Professional Documents
Culture Documents
DEPARTMENTÓ OF POTOSI
PROJECT ANALYSIS
12.0 DEPARTMENT OF POTOSI: PROJECT ANALYSIS………………………. 112.1 LINE
EXTENSION PROJECTS………………………………………………… 1
12.1.1 SUMMARY OF ANALYSIS………………………………………………………
1
12.1.2 Project Analysis……………………………………………………………. 1
DEPARTMENT OF POTOSI
In this Chapter, a detailed analysis of the potential for rural electrification projects in
the Department of Potosi is made. The analysis includes line extension projects,
isolated projects, and dispersed projects; and, in each case, the methodology
outlined in Chapter 6 is used.
Using the GIS methodology described in Sec. 6.2, nine (9) line extension projects
have been identified in the Department of Potosi and analyzed. These projects
were previously identified by the Secretaria Nacional de Energía. Table 12.1.1 lists
each project, the project’s location, its cost, and ranking factors for the base case
scenario described in Sec. 6.2.4.c.
As noted in Sec. 6.2, the NPVuser indicator shows the initial payment which each
new user must pay in order for a project to be financially viable.
The total potential investment in the line extension projects listed in Table 12.1.1 is
$1,124,700. However, one notes that the projects do not meet the criteria stated
in Chapter 6. Thus, one does not anticipate a high investment in line extension
projects in the rural areas of this Department unless the line extensions can include
a significant industrial or commercial demand or the projects are subsidized.
As shown in Fig. 12.1.1, the Cala Cala project involves the construction of a single
phase, 14.4 kV line from Uncia to Cala Cala. The total line length is 15 km. Two
communities would be connected in the canton of Cala Cala.
Table 12.1.2 shows the basic technical characteristics of this project including the
number of initial connections (users) and the number of connections projected in
the tenth year.
Table 12.1.3 shows the results of the financial analysis for the five cases defined in
Sec. 6.2.4.c.
The GIS analysis estimated the cost of this project at $64,900 and the number of
initial connections at 49. The number of customers per kilometer was 3. Thus,
neither the number of connections per kilometer nor the cost per connection meets
the criteria for project construction. Moreover, the financial analysis shows that a
high tariff ($0.240) or a subsidy of more than the capital cost of the project would
be needed to make the project viable.
Panacachi Project
bifurcates twice with short extensions to the communities of Ecia. Khenwani and
Amayapampa in the cantons of Irupata and Amayapampa, respectively.
Table 12.1.4 shows the basic technical characteristics of this project including the
number of initial connections (users) and the number of connections projected in
the tenth year.
Table 12.1.5 shows the results of the financial analysis for the five cases defined in
Sec. 6.2.4.c.
The GIS analysis estimated the cost of this project at $115,200 and the number of
initial connections at 95. The number of customers per kilometer was 4. Thus,
neither the number of connections per kilometer nor the cost per connection meets
the criteria for project construction. Moreover, the financial analysis shows that a
high tariff ($0.208) or a subsidy of more than the capital cost of the project would
be needed to make the project viable.
Revelo Project
As shown in Fig. 12.1.2, the Revelo project consists 26 km of single phase, 14.4
kV line from Ocuri to Revelo. Seventeen communities would be connected, eight
in the canton of Coquecota, two in the canton of Coque and seven in the canton of
Revelo.
Table 12.1.6 shows the basic technical characteristics of this project including the
number of initial connections (users) and the number of connections projected in
the tenth year.
Table 12.1.7 shows the results of the financial analysis for the five cases defined in
Sec. 6.2.4.c.
The GIS analysis estimated the cost of this project at $443,500 and the number of
initial connections at 185. The number of customers per kilometer was 2. Thus,
neither the number of connections per kilometer nor the cost per connection meets
the criteria for project construction. Moreover, the financial analysis shows that a
very high tariff of $0.674 per kWh or a subsidy of more than the capital cost of the
project would be needed to make the project viable.
Cotagaita Project
As shown in Fig. 12.1.3, the Cotagaita project consists of three single phase, 14.4
kV line segments from Palca Grande, where each segment taps off of the 24.9 kV
line, to the communities of Santiago de Cotagaita, Villa Abecia, and xxxx. The line
from Palca Grande to Santiago de Cotagaita bifurcates at Majuelo in order to
electrify the community of La Carreta. Twelve communities would be connected:
seven in the canton of Cotagaita, two in the canton of La Correta, and one each in
the cantons of Pampa Grande, Mormorque, and Vichoca.
Table 12.1.8 shows the basic technical characteristics of this project including the
number of initial connections (users) and the number of connections projected in
the tenth year.
Table 12.1.9 shows the results of the financial analysis for the five cases defined in
Sec. 6.2.4.c.
The GIS analysis estimated the cost of this project at $300,000 and the number of
initial connections at 165. The number of customers per kilometer was 2. Thus,
neither the number of connections per kilometer nor the cost per connection meets
the criteria for project construction. Moreover, the financial analysis shows that an
extremely high tariff of $0.930 per kWh or a subsidy of more than the capital cost of
the project would be needed to make the project viable.
Coroma Project
Table 12.1.10 shows the basic technical characteristics of this project including the
number of initial connections (users) and the number of connections projected in
the tenth year.
Table 12.1.11 shows the results of the financial analysis for the five cases defined
in Sec. 6.2.4.c.
The GIS analysis estimated the cost of this project at $81,600 and the number of
initial connections at 12. The number of customers per kilometer was 1. Thus,
neither the number of connections per kilometer nor the cost per connection meets
the criteria for project construction. Moreover, the financial analysis shows that an
extremely high tariff of $1.759 per kWh or a subsidy of more than the capital cost of
the project would be needed to make the project viable.
Tacobamba Project
Table 12.1.12 shows the basic technical characteristics of this project including the
number of initial connections (users) and the number of connections projected in
the tenth year.
Table 12.1.13 shows the results of the financial analysis for the five cases defined
in Sec. 6.2.4.c.
The GIS analysis estimated the cost of this project at $126,200 and the number of
initial connections at 89. The number of customers per kilometer was 2. Thus,
neither the number of connections per kilometer nor the cost per connection meets
the criteria for project construction. Moreover, the financial analysis shows that a
very high tariff of $0.514 per kWh or a subsidy of more than the capital cost of the
project would be needed to make the project viable.
Urmiri Project
As shown in Fig. 12.1.5, the Urmiri project consists of 20 km of single phase, 14.4
kV line from Salinas de Yocalla to Urmiri. The line interconnects with a 24.9 kV line
in Salinas de Yocalla. Four communities would be connected: three in the canton
of Yocalla and one in the canton of Urmiri.
Table 12.1.14 shows the basic technical characteristics of this project including the
number of initial connections (users) and the number of connections projected in
the tenth year.
Table 12.1.15 shows the results of the financial analysis for the five cases defined
in Sec. 6.2.4.c.
The GIS analysis estimated the cost of this project at $91,800 and the number of
initial connections at 87. The number of customers per kilometer was 4. Thus,
neither the number of connections per kilometer nor the cost per connection meets
the criteria for project construction. Moreover, the financial analysis shows that a
very high tariff of $0.312 per kWh or a subsidy of more than the capital cost of the
project would be needed to make the project viable.
As shown in Fig. 12.1.5, the Sta. Lucia project consists of a short 6 km extension of
single phase, 14.4 kV line La Puerta to Sta. Lucia. One community, Sta. Lucia,
would be electrified.
Table 12.1.16 shows the basic technical characteristics of this project including the
number of initial connections (users) and the number of connections projected in
the tenth year.
Table 12.1.17 shows the results of the financial analysis for the five cases defined
in Sec. 6.2.4.c.
The GIS analysis estimated the cost of this project at $27,000 and the number of
initial connections at 24. The number of customers per kilometer was 4. Thus,
neither the number of connections per kilometer nor the cost per connection meets
the criteria for project construction. Moreover, the financial analysis shows that a
very high tariff of $0.322 per kWh or a subsidy of more than the capital cost of the
project would be needed to make the project viable.
Suipacha Project
Table 12.1.18 shows the basic technical characteristics of this project including the
number of initial connections (users) and the number of connections projected in
the tenth year.
Table 12.1.19 shows the results of the financial analysis for the five cases defined
in Sec. 6.2.4.c.
The GIS analysis estimated the cost of this project at $191,500 and the number of
initial connections at 203. The number of customers per kilometer was 5. Thus,
neither the number of connections per kilometer nor the cost per connection meets
the criteria for project construction. Moreover, the financial analysis shows that a
high tariff of $0.292 per kWh or a subsidy of more than the capital cost of the
project would be needed to make the project viable.
The criteria for identifying isolated projects set the minimum number of households
at 500 and required further that the level of electrification be less than 50%. No
communities were identified in the Department of Potosi which met these criteria.
12.3 DISPERSED SYSTEMS
Using the indicators and methodology explained in Chapter 6, all cantons in the
department of Potosi were analyzed. Two principal results were calculated for
each province: 1) the total investment potential for the province, and 2) the
prioritization of project investment by canton in each province. Cantons with a
ranking less than zero were not considered to be investment opportunities and no
investment funds for such cantons have been included in the total investment
potential for the province.
12.3.1 Project Investment Potential
Table 12.3.1 shows the results of the investment analysis for each province. Over
$38 million would need to be invested to electrify just those cantons with a positive
ranking factor.
Table 12.3.2 shows the prioritization of projects by canton and by province for
those cantons with a positive ranking. Rankings for all cantons is shown in Annex
12.1. Those cantons, which are not listed in Table 12.3.2 or in Annex 12.1, are
contained within a buffer zone for a conventional electrification project.
The map of the Department of Potosi shows the rankings in three categories:
rankings greater than 4.0 (yellow), rankings between 2.0 and 4.0 (green) and
rankings between 0.0 and 2.0 (red). Uncolored areas have rankings below 0.0, or
are electrified, or are part of a proposed electrification project.
Calcha 0.26
Nor Lipez San Christobal 3.00
San Pedro de Quemes 2.27
Soniquera 1.72
Pelcoya 1.68
Rio Grande 1.66
Colcha “K” 1.27
Llavica 1.02
Chiguana 0.91
Culpina 0.47
San Juan 0.46
Santiago de Agencha 0.39
Cana 0.32
Pajancha 0.27
Atulcha 0.07
Antonio Quijarro Coroma 4.03
Porco 2.92
Thola Pampa 2.52
Tomave 2.34
Yura 1.85
Tica Tica 0.70
Calasaya 0.58
Cerdas 0.39
Sur Chichas Chocaya 2.66
Portugalete 1.87
Nazareno 1.40
Estarca 1.37
Santa Barbara 1.20
Telamayu 1.12
Villa Pacheco 0.90
Esmoraca 0.84
Talina 0.60
San Jose de Pampa 0.53
Grande
Cuchu 0.47
Espicaya 0.25
Chorolque Viejo 0.22
Tocloca 0.12
Atocha 0.09
Rio Blanco 0.08
Cornelio Saavedra Tecoya 2.17
Potobamba 2.07
Otuyo 2.00
Poco Poco 1.70
Millares 1.05
Quivincha 0.97
Chaqui 0.96
Sur Lipez Quetena Grande 5.23
Quetena Chico 4.79
San Antonio de 0.53
Esmoruco
Casa Grande 0.12
Mojinete 0.03
Tomas Frias Santa Lucia 3.45
Chulchucani 3.44
Tinquipaya 2.17
Salinas de Yocalla 1.59
Urmiri 1.28
One notes from Table 12.3.2 that all provinces in the Department of Potosi have
cantons with positive ranking factors. Four cantons have a ranking factor greater
than 4.0 indicating a high correlation of positive factors. If one considers only
those cantons with a ranking factor greater than 4.0, the market for solar home
systems is 5,633 households. Thus, the immediate market has a value of about
$3.9 million.
12.3.3 Conclusions
The Department of Potosi offers a large investment potential for solar energy
systems. The solar resource is excellent and a very large number of cantons have
positive ranking factors. Twelve provinces and 31 cantons have rankings over 2.0.
Moreover, both the municipalities and the Prefectura have focused funds on rural
electrification and it appears that this focus will continue in 1997.