NOTE:- Pump Shaft level not required. Permissible Limit:- Pump must be leveled by putting the ± 0.04mm /meter Master Level on Pump discharge flange only. 6 Completion of BFP piping supports Verification
7 Removal of all BFP piping temporary Verification
supports 8 Parallelity of BFP flanges with pipe line Verification flanges
9 Installation of Protective and Safety Verification
guards 10 Completion of Cooling water piping and Verification Fitting Connection 11 Position of Motor Rotor in case of Measurement Motors with Shell Bearings / Forced Oil Lubrication. NOTE:- During DBSE /alignment checking, keep motor rotor on its geometric centre. 12 Distance between shaft Ends (DBSE) / Micrometer coupling NOTE:- DBSE must be +1 mm higher as given in Pump supplier GA drawing.
13 Coupling Alignment Alignment by
Permissible Limit:- ± 0.04 mm using three dial gauge, two for axial & one for radial.