Professional Documents
Culture Documents
period was intended, the court may fix the duration thereof
112230. July 17, 1995 because the fulfillment of the obligation itself cannot be
demanded until after the court has fixed the period for
compliance therewith & such period has arrived. However, this
FACTS: general rule cannot be applied in this case considering the
In 1939, Don Ramon Lopez Sr. executed a deed of donation in different set of circumstances existing more than a reasonable
favor of CPU together with the following conditions: period of 50yrs has already been allowed to petitioner to avail
a) The land should be utilized by CPU exclusively for the of the opportunity to comply but unfortunately, it failed to do so.
establishment & use of medical college; Hence, there is no need to fix a period when such procedure
b) The said college shall not sell transfer or convey to any 3rd would be a mere technicality & formality & would serve no
party; purpose than to delay or load to unnecessary and expensive
c) The said land shall be called “Ramon Lopez Campus” and multiplication of suits.
any income from that land shall be put in the fund to be known
as “Ramon Lopez Campus Fund”. Under Art. 1191, when one of the obligors cannot comply with
what is incumbent upon him, the obligee may seek rescission
However, on May 31, 1989, PR, who are the heirs of Don before the court unless there is just cause authorizing the fixing
Ramon filed an action for annulment of donation, of a period. In the absence of any just cause for the court to
reconveyance & damages against CPU for not complying with determine the period of compliance there is no more obstacle
the conditions. The heirs also argued that CPU had negotiated for the court to decree recission.
with the NHA to exchange the donated property with another
land owned by the latter.
ISSUE:
1) WON petitioner failed to comply the resolutely conditions
annotated at the back of petitioner’s certificate of title without a
fixed period when to comply with such conditions? YES
2) WON there is a need to fix the period for compliance of the
condition? NO
HELD:
Records are clear and facts are undisputed that since the
execution of the deed of donation up to the time of filing of the
instant action, petitioner has failed to comply with its obligation
as donee. Petitioner has slept on its obligation for an
unreasonable length of time. Hence, it is only just and
equitable now to declare the subject donation already
ineffective and, for all purposes, revoked so that petitioner as
donee should now return the donated property to the heirs of
the donor, private respondents herein, by means of
reconveyance.
2)Under Art. 1197, when the obligation does not fix a period
but from its nature & circumstance it can be inferred that the
Catungal vs Rodriguez Paragraph 1(b) of the Conditional Deed of Sale, stating that respondent
shall pay the balance of the purchase price when he has successfully
Facts: negotiated and secured a road right of way, is not a condition on the
Agapita T. Catungal (Agapita) owned a parcel of land (Lot 10963) perfection of the contract nor on the validity of the entire contract or its
situated in the Barrio of Talamban, Cebu City. Agapita, with the consent compliance as contemplated in Article 1308. It is a condition imposed
of her husband Jose, entered into a Contract to Sell [6] with respondent only on respondent’s obligation to pay the remainder of the purchase
Rodriguez which subsequently purportedly “upgraded” into a price. In our view and applying Article 1182, such a condition is not
Conditional Deed of Sale.Both the Contract to Sell and the Conditional purely potestative as petitioners contend. It is not dependent on the sole
Deed of Sale were annotated on the title. will of the debtor but also on the will of third persons who own the
adjacent land and from whom the road right of way shall be negotiated.
The provisions of the Conditional Deed of Sale pertinent to the
present dispute are quoted below: The condition is a mixed condition which is allowed by Article 1182.
"potestative condition" is imposed not on the birth of the obligation but
1.price 25 Million pesos on its fulfillment, only the condition is avoided, leaving unaffected the
2. downpayment 500 Thousand obligation itself.
3. balance shall be paid after the VENDEE have successfully
negotiated, secured and provided a Road Right of Way . If however said With respect to petitioners’ argument that paragraph 5 of the Conditional
Road Right of Way could not be negotiated, the VENDEE shall give Deed of Sale likewise rendered the said contract void, we find no merit
notice to the VENDOR for them to reassess and solve the problem by to this theory.
taking other options and should the situation ultimately prove futile, he
shall take steps to rescind or cancel the herein Conditional Deed of Sale. Reading paragraph 5 in its entirety will show that Rodriguez’s option to
He likewise alleged that he actively negotiated for the road right of way rescind the contract is not absolute as it undeniably only limited to the
as stipulated in the contract.[9] contingency that Rodriguez shall not be able to secure the road right of
way. .
On August 31, 1990 the spouses Catungal requested an advance
of P5,000,000.00 on the purchase price for personal In sum, Rodriguez’s option to rescind the contract is not purely
reasons. Rodriquez allegedly refused on the ground that the amount potestative but rather also subject to the same mixed condition as his
was substantial and was not due under the terms of their obligation to pay the balance of the purchase price – i.e., the negotiation
agreement. The Catungal’s rescinded the contract. of a road right of way. In the event the condition is fulfilled (or the
negotiation is successful), Rodriguez must pay the balance of the
Rodirguez filed a complaint against the Catungal’s for arbitrarily purchase price. In the event the condition is not fulfilled (or the
rescinding the contract. In a Decision dated May 30, 1992, the trial court negotiation fails), Rodriguez has the choice either (a) to not proceed with
ruled in favor of Rodriguez, finding that: (a) under the contract it was the sale and demand return of his downpayment or (b) considering that
complainant (Rodriguez) that had the option to rescind the sale; (b) the condition was imposed for his benefit, to waive the condition and still
Rodriguez’s obligation to pay the balance of the purchase price arises pay the purchase price despite the lack of road access. This is the most
only upon successful negotiation of the road right of way; (c) he proved just interpretation of the parties’ contract that gives effect to all its
his diligent efforts to negotiate the road right of way; (d) the spouses provisions.
Catungal were guilty of misrepresentation which defeated Rodriguez’s
efforts to acquire the road right of way; and (e) the Catungals’ rescission In any event, even if we assume for the sake of argument that the grant
of the contract had no basis and was in bad faith. to Rodriguez of an option to rescind, in the manner provided for in the
During the pendency of the case with the Court of Appeals, contract, is tantamount to a potestative condition, not being a condition
Agapita Catungal passed away and thus, her husband, Jose, filed on affecting the perfection of the contract, only the said condition would be
February 17, 1999 a motion for Agapita’s substitution by her surviving considered void and the rest of the contract will remain valid.
children.[46]
WHEREFORE, the Decision dated August 8, 2000 and
The Catungals alleged that the conditional deed of sale was void ab initio the Resolution dated January 30, 2001 of the Court of Appeals in CA-
because it violates the mutuality of contract in view of Article 1308 G.R. CV No. 40627 consolidated with CA-G.R. SP No. 27565
ncc. Petitioners rely on Article 1308 of the Civil Code to support are AFFIRMED with the following MODIFICATION:
their conclusion regarding the claimed nullity of the aforementioned
provisions. Article 1308 states that “[t]he contract must bind both
contracting parties; its validity or compliance cannot be left to the will of If still warranted, respondent Angel S. Rodriguez is given a period of
one of them.” thirty (30) days from the finality of this Decision to negotiate a road right
of way. In the event no road right of way is secured by respondent at the
Article 1182 of the Civil Code, in turn, provides: end of said period, the parties shall reassess and discuss other options
as stipulated in paragraph 1(b) of the Conditional Deed of Sale and, for
Art. 1182. When the fulfillment of the condition depends upon the this purpose, they are given a period of thirty (30) days to agree on a
sole will of the debtor, the conditional obligation shall be void. If it course of action. Should the discussions of the parties prove futile after
depends upon chance or upon the will of a third person, the obligation the said thirty (30)-day period, immediately upon the expiration of said
shall take effect in conformity with the provisions of this Code. period for discussion, Rodriguez may (a) exercise his option to rescind
the contract, subject to the return of his downpayment, in accordance
with the provisions of paragraphs 1(b) and 5 of the Conditional Deed of
Issue: W/N Conditional Deed of Sale violate the principle of mutuality of Sale or (b) waive the road right of way and pay the balance of the
contracts under Article 1308 of the Civil Code? deducted purchase price as determined in the RTC Decision dated May
30, 1992.
.
Held: No. In the past, this Court has distinguished between a condition
imposed on the perfection of a contract and a condition imposed merely
on the performance of an obligation. While failure to comply with the
first condition results in the failure of a contract, failure to comply with
the second merely gives the other party the option to either refuse to
proceed with the sale or to waive the condition. This principle is evident
in Article 1545 of the Civil Code on sales, which provides in part: Case of SECURITY BANK & TRUST COMPANY and ROSITO C.
MANHIT vs COURT OF APPEALS and YSMAEL C. FERRER
Art. 1545. Where the obligation of either party to a
G.R.No. 117009 11October1995
contract of sale is subject to any condition which is not performed,
such party may refuse to proceed with the contract or he may waive
performance of the condition x x x.
This case is with regard to Art 1182 of the NCC- Potestative Condition-
Stipulation dependent upon the sole will of the debtor
Is SBTC liable for the increase in cost of the construction due to drastic
increases in cost of material?
- Yes, since under Art 1182 of the NCC, a conditional obligation shall
be void if its fulfillment depends upon the sole will of the debtor. Under
Art IX of the building contract it allows for the adjustment of the
contract price upon mutual agreement of the parties.
- It is the absence of this mutual agreement that the bank is using to
support its contention that it is not liable for the increased cost, and in
effect this is an obligation dependent on SBTC’s sole will, since its
consent is required for the recovery of the increased cost to be
allowed.
- This in effect allows SBTC to acquire the constructed building at a
price that is far below its actual construction cost, and this constitutes
unjust enrichment for SBTC at the expense of Ferrer. This is not
allowed by law by virtue of Art 22 of NCC.
HELD:
FACTS
Ø Taylor contracted his services to Tan Liuan & Co as superintendent of
an oil factory which the latter contemplated establishing
Ø The contract extended over 2 years and the salary was P600/month
during the first year and P700/month during the second with electric,
light and water for domestic consumption or in lieu thereof, P60/month
Ø At this time, the machinery for contemplated factory had not been
acquired, though ten expellers had been ordered from the US
Ø It was understood that should the machinery to be installed fail, for
any reason, to arrive in Manila within the period of 6 months, the
contract may be cancelled by the party of the second part at its option,
such cancellation not to occur before the expiration of such 6 months
Ø The machinery did not arrive in Manila within the 6 months; the
reason does not appear, but a preponderance of evidence show that
the defendants seeing that oil business no longer promised large
returns, either cancelled the order for machinery from choice or were
unable to supply the capital necessary to finance the project.
Ø Defendants communicated to Taylor that they had decided to rescind
the contract.
Ø Taylor instituted this action to recover damages in the amount of
P13k, covering salary and perks due and to become due
ISSUE
WON in a contract for the prestation of service, it is lawful for the
parties to insert a provision giving the employer the power to cancel
the contract in contingency which may be dominated by himself
HELD
Ø YES. One of the consequences of the stipulation was that the
employers were left in a position where they could dominate the
contingency, and the result was about the same as if they had been
given an unqualified option to dispense with the services of Taylor at
the end of 6 months. But this circumstance does not make the
stipulation illegal.
Ø A condition at once facultative and resolutory may be valid even
though the condition is made to depend upon the will of the obligor.
Ø If it were apparent, or could be demonstrated that the defendants
were under positive obligation to cause the machinery to arrive
in Manila, they would of course be liable, in the absence of affirmative
proof showing that the non-arrival of the machinery was due to some
cause not having its origin in their own act or will.
Ø The contract, however, expresses no such positive obligation, and its
existence cannot be implied in the face of the stipulation, defining the
conditions under which the defendants can cancel the contract.
Ø CFI no error in rejecting Taylor’s claim in so far as damages are
sought for the period subsequent to the expiration of 6 months, but in
assessing the damages due for the six-month period, the trial judge
overlooked the item of P60 (commutation of house rent) This amount
Taylor is entitled to recover in addition to P300 awarded by CFI.
ISSUE:
Is rescission proper in this case?
HELD: Article 1191 of the Civil Code provides that the power
to rescind obligations is implied in reciprocal ones, in case one
of the obligors should not comply with what is incumbent upon
him. A lease contract is a reciprocal contract.By signing the
lease agreement, the lessor grants possession over his/her
property to the lessee for a period of time in exchange for
rental payment. The aggrieved party is given the option to the
aggrieved party to ask for: (1) the rescission of the contract; (2)
rescission and indemnification for damages; or (3) only
indemnification for damages, allowing the contract to remain in
force.
DENIED
Facts:
Estelita villamar a registered owner of 3.6080 hectares of parcel of
land, decided to sell it Balbino Mangaoil with the certain
conditions; The price of the land is ONE HUNDRED AND
EIGHTY THOUSAND (180,000.00) PESOS per hectare but
only the 3.5000 hec. shall be paid and the rest shall be given
free, so that the total purchase or selling price shall be
[P]630,000.00 only. The respondent paid the amount of
185,000 as a down payment for the land title to be given to him
. After some time, Mangaoil decided to back out from the
agreement because the area is not yet fully cleared by
incumbrances as these are tenants who are not willing to
vacate the land without giving them back the amount that they
mortgage the lad.
Mangaoil demanded a refund for his 185,000, reiterating his
demand on another date but the same as unheeded. The
respondent filed a complaint in the RTC and the latter ordered
the rescission of the agreement and the deed of absolute sale
in accordance of Art. 1458 and Art. 1191 of the Civil Code. The
petitioner filed before the CA an appeal to challenge the
foregoing. She ascribed error on the part of the RTC when the
latter ruled that the agreement and deed of sale executed by
and between the parties can be rescinded as she failed to
deliver to the respondent both the subject property and the
certificate of title covering the same. On February 20, 2009, the
CA rendered the now assailed decision dismissing the
petitioners appeal.
The Petitioner filed an instant petition in the supreme court. The
petitioner contends that in her case, she had already complied
with her obligations under the agreement and the law when
she had caused the release of TCT No. T-92958-A from the
Rural Bank of Cauayan, paid individual mortgagees Romeo
Lacaden and Florante Parangan, and executed an absolute
deed of sale in the respondent’s favor.
Issue:
Whether or not the failure of petitioner-seller to deliver the
certificate of title over the property to respondent-buyer is a
breach of obligation in a contract of sale of real property that
would warrant rescission of the contract?
Held:
The RTC and CA both found the petitioner failed to comply with her
obligations to deliver to the respondent both the possession of
the subject property and the certificate of title covering the
same.
The petition was denied for failure to deliver to the respondent the
possession of the subject property due to the continued
presence and occupation of one Parangan and Lacaden. The
Court directed the rescission of the agreement and absolute
deed of sale entered by Estelita Villamar and Balbino Mangaoil
and return of the down payment made for the purchase of the
subject property. And an interest of 12% per annum on the
sum of 185,000 to be returned to Balbino Mangaoil.
ISSUE:
Whether or not the penalty (liquidated damages) of P15,000.00 per
day of delay shall be binding upon mutual agreement of
parties.
RULING:
NO. As a general rule, courts are not at liberty to ignore the
freedom of the parties to agree on such terms and conditions
as they see fit as long as they are not contrary to law, morals,
good customs, public order or public policy. The judge shall
equitably reduce the penalty when the principal obligation has
been partly or irregularly complied with by the debtor. Even if
there has been no performance, the penalty may also be
reduced by the courts if it is iniquitous or unconscionable
(Art.1229, NCC). A penalty interest of P15,000.00 per day of
delay as liquidated damages or P3,990,000.00 (representing
32% penalty of the P12,470,000.00 contract price) is
unconscionable considering that the construction was already
not far from completion.