You are on page 1of 3

Sl no. Heating schedule( Partial Iining) Hrs Cummulative Time Temp in deg.

c
After completion of castable lining keep DRI kiln as such for air drying for at least
1 12 hrs. After 12 hrs. kiln can be rotate for air tube fitting.Pls. don't hammer the kiln 0 0 0
shell during inserting of airtube inside kiln.

2 Start wood firing for 12 hrs. .(At cooler Inlet) 0 0 60

3 Raise the temp from 60 0 C to 130 0 C @ 15 0 C/hr. 0 4 130

4 Soak at this temp. for 18 hrs. 24 28 130


0 0
5 Raise the temp. up to 250 C @ 25 C/hr. 5 33 250
6 Soak at this temp. for 24 hrs. 24 57 250
7 Raise the temp. 350 0C @ 250C/hr 4 61 350
8 Soak at this temp for 12 hrs 12 73 350
9 Raise the temp 350 to 550 deg.c @ 40 deg.c 5 78 550
10 Soak at this temp for 8 hrs 12 90 550
Raise the temp from 550 to 750 deg. C by charging 300 to 350 kg coal fines & HSD (
11 Kiln should be in rotation in main drive after soaking at 550 deg. C ) HSD flow 6 96 750
rate to reduce slowly after coal fines catches fire.) Soak at this temp for 6 hrs.

Check Hot gas temp. of T-9, T-8 & T-7 in every one hr. Avg. temp to be noted down. Hot gas
Total 96 hrs
temp at inletside should be 350 0 C & more during soaking at 550 deg.c.

Note:Depending upon F.C % in coal, Fines to be feed during raising from 550 deg.c to 750 deg.c & Soaking. If F.C is ( 35 -40%) then feed 300-350 kg. approx in
every 2 hrs. of interval.If F.C is (45-55 %) feed rate will be 200-250 kg in every 2 hrs. of interval. After soaking at 750 to 800 deg. c feed rate of fine coal can be
increased upto process temp.

Fuels recommendation
0
Raise temperature upto 550 C by firing HSD or LDO inside the kiln,after that coal
1 fines & HSD/LDO to be used. HSD/LDO flow rate to be reduce slowly after coal fine
catches fire.
2 Raise temperature upto operating temperature by coal fines after 750 deg.c.
Dry out schedule for 350 tpd DRI Kiln (Partial Repairing)
a) From kiln temp 60 deg.c to 130 deg.C @ 15 deg.C/hr.------4 hrs.

b) Hold at 130 deg.C for 24 hrs-------- 24 hrs (Kiln rotation 1/4th in every 3 hr)

c) From 130 deg.C to 250 deg.C @ 25 deg.C/hr.-------5 hrs

d) Hold at 250 deg.C for 24 hrs-------24 hrs (Kiln rotation 1/4th in every 3 hr)

e) From 250 deg.C to 350 deg.C @ 25 deg.C/hr------4 hrs

f) Hold at 350 deg.C for 12 hrs-----12 hrs (Kiln rotation 1/4 th in every 3 hr)

g) From 350 deg.C to 550 deg.C @ 40 deg.C/hr.------5hrs

h) Hold at 550 deg.C for 12 hrs---12 hrs (Kiln rotation 1/4th in every 2 hr)

I) From 550 deg. C to 750 deg.c- 6 hrs.(Continue kiln rotation in main drive)

Dry-Out Schedule
800 750

700
600 550 550

500
TEMP. IN C

400 350 350

300 250 250

200 130 130


60
100
0
0
0 0 4 28 33 57 61 73 78 90 96
TIME IN HR
TIME IN HR

You might also like