reinforcing steel or dowels.
Stripping time
Forms shall not be released until the concrete has achieved strength of at least twice the
stress to which the concrete may be subjected at the time of removal of formwork. The
strength referred to shall be that of concrete using the same cement and aggregates and
admixtures, if any, with the same proportions and cured under conditions of temperature and
moisture similar to those existing on the work.
While the above criteria of strength shall be the guiding factor for removal of formwork,
in normal circumstances where ambient temperature does not fall below 15oC and where
ordinary Portland cement is used and adequate curing is done, following striking period may
deem to satisfy the guideline given below.
For other cements and lower temperatures, the stripping time recommended above
may be suitably modified.
The number of props left under, their sizes and disposition shall as to be able to safely
carry the full dead load of the slab, beam or arch as the case may be together with any live
load likely to occur during curing or further construction.
Where the shape of the element is such that the formwork has re-entrant angles, the
formwork shall be removed as soon as possible after the concrete has set, to avoid shrinkage
cracking occurring due to the restraint imposed.
Deflection consideration
Allowable deflection = L/360 or 6 mm whichever is less,
Maximum deflection is given by
d = (5/384) x W x L^4 / (E I) = (5/384) x 2.85 x L^4 / 145
By equating the maximum deflection to the allowable deflection,
L = ((384 / 5) x 1.45 / (2.85 x 360)) ^ 0.333 = 2210 mm
Minimum of the above values is 2210 mm
Therefore max. Span of secondary H 16 is 2210 mm
Say 2000 mm
Primary member
H 16 Beam is used as a primary member
Simply supported end condition is assumed
Spacing of primary member = 2000 mm
Width of lading = 2000 mm
W = loading intensity = 2.0 x 5.7 = 11.4 kN / m
Bending moment consideration
Allowable moment = 3 kN m
Maximum moment is given by,
M = w x L^2/8 = 11.4 x L ^2/8
By equating the allowable moment to the maximum moment, Effective span is
L = (3.0 x 8 / 11.4) ^0.5 = 1450 mm
Shear Force consideration
Allowable shear = 6 kN
Maximum shear is given by the equation,
Q = W^L/2 = 11.4 x L/2
By equating the allowable shear to the maximum shear,
Effective span, L = 2.6 / 11.4 =1050 mm
Deflection Consideration
Allowable deflection = L / 360 or 6 mm whichever is less,
Maximum deflection is given by the equation
d = (5/384) x w x L^4 / (E I) = (5 /384) x 11.4 x L ^ 4 / 145
Fx
Fx
Fy
Secondary Beam
Simply supported end condition is assumed
Spacing = 54 cm
Width of loading = 54 cm
W = loading intensity = 0.54 x 5.7 = 3.08 kN / m
Bending moment Consideration
Allowable bending moment = 1.167 kN m
Maximum moment of the member is given by,
M = w x L2/8 = 3.08 x L 2/8
By equating the maximum moment to the allowable moment, effective span is given by
L = (1.167 x 8 / 3.08) ^ 0.5 = 1740 mm
Shear Force consideration
Allowable shear force = 6 kN
The maximum shear force is given by,
Q = W x L/2 = 3.08 x L/2
By equating the maximum shear force to the allowable shear force, effective span is given by
L = 2.6 / 3.08 = 3900 mm
Deflection condition
Allowable deflection = L / 360 or 6 mm whichever is less
The maximum deflection is given by,
d = (5/384) x W x L^4 / (E I) = (5/384) x 3.08 x L^4 / 64.17
By equating the maximum deflection to the limiting deflection,
L = (((384 / 5) x 64.17 / (3.08 x 360)) ^ 0.333 = 1640 mm
Minimum of the above values is = 1640 mm
Therefore max. span of secondary member is = 1640 mm
Say 1600 mm
Primary Beam
Simply supported end condition is assumed
Spacing = 1600 mm
Width of lading = 1600 mm
W = loading intensity = 1.6 x 5.7 = 9.12 kN / m
EARLY STRIPPING
Any floor is designed for Dead Loads + Live Loads
Dead load includes,
¾ Self weight of floor
¾ Floor finishes
¾ Partitions
¾ False ceiling etc
The percentage of self weight alone when compared to the total design load could vary
from 30 % to 60 %. After concreting of the floor the loads are only the sum of self weight
and nominal live load. This could be between 40 % and 70 % of the design load. This
reduction in load is more advantageous for early stripping. This is more helpful when the
percentage is less. Hence when the concrete attains the above percentage of its 28 day
strength it is possible to remove the form work fully. Normally concrete attains 40 % strength
in 3 days and 70 % strength in 8 days.
It is also possible to remove the formwork after leaving props known as “Reshores”
to reduce the span of the beam and slab even when the concrete has not attained sufficient
strength for getting fully deshuttered. This will help it getting more number of uses from the
available form work. In case the floor above is to be supported when concreted, then
additional supporting props or scaffolds will have to be provided in the slab below to
withstand the additional load due to weight and construction live loads from floor above.
19 MM THIICK PLYWOOD
TABLE. F3. ALLOWABLE SPAN OF H-BEAMS (PRIMAYR) BELOW RC. SLAB (FOR INTERMEDIATE ROWS)
TABLE. F4. ALLOWABLE SPAN OF H-BEAMS (PRIMARY) BELOW RC. SLAB (FOR END ROWS)
TABLE. F6. ALLOWABLE SPAN OF H-16 BEAM @ BEAM BOTTOM (FORINTERMEDIATE BEAMS)
TABLE. F7. ALLOWABLE SPAN OF H-16 BEAM @ BEAM BOTTOM (FOR END BEAMS)
TABLE. F8. ALLOWABLE SPAN OF H-20 BEAM @ BEAM BOTTOM (FOR INTERMEDIATE BEAMS)
TABLE. F9. ALLOWABLE SPAN OF H-20 BEAM @ BEAM BOTTOM (FOR END BEAMS)
TABLE. F11. SUGGESTED ARRANGEMENTS OF BEAM FORMING SUPPORT AND TRANSVERSE H-20W BEAMS
FCCE
41
LARSEN & TOUBRO LIMITED FCCE
SLAB THICK (mm) 100 120 150 180 200 230 250 280 300
Total Load (kN/m2) 4.4 4.9 5.7 6.5 7.0 7.8 8.3 9.1 9.7
Max. eff. Span of 500 480 460 440 430 410 400 390 380
12 mm plywood (mm)
Max. eff. Span of 680 660 630 600 590 560 550 540 530
19mm plywood (mm)
SLAB THICK (mm) 350 400 450 500 550 600 800 1000 1200
Total Load (kN/m2) 11.2 12.8 14.3 16 17.5 19 25.3 31.5 37.7
Max. eff. Span of 370 350 330 320 300 290 250 230 210
12 mm plywood (mm)
Max. eff. Span of 490 460 440 410 390 380 330 290 270
19mm plywood (mm)
FLOOR PROP
B
C
A
A
B
C
53
LARSEN & TOUBRO LIMITED FCCE