Dear Sir
With reference to the China State's submission letter ref. CSHK/CDR/CA1/2019/0583 received at 13
December 2019, we would like to advise our comment as follow:-
Please note that the checking of sub-contractor’s submission does not absolve the sub-contractor of their
responsibility to co-ordinate their work with other sub-contractors and direct contractors of main
contract and comply with the design intent and requirement of the contract documentation.
Yours faithfully
Tony Lau
Project Manager