ID Task Name Duration Start Finish 17 April 2017 May 2017 June 2017 July 2017 August 2017

Finish 17 April 2017 May 2017 June 2017 July 2017 August 2017 September 2017 October 2017 November 2017 December 2017 January 2018 February 2018 M
3/19 3/26 4/2 4/9 4/16 4/23 4/30 5/7 5/14 5/21 5/28 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29 11/5 11/12 11/19 11/26 12/3 12/10 12/17 12/24 12/31 1/7 1/14 1/21 1/28 2/4 2/11 2/18 2/25 3/4
1 PROYEK RUKO SOHO CIREBON 233 days Wed 4/5/17 Fri 3/2/18
2 PERENCANAAN 7 days Wed 4/5/17 Thu 4/13/17
3 SAP 7 days Wed 4/5/17 Thu 4/13/17
4 MEKANIKAL ELEKTRIKAL 7 days Wed 4/5/17 Thu 4/13/17
5 TENDER 16 days Fri 4/14/17 Fri 5/5/17
6 Preliminary cost plan 3 days Fri 4/14/17 Tue 4/18/17
7 Approval Rencana Biaya 7 days Fri 4/14/17 Mon 4/24/17
8 Bill of Quantity 7 days Fri 4/14/17 Mon 4/24/17
9 Tender progress 7 days Wed 4/26/17 Thu 5/4/17
10 Penunjukan kontraktor 0 days Fri 5/5/17 Fri 5/5/17 5/5
11 KONSTRUKSI 232 days Thu 4/6/17 Fri 3/2/18
12 PEKERJAAN PERSIAPAN 84 days Thu 4/6/17 Wed 8/9/17
13 Pembongkaran & persiapan lahan 30 days Thu 4/6/17 Wed 5/17/17
14 Groundbreaking 0 days Wed 8/9/17 Wed 8/9/17 8/9
15 PROCUREMENT 30 days Wed 6/21/17 Tue 8/8/17
16 Tender cut fill & dinding batu kali 30 days Wed 6/21/17 Tue 8/8/17
17 PEKERJAAN CUT FILL & DINDING BATU85
KALI
days Wed 8/9/17 Tue 12/5/17
18 Talut/ Dinding Batu kali 60 days Wed 8/9/17 Tue 10/31/17
19 Cut Fill 60 days Wed 9/13/17 Tue 12/5/17
20 PEKERJAAN UTAMA 116 days Wed 9/13/17 Wed 2/21/18
21 Tiang pancang 30 days Wed 9/13/17 Tue 10/24/17
22 Pondasi (pilecap) 21 days Wed 9/27/17 Wed 10/25/17
23 Struktur lantai 1 26 days Wed 9/27/17 Wed 11/1/17
24 Kolom pedestal 7 days Wed 9/27/17 Thu 10/5/17
25 Tie Beam 7 days Wed 9/27/17 Thu 10/5/17
26 Slab On Grade 12 days Fri 10/6/17 Mon 10/23/17
27 Kolom 9 days Fri 10/20/17 Wed 11/1/17
28 Struktur lantai 2 16 days Tue 10/31/17 Tue 11/21/17
29 Beam 10 days Tue 10/31/17 Mon 11/13/17
30 Slab 10 days Tue 10/31/17 Mon 11/13/17
31 Kolom 9 days Thu 11/9/17 Tue 11/21/17
32 Struktur lantai 3 16 days Mon 11/20/17 Mon 12/11/17
33 Beam 10 days Mon 11/20/17 Fri 12/1/17
34 Slab 10 days Mon 11/20/17 Fri 12/1/17
35 Kolom 9 days Wed 11/29/17 Mon 12/11/17
36 Struktur lantai 4 (roof) 12 days Fri 12/8/17 Mon 12/25/17
37 Beam 7 days Fri 12/8/17 Mon 12/18/17
38 Slab 7 days Fri 12/8/17 Mon 12/18/17
39 Kolom 5 days Tue 12/19/17 Mon 12/25/17
40 Arsitektur lt-1 42 days Tue 11/14/17 Wed 1/10/18
41 Kolom 10 days Tue 11/14/17 Mon 11/27/17
42 Beam 7 days Thu 11/23/17 Fri 12/1/17
43 Slab 7 days Thu 11/23/17 Fri 12/1/17
44 Wall+plester/aci 14 days Mon 12/4/17 Thu 12/21/17
45 Kusen/ jendela 7 days Mon 12/18/17 Tue 12/26/17
46 Plafond 9 days Tue 12/19/17 Fri 12/29/17
47 Floor 7 days Wed 12/27/17 Thu 1/4/18
48 Cat 7 days Tue 1/2/18 Wed 1/10/18
49
50 Arsitektur lt-2 42 days Mon 12/4/17 Tue 1/30/18
51 Kolom 10 days Mon 12/4/17 Fri 12/15/17
52 Beam 7 days Wed 12/13/17 Thu 12/21/17
53 Slab 7 days Wed 12/13/17 Thu 12/21/17
54 Wall+plester/aci 14 days Fri 12/22/17 Wed 1/10/18
55 Kusen/ jendela 7 days Fri 1/5/18 Mon 1/15/18
56 Plafond 9 days Mon 1/8/18 Thu 1/18/18
57 Floor 7 days Tue 1/16/18 Wed 1/24/18
58 Cat 7 days Mon 1/22/18 Tue 1/30/18
59
60 Arsitektur lt-3 42 days Tue 12/19/17 Wed 2/14/18
61 Kolom 10 days Tue 12/19/17 Mon 1/1/18
62 Beam 7 days Thu 12/28/17 Fri 1/5/18
63 Slab 7 days Thu 12/28/17 Fri 1/5/18
64 Wall+plester/aci 14 days Mon 1/8/18 Thu 1/25/18
65 Kusen/ jendela 7 days Mon 1/22/18 Tue 1/30/18
66 Plafond 9 days Tue 1/23/18 Fri 2/2/18
67 Floor 7 days Wed 1/31/18 Thu 2/8/18
68 Cat 7 days Tue 2/6/18 Wed 2/14/18
69
70 Arsitektur lt-4 (roof) 33 days Mon 1/8/18 Wed 2/21/18
71 Kolom 9 days Mon 1/8/18 Thu 1/18/18
72 Beam 5 days Tue 1/16/18 Mon 1/22/18
73 Slab 5 days Tue 1/16/18 Mon 1/22/18
74 Wall+plester/aci 12 days Tue 1/23/18 Wed 2/7/18
75 Kusen/ jendela 5 days Tue 2/6/18 Mon 2/12/18
76 Plafond 7 days Mon 2/5/18 Tue 2/13/18
77 Floor 5 days Fri 2/9/18 Thu 2/15/18
78 Cat 7 days Tue 2/13/18 Wed 2/21/18
79 MEP 43 days Wed 12/13/17 Fri 2/9/18
80 MEP lt-1 10 days Wed 12/13/17 Tue 12/26/17
81 MEP lt-2 10 days Tue 1/2/18 Mon 1/15/18
82 MEP lt-3 10 days Wed 1/17/18 Tue 1/30/18
83 MEP lt-4 7 days Thu 2/1/18 Fri 2/9/18
84 Tes comissioning 7 days Thu 2/22/18 Fri 3/2/18
85 Handover 0 days Fri 3/2/18 Fri 3/2/18 3/2

Project: SCHEDULE RUKO SOHO R. Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline
Date: Thu 6/15/17

Page 1