PROJECT TITLE :
LOCATION :
PROCURING ENTITY :
A GENERAL REQUIREMENTS
1.0 Mobilization/Demobilization 1 lot ₱50,000.00
2.0 Safety and Security 1 lot ₱150,000.00
3.0 Temporary Facilities 1 lot ₱20,000.00
4.0 Government Permits 1 lot ₱30,000.00
5.0 Bonds and Insurances 1 lot ₱150,000.00
6.0 Others (Material Testings) 1 lot ₱50,000.00
B BUILDING STRUCTURE
1.0 Structural Works
1.1 Site Preparation,Lay-out & Staking 1 lot ₱50,000.00
1.2 Earthwork excavation 220 cum ₱2,500.00
1.3 Gravel Bedding 100 cum ₱2,500.00
1.4 Rebarworks
1.4.1 Footings 1670 kgs ₱310.00
tie wires 25 kgs ₱60.00
1.4.2 Columns 950 kgs ₱310.00
tie wires 100 kgs ₱60.00
1.4.3 Beams 1265 kgs ₱310.00
tie wires 235 kgs ₱60.00
1.4.4 Slab on Fill 355 kgs ₱310.00
1.4.5 Elevated Floor Slab 285 kgs ₱310.00
1.5 Formworks 225 sqm ₱927.00
1.6 Concrete Works
1.6.1 Footings 10.29 cum ₱1,840.00
1.6.2 Columns 21.528 cum ₱1,840.00
1.6.3 Beams 105 cum ₱1,840.00
1.6.4 Slab on Fill 160 cum ₱1,840.00
1.6.5 Elevated Floor Slab 15 cum ₱1,840.00
1.7 Backfill & Compaction 255 cum ₱450.00
9.0 Waterlines
9.1 Pipes
9.1.1 PVC Pipe, 20mm dia 25 pcs ₱120.00
9.1.2 PVC pipe, 15mm dia 25 pcs ₱115.00
9.2 PVC Pipe Fittings and Accessories 25 lot ₱35.00
9.3 Plumbing Fixtures and Accessories
9.3.1 Hose Bib Faucet 10 pc ₱250.00
9.3.2 Lavatory 6 pc ₱5,000.00
9.3.3 Water Closet 6 pc ₱15,000.00
9.3.4 Soap & Tissue Holder 7 sets ₱750.00
9.3.5 Shower Head & Valve 6 pc ₱1,350.00
9.3.6 Gate Valves 20 pc ₱100.00
9.3.8 Kitchen Sink 1 pc ₱2,500.00
9.4 Fittings and Accessories 1 lot ₱10,000.00
GRAND TOTAL
5% Contractor's Profit
5% OCM
5% TAX
total construction cost
ABC
VARIANCE
TOTAL COST% 1.15
TRIMDOWN 22.07%
DETAILED COST ESTIMATES
Material Cost Labor Cost TOTAL COST TCOST * Indirect Cost% WGT
0.30
₱11,000,000.00
₱2,427,710.52
Material Cost Labor Cost