EPFL Computing
EPFL Computing
Agenda
Current situation
• EPFL has currently 2 Datacenters:
• 1 MW in building INJ
• 500 kW in building MA
1 MW Datacenter en INJ
Electrical panel
(mai 2012)
in MA (1982)
Solution accepted
• Replacement of MA room with a new Datacenter integrated in the project of
renovation of the Heating Center
• Reduced CAPEX, because a number of facilities generally expensive are already here because of the
proximity of the Heating Center (water, power, with redondancy)
• Projected PUE < 1.10 completed with the possibility to reuse of 80% of the electrical energy consumed
by the Datacenter to heat the EPFL campus (only 3 months of summer without reinjection)
2016 2020
Datacenter@CCT Project From 2016 to 2020 September 29th 2016 5
Datacenter@CCT
Module 3
Anti fire room
Aisles
unloading dock
and lift platform
Flexibility of evolution
High structural and technical modularity in:
• Surfaces
• Power
• Power density (power per rack)
• Tiering
Modular design enabling deployment of a new tranche of 0.5 to 1 MW possible in less than 3 months, we invest
only when it is necessary (CAPEX very close to OPEX):
«Datacenter on demand»
Phase 3
4 000
Phase 1 Phase 2
Critical
Puissance (KW)
3 000
period
2 000
1 000
2030
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
Total KW avec Datacenter@CCT Total consommation