Welcome to this presentation.

It is part of a suite of Engineering training modules.

It shows the activities and deliverables of the Process


discipline.

Comments are most welcome (herve.baron@gmail.com),


which I will incorporate for the benefit of all.

Please download this file so that you can see my trainer’s


notes in the top left corner – latest Acrobat Pro feature.

© 2015 – Hervé Baron


Hervé
HERVE Engineering disciplines: activities and deliverables
BARON

 PROCESS

 PLANT LAYOUT

 EQUIPMENT

 SAFETY & ENVIRONMENT

 CIVIL

 PIPING

 PIPELINE

© 2015 – Hervé Baron


 INSTRUMENTATION

 ELECTRICAL
HERVE Engineering disciplines: activities and deliverables
BARON

 PROCESS
• Design basis and criteria
• Process Flow Scheme, PFD, HMB
• Process description
• Process Operating and Control Philosophy
• Equipment sizing
• P&IDs
• Piping specification and sizing
• Instrument process specification
• Process and Emergency shutdown
• Flare study

© 2015 – Hervé Baron


• Operating manual
HERVE Engineering disciplines: activities and deliverables
BARON

 PROCESS
• Design basis and criteria
• Process Flow Scheme, PFD, HMB
• Process description
• Process Operating and Control Philosophy
• Equipment sizing
• P&IDs
• Piping specification and sizing
• Instrument process specification
• Process and Emergency shutdown
• Flare study

© 2015 – Hervé Baron


• Operating manual
HERVE Process Design Basis
BARON

What constitutes the Design Basis of a Process/Utility Unit?

© 2015 – Hervé Baron


HERVE Process Design Basis
BARON

What constitutes the Design Basis of a Process/Utility Unit?

• Sizing cases: max capacity /turndown

• Other operating cases

• Feedstock composition and condition

• Product specifications

• Battery limit conditions

© 2015 – Hervé Baron


HERVE Process design basis
BARON
Compressor Station

© 2015 – Hervé Baron


HERVE Engineering disciplines: activities and deliverables
BARON

 PROCESS
• Design basis and criteria
• Process simulations, Process Flow Diagram, HMB
• Process description
• Process Operating and Control Philosophy
• Equipment sizing
• P&IDs
• Piping specification and sizing
• Instrument process specification
• Process and Emergency shutdown
• Flare study

© 2015 – Hervé Baron


• Operating manual
HERVE Choice of Process Scheme
BARON

© 2015 – Hervé Baron


What are the bases of process scheme definition?
HERVE Overall Plant Process Design
BARON

What is the name of


this drawing?

© 2015 – Hervé Baron


HERVE The Block Flow Diagram (BFD)
BARON

© 2015 – Hervé Baron


 Results from the high level functional requirements of the plant
 Depicts the various Processes carried out within the facility and their sequence
 Shows the inputs (feed) and outputs (products)
 The item of the BFD is the Process Unit
HERVE Unit Process Design
BARON

© 2015 – Hervé Baron


HERVE The Process Flow Diagram (PFD)
BARON

© 2015 – Hervé Baron


HERVE Unit Process Scheme Optimization
BARON

TEG HP Compression & TEG

1200 psig Gas Injection

3000 psig 5500 psig

500 psig 200 psig 50 psig

IP Compression LP Compression

From Wells HP Separator


Cooler 5 psig
165 - 205 F 500 psig

Emul. Treater
50 psig 150 F

Degasser
Oil Production
5 psig

© 2015 – Hervé Baron


What are the elements taken into account in the
definition/optimization of the process scheme?
HERVE Process simulations
BARON

© 2015 – Hervé Baron


HERVE Process simulations
BARON

Simulator settings
Output
Input
- Flow scheme
- Stream flows and
- Feed composition and - Thermodynamic model
composition
conditions - Equipment performance
- Equipment duty

© 2015 – Hervé Baron


HERVE Process simulations
BARON

Simulator settings Output


Input
- Flow scheme - Stream flows and
- Feed composition and
- Thermodynamic model composition
conditions
- Equipment performance - Equipment duty

© 2015 – Hervé Baron


HERVE Process simulations
BARON

Simulator settings
Output
Input
- Flow scheme
- Stream flows and
- Feed composition and - Thermodynamic model
composition
conditions - Equipment performance
- Equipment duty

© 2015 – Hervé Baron


HERVE Process simulations
BARON

Simulator settings
Output
Input
- Flow scheme
- Stream flows and
- Feed composition and - Thermodynamic model
composition
conditions - Equipment performance
- Equipment duty

© 2015 – Hervé Baron


HERVE Process simulations
BARON

Simulator settings
Output
Input
- Flow scheme
- Stream flows and
- Feed composition and - Thermodynamic model
composition
conditions - Equipment performance
- Equipment duty

© 2015 – Hervé Baron


HERVE Process simulations
BARON

Simulator settings
Output
Input
- Flow scheme
- Stream flows and
- Feed composition and - Thermodynamic model
composition
conditions - Equipment performance
- Equipment duty

© 2015 – Hervé Baron


HERVE The Process Flow Diagram (PFD)
BARON

© 2015 – Hervé Baron


HERVE The Process Flow Diagram (PFD)
BARON

 Results from process simulations

Depicts the various Equipment within a Process (or Utility) Unit and their sequence

© 2015 – Hervé Baron


 Shows the process controls

 The individual drawing item of the PFD is the Equipment Item


HERVE The Process Flow Diagram (PFD)
BARON

Scheme including the following information, as a minimum:


 Main equipment (all the itemized ones),
 Process lines between equipment,
 All control loops and main instruments,
 For each stream, indication of:
• Temperature
• Pressure
• Composition Heat & Mass Balance (HMB)
• Specific gravity
• Operating density
• Heat content
• Flow rate (relevant to each phase)

© 2015 – Hervé Baron


 Design conditions of main equipment.
 It shall be drawn-up according to ISA 6.12 regulation as far as symbology is
concerning
HERVE Heat & Material Balance
BARON

© 2015 – Hervé Baron


HERVE Engineering disciplines: activities and deliverables
BARON

 PROCESS
• Design basis and criteria
• Process Flow Scheme, PFD, HMB
• Process description
• Process Operating and Control Philosophy
• Equipment sizing
• P&IDs
• Piping specification and sizing
• Instrument process specification
• Process and Emergency shutdown
• Flare study

© 2015 – Hervé Baron


• Operating manual
HERVE Process Description
BARON

© 2015 – Hervé Baron


HERVE Engineering disciplines: activities and deliverables
BARON

 PROCESS
• Design basis and criteria
• Process Flow Scheme, PFD, HMB
• Process description
• Process Operating and Control Philosophy
• Equipment sizing
• P&IDs
• Piping specification and sizing
• Instrument process specification
• Process and Emergency shutdown
• Flare study

© 2015 – Hervé Baron


• Operating manual
HERVE Engineering disciplines: activities and deliverables
BARON

© 2015 – Hervé Baron


HERVE Engineering disciplines: activities and deliverables
BARON

 PROCESS
• Design basis and criteria
• Process Flow Scheme, PFD, HMB
• Process description
• Process Operating and Control Philosophy
• Equipment sizing
• P&IDs
• Piping specification and sizing
• Instrument process specification
• Process and Emergency shutdown
• Flare study

© 2015 – Hervé Baron


• Operating manual
HERVE Equipment sizing
BARON

© 2015 – Hervé Baron


HERVE Cass study: Equipment Sizing
BARON

© 2015 – Hervé Baron


32
33

© 2015 – Hervé Baron


BARON
HERVE
HERVE Case study: Equipment Sizing
BARON
Production separator

Sets the gas


cross section
Vessel size

Sets the liquid volume

© 2015 – Hervé Baron


HERVE Process data sheet
BARON
Drums

© 2015 – Hervé Baron


HERVE Process data sheet
BARON
Contents of the Process Data Sheet:
• Design conditions
• Overdesign
• Fluid properties
• Equipment duty
• Skeleton drawing & dimensions
• Material (generic type) and
corrosion allowance
• Specification of internals:
demister, distributor, baffle etc.
• Nozzles list
• Allowable pressure drop, fouling

© 2015 – Hervé Baron


factor, Cp, Cv, enthalpy curve (for
HX, heaters)
•Available NPSH (for pumps)
HERVE Process Data sheet
BARON
Column

© 2015 – Hervé Baron


HERVE Columns and Drums
BARON
Column internals must be specified.

© 2015 – Hervé Baron


These pictures are excerpts from Sulzer douments
HERVE Process Data sheet
BARON
Column

© 2015 – Hervé Baron


HERVE Process Data sheet
BARON
Rotating equipment

© 2015 – Hervé Baron


HERVE Process Data sheet
BARON
Rotating equipment

© 2015 – Hervé Baron


HERVE Process Data sheet
BARON
Heat Exchangers / Shell & Tubes

© 2015 – Hervé Baron


HERVE Heat Exchanger thermal sizing
BARON
TEMA Data Sheet
A Thermal data sheet is
received from Process for
shell & tubes heat
exchangers following
thermal sizing

© 2015 – Hervé Baron


HERVE Process Data sheet
BARON
Heat Exchangers / Other types

© 2015 – Hervé Baron


HERVE Process Data sheet
BARON
Air Cooled HX

© 2015 – Hervé Baron


HERVE Process Data Sheet
BARON
Fired heaters

© 2015 – Hervé Baron


HERVE Process Data Sheet
BARON
Fired heaters

© 2015 – Hervé Baron


What is particularly important while specifying a heater ?
HERVE Process Data Sheet
BARON
Storage tank

© 2015 – Hervé Baron


HERVE Process Sizing
BARON

Process Equipment Sizing is done on the basis of:

 Sizing cases

 Over design

 Design criteria

© 2015 – Hervé Baron


HERVE Process Sizing
BARON

Process Equipment Sizing is done on the basis of:

 Sizing cases – all operating cases

 Over design

 Design criteria

© 2015 – Hervé Baron


HERVE Process Sizing
BARON

Process Equipment Sizing is done on the basis of:

 Sizing cases – all operating cases

 Over design – 10% as a rule

 Design criteria

© 2015 – Hervé Baron


HERVE Process Sizing
BARON

Process Equipment Sizing is done on the basis of:

 Sizing cases – all operating case

 Over design – 10% as a rule

 Sizing criteria On which basis are the following


equipment sized?

© 2015 – Hervé Baron


HERVE Process Sizing
BARON

Process Sizing is done on the basis of:

 Sizing cases – all operating case

 Over design – 10% as a rule

 Sizing criteria
• Separator
• KO drum
• Distillation/Absorption column
• Reactor
• Storage tank

© 2015 – Hervé Baron


HERVE Process Sizing
BARON

Process Equipment Sizing is done on the basis of:

 Sizing cases – all operating case

 Over design – 10% as a rule

 Sizing criteria
• Separator – Size of droplet => velocity, residence time + Surge
• KO Drum – Hold up time
• Distillation/Absorption column – Diameter based on flow. Number
of trays/height of packing based on purity required
• Reactor – Contact time (also called space velocity)
• Tank – Storage capacity

© 2015 – Hervé Baron


HERVE Process specification
BARON
Package

© 2015 – Hervé Baron


What document is issued by Process for packages?
HERVE Process specification
BARON
Package

© 2015 – Hervé Baron


HERVE Process specification
BARON
Package

What type of guarantees


are requested?

© 2015 – Hervé Baron


HERVE Process Equipment list
BARON

© 2015 – Hervé Baron


HERVE Process Equipment list
BARON

© 2015 – Hervé Baron


HERVE Engineering disciplines: activities and deliverables
BARON

 PROCESS
• Design basis and criteria
• Process Flow Scheme, PFD, HMB
• Process description
• Process Operating and Control Philosophy
• Equipment sizing
• P&IDs
• Piping specification and sizing
• Instrument process specification
• Process and Emergency shutdown
• Flare study

© 2015 – Hervé Baron


• Operating manual
HERVE Piping & Instrumentation Diagram (P&ID)
BARON

Compare the
information shown on

© 2015 – Hervé Baron


the PFD and the P&ID
HERVE Piping & Instrumentation Diagram (P&ID)
BARON

Compare
Comparethe
the
information
informationshown
shownon
on

© 2015 – Hervé Baron


the
thePFD
PFDand
andthe
theP&ID
P&ID
HERVE Piping & Instrumentation Diagram (P&ID)
BARON

What are the


purposes of P&IDs?

Compare the
information shown on

© 2015 – Hervé Baron


the PFD and the P&ID
HERVE Piping & Instrumentation Diagram (P&ID)
BARON

What are the


purposes of P&IDs?

At design stage:
• Defines the design basis for Piping & Instrumentation disciplines
Serves to
•Compare theshow and agree the operating and maintenance features between
Engineer and Owner or between Engineer and Vendor
information shown on
• Serves to show the interface with equipment/package vendors

© 2015 – Hervé Baron


the PFD and the P&ID
• Perform HAZOP review

During operation:
• Reference drawing for operator, work permit, plant modifications etc.
HERVE Piping & Instrumentation Diagram (P&ID)
BARON

What are the


purposes of P&IDs?

P&ID
At design stage: review
• Defines the design basis for Piping & Instrumentation disciplines
Serves to
•Compare theshow and agree the operating and maintenance features between
Engineer and Owner or between Engineer and Vendor
information shown on
• Serves to show the interface with equipment/package vendors

© 2015 – Hervé Baron


the PFD and the P&ID
• Perform HAZOP review

During operation:
• Reference drawing for operator, work permit, plant modifications etc.
HERVE Piping & Instrumentation Diagram (P&ID)
BARON

What are the


purposes of P&IDs?
Which are the usual
points reviewed
during a P&ID
review?

P&ID
At design stage: review
• Defines the design basis for Piping & Instrumentation disciplines
Serves to
•Compare theshow and agree the operating and maintenance features between
Engineer and Owner or between Engineer and Vendor
information shown on
• Serves to show the interface with equipment/package vendors

© 2015 – Hervé Baron


the PFD and the P&ID
• Perform HAZOP review

During operation:
• Reference drawing for operator, work permit, plant modifications etc.
HERVE Piping & Instrumentation Diagram (P&ID)
BARON
P&ID review

Ease of operation and maintenance:

• Isolation /bypass of equipment

• Isolation/bypass of valves

• Vents/drains

© 2015 – Hervé Baron


HERVE Piping & Instrumentation Diagram (P&ID)
BARON
P&ID review

Ease of operation and maintenance:

• Isolation /bypass of equipment

• Isolation/bypass of valves

• Vents/drains

What do you call each type of

© 2015 – Hervé Baron


isolation?
HERVE Piping & Instrumentation Diagram (P&ID)
BARON
P&ID review

Ease of operation and maintenance:

• Isolation /bypass of equipment

• Isolation/bypass of valves

• Vents/drains

Where do you use double block


and bleed?

© 2015 – Hervé Baron


HERVE Isolation philosophy
BARON

© 2015 – Hervé Baron


HERVE Isolation philosophy
BARON

© 2015 – Hervé Baron


HERVE Isolation philosophy
BARON

© 2015 – Hervé Baron


HERVE Piping & Instrumentation Diagram (P&ID)
BARON
P&ID review

Ease of operation and maintenance:

• Isolation /bypass of equipment

• Isolation/bypass of valves

• Vents/drains

© 2015 – Hervé Baron


HERVE Piping & Instrumentation Diagrams (P&IDs)
BARON

Important features
Normal operation
• Redundancy for critical instruments / safety switches
Shutdown
• Check valves
Start-up
• Pressurization
• warm-up / purge lines
Maintenance
• Equipment isolation & bypass: valves, spectacle/blind
• Nitrogen injection, vent
• Drains

© 2015 – Hervé Baron


• Control and ON/OFF valves isolation
• Instrument isolation
HERVE Piping & Instrumentation Diagrams (P&IDs)
BARON
It includes:

1. All itemized equipment,

2. Item number and service description of each equipment with relevant


design condition

3. All lines (process , utilities, start-up, maintenance), with indication of


• Diameter
• Rating
• Material
• Service
• Line number

© 2015 – Hervé Baron


• Piping class
• Piping class break / change
• External finishing (such as insulation, personal protection, tracing…)
HERVE Piping & Instrumentation Diagrams (P&IDs)
BARON

4. Battery limits between Parties, e.g. contractor and vendor

5. All valves for operation, start-up, maintenance with indication of


valve type, including isolation valves, check valves etc.

6. All instruments with detailed control loops:


• All instruments shall be tagged as per united numbering system,
• Local instruments or instruments on local panel,
• Sequences and interlocks (with brief description e.g.: comp. start / stop,
permissive to start, etc.),

7. Control valves, ON/OFF valves,

8. Safety valves (with set point and inlet/outlet size),

© 2015 – Hervé Baron


9. Electrical controls, such as pump local or remote start/stop,
emergency shutdown
HERVE Piping & Instrumentation Diagrams (P&IDs)
BARON
9. Particular data or notes relevant to equipment/instruments
installation, such as:
• Max or mini length of piping (requirement regarding suction / discharge
piping straight length, etc.),
• Slope of piping
• Elevation of equipment
• Pertinent interior arrangement of equipment
• Safe location requirement
• Control and monitoring signals for rotating equipment and electrical
motors,

10. Item number and service description of each equipment with relevant
design condition

© 2015 – Hervé Baron


11. Connecting flags for pipe lines running from one drawing to another

Instruments and controls must be drawn-up according to ISA 6.12


requirements.
HERVE Piping & Instrumentation Diagrams (P&IDs)
BARON

 Various types of P&IDs


• Legend and Symbols
• Identification & Numbering
• Details and Typicals
• Process or Utility P&ID
• Distribution P&ID
• Interconnection P&ID
• Pumps auxiliary P&ID
• Package P&ID

© 2015 – Hervé Baron


HERVE Piping & Instrumentation Diagrams (P&IDs)
BARON

 Various types of P&IDs


• Legend and Symbols
• Identification & Numbering
• Details and Typicals
• Process or Utility P&ID
• Distribution P&ID
• Interconnection P&ID
• Pumps auxiliary P&ID
• Package P&ID

© 2015 – Hervé Baron


HERVE P&IDs legend & symbols
BARON

© 2015 – Hervé Baron


HERVE Piping & Instrumentation Diagrams (P&IDs)
BARON

 Various types of P&IDs


• Legend and Symbols
• Identification & Numbering
• Details and Typicals
• Process or Utility P&ID
• Distribution P&ID
• Interconnection P&ID
• Pumps auxiliary P&ID
• Package P&ID

© 2015 – Hervé Baron


HERVE Identification and numbering system
BARON

© 2015 – Hervé Baron


HERVE Identification and numbering system
BARON

© 2015 – Hervé Baron


HERVE Piping & Instrumentation Diagrams (P&IDs)
BARON

 Various types of P&IDs


• Legend and Symbols
• Identification & Numbering
• Details and Typicals
• Process or Utility P&ID
• Distribution P&ID
• Interconnection P&ID
• Pumps auxiliary P&ID
• Package P&ID

© 2015 – Hervé Baron


HERVE Piping & Instrumentation Diagrams (P&IDs)
BARON

 Various types of P&IDs


P&ID
• Legend and Symbols representation
• Identification & Numbering
• Details and Typicals
• Process or Utility P&ID
• Distribution P&ID
• Interconnection P&ID
• Pumps auxiliary P&ID Details

• Package P&ID

© 2015 – Hervé Baron


HERVE Piping & Instrumentation Diagrams (P&IDs)
BARON

 Various types of P&IDs


• Legend and Symbols
• Identification & Numbering
• Details and Typicals
• Process or Utility P&ID
• Distribution P&ID
• Interconnection P&ID
• Pumps auxiliary P&ID
• Package P&ID

© 2015 – Hervé Baron


HERVE Piping & Instrumentation Diagrams (P&IDs)
BARON

 Various types of P&IDs


• Legend and Symbols
• Identification & Numbering
• Details and Typicals
• Process or Utility P&ID
• Distribution P&ID
• Interconnection P&ID
• Pumps auxiliary P&ID
• Package P&ID

What are the different typicals that should be


defined?

© 2015 – Hervé Baron


HERVE Piping & Instrumentation Diagram (P&ID) - Typicals
BARON

© 2015 – Hervé Baron


How would you call each of these two types
of arrangement?
For what service(s) would each be used?
HERVE Piping & Instrumentation Diagrams (P&IDs)
BARON

 Various types of P&IDs


• Legend and Symbols
• Identification & Numbering
• Details and Typicals
• Process or Utility P&ID
• Distribution P&ID
• Interconnection P&ID
• Pumps auxiliary P&ID
• Package P&ID

© 2015 – Hervé Baron


HERVE P&ID work sequence
BARON

P&IDs are typically issued 3 times, as design progresses

© 2015 – Hervé Baron


HERVE P&ID work sequence
BARON

P&IDs are typically issued 3 times, as design progresses

IFR IFD IFC

© 2015 – Hervé Baron


HERVE P&ID work sequence
BARON

P&IDs are typically issued 3 times, as design progresses

IFR IFD IFC

© 2015 – Hervé Baron


HERVE P&ID work sequence
BARON

P&IDs are typically issued 3 times, as design progresses

P&ID
Review

IFR IFD IFC

© 2015 – Hervé Baron


HERVE P&ID work sequence
BARON

P&IDs are typically issued 3 times, as design progresses

P&ID
HAZOP
Review

IFR IFD IFC

© 2015 – Hervé Baron


HERVE Quiz
BARON
Which revision of P&IDs has the following purpose/contents?
Purpose IFR IFD IFC
Collect Client comments
Perform PID review
Perform HAZOP
Perform Piping MTO for 1st Piping purchase
Freeze Control system I/O list
Issue Piping ISOs
Contents IFR IFD IFC
Comments from all disciplines
Comments from Piping, I&C disciplines
Finalized interfaces with eqt/package
Exercised Contract Option(s)
Size, number of PSVs and CVs

© 2015 – Hervé Baron


Diameter of process lines
Diameter of utility lines
HAZOP comments incorporated
Client comments incorporated
HERVE Quiz
BARON
Which revision of P&IDs has the following purpose/contents?
Purpose IFR IFD IFC
Collect Client comments X
Perform PID review X
Perform HAZOP X
Perform Piping MTO for 1st Piping purchase X
Freeze Control system I/O list X
Issue Piping ISOs X
Contents IFR IFD IFC
Comments from all disciplines X
Comments from Piping, I&C disciplines X
Finalized interfaces with eqt/package X
Exercised Contract Option(s) X
Size, number of PSVs and CVs X

© 2015 – Hervé Baron


Diameter of process lines X
Diameter of utility lines X
HAZOP comments incorporated X
Client comments incorporated X
HERVE P&ID work sequence
BARON

P&IDs are typically issued 3 times, as design progresses

P&ID
HAZOP
Review

IFR IFD IFC

© 2015 – Hervé Baron


HERVE P&ID work sequence
BARON
The different revisions

 The prime purpose of the first issue (IFR: Issued for Review) is to
obtain COMPANY’s comments/APPROVAL – this APPROVAL is
necessary before progressing the design further to avoid re-work
 The IFD revision, which incorporates COMPANY comments, aims
at transferring information from Process to other disciplines:
• to Piping, to perform routing studies
• to Piping materials, to perform 1st MTO for purchase
• To Instrumentation, to perform Instrument list
• To Civil for routing of Undeground Piping

 IFC incorporates HAZOP impacts and information from Vendors. It


is a pre-requisite to:
• Start production of Piping isometrics

© 2015 – Hervé Baron


HERVE P&ID work sequence
BARON

P&ID
HAZOP
Review  Piping Isometric
drawings
 Piping material
top-up’s

IFR IFD IFC


 Piping routing

© 2015 – Hervé Baron


 Piping 2nd MTO & 1st material purchases
 Instrumenation & Control design
 Undeground piping (civil)
HERVE P&ID work sequence
BARON

Sometimes an « IFH » revision, mark-up’s of the P&ID review,


is used to anticipate the HAZOP

P&ID
HAZOP
Review

IFR IFD IFC

© 2015 – Hervé Baron


HERVE P&ID work sequence
BARON

An IFD2 revision is issued in case major change from Vendors/HAZOP to


up-date piping material purchases, instrumentation design etc.

P&ID HAZOP
Review  Piping Isos
 Piping material
Start top-up

IFR IFD IFD2 IFC


Up-date

© 2015 – Hervé Baron


 Piping routing
 Piping 1st material purchases
 Instrumenation & Control design
 Undeground piping (civil)
HERVE Engineering disciplines: activities and deliverables
BARON

 PROCESS
• Design basis and criteria
• Process Flow Scheme, PFD, HMB
• Process description
• Process Operating and Control Philosophy
• Equipment sizing
• P&IDs
• Piping specification and sizing
• Instrument process specification
• Process and Emergency shutdown
• Flare study

© 2015 – Hervé Baron


• Operating manual
HERVE Fluids list
BARON

© 2015 – Hervé Baron


© 2015 – Hervé Baron
Line list
BARON
HERVE
HERVE Line sizing
BARON

© 2015 – Hervé Baron


HERVE Engineering disciplines: activities and deliverables
BARON

 PROCESS
• Design basis and criteria
• Process Flow Scheme, PFD, HMB
• Process description
• Process Operating and Control Philosophy
• Equipment sizing
• P&IDs
• Piping specification and sizing
• Instrument process specification
• Process and Emergency shutdown
• Flare study

© 2015 – Hervé Baron


• Operating manual
HERVE Instrument process data sheet
BARON

© 2015 – Hervé Baron


HERVE Instrument process data sheet
BARON

© 2015 – Hervé Baron


What is the most
important process data
for control valves?
HERVE Instrument process data sheet
BARON

Operating range, typ.


 Maximum flow rate: 110 % of max. operating flow rate
 Minimum flow rate: 30 % of minimum operating flow

© 2015 – Hervé Baron


rate,
in order to guarantee correct functioning at the extremes
of the operating range.
HERVE Engineering disciplines: activities and deliverables
BARON

 PROCESS
• Design basis and criteria
• Process Flow Scheme, PFD, HMB
• Process description
• Process Operating and Control Philosophy
• Equipment sizing
• P&IDs
• Piping specification and sizing
• Instrument process specification
• Process and Emergency shutdown
• Flare study

© 2015 – Hervé Baron


• Operating manual
HERVE Process Shut Down
BARON

Look at the extracts of these 2 P&IDs.


How is the protection against loss of
liquid level achieved in each case?

© 2015 – Hervé Baron


HERVE ESD logic diagram
BARON

© 2015 – Hervé Baron


HERVE Safeguarding narrative & Cause and Effects charts
BARON

© 2015 – Hervé Baron


HERVE Process and Safety Diagrams (PSD)
BARON

© 2015 – Hervé Baron


HERVE Engineering disciplines: activities and deliverables
BARON

 PROCESS
• Design basis and criteria
• Process Flow Scheme, PFD, HMB
• Process description
• Process Operating and Control Philosophy
• Equipment sizing
• P&IDs
• Piping specification and sizing
• Instrument process specification
• Process and Emergency shutdown
• Flare study

© 2015 – Hervé Baron


• Operating manual
HERVE Relief load summary
BARON

© 2015 – Hervé Baron


HERVE Flare study
BARON

© 2015 – Hervé Baron


HERVE Flare study
BARON

© 2015 – Hervé Baron


HERVE Engineering disciplines: activities and deliverables
BARON

 PROCESS
• Design basis and criteria
• Process Flow Scheme, PFD, HMB
• Process description
• Process Operating and Control Philosophy
• Equipment sizing
• P&IDs
• Piping specification and sizing
• Instrument process specification
• Process and Emergency shutdown
• Flare study

© 2015 – Hervé Baron


• Operating manual
HERVE Operating manual
BARON

© 2015 – Hervé Baron


HERVE Operating manual
BARON

What are the most important contents of the


operating manual?

© 2015 – Hervé Baron


HERVE Operating Manual
BARON
Table of Contents (typ.)
1 INTRODUCTION 4 OPERATION
1.1 General presentation 4.1 Start-up
1.2 Glossary 4.2 Normal operation
1.3 Basic data 4.4 Shutdown
4.5 Depressurization
2 DESCRIPTION OF FACILITIES
2.1 General 5 SAFETY
2.2 Process 5.1 Operating philosophy
2.3 Utilities 5.2 Escape, evacuation and
2.4 Auxiliaries rescue
5.3 Emergency power system
3 AUTOMATIC CONTROL SYSTEM 5.4 Safety equipment list
3.1 System overview 5.5 Fire protection
3.2 Operator control interfaces
3.3 Telecommunications

© 2015 – Hervé Baron


3.4 Process alarms and trips
3.6 Emergency shutdown system
3.7 Fire & gas system
HERVE Operating Manual
BARON
Annexes (typ.)

 EQUIPMENT LIST  SINGLE LINE DIAGRAM


 PFDs  F&G SYSTEM ARCHITECTURE
DRAWING
 P&IDs
 VESSELS MECHANICAL DATA
 ESD LOGIC DIAGRAM SHEETS

 EQUIPMENT START/STOP &  INSTRUMENT DATA SHEETS (PSVs,


SHUTDOWN SEQUENCES Level instruments)

 GENERAL PLOT PLAN  ESD SIMPLIFIED DIAGRAM

 DCS ARCHITECTURE DRAWING  CONTROL LOOPS AND ALARM LIST

 ELECTRICAL CONTROL SYSTEM  SECURITY SWITCHES LIST


ARCHITECTURE DRAWING

© 2015 – Hervé Baron


HERVE Operating Manual
BARON
Annexes (typ.)

 EQUIPMENT LIST  SINGLE LINE DIAGRAM


 PFDs  F&G SYSTEM ARCHITECTURE
DRAWING
 P&IDs
 VESSELS MECHANICAL DATA
 ESD LOGIC DIAGRAM SHEETS

 EQUIPMENT START/STOP &  INSTRUMENT DATA SHEETS (PSVs,


SHUTDOWN SEQUENCES Level instruments)

 GENERAL PLOT PLAN  ESD SIMPLIFIED DIAGRAM

 DCS ARCHITECTURE DRAWING  CONTROL LOOPS AND ALARM LIST

 ELECTRICAL CONTROL SYSTEM  SECURITY SWITCHES LIST


ARCHITECTURE DRAWING

© 2015 – Hervé Baron


HERVE Operating Manual
BARON
Control loops and Alarms list

© 2015 – Hervé Baron


HERVE Engineering disciplines: activities and deliverables
BARON

 PROCESS
• Design basis and criteria
• Process Flow Scheme, PFD, HMB
• Process description
• Process Operating and Control Philosophy
• Equipment sizing
• P&IDs
• Piping specification and sizing
• Instrument process specification
• Process and Emergency shutdown
• Flare study

© 2015 – Hervé Baron


• Operating manual
HERVE Process design criteria
BARON

What are the different Process design criteria?

© 2015 – Hervé Baron


HERVE Process design criteria
BARON

What are the different Process design criteria?

• Design margins
• Design Pressure and Temperature criteria
• Equipment sizing criteria
• Line sizing criteria
• Control valve sizing criteria

© 2015 – Hervé Baron


HERVE Process design criteria
BARON

• Design margins
• Design Pressure and Temperature criteria
• Equipment sizing criteria
• Line sizing criteria
• Control valve sizing criteria

© 2015 – Hervé Baron


HERVE Process design criteria
BARON

• Design margins: what is the usual Equipment (rotating, heat exchangers, columns) overdesign (%)?
• Design Pressure and Temperature criteria
• Equipment sizing criteria
• Line sizing criteria
• Control valve sizing criteria

+?%

© 2015 – Hervé Baron


HERVE Process design criteria
BARON

• Design margins: what is the usual Equipment (rotating, heat exchangers, columns) overdesign (%)?
• Design Pressure and Temperature criteria
• Equipment sizing criteria
• Line sizing criteria
• Control valve sizing criteria

+10%

© 2015 – Hervé Baron


HERVE Process design criteria
BARON

• Design margins
• Design Pressure and Temperature criteria
• Equipment sizing criteria
• Line sizing criteria
• Control valve sizing criteria

© 2015 – Hervé Baron


HERVE Process design criteria
BARON

• Design margins
• Design Pressure and Temperature criteria
• Equipment sizing criteria
• Line sizing criteria
• Control valve sizing criteria

The design temperature should be the highest or lowest temperature to which the
equipment is subjected, plus a margin.

The following cases must be considered:

(a) A maximum temperature which can occur when bypassing a heat exchanger or
cooler for cleaning.

(b) A high metal temperature on uninsulated equipment due to solar radiation.

© 2015 – Hervé Baron


(c) The lowest temperature that may be caused by auto-refrigeration.

(d) The maximum metal temperature that can occur during steam out or decoking
operation.
HERVE Process design criteria
BARON

• Design margins
• Design Pressure and Temperature criteria
• Equipment sizing criteria
• Line sizing criteria
• Control valve sizing criteria

© 2015 – Hervé Baron


HERVE Process design criteria
BARON

• Design margins
• Design Pressure and Temperature criteria
• Equipment sizing criteria
• Line sizing criteria
• Control valve sizing criteria

© 2015 – Hervé Baron


HERVE Licensed vs Open Art Process
BARON

When one uses a process under license, what are the deliverables
issued by the process LICENSOR?

© 2015 – Hervé Baron


HERVE Typical PROCESS Licensor / Engineering split
BARON

Item Process Licensor Engineer


PFD, H&MB X
Equipment data sheet Equipment process data sheet: Equipment Mechanical data sheet
- Operating conditions,
- Duty
- Diameters of vessels
- Size of Nozzles
- Pump head
+ specific info for internals etc.
P&IDs Generic customized (piping class, line and
valves size, HAZOP comments,
vendor info)

© 2015 – Hervé Baron


Line sizing Line sizing criteria Sizing (takes into account eqt loc,
elevation etc.)
Plot Plan recommendations X
Material selection Basic requirement MSD
HERVE Typical PROCESS Licensor / Engineering split
BARON

Item Process Licensor Engineer


PFD, H&MB X
Equipment data sheet Equipment process data sheet: Equipment Mechanical data sheet
- Operating conditions,
- Duty
- Diameters of vessels
- Size of Nozzles
- Pump head
+ specific info for internals etc.
P&IDs Generic customized (piping class, line and
valves size, HAZOP comments,
vendor info)

© 2015 – Hervé Baron


Line sizing Line sizing criteria Sizing (takes into account eqt loc,
elevation etc.)
Plot Plan recommendations X
Material selection Basic requirement MSD
HERVE The Oil & Gas Engineering Guide
BARON
2nd edition
Do you want to know more... Much more?

© 2015 – Hervé Baron


HERVE The Oil & Gas Engineering Guide - 2nd edition
BARON
Table of Contents

© 2015 – Hervé Baron


HERVE The Oil & Gas Engineering Guide - 2nd edition
BARON
Table of Contents

This suite of training modules


covered the discipline
chapters of the book...

© 2015 – Hervé Baron


HERVE The Oil & Gas Engineering Guide - 2nd edition
BARON
Table of Contents

The Guide contains much more:

The overall picture, interfaces,


methods & tools, etc.

© 2015 – Hervé Baron


HERVE The Oil & Gas Engineering Guide
BARON
2nd edition

Order direct from the publisher:

http://www.editionstechnip.com/en/catalogu
e-detail/1111/oil-gas-engineering-guide-
the.html

© 2015 – Hervé Baron