m Not started
Project Plan mnüu
n On Plan
ü Complete
u Issues
Date of Report Jun 30, 2005
Name Client Performance Management System Sponsor Bill Praxton, CFO
Start Date 10/1/04 End Date 3/28/06
Comple
Balanced Scorecard Design and Development Plan Not Started mOn Plan n
te ü
Issues u
Impact on
Actual Start Tentative Completion Target Completion
Item No Task Comments Deliverables Lead
Date Start Date (Actual vs. date & Status
Target)
1. Refresh the Strategic Plan 12/1/04 4/30/05
Review current strategic planning documents
1.1 and determine if the current plan is 11/15/04 3/31/05 n
appropriate for the Balanced Scorecard
1.2 Prepare for Strategic Planning Off-site 2/1/05 4/15/05 ü
Strategic Planning working group to develop
1) Kick off meeting of technical
1.3 draft revised Strategic Plan - See Planning 3/22/05 m group
Workshop Coordinator for more details
Senior Leadership approves revised Strategic
1.4
Plan
After Phase 3 m
Communicate Strategic Plan and Balanced 1) Strategic Plan booklet
1.5
Scorecard in printed and electronic format
After Phase 3 m 2) Strategy Map Draft
2. Strategy Map / Strategic Plan 3/1/05
Preliminary Draft Map with no extras for Gap
2.1 3) Very Basic Strategy Map
Analysis only
4) Gap Analysis Results and
Isolate holes / gaps between draft strategic
2.2 recommendations to fill out S-
plan vs. Draft Strategy Map
Plan
Make revisions to lower level objectives in
Draft Strategic Plan and fill-out Strategy Map 5) Revised Strategic Plan
2.3
for all components - themes, narrative add- 6) Revised Strategy Map
on's and complete cause-effect flows.
Approval of Revised Strategic Plan and Final May have to schedule at joint
2.4 7) Briefing Session
and Complete Strategy Map leadership off-site
Develop Communication Plan for Strategic
2.5 8) Communication Plan
Plan
Launch Action Plan Steps for Strategic Plan May require meetings and other 9) Action Plan for
2.6
with Strategy Map events per the Communication Plan Communication Plan
DRAFT Page 1 of 15
m Not started
Project Plan mnüu
n On Plan
ü Complete
u Issues
Date of Report Jun 30, 2005
Name Client Performance Management System Sponsor Bill Praxton, CFO
Start Date 10/1/04 End Date 3/28/06
Comple
Balanced Scorecard Design and Development Plan Not Started mOn Plan n
te ü
Issues u
Impact on
Actual Start Tentative Completion Target Completion
Item No Task Comments Deliverables Lead
Date Start Date (Actual vs. date & Status
Target)
Centralize feedback and comments for next Output from this step does not get
10) Feedback Collection
2.7 planning cycle. Collect and recommend for acted upon until next annual planning
System and Reports
next planning session cycle. cycle.
3. Measurements and Targets
Create measurement and target development
11) Performance measurement
3.1 workplan complete with templates and
training, tools, methodology
methodology
Final set of tools to
Quality control review to refine and improve
3.2 development enterprise wide
complete measurement approach for client
performance measurements
Extend each objective on the Strategy Map
3.3 Follow the methodology and training
into one to three performance measurements
Solicit input and feedback from functional Revised set of performance
3.4
leads and line and staff personnel measurements
Establish a set of targets in accordance with
3.5 operational goals that are linked to the Targets for each measurement
Strategic Plan
Identify initiatives and projects related to
3.6 Scorecard Model
execution of each objective. Extend the Map
Prototype test Scorecard Model for data points Make sure model is tight / fits across
3.7
that use existing measurement data all components
Complete a comprehensive measurement Performance measurement
3.8
template for database development development template
4. Initiative Mapping and Budgeting
Extend Initiative and Projects that are part
Extended Scorecard Model ensures
4.1 of Scorecard Model into Action Plans or Extended Scorecard Model
execution of the Strategic Plan
document with existing plans
Link the Initiative / Projects within the
4.2
Scorecard Model to the Budgeting Process
DRAFT Page 2 of 15
m Not started
Project Plan mnüu
n On Plan
ü Complete
u Issues
Date of Report Jun 30, 2005
Name Client Performance Management System Sponsor Bill Praxton, CFO
Start Date 10/1/04 End Date 3/28/06
Comple
Balanced Scorecard Design and Development Plan Not Started mOn Plan n
te ü
Issues u
Impact on
Actual Start Tentative Completion Target Completion
Item No Task Comments Deliverables Lead
Date Start Date (Actual vs. date & Status
Target)
Identify gaps and short coming with linking Recommended Changes to
4.3
and make recommendations to improve Link Processes Together
Cross walk all major initiatives against the
Graph of what should get
4.4 Strategic Objectives - Pareto Chart the
resourced vs. what should not
initiatives / projects
Work back upstream from initiatives /
projects not linked and document any Operating Plan / Sub Objective
4.5
missing lower level objectives in strategic Additions
plan and / or strategy map
5. Reporting Framework (Database)
Map and build a framework structure from the
See other similar models from other Visual prototype framework for
5.1 highest organizational level down to the
performance management projects review
managerial level
Align and link lower level components by
5.2 through objective setting - upper to lower by
organizational level / reporting units
Assign performance measurements for lower
5.3 level objectives. Index across common
reporting units for the same objective.
Complete a comprehensive measurement
5.4 template for database development for this
reporting level (lower objectives)
NOTE: The IT Design and
Various automated tools, such
Development Plan covers automation
5.5 as data collection forms,
of the Enterprise Strategic
Prototype test and revise database design of reporting tools, etc.
Management System
Balanced Scorecard System - (ESMS
5.6 Roll out test modules at pilot sites - flush out
lessons learned and update IT Plans
Cascade and development plan for Enterprise ESMS Design and
5.7
Strategic Management System (ESMS) Development Plan
DRAFT Page 3 of 15
m Not started
Project Plan mnüu
n On Plan
ü Complete
u Issues
Date of Report Jun 30, 2005
Name Client Performance Management System Sponsor Bill Praxton, CFO
Start Date 10/1/04 End Date 3/28/06
Comple
Balanced Scorecard Design and Development Plan Not Started mOn Plan n
te ü
Issues u
Impact on
Actual Start Tentative Completion Target Completion
Item No Task Comments Deliverables Lead
Date Start Date (Actual vs. date & Status
Target)
Baseline End Date 3/28/06
Major Issues
Item No. Description Comments Status
DRAFT Page 4 of 15
DRAFT Page 5 of 15
All Measurements Used in the ESMS Database
PM # Performance Measure BSC Framework Strategic Goal or Objective Major Organizational Unit Function / Dept / Sub Group Service or Product Line (if Type of Measure Measure Justification Definition Data Elements To Be Data Source Data Collection Frequency PM Calculation Formula Actual FY 03
per BSC or Strategic Plan applicable) Collected D/W/M/Q/SA/A
What is the PM number for What metric(s) should we use to Is this measure a Customer, Insert major goals or objectives in Insert a list of the major Insert a Link here to reference Insert the Operating Area such Is this measure a Why are we using this How do we define this measure? What are the data elements Where does the data How frequently should the What is the formula for What is the actual
referencing. Could be LMR # or measure whether we have met our Process, Learn & Grow or this box as a reference in organizational unit names in back a list of Functions / as Product or Service Line - To 1) Strategic metric? for caclulating the measure? reside? data be collected? calculating the measure? result of this measure
a unique number for local requirements? Resources measure based on the completing this template this box for reference in Departments and other be used for Product 2) Operational for the Year 2003?
metrics? BSC framework? completing this template organizational units in Performance Analysis 3) Tactical
Definition
completing this template 4) Individual
6 of 15
All Measurements Used in the ESMS Database
PM # Performance Measure Actual FY 04 Green Standard Amber Standard Red Standard Primary Functional POC Data Available? Notes
What is the PM number for What metric(s) should we use to What is the actual What is the Green What is the Amber What is the Red Who is the primary owner Y/N Are there any additional notes regarding the
referencing. Could be LMR # or measure whether we have met our result of this measure Threshold? Threshold? Threshold? for the measure and their measure?
a unique number for local requirements? for the Year 2004? email address?
metrics?
Definition
7 of 15
Balanced Scorecard Project
Degree of Reliability
Update Frequency /
Graded Attributes
vs.Subjective)
Quality Review of Metrics
Repeatable
(Hard Data
Review and score all measurements used in your scorecard model
F1.1 % Revenue Growth 4 4
Financial Objective F1.2
(F1) F1.3
F1.4
F2.1
Financial Objective F2.2
(F2) F2.3
F2.4
F3.1
Financial Objective F3.2
(F3) F3.3
F3.4
C1.1
Customer Objective C1.2
(C1) C1.3
C1.4
C2.1
Customer Objective C2.2
(P2) C2.3
C2.4
P1.1
Process Objective P1.2
(P1) P1.3
P1.4
P2.1
Process Objective P2.2
(P2) P2.3
P2.4
P3.1
Process Objective P3.2
(P5) P3.3
P3.4
P4.1
Process Objective P4.2
(P4) P4.3
P4.4
L1.1
L1.2
L & G Objective (L1)
L1.3
L1.4
L2.1
L & G Objective (L2)
L2.2
L & G Objective (L2)
L2.3
L2.4
L3.1
L3.2
L & G Objective (L3)
L3.3
L3.4
Instructions:
Rate each Measurement for these attributes on a scale of 1 to 5:
1. Update Frequency: Measurement can get updated on a regular basis; M for Monthly, Q for Quarterly, A for Annual, etc.
2. Degree of Reliability: Can you easily measure the performance objective or is it too subjective when it comes to measurabili
3. Encourages the right behavior: Measurements should not confuse, distort, or create the wrong performance behavior within
4. Degree of Fit: Measurement fits with the culture and processes of Organization and flows well from Lower Level to Upper Le
5. Degree of Support: Client has existing procedures and processes that can support the measurement (such as available dat
Maximum Score 25
Degree of Support /
Leading or Lagging
Degree of Fit with
Encourages the
Client's Culture
Single or Index
right behavior
Available Info
NonGraded
Attributes
Metric
Total Overall
Points Grade
3 4 5 20 80% Lagging Single
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
0 0%
Quarterly, A for Annual, etc.
ive when it comes to measurability.
ong performance behavior within the Organization. Controllable?
well from Lower Level to Upper Level. (MACRO FIT - ORGANIZATIONAL)
surement (such as available data is in place)
Alignment Matrix
Vision Mission Values
Strategic
Drivers
Organization
Measures
Critical
Levers
Critical
Processes
Measures
Tools
Project Roster
Name Area Location Desk Phone
Project Intranet Web Site ► www.intranets.com
Cell Phone Email