·0 who is the final authority to approve reject change request- change control board.

·1 _______ are modified into_________- histograms, Pareto charts.

·2 a contract is an agreement but an agreement is not a contract- True.

·3 HLD LLD UAT are stages of- product or project or both.

·4 preassignment of resources means- that resources are assigned in advance to the


project.

·5 requirement collection method in which question direclty sent to experts anonymously-


Delphi technique.

·6 ___means a successor act can start b4 predecessor act completely finish-Lead +1.

·7 precedence diagramming method is a method of- sequencing activities.

·8 in critical chain method the activites are sequenced based on __and____ constraints-
activity and resource.

·9 business,organization and quality are_____in prince2- themes.

·10 in project quality control asect two mutually exclusive events cannot occur-
simultaneously.

·11 in which type of contract max chance of bloating cost- cost plus incentive fee.

·12 activity simulated 500 timmes and found 95% time....- Monte carlo. +1.

·13 what is the major output of project initiation stage- Project charter/stakeholder +1

·14 standard deviation 0 or near 0 means- at or near mean. +1.

·15 requirements traceability matrix contain- all abc. +1.

·16 a project is a temporary endeavour with a fixed- start and end---+1.

·17 EMV= P*I +1

·18 in agile who helps in removing ov=bstacles--scrum master.

·19 in which type of contract buyer risk minimal-fixed price +1.

·20 authority of project manager minimjum- Matrix +1.

·21 risk register is the op of which process-identify risk+1.

·22 Point of total assumption-seller


·23 themes in prine2 continously-true.

·24 progress to senior management- bar chart- +1