STANDARD DATA – USER GUIDELINES

PREAMBLE

1. The existing AP Standard data for various constructions items are based on observations made
several decades back, mostly utilising eployment of machinery was at the barest minimum. The
Board of Chief engineers have been adopting almost the same data, duly modifying the rates of
labour; materials, hire charges of limited machinery, every year. The advent of construction
machinery and its usage in construction industry has changed the structure and methodology of
data formulation & rate structure and hence, the present estimation of work item rates are not
reflecting ground reality. The CWC(Ministry of Irrigation) has also recommended that ”where
standard or schedule of rates are revised or where is necessary to do so, the primary guiding
principle should be escalation in labour and material cost and not on trend of rates quoted by
contractors”. But the above recommended principle is not being followed by the Board of Chief
Engineers in Andhra Pradesh.

2. Government, in GO 7326 (GAD-GPM& AR) Dated 26-10-05, has observed that the age old
“Standard data” requires revision and updation with reference to the latest machinery and
contemporary practices and has constituted a High Level Committee to advise on updating and
revision of standard data and schedule of rates. The work has been taken up by CGG and SPIU-
irrigation. The secretary (Irrigation ) is the member- convener of the committee Accordingly the
data has been revised adopting the procedures and guidelines given by CWC, Report on
“committee on cost control of river valley Projects, BIS specifications, NHAI, MORTH, MORD, CPWD
and Government of Karnataka and revised data and formulated schedule of rates for all
infrastructure Departments (I&CAD, R&B, PR and PH). The team of senior engineers interacted
with the S.R Committee of Karnataka on implementation and improvements needed. For irrigation
works the data pattern as adopted by Karnataka has been considered and for other Departments
the data adopted by MORTH,MORD and NHAI etc., is adopted

3. Sequence followed in revision of standard data is,

(a) The first step is the revision and formulation of standard data for each work
component

(b) The second step is to work out the details of inputs. This enables to generate the unit
work item rates, by incorporating the use rates of machinery, materials, labour charges
and other supplementary parameters

(c) The third step is to develop software tool to generate unit rate using the software
(completed for irrigation works by the SPI Unit of Irrigation)

4. The Detailed draft data was communicated to all the HODs and interacted through many
seminars and discussions and incorporated the relevant features.The Board of chief engineers in
their meetings have recommended for acceptance to the data formulated and schedule of rates.

2
STANDARD DATA – USER GUIDELINES

It was proposed to examine the recommendations on important parameters, to refer to high level
committee, for their specific recommendations for adoption, as they are common to all
departments. The committee made in depth study on the methodology and systems followed by
the reputed National organizations and other States and made detailed deliberations with HODs
and representatives of Builders Association of India and made recommendations to the
Government, on adoption of such parameters in A.P.

5. The Chief Secretary held a detailed discussions on 04-07-2007,with the Secretaries of the
Departments and Heads of Departments.
B. GUIDELINES
1) The Revised Standard Data is formulated under four Parts which are applicable to all the
Engineering Departments and other Organisations.
PART -1: Irrigation& CAD (Dam and Allied Works, Canals And Allied Works, Canal C.D.
Works, Tunnels and Allied Works, Preliminary and Maintenance Works, Hydraulic
Gates and allied works and Leads and Lifts applicable to all Departments
PART -2: Roads and Bridges
PART -3: Buildings including Electrical Works
PART -4: Drinking Water Supply and Public Health (ONLY FOR WORKS DONE BY MANUAL
MEANS)

2) Brief description of item of work. :


Brief description of the item of work to cover all important aspects of the work included in the in
the Data . On reading the item description, the user should be in a position to assess the various
cost components involved in the work.
3) Data for assessing quantities :
The data reflects various assessments / assumptions made in arriving at the quantities of
materials, machinery, labour and other in-puts. In case of plants and equipment the output of
main plant is worked out and the requirement of all other inputs and assessed to match the
output of the main plant. Cycle time of operations is the criteria for assessing the output of
equipment. Generally the equipment manufacturers furnish the output of machinery under ideal
conditions of working. Suitable job and management efficiency factors are considered while
working out the average output of machinery under field conditions. In case of combination of
machinery and manpower the assessment of manpower shall match the output of machinery.
Though cycle time of operations is the criteria for hourly / daily out-put of machinery work-force
,the actual progress of work depends on several other factors such as power interruptions, minor
break-downs, time for meals and other needs of work-force, stray rains etc. Therefore, it is the
general practice to consider 50 minutes as the actual working time per hour for working out the
hourly / daily out-put of machinery / work-force.CWC / BIS guide-lines stipulate the actual working

3
STANDARD DATA – USER GUIDELINES

hours for the purpose of equipment planning and utilisation. The daily out-put is computed duly
considering the actual available working time and feed back from the field.

 For gate and hoist works it is the general practice to specify the quantity of work in
terms of number of sets of embedded parts / gates. The requirement of machinery and work-
force for cutting, bending, fabrication, erection, painting etc., is assessed to commensurate with
the task involved.
 The data for gates and E.M. Parts is arrived per Ton quantity.
 The data for Hoists and Gantry Cranes is worked out on the basis of capacity in tonnage
4) The lead and lift charges provided in PART-I (B) are generally applicable and common to all
Departments. Any item is not covered in this part, the rates as provided in the data of the
relevant works may be adopted in preparation of estimates.
5) The basic material inputs needed for all works are listed and incorporated in the data. The
requirements are analyzed and the specifications adopted shall confirm to Standards published by
the BIS.
 The labour and material rates will be communicated by the Board of Chief engineers.
 Unless otherwise specified, all material rates shall be inclusive of all taxes, duties, levies,
royalty/seigniorage, transportation and handling costs up to project area.
 For sand, gravel , murum, stones , course aggregates etc, the rates are to be fixed for
delivery at Quarry, adding seigniorage ( royality) charges, loading charges by machinery /
manual means and idle hire charges of machinery (as per table under chapter “
conveyance or lead and lift charges”), as applicable.
 For earth/ soil for embankment works from borrow areas, which is not included in the
material list of schedule of rates, seigniorage charges are to be added separately,if
applicable.
 For steel, Cement, AC sheets, GI sheets, Hume pipes, wood and stone slabs, the rates are
to be taken prevailing at major commercial centre near project area. The lead charges, as
applicable are to be added in preparing estimates.
 The specifications of the aggregates for sizes and gradation and its adoption shall be as
per IS 383.
6) The labour component in the data is mentioned for unit work.
 No allowance towards labour importation and labour amenities added extra as they are
included in the recommended overheads.
 On Labour Component: Certain additional allowances are added extra to the wages of
labour (,i.e. only on labour component in the work item) in the form of percentage, as
recommended by the Government/Board of chief engineers,due to statutory and other
provisions.

4
STANDARD DATA – USER GUIDELINES

 However, If more than one area allowances, such as those for (1) Municipalities (2)
Agency / Tribal areas (3) Industrial areas are applicable for a particular situation, only the
maximum out of the allowable percentages is to be allowed.

7) HIRE CHARGES OF MACHINERY:


The machinery and /or group of machinery for items of works and their output has been
worked based on the availability of machinery generally in the market and working in the the
field successfully, duly considering cycle time, idle time, operator efficiency, type of work etc.

 The hire charge of a machinery / equipment is worked out based on the guidelines
published by CWC and BIS codes.
 For the other machinery not covered by the list, the R&B and other users may adopt hire
charges as recommended by the MORTH.
8) Lead Charges
 The high level committee has recommended to adopt, for conveyance by head load, a
minimum lead of 50 meters and additional lead up to 150 meters in the intervals of 50
meters. Beyond 150 meters lead ,only machinery rates are to be adopted.
 The basic item rates provided in the schedule of rates include 50 m or 1 km as initial lead
and no lead charges shall be allowed where the source of material is within the initial
lead specified in item rate. Additional lead charges shall be allowed for the lead
exceeding initial lead specified in the item rate.
 The lead charges per unit quantity for conveyance of the materials are worked out,and
included in the schedule of rates in increment of 50 m for head load and in increment of
1 km for mechanical mode.
 The rates for lead charges by head load upto 150 meters and by machinery up to 5 km,
shall be cumulative and inclusive of lead charges for preceding lead. For lead beyond 5
km the lead charges shall be worked out on per km basis.
9) Loading and Unloading charges for Materials
The following features are considered:
(a) Loading and unloading charges are not payable for conveyance by head load.
(b) Loading and unloading charges are not payable for conveyance by mechanical
means, for disposal of excavated material unless specified.
(c) The rates for unloading of materials except earth, sand, gravel, coarse aggregate,
rubble, size stone and cut stone, are inclusive of stackingwherever applicable.
10) LIFT CHARGES :

5
STANDARD DATA – USER GUIDELINES

 The data includes initial lift charges of 3 meters ,for materials conveyance by head load,
Additional leads in the interval of 1.0 meters are worked out, as additional labour input
and incorporated in the chapter on” Lead and lifts” .
 Where the conveyance / lifting of material is done by mechanical means, lift charges shall
not be considered, as the cycle time of operation of the machine includes lifts involved.
 The data and rates for lift charges is cumulative and are inclusive of rates for preceding
lifts also.
11) Wastage of Materials
 Cement : No wastage allowance is recommended towards the quantity of cement
used in works, as the wastage is already included in the input and in major works
bulk quantities are used.
 steel : The wastage of steel @ 2.5% is allowed for gates and allied structures. For
RCC works the wastage is @2.5% for the reinforcement rods above 36mm did and
@ 5% for rods below 36mm dia. including overlaps, if they are not welded. If welding
is adopted for the reinforcement rods even for below 36mm dia, 2.5% of wastage is
only recommended.
12) Provision for rate for water:-
The Committee has recommended not considering the water charges in the Irrigation
Project works. But, it may be considered in specific cases as per the site conditions.

13) In respect of RCC works the rate for cement concrete for 1 cum is worked separately for
all grades based on Indian Standards. The rate for ton is calculated separately and to be added
separately in the estimates of RCC works as a separate item.

14) Soil classification: The Committee recommended to allow uniform classification of soils for all
Departments and data is worked out accordingly.
1. All soils
2. Marshy soil
3. ordinary rock ( not requiring blasting),
4. hard rock
a. hard rock (requiring blasting)
b. hard rock (controlled blasting)
c. removable by chiseling(blasting prohibited)

15) Use of Super Plasticizers and Admixtures:


Concrete admixtures such as Air-Entraining Agent (AEA) / Water reducing agent can be
used advantageously for better quality concrete. The high level committee has
recommended adopting for super plasticizers and admixtures at 0.4% on cement for
concrete work as per MORTH standards for batching plants.
16) Contractors overheads, profit and other provisions:

6
STANDARD DATA – USER GUIDELINES

 High Level Committee has recommended to add 14% plus 4% towards VAT or as
applicable on item rate towards overheads labour including importation and amenities &
contractor profits, which includes various items recommended in MORTH.
 This also includes 4% of VAT and should be exhibited separately. In the
agreements, it should be mentioned that it will be reimbursed as per actuals. The
provisions allowed in Go Ms. No. 94, I & CAD, Dt. 1-7-03, need not be added separately.
The overhead charges include the following elements:
 Site accommodation, setting up plant, access road, water supply, electricity and general
site arrangements.
 Office furniture, equipment and communications
 Expenditure on:
 Corporate office of contractor
 site supervision
 Documentation and “as built” drawings
 Mobilisation/ de-mobilisation of resources
 Labour camps with minimum amenities and transportation to work sites.
 Light vehicles for site supervision including administrative and managerial requirements.
 Laboratory equipment and quality control including field and laboratory testing.
 Minor T & P and survey instruments and setting outworks, including verification of line,
dimensions, trial pits and bore holes, where required.
 Watch and ward
 Traffic management during construction
 Expenditure on safeguarding environment
 Sundries
 Financing Expenditure
 Sales/ Turn overtax
 Work Insurance/ compensation
17) EXCISE DUTY ON SUPPLIES :

In respect of gates, hoists and allied works excise duty is applicable on the value of
fabricated components supplied to site. Excise duty is not applicable on erection charges.
Further, the excise duty shall not be considered in the rate analysis on material
component, as basic material rates are inclusive of excise duty.
Therefore, excise duty is considered in the rate analysis only on
machinery and labour components required for fabrication of gates and hoists at the
central fabrication yard. It is difficult to determine the machinery and labour components
separately for fabrication and erection.

7
STANDARD DATA – USER GUIDELINES

For the purpose of computation of excise duty to be included in the rate analysis the
machinery and labour components may apportioned at 75 % for central fabrication yard
and 25 % for field erection and commissioning. Therefore, 75 % of the machinery and
labour components may be considered for assessing the extent of excise duty to be
added in the rate analysis.

18) DEWATERING & DESILTING:


The High level committee considering the local conditions of rainfall / seepage has
recommended towards de-watering and de-silting at 3 percent on the relevant work
component for which dewatering is required.
It is also proposed as per CWC guidelines; to keep a condition in the agreements shall be
incorporated, to fix a ceiling of 5% in extreme cases, with the specific approval of chief
engineer/Government.

19) Computerization of Data:

 A software program is developed by the SPI Unit(Irrigation), which facilitates automatic


changes and generation of unit rates, based on basic input rates of Labour, materials and capital
cost of machinery.
 A soft ware tool is also developed for auto preparation of estimates based on in put
quantities.
 Other Departments are also advised to develop such program.
20) For each chapter separate additional details are incorporated for clarity.
USER GUIDELINES OF REVISED STANDARD DATA

i) Please select the item of work, as given in Index Code, and view the relevant data.
ii) The common data items like, lead, lift, conveyance and manual excavation (without involving
contracting agencies) is applicable to all Departments (volume-1)
iii) The departments have to adopt the relevant data from other Departments, if such works are
executed by them
iv) The unit rate /hire charges, of machinery not covered in the Irrigation data, the MORTH data
may be taken with the approval of Board of Chief Engineers
v) For “Drinking water Supply works”(PART-IV), the data incorporated is generally applicable
only for manual means of execution. The rates deploying machinery have to be worked out
by the Board of Chief engineers and approved for adoption.

8
STANDARD DATA – USER GUIDELINES

ROLE OF CENTRAL COMPETENT AGENCY FOR SCHEDULE OF RATES


( BOARD OF CHIEF ENGINEERS)

a) The Board Of Chief Engineers under the chairman ship of Engineer-in-chief,


(administration) I&CAD Department is the competent authority to finalise and recommend the Schedule of
Rates applicable for all engineering Departments. The board has to assess and incorporate only the three
basic inputs required to generate unit work item rates as below.

Basic rates of labour:


Wages of labour commonly required in execution of works has to be arrived and incorporated in the
schedule of rates ( Basic Input Of Labour Wages), without adding extra towards area allowances ( like
municipality allowance, tribal area and ghat road allowances etc, which shall be added to the rates where
applicable in the form of separate percentage as explained in the preceeding paras. The rates shall be the
prevailing daily rates in the State and shall not be less than the minimum wages fixed by the
Government from time to time.

Materials rates:
The basic input material rates common to all departmental works are listed out and
incorporated (in the chapter “Basic inputs”) The material specifications adopted shall confirm to
Standards published by the BIS The Prevailing market rates for all basic input materials shall be obtained
from the major commercial centers near the project areas. Average of the rates, ignoring freak rates, shall
be reckoned as the prevailing market rate. Unless otherwise specified, all material rates shall be inclusive
of all taxes, duties, levies, royalty, transportation and handling costs up to project area. For sand, gravel,
murrum, stones , aggregates etc, the rates are For delivery at Quarry including seigniorage, loading
charges and idle hire charges. For steel, Cement, AC sheets, GI sheets, Hume pipes, wood and stone slabs,
the rates prevailing at major commercial centre near project area has to be adopted.

Use rate of machinery:


The third parameter for incorporation in the Basic Inputs, is the use rate
of machinery. To arrive at the use rate of machinery, the inputs to be
incorporated are
 The list and capital cost of machinery required to be used in the construction activity, The rate
has to be obtained from major manufacturers and outlet sources and the rate shall be the current market
price inclusive of all taxes, duties and freight charges.
 The prevailing fuel charges of petrol and diesel are ascertained and average rate adopted
 Borrow rate of interest as fixed by the Government/competent authority be indicated.
 For the other machinery not covered by the list, the R&B and other users may adopt hire
charges as recommended by the MORTH

b) The Chairman, Board of Chief Engineers or competent authority


appointed by the Government, based on the approved basic inputs, load the above three basic
parameters in the software program. The unit rate of all works including hire charges of all machinery will
be generated automatically for adoption.

He shall communicate the uniform Schedule of rates arrived from Standard Data, to all users for
uniform and direct adoption in all infrastructure Departments, as applicable

9
STANDARD DATA BOOK – BUILDING WORK ITEMS – BASIC APPROACH

Basic approach and General conditions and assumptions for the preparation of Standard Data
Book for Building Works.

The Basic approach for the preparation of Standard Data for Building works is indicated as under.

1. Description of Items: The description of items is given briefly and linked with the relevant
specifications in AP Standard Specifications.

2. Use of Machinery: For concrete work mixing is proposed with machinery as well as
manually. For laying concrete, lifting is proposed with either by winches or machinery.
Manual means have been proposed for all other items.

3. Working Conditions: The inputs for the Data have been analyzed for the average working
conditions prevailing in the state.

4. Over Heads : This is assumed to include interalia the following elements:

i. Site accommodation, setting up plant, access road, water supply, electricity and general
site arrangements

ii. Office furniture, equipment and communications

iii. Provision towards expenditure on:

(a) Corporate office of contractor

(b) Site supervision

(c) Documentation and "as built" drawings

iv. Mobilisation / de-mobilisation of resources .

v. Labour camps with minimum amenities required as per labour laws and transportation
to work sites

vi. Light vehicles for site supervision including administrative and managerial requirements

vii. Setting up of Laboratories for quality control, field and laboratory testing for control of
quality of various items of work and documentation of test results as per requirement of
the Specifications.

viii. Minor T&P including vibrators for concrete work and survey instruments and setting
outworks, including verification of line, dimensions, taking trial pits and bore holes,
where required.

10
STANDARD DATA BOOK – BUILDING WORK ITEMS – BASIC APPROACH

ix. Watch and ward

x. Arraignment for Traffic and Traffic Management during construction.

xi. Provision towards safeguarding environment

xii. Sundries

xiii. Financing expenditure of the Contractor

xiv. Work Insurance / compensation.

4.1 Sales/Turnover Tax / VAT: Allow 4% and which should be exhibited separately. In
agreements it should be mentioned that it will be reimbursed as per actuals.

5. Contractor’s Profit : It is considered to allow 14% towards over head charges (Item 4) and
Contractor Profits put together.

6. General :

a) The AP Standard Specifications shall be followed with relevant BIS Specifications of


various materials and construction work.

b) The sources of all materials and samples of materials are required to be approved by the
Engineer-in- Charge before starting of the work.

c) For reinforced steel both HYSD and TMT bars continuing to IS 1786 and MS bars upto 36
mm dia as per IS 432 – Part 1 have been considered.

d) The Data includes inputs for testing of soil, materials and works.

e) The contractor shall arrange and to provide and maintain an adequate equipped field
laboratory.

f) Quality Control of Works shall be governed by relevant AP Standard Specifications read


with BIS Specifications.

g) Sundries to cater for unforeseen contingency and miscellaneous items have been added
in the overheads.

h) The various activities of works shall also be documented in photographs and video
cassettes.

i) The Data for various Earth Work Excavation Items including classification of soils shall be
as in Standard Data for Roads and Bridges.

j) The course and fine aggregates shall conform to IS : 383

11
STANDARD DATA BOOK – BUILDING WORK ITEMS – BASIC APPROACH

7. Basic Inputs :

Standard Data Book is based on the requirements of basic inputs of materials, labour and
machineries for various items. The rates for labour, material and usage charges of machinery
for the area where the project is located are to be ascertained from local authorities/enquiries
to prepare Schedule of Rates for the area. The basic rates of materials, such as, stone
boulders, stone for masonry, stone ballast, stone dust, moorum, gravel, lime, manure,
sludge, quarry sweep, kankar, bricks, brick ballast, crushed slag, etc. at quarry / crusher sites
shall be fixed by the Board of Chief Engineers yearly (effective from 1st June to 31st May).
However, the basic rate of materials hand broken / machine broken, crushed aggregates
shall be based on Analysis in Chapter 1 of Roads & Bridges. The cost of materials should
include the cost at source and the cost of their carriage (as per Schedule of rates arrived in
Chapter 1 of Roads & Bridges for conveyance, loading and unloading charges) upto the work
site.

8. Labour

The labour wages should be as per rates fixed by the Board of Chief Engineers keeping the
minimum wages fixed as per Minimum Wages Act. Skilled labour include mason, carpenter,
blacksmith, mechanics and other trades.

9. Materials :

Quantities of materials considered in the rate analysis are approximate for the purpose of
estimation and include normal wastages. Actual consumption would depend on mix design.

The rates of material should include basic cost at locations of stone crushers/factory/rail head
and cost of its carriage to the site of work/plant including loading, unloading and stacking.
Credit for Dismantled Material: The dismantled materials should be examined and a realistic
assessment made for credit for such materials, which can be utilized for works or auctioned.
The basic rates should include all octroi charges, toll tax, sale tax, VAT, municipal taxes and
other local taxes, etc.

10. The Data for the following items of work shall be as per Data Items covered in AP Standard
Data for Roads & Bridges

i. Loading, Unloading, Carriage, Crushing of Materials


ii. Site Clearance
iii. Earth Work Items including classification of Excavated Material.
iv. Horticulture

12
STANDARD DATA BOOK – BUILDING WORK ITEMS – BASIC APPROACH

11. Concrete Items :

For Concrete Work, the Grades of Concrete covered by Data Book is in accordance to IS 456 :
2000. The nominal mix of concrete shall be used upto M 20 Grade only. For RCC Work, M 20
Grade nominal mix may be used in exceptional cases of Remoteness. The design mix shall
invariably used for M 20 and above Grades of Concrete as per IS 456 : 2000. The Data
accounts for inputs of Material by Weight and use of ordinary mixture or ordinary mixer with
weight batch arrangement. The Hire charges for vibrators are included in overhead charges.
10% extra cement may be provided for concreting under water, where ever required. Steel
requirement of cement concrete work is required to be provided separately.

12. Plants and Equipment : The usage charges for machines include ownership charges, cost of
repair and maintenance including replacement of tyres and running and operating charges
which includes crew, fuel and lubricants. The hire charges shall be worked out based on the
Guidelines issued CWC for machinery covered in CWC Guidelines.

13. Measurement and Rates

Measurement of various items and their units shall be as defined in the respective Clauses
of AP Standard Specifications. The rates for various items of work shall include all sub items
defined in the respective Clauses of AP Standard Specifications.

14. Privileged Document

The Standard Data Book is for Department use only. It should not be produced in any court of
law as reference/ authority and to that extent it is a privileged document.

13
STANDARD DATA BOOK – BUILDING WORK ITEMS

Andhra Pradesh Standard Data


BUILDINGS
Sl Rate Amount Rem
Index-code Description Unit Quantity
No Rs. Rs. arks
1 2 3 4 5 6 7
BLD-CSTN- MORTARS
1
BLD-CSTN- 1 Cement Mortar (1 : 1)
1-1
Unit : 1cum
A. MATERIALS:
Cement kg. 1440.00
Sand (including 5% wastage) cum 1.05
Seigniorage charges for sand cum 1.05
B. MACHINERY
- Nil - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20
Grand Total
BLD-CSTN- 2 Cement Mortar (1 : 1.5)
1-2
Unit : 1cum
A. MATERIALS:
Cement kg. 960.00
Sand (including 5% wastage) cum 1.05
Seigniorage charges for sand cum 1.05
B. MACHINERY
- Nil - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20
Grand Total
BLD-CSTN- 3 Cement Mortar (1 : 2)
1-3
Unit : 1cum
A. MATERIALS:
Cement kg. 720.00
Sand (including 5% wastage) cum 1.05
Seigniorage charges for sand cum
B. MACHINERY
- Nil - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20
Grand Total
BLD-CSTN- 4 Cement Mortar (1 : 3)
1-4
Unit : 1cum
A. MATERIALS:
Cement kg. 480.00
Sand (including 5% wastage) cum 1.05
Seigniorage charges for sand cum 1.05
B. MACHINERY
- Nil - -
C. LABOUR:

14
STANDARD DATA BOOK – BUILDING WORK ITEMS

Man mazdoor for mixing mortar day 0.20


Grand Total
BLD-CSTN- 5 Cement Mortar (1 : 4)
1-5
Unit : 1cum
A. MATERIALS:
Cement kg. 360.00
Sand (including 5% wastage) cum 1.05
Seigniorage charges for sand cum 1.05
B. MACHINERY
- Nil - - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20
Grand Total
BLD-CSTN- 6 Cement Mortar (1 : 5)
1-6
Unit : 1cum
A. MATERIALS:
Cement kg. 288.00
Sand (including 5% wastage) cum 1.05
Seigniorage charges for sand cum 1.05
B. MACHINERY
- Nil - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20
Grand Total
BLD-CSTN- 7 Cement Mortar (1 : 6)
1-7
Unit : 1cum
A. MATERIALS:
Cement kg. 240.00
Sand (including 5% wastage) cum 1.05
Seigniorage charges for sand cum 1.05
B. MACHINERY
- Nil - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20
Grand Total
BLD-CSTN- 8 Cement Mortar (1 : 8)
1-8
Unit : 1cum
A. MATERIALS:
Cement kg. 180.00
Sand (including 5% wastage) cum 1.05
Seigniorage charges for sand cum 1.05
B. MACHINERY
- Nil - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20
Grand Total
Excavation for Foundations

15
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- Earth work excavation for foundations and


2 depositing on bank for all lifts and with an
initial lead of 10m including all operational,
incidental, labour charges such as shoring
,sheeting, planking, strutting, etc. complete
for finished item of work including
seigniorage excluding dewatering charges etc
as per SS - 20 B (APSS 308).

BLD-CSTN- 9 Ordinary Soil-Manual Means-Upto 3 m depth


2-1
Unit = cum
Taking output = 10 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 3.64
b&c) Overheads & Contractors Profit
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10
Note : 1. Cost of dewatering may be added, where required, up to 5 per cent of
labour cost. Assessment for dewatering shall be made as per site conditions.
BLD-CSTN- 10 Ordinary soils-Mechcanical Means-Upto 3 m
2-2 depth
Unit = cum
Taking output = 240 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 8.32
b) Machinery
Hydraulic Excavator 1 cum bucket capacity hour 6.00
c&d) Overheads & Contractors Profit
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/240
Note : 1. Cost of dewatering upto 5% of a+b may be added, where required, up to
10 per cent of labour cost. Assessment for dewatering shall be made as per site
conditions.
BLD-CSTN- 11 Ordinary Soils-Mechcanical Means-3 m to 6
2-3 m depth
Unit = cum
Taking output = 210 cum
a) Labour
Mate day -
day 8.32
Mazdoor (Unskilled)
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00
c&d) Overheads & Contractors Profit
Cost for 210 cum = a+b+c+d

16
STANDARD DATA BOOK – BUILDING WORK ITEMS

Rate per cum = (a+b+c+d)/210

Note : Cost of dewatering upto 5 per cent of (a+b) may be added, where required.
Assessment for dewatering shall be made as per site conditions.
BLD-CSTN- 12 Ordinary rock (not requiring blasting)-Manual
2-4 Means-Upto 3 m depth
Unit = cum
Taking output = 10 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 5.20
b&c) Overheads & Contractors Profit
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10
Note : Cost of dewatering upto 5 per cent of labour cost may be added, where
required as per site condition.

BLD-CSTN- 13 Ordinary rock (not requiring blasting)-


2-5 Mechanical Means-Upto 3 m depth
Unit = cum
Taking output = 180 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 6.24
b) Machinery
Hydraulic Excavator 1 cum bucket capacity hour 6.00
c&d) Overheads & Contractors Profit
Cost for 180 cum = a+b+c+d
Rate per cum = (a+b+c+d)/180
Note : 1. Cost of dewatering upto 5% of a+b may be added, where required, up to
10 per cent of labour cost. Assessment for dewatering shall be made as per site
conditions.

BLD-CSTN- 14 Hard rock (requiring blasting)-Upto 3 m


2-6 depth
Unit = cum
Taking output = 10 cum
a) Labour
Mate day -
Driller day 0.50
Blaster day 0.25
Mazdoor (Unskilled) day 8.35
b) Machinery
Air compressor 210 cfm / 250 cfm with 2 jack hour 1
hammers for drilling at 15 cum per hour
c) Material

17
STANDARD DATA BOOK – BUILDING WORK ITEMS

Gelatin 80% kg 3.50


Detonator electric Nos. 14.00
d&e) Overheads & Contractors Profit
Cost for 10 cum = a+b+c+d+e
Rate per cum = a+b+c+d+e)/10
Note : 1. Cost of dewatering @ 5 per cent of
(a+b) may be added, where required as per
site condition.
BLD-CSTN- 15 Hard rock (blasting prohibited)-Upto 3 m
2-7 depth

Unit = cum
Taking output = 10 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 5.20
b) Machinery
Air compressor 210 cfm / 250 cfm with 2 jack hour 6.00
hammers of pneumatic breaker at 1 cum per
hour
c) & d) Overheads & Contractors Profit
Cost for 10 cum = a+b+c+d
Rate per cum = a+b+c+d)/10
Note : Cost of dewatering up to 5 per cent of
(a+b) may be added, where required as per
site conditions.
Filling with useful available excavated earth
(excluding rock) in trenches, sides of
foundations and basement with initial lead in
layers not exceeding 15 cm thick,
consolidating each deposited layer by
watering and ramming including cost and
conveyance of water to work site and all
operational, incidental, labour charges, hire
charges of T & P etc., complete for finished
item of work. (APSS NO. 309 & 310)

BLD-CSTN- 16 Sand filling


2-8
Unit = cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 0.31
b) Material
Sand cum 1.00
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
BLD-CSTN- 17 Earth filling (ordinary soil)
2-9
Unit = cum

18
STANDARD DATA BOOK – BUILDING WORK ITEMS

Taking output = 6 cum


a) Labour
Mate day -
Mazdoor (Unskilled) day 3.12
b) & c) Overheads & Contractors Profit
Cost for 6 cum = a+b+c
Rate per cum = (a+b+c)/6
Note : Cost of transportation of good quality earth has not been included. Only
labour for carrying carted earth with a lead of 50 m to the foundation pits has been
taken in the rate. The cost of carted earth/ sand may be worked out separately if
the same is not available from the adjoining area.

BLD-CSTN- CONCRETE, DAMP PROOF COURSE &


3 REINFORCEMENT
BLD-CSTN- 18 Plain Cement concrete Grade M20 - Nominal
3-1 Mix
using 20mm metal with hand mixing
Unit : 1cum
A. MATERIALS:
Cement Kg 400.00
Coarse aggregate 20mm cum 0.90
Fine aggregate (Sand) cum 0.45
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
B. LABOUR:
st
Mason 1 class day 0.10
Mazdoor (unskilled) day 2.36
Water (including for curing) kl 1.20
Grand Total
Note : For Nominal Mix : Considering table 9 IS 456 :
2000, the quantity of cement needed is 405 kgs / cum.
Hence proposed 400 kgs of cement for cum of CC M20
BLD-CSTN- 19 Plain Cement concrete Grade M10 - Nominal
3-2 Mix upto Plinth level
using 40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement Kg 220.00
Coarse aggregate 40mm cum 0.90
Fine aggregate (Sand) cum 0.45
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
Water (including for curing) kl 1.20
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.00
capacity
C. LABOUR:
st
Mason 1 class day 0.10
Mazdoor (unskilled) day 1.39
Grand Total

19
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 20 PCC Grade M15 - Nominal mix 1:2.5:5 (Hand


3-3 mixing)
Unit = 1cum
A) Material
Cement kg 275.00
Coarse sand cum 0.48
40 mm aggregate cum 0.54
20 mm aggregate cum 0.27
10 mm aggregate cum 0.09
Water (including for curing) kl 1.20
B) Labour
Mason (1st Class) day 0.10
Mazdoor (Unskilled) day 2.36
Grand Total
BLD-CSTN- 21 Plain Cement concrete (1:4:8) using 40 mm
3-4 metal with hand mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement kg 162.00
Coarse aggregate 40 mm cum 0.90
Fine aggregate (Sand) cum 0.45
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
Water (including for curing) kl 1.20
B. LABOUR:
st
Mason 1 class day 0.10
Mazdoor (unskilled) day 2.36
Grand Total
BLD-CSTN- 22 Plain Cement concrete (1:4:8) using 40 mm
3-5 metal with concrete mixture. All work
upto plinth level.
Unit = 1cum
A. MATERIALS:
Cement kg 162.00
Coarse aggregate 40 mm cum 0.90
Fine aggregate (Sand) cum 0.45
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
Water (including for curing) kl 1.20
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.00
capacity
C. LABOUR:
st
Mason 1 class day 0.10
Mazdoor (unskilled) day 1.39
Water Charges 1% -
Grand Total
BLD-CSTN- 23 Plain Cement concrete (1:5:10) using 40 mm
3-6 metal with hand mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement kg 129.60

20
STANDARD DATA BOOK – BUILDING WORK ITEMS

Coarse aggregate 40 mm cum 0.90


Fine aggregate (Sand) cum 0.45
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
Water (including for curing) kl 1.20
B. LABOUR:
st
Mason 1 class day 0.10
Mazdoor (unskilled) day 2.36
Grand Total
BLD-CSTN- 24 Plain Cement concrete (1:5:10) using 40 mm
3-7 metal with Concrete mixture. All work upto
plinth level.
Unit = 1cum
A. MATERIALS:
Cement kg 129.60
Coarse aggregate 40 mm cum 0.90
Fine aggregate (Sand) cum 0.45
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
Water (including for curing) kl 1.20
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.00
capacity
C. LABOUR:
st
Mason 1 class day 0.10
Mazdoor (unskilled) day 1.39
Grand Total
BLD-CSTN- 25 Plain Cement concrete (1:6:10) using 40 mm
3-8 metal with hand mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement kg 129.60
Coarse aggregate 40 mm cum 0.90
Fine aggregate (Sand) cum 0.54
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.54
Water (including for curing) kl 1.20
B. LABOUR:
st
Mason 1 class day 0.10
Mazdoor (unskilled) day 2.36
Grand Total
BLD-CSTN- 26 Plain Cement concrete (1:6:10) using 40 mm
3-9 metal with Concrete mixture upto Plinth level

Unit = 1cum
A. MATERIALS:
Cement kg 129.60
Coarse aggregate 40 mm cum 0.90
Fine aggregate (Sand) cum 0.54
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.54
Water (including for curing) kl 1.20

21
STANDARD DATA BOOK – BUILDING WORK ITEMS

B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.00
capacity
C. LABOUR:
st
Mason 1 class day 0.10
Mazdoor (unskilled) day 1.39
Grand Total
BLD-CSTN- 27 Plain Cement concrete - Nominal Mix (1:3:6)
3-10
using 40mm metal with hand mixing
Unit : 1cum
A. MATERIALS:
Cement Kg 220.00
Coarse aggregate 40mm cum 0.90
Fine aggregate (Sand) cum 0.45
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
Water (including for curing) kl 1.20
B. LABOUR:
st
Mason 1 class day 0.10
Mazdoor (unskilled) day 2.36
Grand Total
BLD-CSTN- 28 Plain Cement concrete (M 20) Nominal Mix
3-11 using 40mm metal using concrete mixer

Unit : 1cum
A. MATERIALS:
Cement Kg 330.00
Coarse aggregate 40mm graded cum 0.90
Fine aggregate (Sand) cum 0.45
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
Water (including for curing) kl 1.20
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.00
capacity
C. LABOUR:
st
Mason 1 class day 0.10
Mazdoor (unskilled) day 1.39
Grand Total
BLD-CSTN- 29 Plain Cement concrete (M 15) Nominal Mix
3-12 1:2.5:5
using 40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement Kg 275.000
Coarse aggregate 40mm cum 0.540
Coarse aggregate 20mm cum 0.270
Coarse aggregate 10mm cum 0.090
Fine aggregate (Sand) cum 0.480
Seigniorage charges for C.A cum 0.900
Seigniorage charges for F.A cum 0.480

22
STANDARD DATA BOOK – BUILDING WORK ITEMS

Water (including for curing) kl 1.20


B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.000
capacity
C. LABOUR:
st
Mason 1 class day 0.100
Mazdoor (unskilled) day 1.390
Grand Total
BLD-CSTN- 30 R.C.C. M-20 Nominal Mix
3-13
RCC M- 20 Nominal mix (Cement:fine
aggregate: coarse aggregate) corresponding
to Table 9 of IS 456 using 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including
cost and conveyance of all materials like
cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on
all materials including all operational,
incidental and labour charges such as
machine mixing, laying concrete, curing
etc.,complete but excluding cost of steel and
its fabrication charges for finished item of
work, but excluding centering, shuttering.

A FOUNDATIONS, PLINTH, PEDESTALS (Below


Plinth)
A. MATERIALS:
20mm HBG graded metal cum 0.900
Sand cum 0.450
Cement Kgs 400.000
B. LABOUR:
1st Class Mason day 0.133
2nd Class Mason day 0.267
Mazdoor (Both Men and Women) day 3.600
C. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.000
capacity
Vibrator hire charges hour 1.000
Water (including for curing) kl 1.200
BASIC COST per 1 cum
B COLUMNS, LINTELS, WATER TANKS, RCC
WALLS IN BUILDINGS
A. MATERIALS:
20mm HBG graded metal cum 0.900
Sand cum 0.450
Cement Kgs 400.000
B. LABOUR:
1st Class Mason day 0.167
2nd Class Mason day 0.167
Mazdoor (Both Men and Women) day 4.700
C. MACHINERY

23
STANDARD DATA BOOK – BUILDING WORK ITEMS

Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.000


capacity
Vibrator hire charges hour 1.000
Water (including for curing) kl 1.200
BASIC COST per 1 cum
C RCC SLABS, BEAMS
A. MATERIALS:
20mm HBG graded metal cum 0.900
Sand cum 0.450
Cement Kgs 400.000
B. LABOUR:
1st Class Mason day 0.067
2nd Class Mason day 0.133
Mazdoor (Both Men and Women) day 2.500
C. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 0.267
capacity
Vibrator hire charges hour 0.267
Water (including for curing) kl 1.200
BASIC COST per 1 cum
31 DESIGN MIX CONCRETE (WEIGH BATCH at
SITE)
Supply and placing of the Design Mix
Concrete corresponding to IS 456 using
WEIGH BATCHER / MIXER with 20mm size
graded machine crushed hard granite metal
(coarse aggregate) from approved quarry
including cost and conveyance of all
materials like cement, fine aggregate (sand)
coarse aggregate, water etc., to site and
including Seigniorage charges, sales & other
taxes on all materials including all
operational, incidental and labour charges
such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication
charges for finished item of work (APSS No.
402)with minimum cement content as per IS
code from standard suppliers approved by
the department including pumping,
centering, shuttering, laying concrete,
vibrating, curing etc. complete but excluding
cost of steel and its fabrication charges for
finished item of work.

BLD-CSTN- A FOUNDATIONS, PLINTH, PEDESTALS (Below Excluding Cement cost


3-14 Plinth)
ANY GRADE OF MIX
A. MATERIALS:
20mm HBG graded metal cum 0.80
Sand cum 0.40
B. LABOUR:
1st Class Mason day 0.133

24
STANDARD DATA BOOK – BUILDING WORK ITEMS

2nd Class Mason day 0.267


Mazdoor (Both Men & Women) day 4.600
C. MACHINERY
Weigh Batcher Hire charges (Machine mixing) hour 1.333
charges
Vibrator hire charges hour 1.333
Water (including for curing) Kl 1.200
BASIC COST per 1 cum
BLD-CSTN- B COLUMNS, LINTELS, WATER TANKS, RCC
3-15 WALLS IN BUILDINGS
ANY GRADE OF MIX
A. MATERIALS:
20mm HBG graded metal cum 0.80
Sand cum 0.40
B. LABOUR:
1st Class Mason day 0.167
2nd Class Mason day 0.167
Mazdoor (Both Men & Women) day 5.600
C. MACHINERY
Weigh Batcher Hire charges (Machine mixing) hour 1.333
charges
Vibrator hire charges hour 1.333
Water (including for curing) kl 1.200
BASIC COST per 1 cum
BLD-CSTN- C RCC SLABS, BEAMS
3-16
ANY GRADE OF MIX
A. MATERIALS:
20mm HBG graded metal cum 0.80
Sand cum 0.40
B. LABOUR:
1st Class Mason day 0.067
2nd Class Mason day 0.133
Mazdoor (Both Men & Women) day 3.077
C. MACHINERY
Weigh Batcher Hire charges (Machine mixing) hour 0.308
charges
Vibrator hire charges hour 0.308
Water (including for curing) kl 1.200
BASIC COST per 1 cum
DESIGN MIX CONCRETE (BATCHING PLANT at
site)
BLD-CSTN- D FOUNDATIONS, PLINTH, PEDESTALS (Below
3-17 Plinth)
Unit : 1cum
A. MATERIALS:
Coarse aggregate 20mm graded cum 0.80
Fine aggregate (Sand) cum 0.40
Seigniorage charges for C.A cum 0.80
Seigniorage charges for F.A cum 0.40
Water (including for curing) kl 1.20
B. MACHINERY

25
STANDARD DATA BOOK – BUILDING WORK ITEMS

Batching plant at 20 cum per hour hour 0.222


Transit mixer 4cum capacity for lead upto hour 0.222
1km
Concrete Pump day 0.222
C. LABOUR:
st
Mason 1 class day 0.056
nd
Mason 2 class day 0.056
Mazdoor (unskilled) day 0.917
Grand Total
Note : Wherever concrete is carried out using
batching plant, transit mixer, concrete pump,
then Admixtures @ 0.4% of weight of cement
may be added for achieving desired slump of
concrete. If concentrated Admixture is
proposed, only 0.04% of weight of Cement
shall be used.
BLD-CSTN- E COLUMNS, LINTELS, WATER TANKS, RCC
3-18 WALLS IN BUILDINGS
Unit : 1cum
A. MATERIALS:
Coarse aggregate 20mm graded cum 0.80
Fine aggregate (Sand) cum 0.40
Seigniorage charges for C.A cum 0.80
Seigniorage charges for F.A cum 0.40
Water (including for curing) kl 1.20
B. MACHINERY
Batching plant at 20 cum per hour hour 0.444
Transit mixer 4cum capacity for lead upto hour 0.444
1km
Concrete Pump day 0.444
C. LABOUR:
st
Mason 1 class day 0.111
nd
Mason 2 class day 0.222
Mazdoor (unskilled) day 1.556
Grand Total
BLD-CSTN- F RCC SLABS, BEAMS
3-19
Unit : 1cum
A. MATERIALS:
Coarse aggregate 20mm graded cum 0.80
Fine aggregate (Sand) cum 0.40
Seigniorage charges for C.A cum 0.80
Seigniorage charges for F.A cum 0.40
Water (including for curing) kl 1.20
B. MACHINERY
Batching plant at 20 cum per hour hour 0.133
Transit mixer 4cum capacity for lead upto hour 0.133
1km
Concrete Pump day 0.133
C. LABOUR:
st
Mason 1 class day 0.033
nd
Mason 2 class day 0.067

26
STANDARD DATA BOOK – BUILDING WORK ITEMS

Mazdoor (unskilled) day 0.433


Note : Quantity of cement proposed for various
design mixes is for estimating purpose only. Actual
quantity of cement will be as per approved mix design.
Similarly quantity for coarse and fine aggregates is for
estimating purpose and the exact quantity shall be as
per the mix design. Nominal mix of grades M20 is to
be used with adequate supervision and quality control
requirements.

For Design mix concrete, allow Cement as Grade Kgs


follows (for estimate purpose only) :
M 20 350
M 25 380
M 30 400
M 35 420
M 40 430
BLD-CSTN- 32 Damp proof course 40mm thick with cement
3-20 concrete (1:2:4 Nominal mix), using 12mm
hard broken stone aggregate including cost
of all materials, seigniorage charges,
excluding conveyance charges of materials,
including the cost of machinery, labour
charges, mixing, placing in position, leveling,
vibrating, curing etc. complete for finished
item of work. (Using concrete mixer)

Unit = 25 sqm
A. MATERIALS:
Cement kgs 320.00
Coarse aggregate 12mm cum 0.90
Fine aggregate (sand) cum 0.45
Seigniorage charges of coarse aggregate cum 0.90
Seigniorage charges of sand cum 0.45
Form work L.S.
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.00
capacity
C. LABOUR:
st
Mason 1 class day 0.1
Mazdoor (unskilled) day 1.98
D. Grand Total for 25 sqm
Rate per Sqm = D/25
BLD-CSTN- 33 Damp proof course 50mm thick with 1:2:4
3-21 cement concrete Nominal mix, using 12mm
hard broken stone aggregate including cost
of all materials, seigniorage charges,
excluding conveyance charges of materials
including the cost of machinery, labour
charges, mixing, placing in position, leveling,
vibrating, curing etc. complete for finished
item of work. (Using concrete mixer)

Unit = 20 sqm
A. MATERIALS:

27
STANDARD DATA BOOK – BUILDING WORK ITEMS

Cement kgs 320.00


Coarse aggregate 12mm cum 0.90
Fine aggregate (sand) cum 0.45
Seigniorage charges of coarse aggregate cum 0.90
Seigniorage charges of sand cum 0.45
Form work L.S.
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.00
capacity
C. LABOUR:
st
Mason 1 class day 0.1
Mazdoor (unskilled) day 1.98
D. Grand Total for 20 sqm
Rate per Sqm = D/20
BLD-CSTN- 34 Supplying, fitting and placing HYSD bar
4-1 reinforcement in foundation complete as per
drawings and technical specifications for Bars
below 36 mm dia including over laps and
wastage, where they are not welded
Unit = MT
(a) Material
HYSD bars including 5 per cent for overlaps MT 1.05
and wastage
Binding wire kg 6.00
(b) Labour for cutting, bending, shifting to
site, tying and placing in position
Blacksmith / Bar bender day 2.00
Mazdoor (Unskilled) day 6.40
Sundries on Material
Rate per t = a+b+c+d
35 Supplying, fitting and placing HYSD bar
reinforcement in VRCC works complete
including wastage, as per drawings and
technical specifications Clauses 1000 and
1202 MORD & 1100, 1600 MORTH for Bars
36 mm dia and above, where welding
required to be done compulsorily.
Unit = t
(a) Material
HYSD bars including 2.5 per cent for wastage t 1.025
Welding Electrodes @ 5 per joint (14 joints / each 70.000
ton)
Welding Charges (Hire charges of Welding Hr 10.00
Machine)
Binding wire kg 6.00
(b) Labour for cutting, bending, shifting to
site, tying and placing in position
Welder day 2.50
Blacksmith day 2.00
Mazdoor (Unskilled) day 6.40
(c) Overheads on (a+b)
(d) Contractor’s profit on (a+b+c)

28
STANDARD DATA BOOK – BUILDING WORK ITEMS

Rate per t = a+b+c+d


BLD-CSTN- 36 Supplying, fitting and placing TMT bar
4-2 reinforcement in VRCC works complete as
per drawings and technical specifications for
Bars below 36 mm dia including over laps and
wastage, where they are not welded.

Unit = t
(a) Material
TMT bars including 5 per cent for overlaps t 1.05
and wastage
Binding wire kg 6.00
(b) Labour for cutting, bending, shifting to
site, tying and placing in position
Blacksmith / Bar bender day 2.00
Mazdoor (Unskilled) day 6.40
(c) Overheads on (a+b)
(d) Contractor’s profit on (a+b+c)
Rate per t = a+b+c+d
37 Supplying, fitting and placingTMT bar
reinforcement in VRCC works complete
including wastage, as per drawings and
technical specifications Clauses 1000 and
1202 MORD & 1100, 1600 MORTH for Bars
36 mm dia and above, where welding
required to be done compulsorily.
Unit = t
(a) Material
TMT bars including 2.5 per cent for wastage t 1.025

Welding Electrodes @ 5 per joint (14 joints / each 70.000


ton)
Welding Charges (Hire charges of Welding Hr 10.00
Machine)
Binding wire kg 6.00
(b) Labour for cutting, bending, shifting to
site, tying and placing in position
Welder day 2.50
Blacksmith day 2.00
Mazdoor (Unskilled) day 6.40
(c) Overheads on (a+b)
(d) Contractor’s profit on (a+b+c)
Rate per t = a+b+c+d
BLD-CSTN- 38 Supplying, fitting and placing MS bar
4-3 reinforcement in VRCC works complete as
per drawings and technical specifications for
Bars below 36 mm dia including over laps and
wastage, where they are not welded
Unit = t
(a) Material
MS bars including 5 per cent for overlaps and t 1.05
wastage
Binding wire kg 6.00

29
STANDARD DATA BOOK – BUILDING WORK ITEMS

(b) Labour for cutting, bending, shifting to


site, tying and placing in position
Blacksmith / Bar bender day 2.00
Mazdoor (Unskilled) day 6.40
(c) Overheads on (a+b)
(d) Contractor’s profit on (a+b+c)
Rate per t = a+b+c+d
BLD-CSTN- BRICK WORK, HONEY - COMBWORK
5
BLD-CSTN- 39 Brick Masonry in CM (1:3) with Bricks with
5-1 traditional size 23 x 11 x 7 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement kg 96.00
Bricks traditional size 23 x 11 x 7 cms 2nd Nos 512.00
class
Fine aggregate (Sand) cum 0.20
Seigniorage charges for F.A cum 0.20
B. LABOUR:
st
Mason 1 class day 0.24
nd
Mason 2 class day 0.56
Mazdoor (unskilled) day 1.89
Grand Total
Note : For Bricks 2.4 % wastage taken.
BLD-CSTN- 40 Brick Masonry in CM (1:4) with Bricks
5-2 traditional size 23 x 11 x 7 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement kg 72.00
Bricks traditional size 23 x 11 x 7 cms 2nd Nos 512.00
class
Fine aggregate (Sand) cum 0.20
Seigniorage charges for F.A cum 0.20
B. LABOUR:
st
Mason 1 class day 0.24
nd
Mason 2 class day 0.56
Mazdoor (unskilled) day 1.89
Grand Total
BLD-CSTN- 41 Brick Masonry in CM (1:5) with Bricks
5-3 traditional size 23 x 11 x 7 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement kg 57.60
Bricks traditional size 23 x 11 x 7 cms 2nd Nos 512.00
class
Fine aggregate (Sand) cum 0.20
Seigniorage charges for F.A cum 0.20
B. LABOUR:
st
Mason 1 class day 0.24
nd
Mason 2 class day 0.56
Mazdoor (unskilled) day 1.89

30
STANDARD DATA BOOK – BUILDING WORK ITEMS

Grand Total
BLD-CSTN- 42 Brick Masonry in CM (1:6) with 2nd class
5-4 Bricks traditional size 23 x 11 x 7 cms
Unit = 1cum
A. MATERIALS:
Cement kg 48.00
Bricks traditional size 23 x 11 x 7 cms 2nd Nos 512.00
class
Fine aggregate (Sand) cum 0.20
Seigniorage charges for F.A cum 0.20
B. LABOUR:
st
Mason 1 class day 0.24
nd
Mason 2 class day 0.56
Mazdoor (unskilled) day 1.89
Grand Total
BLD-CSTN- 43 Brick Masonry in CM (1:8) with Bricks
5-5 traditional size 23 x 11 x 7 cms 2nd Class
Unit = 1cum
A. MATERIALS:
Cement kg 36.00
Bricks traditional size 23 x 11 x 7 cms 2nd Nos 512.00
class
Fine aggregate (Sand) cum 0.20
Seigniorage charges for F.A cum 0.20
B. LABOUR:
st
Mason 1 class day 0.24
nd
Mason 2 class day 0.56
Mazdoor (unskilled) day 1.89
Grand Total
Note : 1. When Mortar mix is changed as CM 1:4, 1:5,
1:6 and 1:8, proportionate quantity of cement has to
be substituted. No change in other data.
2. When First class Modular Bricks are used provide
570 nos bricks of size 19 x 9 x 9 cms.
BLD-CSTN- 44 Brick Masonry in CM (1:3) with Modular
5-6 Bricks 19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement kg 100.60
Bricks modular size 19 x 9 x 9 cms 2nd class Nos 520.00

Fine aggregate (Sand) cum 0.21


Seigniorage charges for F.A cum 0.21
B. LABOUR:
st
Mason 1 class day 0.24
nd
Mason 2 class day 0.56
Mazdoor (unskilled) day 1.89
Grand Total
BLD-CSTN- 45 Brick Masonry in CM (1:4) with Modular
5-7 Bricks 19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:

31
STANDARD DATA BOOK – BUILDING WORK ITEMS

Cement kg 75.60
Bricks modular size 19 x 9 x 9 cms 2nd class Nos 520.00

Fine aggregate (Sand) cum 0.21


Seigniorage charges for F.A cum 0.21
B. LABOUR:
st
Mason 1 class day 0.24
nd
Mason 2 class day 0.56
Mazdoor (unskilled) day 1.89
Grand Total
BLD-CSTN- 46 Brick Masonry in CM (1:5) with Modular
5-8 Bricks 19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement kg 60.48
Bricks modular size 19 x 9 x 9 cms 2nd class Nos 520.00

Fine aggregate (Sand) cum 0.21


Seigniorage charges for F.A cum 0.21
B. LABOUR:
st
Mason 1 class day 0.24
nd
Mason 2 class day 0.56
Mazdoor (unskilled) day 1.89
Grand Total
BLD-CSTN- 47 Brick Masonry in CM (1:6) with Modular
5-9 Bricks 19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement kg 50.40
Bricks modular size 19 x 9 x 9 cms 2nd class Nos 520.00

Fine aggregate (Sand) cum 0.21


Seigniorage charges for F.A cum 0.21
B. LABOUR:
st
Mason 1 class day 0.24
nd
Mason 2 class day 0.56
Mazdoor (unskilled) day 1.89
Grand Total
BLD-CSTN- 48 Brick Masonry in CM (1:8) with Modular
5-10 Bricks 19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement kg 37.80
Bricks modular size 19 x 9 x 9 cms 2nd class Nos 520.00

Fine aggregate (Sand) cum 0.21


Seigniorage charges for F.A cum 0.21
B. LABOUR:
st
Mason 1 class day 0.24
nd
Mason 2 class day 0.56
Mazdoor (unskilled) day 1.89

32
STANDARD DATA BOOK – BUILDING WORK ITEMS

Grand Total
BLD-CSTN- 49 11.5 cm wide Brick masonry for super-
5-11 structure on ground floor in cm (1:3) using
second class traditional size bricks including
cost of all materials, seigniorage charges,
labour and all operations for constructing
half brick masonry, mixing cement mortar,
curing etc., complete for finished item of
work, but excluding conveyance charges of
materials.

unit:10sqm
A. MATERIALS:
Country bricks, second class traditional size nos 565.000
23x11x7cm
Cement kg. 106.000
Sand cum 0.220
Seigniorage charges for sand cum 0.220
B. LABOUR:
st
Mason 1 class day 0.600
nd
Mason 2 class day 0.600
Mazdoor (unskilled) day 2.750
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 50 Reinforced Brick Masonary walls of 11.5cm in
5-12 CM(1:6) using 2nd bricks having a crushing
strength of not less than 35.00kg/cm2 and
using two mild steel bars of 6m dia in every
third layer of brick masory, with free joints of
the main block work including cost and
seignorage charges and conveyance of all
materials and water from approved sources
to work site and all operational, incidental,
labour charges such as scaffolding mixing
mortor constructing masonary lift charges,
curing etc. complete but excluding the cost of
steel and its fabrication charges for finished
item of work as per SS 509

Ground Floor :
A. MATERIALS:
II Class Bricks Nos 512.000
C.M.(1:6) cum 0.200
B. LABOUR:
st
Mason 1 class day 0.600
nd
Mason 2 class day 0.600
Mazdoor (unskilled) day 2.750
Grand Total

33
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 51 Exposed brick masonry for super structure on


5-13 ground floor in cm (1:6) using wire cut bricks
or moulded bricks including making
horizontal and vertical grooves 10mm Wide
12mm deep, cost of all materials, seigniorage
charges, labour and all operations, mixing
cement mortar, curing etc., complete for
finished item of work, but excluding
conveyance charges of materials

unit:1cum
A. MATERIALS:
Wire cut bricks or moulded bricks size nos 520.000
19x9x9cm
Cement kg. 48.00
Sand cum 0.20
Seigniorage charges for sand cum 0.20
B. LABOUR:
st
Mason 1 class day 0.57
nd
Mason 2 class day 0.57
Mazdoor (unskilled) day 2.54
Add water charges 1% 1.00%
Grand Total
Note : Compressive strength of individual
2
Brick shall not be less than 70 kg / cm
BLD-CSTN- 52 Brickwork in arches in cement mortar 1:4
5-14 complete including centering and shuttering
excluding pointing and plastering as per
drawing and technical specifications Clauses
606 and 1205.1 MORD

Unit = cum
a) Material
Wire cut bricks or moulded bricks size Nos. 525.00
19x9x9cm
Cement mortar (1:4) cum 0.24
b) Labour
Mazdoor (Unskilled) day 1.88
Mason (1st Class) day 2.00
c) Add for centering and shuttering @ 110%
of (a+b)
Grand Total
Note : 1 ) In case cement mortar 1:3 is used, proportionate rate is to be adopted.
2) Quantity of bricks for arches will be about 10 per cent more than that for
ordinary brickwork .
3) In case special arch bricks are used, the quantity of bricks per cum shall be taken
as 580 Nos.
4) Rates for spandrel walls shall be taken same as for brickwork in substructure.
5) Rate for spandrel filling will depend on the filling material adopted
BLD-CSTN- 53 Honey Comb work with Bricks of traditional
5-15 Size and Plastered One Coat 10 mm. thick
Cement Mortar 1:5 including White Washing
2 Coats
Unit = cum

34
STANDARD DATA BOOK – BUILDING WORK ITEMS

a) Material
Brick 2nd class 23 x 11 x 7 Nos. 750.00
Cement mortar (1:5) cum 0.67
b) Labour
Mazdoor (Unskilled) day 6.60
Mason (1st Class) day 2.41
Mason (2nd Class) day 6.21
White Washing 2 Coats LS LS
Grand Total
BLD-CSTN- 54 Honey Comb work with Bricks of Modular
5-16 Size and Plastered One Coat 10 mm. thick
Cement Mortar 1:5 including White Washing
2 Coats
Unit = cum
a) Material
Brick 2nd class 19 x 9 x 9 Nos. 790.00
Cement mortar (1:5) cum 0.67
b) Labour
Mazdoor (Unskilled) day 6.60
Mason (1st Class) day 2.41
Mason (2nd Class) day 6.21
White Washing 2 Coats LS LS
Grand Total
BLD-CSTN- 55 Masonry work in CM (1:8) prop with Flyash
5-17 Cement solid blocks of size 290 x 225 x 140
mm for manufacturing of flyash solid blocks
using flyash of 80 kgs, cement of 15 kgs.
Gypsum of 5 kgs. and stone dust including
cost and conveyance of all materials, labour
charges, seiniorage charges, scaffolding and
curing etc., cpomplete with a compresive
strength not lessthan 50 kg/sqm for walls for
Superstructure Walls.

Ground Floor
Unit = 1 cum
A. MATERIALS:
No of blocks required for one cum of Nos 110.000
Masonry
Cost of Cement Mortar (1:6) cum 0.100
B. LABOUR
Mason 1st class day 0.420
Mason 2nd class day 0.920
Man Mazdoor day 0.700
Woman Mazdoor day 2.100
Total
BLD-CSTN- STONE MASONRY, DAMP PROOF COURSE,
6 DRY STONE PACKING, QUARRY RUBBISH &
GRAVEL BACKING
BLD-CSTN- 56 Cut Stone Masonry in CM 1:2
6-1
Unit = 1cum
A. MATERIALS:
Cement kg 115.20

35
STANDARD DATA BOOK – BUILDING WORK ITEMS

Cut Stone Roughly dressed to shape at quarry cum 0.89


Bond Stones cum 0.16
Fine aggregate (Sand) cum 0.16
Seigniorage charges for F.A cum 0.16
B. LABOUR:
st
Mason 1 class day 1.05
nd
Mason 2 class day 2.45
Man mazdoor day 3.50
Woman mazdoor day 2.80
Grand Total
Note : When Mortar mix is changed as CM 1:3, 1:4,
1:5, 1:6 and 1:8, proportionate quantity of cement has
to be substituted. No change in other data.
BLD-CSTN- 57 CRS Masonry in CM (1:2) 1st Sort
6-2
Unit = 1cum
A. MATERIALS:
Cement kg 201.60
Coursed Rubble Stone cum 0.94
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 7Nos. 0.16
0.16cum
Fine aggregate (Sand) cum 0.28
Seigniorage charges for F.A cum 0.28
Seigniorage charges for Stone cum 1.10
B. LABOUR:
st
Mason 1 class day 2.50
Mazdoor (unskilled) day 2.32
Grand Total
BLD-CSTN- 58 CRS Masonry in CM (1:3) 1st Sort
6-3
Unit = 1cum
A. MATERIALS:
Cement kg 134.40
Coursed Rubble Stone cum 0.94
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 7Nos. 0.16
0.16cum
Fine aggregate (Sand) cum 0.28
Seigniorage charges for F.A cum 0.28
Seigniorage charges for Stone cum 1.10
B. LABOUR:
st
Mason 1 class day 2.50
Mazdoor (unskilled) day 2.32
Grand Total
BLD-CSTN- 59 CRS Masonry in CM (1:4) 1st Sort
6-4
Unit = 1cum
A. MATERIALS:
Cement kg 100.80
Coursed Rubble Stone cum 0.94
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 7Nos. 0.16
0.16cum
Fine aggregate (Sand) cum 0.28

36
STANDARD DATA BOOK – BUILDING WORK ITEMS

Seigniorage charges for F.A cum 0.28


Seigniorage charges for Stone cum 1.10
B. LABOUR:
st
Mason 1 class day 2.50
Mazdoor (unskilled) day 2.32
Grand Total
BLD-CSTN- 60 CRS Masonry in CM (1:6) 1st Sort
6-5
Unit = 1cum
A. MATERIALS:
Cement kg 67.20
Coursed Rubble Stone cum 0.94
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 7Nos. 0.16
0.16cum
Fine aggregate (Sand) cum 0.28
Seigniorage charges for F.A cum 0.28
Seigniorage charges for Stone cum 1.10
B. LABOUR:
st
Mason 1 class day 2.50
Mazdoor (unskilled) day 2.32
Grand Total
BLD-CSTN- 61 CRS Masonry in CM (1:6) 2nd Sort
6-6
Unit = 1cum
A. MATERIALS:
Cement kg 76.80
Coursed Rubble Stone cum 0.94
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = cum 0.16
0.16cum
Fine aggregate (Sand) cum 0.32
Seigniorage charges for F.A cum 0.32
Seigniorage charges for Stone cum 1.10
B. LABOUR:
st
Mason 1 class day 1.50
Mazdoor (unskilled) day 2.32
Grand Total
Note : When Mortar mix is changed proportionate
quantity of cement has to be substituted. No change in
other data.
BLD-CSTN- 62 Coursed rubble stone masonry arch (Ist sort)
6-7 in cement mortar (1:4) complete including
centering etc. complete as per drawing and
technical specifications Clauses 706 and
1205.1
Unit = cum
A. Material
Stone for CR masonry 1st sort cum 0.94
Through and bond stone (7 Nos Nos. 0.16
0.24x0.24x0.39 = 0.16 cum)
Cement mortar (Rate as in item 11.5 II) cum 0.30
B. Labour
Mason (1st Class) day 3.00

37
STANDARD DATA BOOK – BUILDING WORK ITEMS

Mazdoor (Unskilled) day 2.43


C. Add for centering and shuttering @ 100 %
of (a+b)
Grand Total
Note : 1) In case cement mortar 1:3 is used,
proportionate rate is to be adopted.
2) The addition for centering and sluttering at (c)
above is for arch above 6 m span. For lesser span
length the addition shall be 80 per cent for span above
4 m length and 50 per cent for spans less than 4 m.

BLD-CSTN- 63 Ashlar Arch Work in Cement Mortar (1:4)


6-8
Unit = 1cum
A. MATERIALS:
Cement kg 57.60
Cut Stone Roughly dressed to shape at quarry cum 0.89

Bond Stones of Cutstone quality 0.16


Fine aggregate (Sand) cum 0.16
Seigniorage charges for F.A cum 0.16
B. LABOUR:
st
Mason 1 class day 5.05
nd
Mason 2 class day 2.45
Mazdoor (unskilled) day 6.30
Centering Charges LS
Grand Total
BLD-CSTN- 64 Rubble Arch Work in Cement Mortar (1:4)
6-9
Unit = 1cum
A. MATERIALS:
Cement kg 100.80
Seleted Stone of sizes as per specification cum 1.15
(including Bond Stones)
Fine aggregate (Sand) cum 0.28
Seigniorage charges for F.A cum 0.28
B. LABOUR:
st
Mason 1 class day 0.90
nd
Mason 2 class day 2.10
Mazdoor (unskilled) day 2.43
Centering Charges LS
Grand Total
65 Providing & Laying reinforced cement
concrete arch complete including centering
and shuttering excluding reinforcement as
per drawings and technical specifications
Clauses 800, 900 and 1205.1
Unit = cum
BLD-CSTN- RCC grade M20 nominal mix
6-10
a) Material
Cement t 0.40

38
STANDARD DATA BOOK – BUILDING WORK ITEMS

Coarse sand cum 0.45


20 mm aggregate cum 0.54
10 mm aggregate cum 0.36
b) Labour
Mason (1st Class) day 0.20
Mazdoor (Unskilled) day 2.15
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40
d) Add for cost of centering and shuttering as
per the rates worked out on relevant data
items
Grand Total
BLD-CSTN- 66 RCC Grade M 25 (Design mix)
6-11
a) Material
Cement t 0.38
Coarse sand cum 0.45
20 mm aggregate cum 0.54
10 mm aggregate cum 0.36
b) Labour
Mason (1st Class) day 0.20
Mazdoor (Unskilled) day 2.15
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40
d) Add for cost of centering and shuttering as
per the rates worked out on relevant data
items
Grand Total
Note : The additional cost of centering and shuttering
@ 50 per cent of cost of material and labour shall hold
good for arch spans of 6 m and above. For lesser
length of spans, the corresponding additional cost can
be taken as 40 per cent for spans above 4 m length
and 30 per cent for spans less than 4 m.
BLD-CSTN- 67 RR Masonry in CM (1:6)
6-12
Unit = 1cum
A. MATERIALS:
Cement kg 79.20
CR Stone cum 0.44
Rough Stone cum 0.50
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = cum 0.16
0.16cum
Fine aggregate (Sand) cum 0.33
Seigniorage charges for F.A cum 0.33
Seigniorage charges for Stone cum 1.10
B. LABOUR:
st
Mason 1 class day 1.20
Mazdoor (unskilled) day 2.00
Grand Total
BLD-CSTN- 68 RR Masonry in CM (1:8)
6-13
Unit = 1cum

39
STANDARD DATA BOOK – BUILDING WORK ITEMS

A. MATERIALS:
Cement kg 59.40
CR Stone cum 0.44
Rough Stone cum 0.50
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = cum 0.16
0.16cum
Fine aggregate (Sand) cum 0.33
Seigniorage charges for F.A cum 0.33
Seigniorage charges for Stone cum 1.10
B. LABOUR:
st
Mason 1 class day 1.20
Mazdoor (unskilled) day 2.00
Grand Total
Note : When Mortar mix is changed proportionate
quantity of cement has to be substituted. No change in
other data
BLD-CSTN- 69 Dry Stone Masonry for Retaining Walls
6-14
Unit = 1cum
A. MATERIALS:
Rough Stone cum 1.04
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = cum 0.16
0.16cum
Seigniorage charges for Stone cum 1.20
B. LABOUR:
st
Mason 1 class day 0.33
nd
Mason 2 class day 0.77
Mazdoor (unskilled) day 1.10
Grand Total
BLD-CSTN- 70 Dry Stone Masonry for Well steining
6-15
Unit = 1cum
A. MATERIALS:
Rough Stone cum 1.04
Bond Stones cum 0.16
Seigniorage charges for Stone cum 1.20
B. LABOUR:
st
Mason 1 class day 0.45
nd
Mason 2 class day 1.05
Mazdoor (unskilled) day 1.10
Grand Total
BLD-CSTN- 71 Damp Proof, Course Damp Proof (or anti
6-16 Proof) Course with Cuddapah / Shabad slabs
50 mm. thick in CM (1:3) (Unit - 10 sqm)

A. MATERIALS:
Cuddapah / Shabad slabs 50 mm. thick sqm 10.50
Cement Mortar 1:3 cum 0.15
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class day 0.90

40
STANDARD DATA BOOK – BUILDING WORK ITEMS

nd
Mason 2 class day 2.10
Mazdoor (unskilled) day 2.00
Grand Total
BLD-CSTN- POINTING
7
BLD-CSTN- 72 Flush Pointing with CM (1:3) to Brick / CRS
7-1 Masonry
Unit = 10 sqm
A. MATERIALS:
Cement kg 14.40
Fine aggregate (Sand) cum 0.03
Seigniorage charges for F.A cum 0.03
B. LABOUR:
nd
Mason 2 class day 0.50
Mazdoor (unskilled) day 0.74
Grand Total
BLD-CSTN- 73 Flush Pointing with CM (1:3) to RR Masonry
7-2
Unit = 10 sqm
A. MATERIALS:
Cement kg 14.40
Fine aggregate (Sand) cum 0.03
Seigniorage charges for F.A cum 0.03
B. LABOUR:
nd
Mason 2 class day 0.50
Mazdoor (unskilled) day 0.74
Grand Total
BLD-CSTN- 74 Raised Pointing with CM (1:3) to RR Masonry
7-3
Unit = 10 sqm
A. MATERIALS:
Cement kg 28.80
Fine aggregate (Sand) cum 0.06
Seigniorage charges for F.A cum 0.06
B. LABOUR:
nd
Mason 2 class day 0.50
Mazdoor (unskilled) day 0.74
Grand Total
BLD-CSTN- 75 Raised and cut pointing on coursed or Ashlar
7-4 stone masonry or concrete block walling in
white cement mortar 1 : 3 (1 white cement :
3 marble dust).
Details of cost for 10 sq.m
Materials :-
Cement mortar 1 :4 cum 0.038
Labour :—
Mason llnd class day 1.460
Mazdoor (unskilled) day 2.260
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
Note : When Mortar mix is changed as CM 1:4

41
STANDARD DATA BOOK – BUILDING WORK ITEMS

proportionate quantity of cement has to be


substituted. No change in other data.
BLD-CSTN- PLASTERING
8
BLD-CSTN- 76 Plastering with CM (1:3), 12 mm thick
8-1
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3) cum 0.15
Seigniorage charges for F.A cum 0.15
B. LABOUR:
st
Mason 1 class day 0.60
Mazdoor (unskilled) day 0.96
Grand Total
BLD-CSTN- 77 Plastering with CM (1:4), 12 mm thick
8-2
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4) cum 0.15
Seigniorage charges for F.A cum 0.15
B. LABOUR:
st
Mason 1 class day 0.60
Mazdoor (unskilled) day 0.96
Grand Total
BLD-CSTN- 78 Plastering with CM (1:5), 12 mm thick
8-3
Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:5) cum 0.150
Seigniorage charges for F.A cum 0.150
B. LABOUR:
st
Mason 1 class day 0.60
Mazdoor (unskilled) day 0.96
Grand Total
BLD-CSTN- 79 Plastering with CM (1:6), 12 mm thick
8-4
Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:6) cum 0.15
Seigniorage charges for F.A cum 0.15
B. LABOUR:
st
Mason 1 class day 0.60
Mazdoor (unskilled) day 0.96
Grand Total
BLD-CSTN- 80 Plastering with CM (1:8), 12 mm thick
8-5
Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:5) cum 0.15
Seigniorage charges for F.A cum 0.15
B. LABOUR:
st
Mason 1 class day 0.60

42
STANDARD DATA BOOK – BUILDING WORK ITEMS

Mazdoor (unskilled) day 0.96


Grand Total
BLD-CSTN- 81 Plastering with CM (1:4), 15 mm thick
8-6
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4) cum 0.19
Seigniorage charges for F.A cum 0.19
B. LABOUR:
nd
Mason 2 class day 0.60
Mazdoor (unskilled) day 0.96
Grand Total
BLD-CSTN- 82 Plastering with CM (1:4), 20 mm thick
8-7
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4) cum 0.210
Seigniorage charges for F.A cum 0.21
B. LABOUR:
nd
Mason 2 class day 0.94
Mazdoor (unskilled) day 1.60
Grand Total
BLD-CSTN- 83 Plastering with CM (1:3), 20 mm thick
8-8
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3) cum 0.210
Seigniorage charges for F.A cum 0.21
B. LABOUR:
nd
Mason 2 class day 0.94
Mazdoor (unskilled) day 1.60
Grand Total
Note : When Mortar mix is changed proportionate
quantity of cement has to be substituted
BLD-CSTN- 84 Plastering with CM 2 coats, 20 mm thick,
8-9 base coat in CM (1:6), 16mm thick and top
coat in CM (1:4), 4mm thick with Dubara
sponze finishing.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:6), 16 mm thick
Cement kg 43.00
Fine aggregate (Sand) cum 0.18
Top Coat in CM(1:4), 4 mm thick
Cement kg 14.50
Fine aggregate (Sand) cum 0.04
Seigniorage charges for F.A cum 0.22
B. LABOUR:
st
Mason 1 class day 0.63
nd
Mason 2 class day 1.47
Mazdoor (unskilled) day 3.90
Grand Total

43
STANDARD DATA BOOK – BUILDING WORK ITEMS

Note : When Mortar mix is changed proportionate


quantity of cement has to be substituted
BLD-CSTN- 85 Plastering with CM 2 coats, 12 mm thick,
8-10 base coat in CM (1:5), 8mm thick and top
coat in CM (1:3), 4mm thick with sponze
finishing.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:5), 8 mm thick
Cement kg 31.70
Fine aggregate (Sand) cum 0.11
Top Coat in CM(1:3), 4 mm thick
Cement kg 19.20
Fine aggregate (Sand) cum 0.04
Seigniorage charges for F.A cum 0.15
B. LABOUR:
st
Mason 1 class day 0.63
nd
Mason 2 class day 1.47
Mazdoor (unskilled) day 3.90
Grand Total
Note : When Mortar mix is changed proportionate
quantity of cement has to be substituted
RCM FACIA WORKS
BLD-CSTN- 86 RCM facia 5cm thick in CM (1:3) for drop walls, fins
8-11 with rabbit wire mesh & nominal reinforcement as
directed by Engineer-in-charge with dubara sponge
finishing, including cost & conveyance of all materials
to site, seigniorage charges, sales & other taxes on all
materials, operational & incidental, cost and
conveyance of cement, wire mesh, water to work site,
centering, scaffolding and form work, lift charges etc.,
complete for finished items of work but excluding cost
of steel & its fabrication charges, for finished item of
work. (APSS No.403 & 903)
Unit - 10 sqm
A) MATERIALS
Rabbit wire mesh (1.0 M panna for 0.6 M sqm 13.30
drop)
Cement Mortar 1:3 for 25 mm thick cum 0.25
Dry Cement for making Lumps kg 50.00
12 mm Plastering 2 coats in 1:4 & 1:2 cm sqm 21.80
both sides
Excluding HYSD Steel/ Mild steel & Binding
wire
B) LABOUR CHARGES
1st Class Mason day 8.00
Miller Operator day 1.00
Mazdoor (unskilled) day 10.00
c) Machinery 32.00
Machine Mixing Mortar with Miller - Hire Hrs 2.00
charges
BASIC COST per 10 sqm

44
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 87 20 mm thick rough cast exterior cement


8-12 plaster on walls upto height of 10 metres
above ground level consisting of 10 mm thick
backing coat of 1 : 3 cement mortar (1
cement : 3 sand) and 10 mm thick finishing
coat of 1 : 3 cement mortar (1 cement : 3
coarse aggregate of size 6 mm to 10 mm)
including arrises, chamfers and/or rounded
angles not exceeding 80 mm in girth.
Details of cost for 10 sq.m
Materials :-
Cement mortar 1:3 (1 cement: 3 sand) cum 0.110
Cement mortar 1:3(1 cement: 3 coarse
aggregate of size 6 mm to 10 mm)
Cement kg 52.800
Coarse aggregate of size 6 mm -10 mm cum 0.110
Mazdoo (unskilled) for mixing mortar with day 0.020
coarse aggreagate 6 - 10 mm
Labour for backing coat and finishing coat -
Plaster work :—
Mason, llnd class day 1.710
Mazdoo (unskilled) day 3.270
Extra labour for scooping : —
Mason, llnd class day 0.250
Mazdoor (male) day 0.250
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
BLD-CSTN- 88 Rough cast exterior cement plaster on walls
8-13 upto a height of 10 metres above ground
level with a mixture of sand and gravel or
crushed stone graded from 6 mm to 10 mm
nominal size dashed over and including fresh
plaster in two coats, backing coat 10 mm
cement plaster 1 : 3 (1 cemen" : 3 sand) and
finishing coat 10 mm cement plaster with
cement mortar 1:3 (1 cement: 3 sand) mixed
with 10% finely grounded hydrated lime by
volume of cement including arrises, chamfers
and/or rounded angles not exceeding 80 mm
in girth.

(a) Natural cement finish using ordinary


cement.
Details of cost for 10 sq.m.
Materials :—
Cement mortar 1:3 (1 cement: 3 sand) cum 0.224
Sand and gravel or crushed stone graded
from 6 mm to 10 mm nominal size
Coarse aggregate of size 6 mm -10 mm cum 0.100
Carriage
Grounded hydrated lime kg 9.280
Carriage

45
STANDARD DATA BOOK – BUILDING WORK ITEMS

Labour for backing coat and finishing coat -


Plaster work :—
Mason, llnd class day 1.710
Mazdoo (unskilled) day 3.270
Add labour for dashing crushed stone
Mason 1st class day 0.500
Mazdoo (unskilled) day 1.000
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
BLD-CSTN- 89 (b) Dark coloured finish using ordinary
8-14 cement and pigment
Details of cost for 10 sq.m.
Same rate as per (a) above item ()
Add cost of colour kg 6.000
Add for water charges @ 1 %
Add for contractor's profit and overheads
Cost for 10 sq.m.
Cost per sq.m
BLD-CSTN- 90 (c) Light coloured finish using white cement
8-15 and pigment
Details of cost for 10 sq.m.
Same rate as per (a) above item ()
Add cost of light colour kg 6.000
Add for water charges on cost of colour @ 1
%
Add for contractor's profit and overheads on
cost of colour and water charges
Cost for 10 sq.m.
Cost per sq.m
BLD-CSTN- 91 Pebble dash exterior plaster on walls upto a
8-16 height of 10 metres above ground level with
a mixture of washed pebble or crushed stone
graded from 6 mm to 12 mm nominal size
dashed over and including fresh cement
plaster in two coats, backing coat 10 mm
cement plaster 1 : 3 (1 cement : 3 sand) and
finishing coat 10 mm cement plaster 1 : 3 (1
cement : 3 sand) mixed with 10% finely
grounded hydrated lime by volume of
cement including arrises, chamfers and/or
rounded angles not exceeding 80 mm in girth

Details of cost for 10 sq.m


Materials :—
Cement mortar 1:3 cum 0.224
Grounded hydrated lime kg 9.280
Pebbles or crushed stone graded from 6 mm
to 12 mm nominal size
Crushed stone / Pebble of size 6 mm -12 mm cum 0.100
Labour for backing coat and finishing coat :-

Mason llnd class day 1.710


Mazdoor (unskilled) day 3.270

46
STANDARD DATA BOOK – BUILDING WORK ITEMS

Labour for pebble dashing


Mason llnd class day 0.500
Mazdoor (unskilled) day 0.610
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
Plain Cement Mortar Bands :
BLD-CSTN- 92 20 mm thick plain cement mortar bands in
8-17 cement mortar 1 : 4 (1cement : 4 sand) upto
300 mm in width
(a) Flush Band :-
Details of cost for 10 metres long and 10 cm
wide band
Materials :-
Cement mortar 1 :4 cum 0.023
Labour :—
Mason llnd class day 0.300
Mazdoor (unskilled) day 0.350
Add for water charges @ 1 %
Cost for 10 metres long and 10 cm wide band

Cost per cm width x metre long


93 b) Sunk band :-
Details of cost for 10 metres long and 10 cm
wide band
Materials :-
Cement mortar 1 :4 cum 0.023
Labour :—
Mason llnd class day 0.300
Mazdoor (unskilled) day 0.350
Add for water charges @ 1 %
Cost for 10 metres long and 10 cm wide band
Cost per cm width x metre long
94 C) Raised Band :-
Materials :-
Cement mortar 1 :4 cum 0.023
Labour :—
Mason llnd class day 0.380
Mazdoor (unskilled) day 0.430
Add for water charges @ 1 %
Cost for 10 metres long and 10 cm wide band
Cost per cm width x metre long
BLD-CSTN- 95 20 mm thick plain cement mortar bands in
8-18 cement mortar 1:4(1 cement: 4 sand) above
300 mm in width
Flush Band :-
Details of cost for 10 sq.m
Materials :-
Cement mortar 1 :4 cum 0.224
Labour :—
Mason llnd class day 2.200
Mazdoor (unskilled) day 2.700

47
STANDARD DATA BOOK – BUILDING WORK ITEMS

Add for water charges @ 1 %


Cost for 10 sq.m.
Cost per sq.m
96 Sunk band :-
Details of cost for 10 sq.m
Materials :-
Cement mortar 1 :4 cum 0.224
Labour :—
Mason llnd class day 2.500
Mazdoor (unskilled) day 3.000
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
97 Raised band
Details of cost for 10 sq.m
Materials :-
Cement mortar 1 :4 cum 0.224
Labour :—
Mason llnd class day 3.000
Mazdoor (unskilled) day 3.500
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
Moulded Cement Mortar Bands 15 mm
BLD-CSTN- 98 15 mm thick moulded cement mortar band in
8-19 cement mortar 1 : 4 (1cement: 4 sand)
Details of cost for 10 metres long and 10 cm
wide band
Materials :-
Cement mortar 1 :4 cum 0.023
Labour :—
Mason llnd class day 0.870
Mazdoor (unskilled) day 0.920
Add for water charges @ 1 %
Cost for 10 metres long and 10 cm wide band
Cost per cm width x metre long
BLD-CSTN- FLOORING
9
BLD-CSTN- 99 Flooring with polished shahabad stones ...
9-1 mm thick set over base coat of CM (1:8) over
already laid CC bed / RCC Roof Slab, including
neat cement slurry of honey like consistency
spread @ 3.3 kgs per sqm. & Jointed with
neat cement to full depth including cost of all
materials like cement, sand, and water and
flooring stones etc., complete, including
seigniorage charges, labour charges for
dressing of flooring stones etc., complete for
finished item of work, .

Unit = 10 sqm
A. MATERIALS:

48
STANDARD DATA BOOK – BUILDING WORK ITEMS

Polished Shabad Stone… mm thick sqm 11.00


Cement for CM (1:8) proportion for base coat kg. 21.60
Cement for slurry kg. 33.00
Cement for jointing kg. 20.00
Sand for CM (1:8) proportion cum 0.12
Seigniorage charges of sand cum 0.12
B. LABOUR:
st
Mason 1 class day 3.10
nd
Mason 2 class day 1.10
Mazdoor (unskilled) day 0.86
Add water charges 1%
Grand Total
BLD-CSTN- 100 Flooring with Rough Kadapa/Shahabad ...
9-2 mm thick stones, set over base coat of
cement mortar (1 : 8) 12 mm thick over CC
bed already laid or RCC roof slab, including
pointing with cement mortar 1:3 duly filling
joints nearly, including cost of all materials
like flooring stone, cement, sand, and water
etc., complete, including seigniorage charges,
labour charges for dressing of flooring stones
etc., complete for finished item of work, .

Unit = 10 sqm
A. MATERIALS:
Rough Cuddapah/Shabad stones (40 mm sqm 10.50
thick) (0.457 x 0.457 m)
Cement for CM (1:8) proportion for base coat kg. 21.60

Cement for CM 1:3 proportion for pointing kg. 9.60


Sand for CM (1:8) proportion cum 0.12
Sand for CM (1:3) proportion cum 0.02
Seigniorage charges of sand cum 0.14
B. LABOUR:
st
Mason 1 class day 0.960
nd
Mason 2 class day 2.240
Mazdoor (unskilled) day 3.30
Add water charges 1%
Grand Total

49
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 101 Flooring with polished marble slab... mm


9-3 thick set over base coat of cement mortar
(1:6) 20 mm thick (joints of stone must be
flushed) over CC bed already laid or RCC roof
slab, including near cement slurry of honey
like consistency spread @ 3.30 kgs per sqm.
Jointed with neat cement to full depth mixed
with pigment of matching shade, including
cost of all materials like flooring slab,
cement, sand, and water etc., complete,
including seigniorage charges, labour charges
for dressing, rubbing and polishing of flooring
stones etc., complete for finished item of
work, .

Unit = 10 sqm
A. MATERIALS:
Marble slab of size… mm….thick…. mm sqm 10.50
Cement for CM (1:8) proportion for base coat kg. 48.00
Cement for slurry for bedding kg. 33.00
White Cement for pointing kg. 5.00
Sand for CM (1:6) cum 0.20
Seigniorage charges of sand cum 0.20
B. Machinery
Machine for rubbing of floor day 1.00
C. LABOUR:
st
Mason 1 class day 2.10
nd
Mason 2 class day 3.00
Mazdoor (unskilled) day 5.00
Add water charges 1%
Grand Total
BLD-CSTN- 102 Flooring with chequrred terrazzo tiles of 22
9-4 mm thick (medium shade) set over base coat
of cement mortar (1:6) 12 mm thick over CC
bed already laid or RCC roof slab, including
near cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed with
neat cement to full depth mixed with
pigment of matching shade including cost of
all materials like cement, sand water and tiles
etc., complete, including seigniorage charges,
complete for finished item of work, .

Unit = 10 sqm
A. MATERIALS:
Chequerred terrazzo tiles of 22 mm thick sqm 10.50
(medium shade)
Cement for CM (1:6) proportion for base coat kg. 28.80
Cement for slurry kg. 33.00
Cement for jointing & pointing kg. 6.00
Pigment kg.
Sand for CM (1:6) proportion cum 0.12

50
STANDARD DATA BOOK – BUILDING WORK ITEMS

Seigniorage charges of sand cum 0.12


B. MACHINERY
Nill
C. LABOUR
nd
Mason 2 class day 0.960
Man mazdoor day 2.240
Mazdoor (unskiled) day 3.30
Add water charges 1%
Grand Total
BLD-CSTN- 103 Flooring with vitrified tiles of 1st quality, set
9-5 over base coat of cement mortar (1:8), 12
mm thick over CC bed already laid or RCC
roof slab, including neat cement slurry of
honey like consistency spread @ 3.3.kgs per
sqm & jointed neatly with white cement
paste to full depth mixed with pigment of
matching shade, including cost of all
materials like cement, sand water and tiles
etc., complete, including seigniorage charges,
etc., complete for finished item of work, .

Unit = 10 sqm
A. MATERIALS:
st
Vitrified tiles of 1 quality of size sqm 10.50
Cement for CM (1:8) proportion for base coat kg. 21.60

Cement for slurry kg. 33.00


Cement for Pointing with CM (1:3) kg. 6.000
Sand for CM (1:8) cum 0.12
Sand for pointing cum 0.020
Seigniorage charges of sand cum 0.140
B. LABOUR
st
Mason 1 class day 0.96
nd
Mason 2 class day 2.24
Mazdoor (unskiled) day 3.30
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 104 Flooring with ceramic tiles, set over base coat
9-6 of cement mortar (1:8), 12 mm thick over CC
bed already laid or RCC roof slab, including
neat cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed neatly
with white cement paste to full depth mixed
with pigment of matching shade, including
cost of all materials like cement, sand water
and tiles etc., complete, including seigniorage
charges, etc., complete for finished item of
work, .
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles sqm 10.50
Cement for CM (1:8) proportion for base coat kg. 21.60

51
STANDARD DATA BOOK – BUILDING WORK ITEMS

Cement for slurry kg. 33.00


White cement kg. 2.00
Sand for CM (1:8) cum 0.12
Seigniorage charges of sand cum 0.12
B. LABOUR
st
Mason 1 class day 0.96
nd
Mason 2 class day 2.24
Mazdoor (unskiled) day 3.30
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 105 Flooring with high polished granite slabs ...
9-7 mm thick other than black set over base coat
of cement mortar (1:8), 20 mm thick over CC
bed already laid or RCC roof slab, including
neat cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed neatly
with white cement paste mixed with pigment
of matching shade to full depth, including
cost of all materials like cement, sand water
and tilesetc., complete, including seigniorage
charges, labour charges for dressing of
tilesetc., complete for finished item of work,

Unit = 10 sqm
A. MATERIALS:
High polished granite slab other than black … sqm 10.50
mm thick
Cement for CM (1:8) proportion for base coat kg. 36.00
Cement for slurry kg. 33.00
White cement for jointing & pointing kg. 6.00
Cement for jointing kg.
Sand for CM (1:8) cum 0.20
Seigniorage charges of sand cum 0.20
B. LABOUR
st
Mason 1 class day 3.00
nd
Mason 2 class day 1.00
Mazdoor (unskiled) day 8.00
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 106 Flooring with marble tiles polished 8 mm
9-8 thick set over base coat of cement mortar
(1:8), 12 mm thick over CC bed already laid or
RCC roof slab, including neat cement slurry of
honey like consistency spread @ 3.3.kgs per
sqm & jointed neatly with white cement
paste mixed with pigment of matching shade
to full depth, including cost of all materials
like cement, sand water and tiles etc.,
complete, including seigniorage charges, etc.,
complete for finished item of work,

Unit = 10 sqm

52
STANDARD DATA BOOK – BUILDING WORK ITEMS

A. MATERIALS:
Marble tiles polished 8 mm thick sqm 10.50
Cement for CM (1:8) for base coat kg. 36.00
Cement for slurry kg. 33.00
White cement for jointing & pointing kg. 5.00
Sand for CM (1:8) cum 0.20
Seigniorage charges of sand cum 0.20
B. LABOUR (including for polishing & rubbing)

st
Mason 1 class day 4.00
Mazdoor (unskiled) day 8.00
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 107 Flooring with granite stone tiles 8 mm thick
9-9 (mirror polished of all shades) set over base
coat of cement mortar (1:6), 12 mm thick
over CC bed already laid or RCC roof slab,
including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm &
jointed neatly with white cement paste
mixed with pigment of matching shade to full
depth, including cost of all materials like
cement, sand water and tiles etc., complete,
including seigniorage charges, etc., complete
for finished item of work, .

Unit = 10 sqm
A. MATERIALS:
Granite stone tiles 8 mm thick (mirror sqm 10.50
polished of all shades)
Cement for CM (1:6) for base coat kg. 48.00
Sand for CM (1:6) cum 0.20
Seigniorage charges of sand cum 0.20
B. LABOUR
st
Mason 1 class day 0.96
nd
Mason 2 class day 2.24
Mazdoor (unskiled) day 3.30
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 108 Flooring with decorated white back ground
9-10 glazed tiles, set over base coat of cement
mortar (1:6), 12 mm thick over CC bed
already laid or RCC roof slab, including neat
cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed neatly
with white cement paste mixed with pigment
of matching shade to full depth, including
cost of all materials like cement, sand water
and tiles etc., complete, including seigniorage
charges, etc., complete for finished item of
work,
Unit = 10 sqm
A. MATERIALS:

53
STANDARD DATA BOOK – BUILDING WORK ITEMS

Decorated white back ground glazed tiles sqm 10.50


Cement for CM (1:6) for base coat kg. 28.80
Cement for slurry kg. 33.00
White cement for jointing & pointing kg. 6.00
Sand for CM (1:6) cum 0.12
Seigniorage charges of sand cum 0.12
B. LABOUR
st
Mason 1 class day 0.96
nd
Mason 2 class day 2.24
Mazdoor (unskiled) day 3.30
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 109 Flooring with pressed clay flooring tiles, set
9-11 over base coat of cement mortar (1:8) 12
mm thick over CC bed already laid or RCC
roof slab, including neat cement slurry of
honey like consistency spread @ 3.3.kgs per
sqm & jointed neatly with cement mixed with
pigment of matching shade to full depth,
including cost of all materials like cement,
sand water and tiles etc., complete, including
seigniorage charges, etc., complete for
finished item of work,

Unit = 10 sqm
A. MATERIALS:
20 X 20 cm pressed clay flooring tiles 1000 0.255
Nos
Cement for CM (1:8) for base coat kg. 21.600
Cement for jointing & pointing kg. 6.000
Pointing with CM (1:3) 10sqm 1.000
Deduct CM (1:3) cum 0.040
Sand for CM (1:8) cum 0.120
Seigniorage charges of sand cum 0.120
B. LABOUR
st
Mason 1 class day 0.960
nd
Mason 2 class day 2.240
Mazdoor (unskiled) day 4.30
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 110 Flooring with Plain Cement tiles, set over
9-12 base coat of cement mortar (1:8) 12 mm
thick over CC bed already laid or RCC roof
slab, including neat cement slurry of honey
like consistency spread @ 3.3.kgs per sqm &
jointed neatly with cement paste mixed with
pigment of matching shade to full depth,
including cost of all materials like cement,
sand water and tiles etc., complete, including
seigniorage charges, etc., complete for
finished item of work,

54
STANDARD DATA BOOK – BUILDING WORK ITEMS

Unit = 10 sqm
A. MATERIALS:
Plain cement Tiles 20 x 20 cms 1000 0.255
Nos
Cement for CM (1:8) for base coat kg. 21.600
Cement for jointing & pointing kg. 6.000
Pointing with CM (1:3) 10sqm 1.000
Deduct CM (1:3) cum 0.040
Sand for CM (1:8) cum 0.120
Seigniorage charges of sand cum 0.120
B. LABOUR
st
Mason 1 class day 0.960
nd
Mason 2 class day 2.240
Mazdoor (unskiled) day 3.30
Add water charges 1% 1.00%
Grand Total
Note : When Mortar mix is changed proportionate
quantity of cement has to be substituted for all above
Flooring Items. The same data holds good for stones
with all colours. Adopt same data for polished Kadapa
Stones and Bethamcherla stones.
BLD-CSTN- 111 Gronolithie Concrete Flooring 20 mm thick
9-13 with (1:1:2), using 6mm to 12 mm size hard
granite machine crushed metal laid over CC
bed already laid or RCC roof slab, in alternate
panels of size not exceeding 1.50 m x 1.50 m
and finishing the top surface to required
smoothness and slopes and thread lining
including cost of all materials like cement,
metal, sand and water etc., complete,
including seigniorage charges, etc., complete
for finished item of work,

Unit = 10 sqm
A. MATERIALS:
6mm to 12 mm H.G. Metal (Machine cum 0.17
crushed)
Cement kg 120.00
Sand cum 0.085
Seigniorage charges of sand cum 0.085
B. LABOUR
st
Mason 1 class day 1.25
nd
Mason 2 class day 0.06
Mazdoor (unskiled) day 3.00
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 112 Flooring with 100mm thick Cement Concrete
9-14 1:6:10, using 40mm metal, 100mm thick and
20 mm Cement Concrete surface (Ellis
Pattern, 1st Sort)
Unit = 10 sqm
A. MATERIALS:

55
STANDARD DATA BOOK – BUILDING WORK ITEMS

Cement Concrete 1:6:10 using concrete cum 1.000


mixer
Stone Chippings 3.34 mm - 10 mm cum 0.250
Cement kg 120.000
B. LABOUR
st
Mason 1 class day 0.150
nd
Mason 2 class day 0.350
Mazdoor (unskiled) day 5.40
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 113 Flooring with Cement Concrete 1:6:10, using
9-15 40mm metal, 100mm thick and plastered
over with 12 mm thick in CM(1:3)
Unit = 10 sqm
A. MATERIALS:
Cement Concrete 1:6:10 using concrete cum 1.00
mixer
Plastering with CM (1:3), 12 mm thick 10 1.00
sqm
B. LABOUR
st
Mason 1 class day 0.150
nd
Mason 2 class day 0.350
Mazdoor (unskiled) day 5.40
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 114 Flooring with Cement Concrete 1:6:10, using
9-16 40mm metal, 100mm thick and plastered
over with 12 mm thick in CM(1:3) using Red
oxid, with polished surface
Unit = 10 sqm
A. MATERIALS:
Cement Concrete 1:6:10 using concrete cum 1.00
mixer
Plastering with CM (1:3), 12 mm thick 10 1.00
sqm
Red oxid kg 10.00
B. LABOUR
st
Mason 1 class day 0.150
nd
Mason 2 class day 0.350
Mazdoor (unskiled) day 5.40
Add water charges 1% 1.00%
Masons for polishing Nos 1.10
Grand Total

56
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 115 6 mm thick terrazzo flooring in situ with


9-17 white, black, chocolate, gray, yellow or green
superior marble chips, over 20 mm thick base
coat of CM (1:3) laid over CC bed already laid
or RCC roof slab, including cost of all
materials like cement marble powder, marble
chips, sand & water etc., complete including
polishing to get high smooth finishing,
seigniorage charges, etc., complete for
finished item of work,

Unit = 10 sqm
A. MATERIALS:
Marble Powder kg 17.000
Marble Chips cum 0.060
Cement for top layer kg. 50.000
Cement for base coat in CM (1:3) kg. 96.000
Sand for base coat cum 0.200
Seigniorage charges of sand cum 0.200
B. MACHINERY
Polishing Charges sqm 10.000
C. LABOUR
st
Mason 1 class day 0.960
nd
Mason 2 class day 2.240
Mazdoor (unskiled) day 3.30
Grand Total
BLD-CSTN- 116 Providing skirting to internal walls to 15 cm
9-18 height/risers of steps with ceramic tiles 7.30
mm thick length equal to flooring stones, set
over base coat of CM (1:3) 12 mm thick with
cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and
jointed with white cement paste mixed with
pigment of matching shade to full depth,
including cost of all materials like tiles,
cement, sand and water etc., complete
including seigniorage charges, etc., complete
for finished item of work,

Unit = 10 sqm
A. MATERIALS:
Ceramic tiles 7.30 mm thick sqm 10.50
Sand for cm 1:3 base coat cum 0.12
Cement for cm 1:3 base coat kgs 57.60
Cement for slurry kgs 33.00
White cement for jointing & pointing kgs 6.00
Seigniorage charges of sand cum 0.12
B. LABOUR
st
Mason 1 class day 0.77
Mazdoor (unskiled) day 0.80
Grand Total

57
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 117 Providing skirting to internal walls to 15 cm


9-19 height/risers of steps with marble
slab……..mm thickness, length equal to
flooring stones, set over base coat of CM
(1:3) 12 mm thick with cement slurry of
honey like consistency spread at the rate of
3.30 kgs per sqm and jointed with white
cement paste mixed with pigment of
matching shade to full depth, including cost
of all materials like marble slab, cement, sand
and water etc., complete including
seigniorage charges, etc., complete for
finished item of work,

Unit = 10 sqm
A. MATERIALS:
Marble slab………mm thickness sqm 10.50
Sand for base coat cum 0.12
Cement for base coat kg 57.60
Cement for slurry kg 33.00
White cement for jointing & pointing kg 5.00
Flate nosing charges RM 66.67
Machine cutting charges RM 67.67
Seigniorage charges of sand cum 0.12
B. LABOUR
Mason Ist class day 2.10
Man mazdoor (Beldar) day 4.90
Man mazdoor (Beldar) for polishing & day 4.00
rubbing
Woman mazdoor day 4.00
Grand Total
BLD-CSTN- 118 Providing skirting to internal walls to 15 cm
9-20 height/risers of steps with vitrified tiles
length equal to flooring stones, set over base
coat of CM (1:5) 12 mm thick with cement
slurry of honey like consistency spread at the
rate of 3.30 kgs per sqm and jointed with
white cement paste mixed with pigment of
matching shade to full depth, including cost
of all materials like tiles, cement, sand and
water etc., complete including seigniorage
charges, etc., complete for finished item of
work,

Unit = 10 sqm
A. MATERIALS:
Vitrified tiles polished 1st quality sqm 10.50
Sand for cm 1:5 base coat cum 0.12
Cement for cm 1:5 base coat kgs 34.56
Cement for slurry kgs 33.00
White cement for jointing & pointing kgs 2.00
Seigniorage charges of sand cum 0.12
B. LABOUR

58
STANDARD DATA BOOK – BUILDING WORK ITEMS

Mason Ist class day 0.96


nd
Mason 2 class day 2.24
Mazdoor (unskilled) day 3.30
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 119 Providing skirting to internal walls to 15 cm
9-21 height/risers of steps with 8 mm thick mirror
polished granite tiles length equal to flooring
stones, set over base coat of CM (1:3) 12 mm
thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per
sqm and jointed with white cement paste
mixed with pigment of matching shade to full
depth, including cost of all materials like tiles,
cement, sand and water etc., complete
including seigniorage charges, etc., complete
for finished item of work,

Unit = 10 sqm
A. MATERIALS:
8 mm thick mirror polished granite tiles sqm 10.50
Sand for cm 1:3 base coat cum 0.12
Cement for cm 1:3 base coat kgs 57.60
Cement for slurry kgs 33.00
White cement for jointing & pointing kgs 5.00
Seigniorage charges of sand cum 0.12
B. LABOUR
Mason Ist class day 2.10
Mazdoor (unskiled) day 0.80
nd
Mason 2 class 4.90
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 120 Providing skirting to internal walls to 15 cm
9-22 height/risers of steps with polished kadapa
stone ... mm thick length equal to flooring
stones, set over base coat of CM (1:3) 12 mm
thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per
sqm and jointed with white cement paste
mixed with pigment of matching shade to full
depth, including cost of all materials like
Cuddapah stone, cement, sand and water
etc., complete including seigniorage charges,
etc., complete for finished item of work,

Unit = 10 sqm
A. MATERIALS:
Polished kadapa stone …. mm thick sqm 10.50
Sand for cm 1:3 base coat cum 0.12
Cement for cm 1:3 base coat kgs 57.60
Cement for slurry kgs 33.00
Seigniorage charges of sand cum 0.12
B. LABOUR

59
STANDARD DATA BOOK – BUILDING WORK ITEMS

Mason Ist class day 0.96


Mason 2nd class day 2.24
Mazdoor (unskiled) day 3.10
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 121 Providing skirting to internal walls to 15 cm
9-23 height/risers of steps with ... mm thick
polished Shahabad stone length equal to
flooring stones, set over base coat of CM
(1:3) 12 mm thick with cement slurry of
honey like consistency spread at the rate of
3.30 kgs per sqm and jointed with white
cement paste mixed with pigment of
matching shade to full depth, including cost
of all materials like Shahabad stone, cement,
sand and water etc., complete including
seigniorage charges, etc., complete for
finished item of work,
Unit = 10 sqm
A. MATERIALS:
25 mm thick polished Shahabad stone sqm 11.00
(White)
Sand for cm 1:3 base coat cum 0.12
Cement for cm 1:3 base coat kgs 57.60
Cement for slurry kgs 33.00
Seigniorage charges of sand cum 0.12
B. LABOUR
Mason Ist class day 0.96
Mason 2nd class 2.24
Mazdoor (unskiled) day 3.10
Add water charges 1% 1.00%
Grand Total
Note : a) When Mortar mix is changed proportionate
quantity of cement has to be substituted for all
Skirting Items.
b) For dadooing or cladding items, data for relevant
Skirting Items may be adopted adding the cutting
charges of the stones/ tiles as the case may be.
c) For treads items, data for relevant flooring Items
may be adopted adding the cutting charges of the
stones/ tiles as the case may be.
d) For risers items, data for relevant skirting Items
may be adopted adding the cutting charges of the
stones/ tiles as the case may be.
BLD-CSTN- 122 Teak Wood Flooring 40mm. Thick Tongued
9-24 and Grooved Planks, including cost of all
materials, labour etc., complete
Unit = 10 sqm
A. MATERIALS:
Teak Wood Planks 40mm thick cum 0.44
75 mm Long Screws 100 3.00
Nos

60
STANDARD DATA BOOK – BUILDING WORK ITEMS

B. LABOUR
Carpenters 1st Class day 1.95
Carpenters 2nd Class day 4.55
Man mazdoor day 5.40
Note : Deduct 4.3 Nos Carpenters if plank rate is for
tongued and grooved ready planned.
Grand Total
BLD-CSTN- 123 Flooring with Gravel 150 mm thick including
9-25 cost of all materials, labour, watering etc.,
complete
Unit = 10 sqm
A. MATERIALS:
Gravel (including 2% wastage) cum 1.53
B. LABOUR
Man mazdoor day 1.10
Woman mazdoor day 0.50
Grand Total
BLD-CSTN- ROOFING & CEILING
10
BLD-CSTN- 124 Roofing with corrugated G.I sheets 0.80mm
10-1 thick fixed with G.I ‘J’ bolts & nuts 8 mm dia
with bitumen & G.I limpet washers filled with
white lead & including a coat of approved
steel primer and two coats of approved paint
on over lapping of sheets complete (up to a
0
pitch of 60 ) and seigniorage charges, etc.,
complete, excluding the cost of purlins,
rafters, trusses & cost of conveyance of all
materials

Unit = 184.518 sqm


A. MATERIALS:
G.I corrugated 0.80 mm thick sheets kgs 103.09
G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884 nos 47.91

G.I bolts & nuts 20 x 6 nos


G.I ‘J’ bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos nos 43.90
= 810 nos. with washers or srews, if wooden
battens used.
Limpet washers (for scam & ‘J’ bolts) nos 91.82
884 + 810 = 1694
Bitumen washers nos 91.82
Zinc cromate yellow paint litre 0.14
Ready mixed paint litre 0.20
B. LABOUR
For roofing
Carpenter II class day 0.84
Man mazdoor (beldar) day 0.91
For premier painting one coat
Painter day 0.06
Mazdoor (coolie) day 0.06
For two coats of painting to over laps
Painter day 0.14

61
STANDARD DATA BOOK – BUILDING WORK ITEMS

Mazdor (coolie) day 0.14


Sundries including 50 x 6 mm iron wind ties LS
white lead etc.
Add for Standard specification 1mm. Thick LS
ridging and 1.25 mm thick sheet vallyes when
such are required for a particular work.
Average allowance for 10 sqm roofing.

Grand Total
Rate per 10 sqm = Grand Total/10
BLD-CSTN- 125 Roofing with corrugated G.I sheets 1.00mm
10-2 thick fixed with G.I ‘J’ bolts & nuts 8 mm dia
with bitumen & G.I limpet washers filled with
white lead & including a coat of approved
steel primer and two coats of approved paint
on over lapping of sheets complete (upto a
0
pitch of 60 ) and seigniorage charges,
turnover tax etc., complete, excluding the
cost of purlins, rafters, trusses & cost of
conveyance of all materials

Unit = 184.518 sqm


A. MATERIALS:
G.I corrugated 1.00 mm thick sheets kgs 126.07
G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884 nos 47.91

G.I ‘J’ bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos nos 43.90


= 810 nos.
Limpet washers (for scam & ‘J’ bolts) nos 91.82
884 + 810 = 1694
Bitumen washers nos 91.82
Zinc cromate yellow paint litre 0.14
Ready mixed paint litre 0.20
B. LABOUR
For roofing
Carpenter II class day 0.84
Man mazdoor (beldar) day 0.91
For premier painting one coat
Painter day 0.06
Mazdoor (coolie) day 0.06
For two coats of painting to over laps
Painter day 0.14
Mazdor (coolie) day 0.14
Grand Total
Rate per 10 sqm = Grand Total/10

62
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 126 Roofing with corrugated G.I sheets 1.25mm


10-3 thick fixed with G.I ‘J’ bolts & nuts 8 mm dia
with bitumen & G.I limpet washers filled with
white lead & including a coat of approved
steel primer and two coats of approved paint
on over lapping of sheets complete (upto a
0
pitch of 60 ) and seigniorage charges,
turnover tax etc., complete, excluding the
cost of purlins, rafters, trusses & cost of
conveyance of all materials

Unit = 184.518 sqm


A. MATERIALS:
G.I corrugated 1.25 mm thick sheets kgs 154.80
G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884 nos 47.91

G.I ‘J’ bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos nos 43.90


= 810 nos.
Limpet washers (for scam & ‘J’ bolts) 884 nos 91.82
+ 810 = 1694
Bitumen washers nos 91.82
Zinc cromate yellow paint litre 0.14
Ready mixed paint litre 0.20
B. LABOUR
For roofing
Carpenter II class day 0.84
Man mazdoor (beldar) day 0.91
For premier painting one coat
Painter day 0.06
Mazdoor (coolie) day 0.06
For two coats of painting to over laps
Painter day 0.14
Mazdor (coolie) day 0.14
Grand Total
Rate per 10 sqm = Grand Total/10
BLD-CSTN- 127 Roofing with 6 mm thick corrugated asbestos
10-4 cement sheets, fixing with G.I ‘J’ bolts & nuts
8 mm dia G.I plain washers complete
including seigniorage charges etc., complete
for finished item of work, but excluding the
cost of purlins, rafters, trusses & cost of
0
conveyance of all materials – upto 60 pitch.

Unit = 216.14 sqm


A. MATERIALS:
6 mm thick corrugated AC sheets T 0.15
/sqm
8 mm dia G.I ‘J’ bolts & nuts nos 22.03
G.I washers nos 22.03
Bitumen washers nos 22.03
B. LABOUR
Carpenter II class day 0.43
Man mazdoor day 0.54

63
STANDARD DATA BOOK – BUILDING WORK ITEMS

Sundries including 50 x 6 mm iron wind ties LS


white lead etc.
Add for Standard specification 1mm. Thick LS
ridging and 1.25 mm thick sheet vallyes when
such are required for a particular work.
Average allowance for 10 sqm roofing.

Grand Total
Rate per 10 sqm = Grand Total/10
BLD-CSTN- 128 Best Tiled Roofing with Pan tiles over Flat
10-5 Tiles and Lime mortar Borders including Teak
Reapers.
Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick 1000 1560
No
Flat Tiles 150 x 150 x 15 mm 1000 470
No
Teak Reepers 50 x 12 mm 10RM 75.000
Wire Nails 40 mm long kgs 0.500
Lime cum 0.008
Lime Mortar cum 0.300
B. LABOUR
Carpenter day 0.800
Bricklayers day 2.200
Man mazdoor day 1.100
Woman mazdoor day 5.400
Sundries including tarring reepers, extra LS LS
labour / for pointing the underside of flat
tiles and white washing the same.
Grand Total
Sub Analysis :
Lime Mortar 1:2
lime cum 0.500
Sand cum 1.000
Grinding Lime Mortar day 1.000
Total
BLD-CSTN- 129 Best Tiled Roofing with Pan tiles and Lime
10-6 mortar Borders including Teak Reapers at
100 mm. centres
Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick 1000 1560
No
Teak Reepers 50 x 12 mm 10RM 107.000
Wire Nails 40 mm long kgs 0.700
Lime Moratar cum 0.120
B. LABOUR
Carpenter day 1.100
Bricklayers day 1.400
Man mazdoor day 1.100
Woman mazdoor day 3.200
Grand Total

64
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 130 Best Tiled Roofing with Pan tiles laid on


10-7 Bamboo Rafters, Bamboo Reepers and
Bamboo Mats, including Lime mortar
Borders
Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick 1000 1560
No
Bamboo rafters (450 mm apart) 75 to 100 RM 25
mm dia
Bamboo reepers, Split 25 mm dia 100 150
No
Bamboo mats 10 10.500
sqm
Lime Moratar for Borders cum 0.120
B. LABOUR
Carpenter day 1.100
Bricklayers day 1.400
Man mazdoor day 1.100
Woman mazdoor day 3.200
Sundries including nails
Grand Total
BLD-CSTN- 131 Best Tiled Roofing with Mangalore tiles set in
10-8 Lime mortar over Flat Tiles and including
Teak Reepers
Unit = 10 sqm
A. MATERIALS:
Mangalore tiles (vide Stadard Specification) 1000 160
No
Flat Tiles 150 x 150 x 15 mm 1000 470
No
Teak Reepers 50 x 12 mm 10RM 75.000
Wire Nails 40 mm long kgs 0.500
Lime cum 0.008
Lime Moratr cum 0.380
B. LABOUR
Carpenter day 0.800
Bricklayers day 1.600
Man mazdoor day 1.100
Woman mazdoor day 4.300
Sundries including tarring reepers iron wind LS LS
ties 30 x 3 mm, G.I. Screw, washers etc., and
extra labour for pointing the underside of flat
tiles and white washing the same.

Grand Total
BLD-CSTN- 132 Best Tiled Roofing with Mangalore tiles
10-9 including Teak Reepers
Unit = 10 sqm
A. MATERIALS:
Mangalore tiles (vide Stadard Specification) 1000 160
No
Teak Reepers 50 x 12 mm 10RM 36.000

65
STANDARD DATA BOOK – BUILDING WORK ITEMS

Wire Nails 50 mm long kgs 0.500


Lime Moratar cum 0.090
B. LABOUR
Carpenter day 0.500
Bricklayers day 0.500
Man mazdoor day 1.100
Woman mazdoor day 2.200
Grand Total
BLD-CSTN- 133 Best Tiled Roofing with Mangalore tiles over
10-10 Ceiling Tiles with Air Spaces and including
Teak Reepers
Unit = 10 sqm
A. MATERIALS:
Rate for "Best Mangalore tiled roofing with 10 10.000
Mangalore tiles including teak reeper". sqm

Add
Terracing tiles 100 156
No
B. LABOUR
Bricklayers day 0.500
Woman mazdoor day 1.100
Grand Total
Common note Applicabable for Items 196 to
201 :-
1. The quantity proposed for Pan Tiles /
Mangalore Tiles includes allowance for cost
of special tiles for ridges and hips.
2. Reepers size is for rafter spacing 600 mm.
including allowance for eves and valleys.

3. Labour including fixing galvanized iron


sheeting-cost of sheeting to be paid
separately.
Sub Analysis :
Lime Mortar (1: 1.5) :
Unit = 1 cum
Lime cum 0.670
Fine Sand cum 1.000
Grinding Mortar (Spl Grinding) day 1.000
Sundries LS
Total
BLD-CSTN- 134 Plastering with Lime Mortar 3 Coats, 25 mm
10-11 thick (Sebara Rendering)
Unit = 10 sqm
Lime Mortar (1:2) cum 0.180
Lime Mortar (1:1.5) cum 0.080
Lime cum 0.023
LABOUR
Bricklayers day 3.200
Mazdoor (unskilled) day 6.500
Sundries LS LS
Total

66
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 135 Terrace Roofing with Brick on edge 75 mm.


10-12 Concrete 2 Courses of Flat Tiles at Top and
pointing Flat Tiles in Cement Mortar (1:3) and
one coat of Cement Plaster (1:3)
Unit = 10 sqm
A. MATERIALS:
Terracing Bricks 150 x 75 x 25mm 1000 2000
No
Flat Tiles 150 x 150 x 15 mm 100 900
No
Broken brick 20 mm cube cum 0.980
Lime cum 0.380
Lime Moratar cum 0.210
Pointing with cement mortar 1:3 (for rate - 10 1.000
vide relevant schedule item) sqm
Cement Mortar 1:3 cum 0.240
B. LABOUR
Bricklayers day 4.300
Mazdoor (unskilled) day 6.500
Grand Total
Note : The quantity proposed for broken brick allows
for the brick powder formed, replacing sand for
concrete layers.
BLD-CSTN- 136 Reinforced cement Concrete Roofing 125 mm
10-13 thick with CC (M 20) using 20 mm graded
metal and 2 courses of Flat Tiles at Top
including pointing with Cement Mortar (1:3)

Unit = 10 sqm
A. MATERIALS:
Reinforced Concrete Roofing slab 125 mm 10 10.000
thick (for rate - vide relevant schedule item) sqm

Flat Tiles 150 x 150 x 20 mm 100 900


No
Cement Mortar 1:3 cum 0.260
Pointing with cement mortar 1:3 (for rate - 10 1.000
vide relevant schedule item) sqm
B. LABOUR
Bricklayers day 2.200
Woman mazdoor day 2.200
Sundries including crude oil LS
Grand Total
Sub Analysis :
RCC (M 20) using 20 mm HG graded metal
using Concrete mixturefor Roofing 125 mm
thick
CC (M 20) (Item No. cum 1.250
Centering Charges 10 1.000
sqm
Form Work
Total

67
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 137 Reinforced cement Concrete Roofing 140 mm


10-14 thick with CC (M 20) using 20 mm graded
metal and 2 courses of Flat Tiles at Top
including Pointing with Cement Mortar (1:3)

Unit = 10 sqm
A. MATERIALS:
Rate of "Reinforced cement Concrete Roofing 10 1.000
125 mm thick and 2 courses of Flat Tiles at sqm
Top including pointing with Cement Mortar
(1:3)"
Add :
For extra thickness of roofing slab cum 0.150
Grand Total
BLD-CSTN- 138 Reinforced cement Concrete Roofing 150 mm
10-15 thick with CC (M 20) using 20 mm graded
metal and 2 courses of Flat Tiles at Top
including Pointing with Cement Mortar (1:3)

Rate of "Reinforced cement Concrete Roofing 10 1.000


125 mm thick and 2 courses of Flat Tiles at sqm
Top including pointing with Cement Mortar
(1:3)"
Add :
For extra thickness of roofing slab cum 0.250
Grand Total
BLD-CSTN- 139 Reinforced cement Concrete Roofing 100 mm
10-16 thick with CC (M 20) using 20 mm graded
metal and 2 courses of Flat Tiles at Top
including Pointing with Cement Mortar (1:3)

Rate of "Reinforced cement Concrete Roofing 10 1.000


125 mm thick and 2 courses of Flat Tiles at sqm
Top including pointing with Cement Mortar
(1:3)"
Deduct :
For Less thickness of roofing slab cum 0.250
Grand Total
BLD-CSTN- 140 Reinforced cement Concrete Roofing 100 mm
10-17 thick with CC (M 20) using 20 mm graded
metal with Imprevious Coat with 12 mm thick
Plastering in CM (1:3) with 1 kg. of Impermo
Compound or ACCO Proof per Bag of Cement
and laid when slab is Green.

Unit = 10 sqm
Reinforced Concrete Roofing slab 100 mm 10 1.000
thick (for rate - vide relevant schedule item) sqm

Centering Charges 10 1.000


sqm
Plastering with CM (1:3), 12 mm thick 10 1.000
sqm

68
STANDARD DATA BOOK – BUILDING WORK ITEMS

Impermo Compound kgs 1.500


Grand Total
Note for Items 204 - 207 :
1. No extra rate will be paid for finishing the
bottom surface of the roofing slab as
described in SS No.
"For estimating purpose the extra allowance
for camber concrete, when such is required
may be given under sundries."
BLD-CSTN- 141 Complete Surface Repairs to Leaky Terrace
10-18 Roofs with Flat Tiles
Unit = 10 sqm
A. MATERIALS:
Flat Tiles 150 x 150 x 15 mm 1000 450
No
Cement Mortar 1:3 cum 0.110
Pointing with cement mortar 1:3 (for rate - 10 1.000
vide relevant schedule item) sqm
B. LABOUR
Bricklayers day 1.100
Man Mazdoor day 1.100
Clean removal of lime plaster from terraced 10 1.000
roofs and raking out joints 12 mm deep (for sqm
rate - vide relevant schedule item)

Sub Analysis :
Mazdoor (unskilled) Day
Mate Day
Sundries including crude oil LS
Grand Total
BLD-CSTN- 142 Best Sloping Bengal Terrace with 3 courses of
10-19 Flat Tiles at Top including Teak Wood
Reepers
Unit = 10 sqm
A. MATERIALS:
Flat Tiles 150 x 150 x 15 mm 1000 1350
No
Lime cum 0.008
Lime Moratar (1:1.5) cum 0.150
Teak Reepers 52 x 12 mm 10 RM 75.000
Wire Nails 40 mm long kgs 0.500
Plastering with lime mortar 3 coats (for rate - 10 1.000
vide relevant schedule item) sqm
B. LABOUR
Carpenter day 0.800
Bricklayers day 2.200
Woman mazdoor day 2.200
Sundries including tarring reepers LS
Grand Total
Note : 1. Reepers size is for rafter spacing 600
mm. including allowance for eves and valleys.

69
STANDARD DATA BOOK – BUILDING WORK ITEMS

2. No extra rate will bepaid for finishing the


bottom surface of the roofing slab as
described in SS No.
BLD-CSTN- 143 Removing Old Tiles and Retiling with New
10-20 Pan Tiles over Old Teak Reepers including
New White Washed Lime Mortar Borders 230
x 50 mm. at 2 Metres Intervals
Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick 1000 1560
No
Lime Moratar cum 0.120
B. LABOUR
Bricklayers day 1.400
Man Mazdoor day 1.100
Woman mazdoor day 4.300
Sundries LS
Grand Total
BLD-CSTN- 144 Shifting Pan Tiles (Labour Only)
10-21
Unit = 10 sqm
Bricklayers day 1.100
Man Mazdoor day 0.800
Grand Total
BLD-CSTN- 145 Shifting Pan Tilesand forming new White
10-22 Washed Lime Mortar Boarders, 230 x 50 mm
at 2 Metres Intervals
Unit = 10 sqm
Rate of "Shifting Pan Tiles" 10 1.000
sqm
Add : Lime Mortar Borders and White LS
Washing
Grand Total
BLD-CSTN- 146 12 mm. Teak Wood Plank Ceiling Tongued
10-23 and Grooved Planking
Unit = 10 sqm
A. MATERIALS:
Teak Wood Planks 150 x 12 mm cum 0.132
Screws 40mm long 100 300
No
B. LABOUR
Carpenter day 6.500
Man Mazdoor day 5.400
Sundries LS
Grand Total
Note : Deduct 4.3 Nos Carpenters if plank
rate is for tongued and grooved ready
planned.
BLD-CSTN- 147 12 mm. Teak Wood Plank Ceiling with 40 x 12
10-24 mm Teak Wood Battens
Unit = 10 sqm
Rate for "12 mm. Teak Wood Plank Ceiling 10 10.000
Tongued and Grooved Planking" sqm

70
STANDARD DATA BOOK – BUILDING WORK ITEMS

Teak Wood Battens 40 x 12 mm 10 RM 66.000


Brass screws 25 mm long 100 240
No
Deduct :
Carpenter day 1.100
Sundries LS
Grand Total
BLD-CSTN- 148 Providing impervious coat to exposed RCC
10-25 roof slab surface with CM(1:3), 20mm thick
with 1kg of water proof compound per bag of
cement laid over roof when it is green
including cost of all materials, seigniorage
charges, excluding conveyance charges of
materials and including all operational,
incidental and labour charges for mixing
mortar, laying, rendering smooth and thread
lining, curing, rounding off junctions of wall
and slab etc,, complete for finished item of
work

Unit = 10 sqm
A. MATERIALS:
Cement Mortal 1:3 cum 0.210
Water proof compound kg 2.000
B. LABOUR
st
Mason 1 class day 0.660
nd
Mason 2 class day 1.540
Mazdoor (unskiled) day 3.70
Grand Total
BLD-CSTN- 149 Providing & fixing insulating board ceiling of
10-26 approved quality with nails etc., complete,
excluding the cost of frame work for base
and cost of conveyance of all materials

Unit = 10 sqm
A. MATERIALS:
12 mm thick insulating board sqm 11.00
B. LABOUR
Carpenter Ist class day 2.50
Man mazdoor day 2.00
Grand Total
BLD-CSTN- 150 Providing & fixing hard board sheet ceiling of
10-27 approved quality with nails etc., complete,
excluding the cost of frame work for base
and cost of conveyance of all materials

Unit = 10 sqm
A. MATERIALS:
3 mm thick standard quality of hard board sqm 11.00
B. LABOUR
Carpenter Ist class day 2.50
Man mazdoor day 2.00
Grand Total

71
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 151 Providing & fixing flat pressed 3 layer


10-28 medium density particle board sheet with
necessary nails etc., complete, excluding the
cost of frame work for base and cost of
conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
Standard quality of flat pressed 3 layer sqm 11.00
medium density board sheet 4.50 mm thick

B. LABOUR
Carpenter Ist class day 2.50
Man mazdoor day 2.00
Grand Total
BLD-CSTN- 152 Providing & fixing plain AC sheet ceiling of
10-29 approved quality with necessary nails etc.,
complete, excluding the cost of frame work
for base and cost of conveyance of all
materials
Unit = 10 sqm
A. MATERIALS:
Plain AC sheet for ceiling sqm 11.00
B. LABOUR
Carpenter Ist class day 2.50
Man mazdoor day 2.00
Grand Total
BLD-CSTN- 153 Providing 10 mm thick plaster of paris
10-30 (Gypsum anhydrous) ceiling upto a height of
5 m above floor level over first class BT wood
strips 25 x 6 mm with 10 mm gap in between
and reinforced with rabbit wire mesh fixed to
wooden frame excluding cost of wooden
frame for base & cost of conveyance of all
materials.
Unit = 10 sqm
A. MATERIALS:
st
Wooden strips 1 class BT wood 25 x 6 mm cum 0.05
size
Nails kg 0.75
Rabbit wire mesh sqm 10.20
Plaster of paris kg 219.76
B. LABOUR
for Jointing the wooden strips including fixing
the rabbit mesh
Carpenter Ist class day 2.60
Man mazdoor (beldar) day 1.60
For doing plaster of paris over wooden strips

Mason Ist class day 2.62


Mason IInd class day 1.62
Mazdoor (unskilled) day 377.00
Grand Total
Gypboard Suspended false ceiling

72
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 154 Supplying and fixing Gyp Board Suspended


10-31 regular single layer false ceiling (GS-MFSC-4.1
as per India Gypsum) using 12.5 mm thick
Gyp Board conforming to IS 2095 - 1982
fixing to Gyp steel GI perimeter channels of
size 20 mm x 27 mm x 30 mm(web) of 0.55
mm thick along the perimeter of ceiling
screw fixed to brick work/ partition at 610
mm c/c and suspending the frame work using
Intermediate channels (45 mm x 15mm x
15mm x 0.9 mm) from soffit at 1220 mm c/c
with ceiling angle (25 mm x 10 mm x 0.55
mm) fixed with GI Cleat and steel expansion
fasteners & connecting clip to the ceiling
channels (with knurled web of 51.5 mm x 26
mm x 10.5 mm x 0.55 mm) fixed in direction
perpendicular to the intermediate channel at
457 mm c/c and fixing the 12.5 mm tapered
edge Gypboard with 25 mm drywall screws at
230 mm c/c & jointing and finishing using
joint compound and paper tape to have a
flush look including filling the tapered &
square edges with jointing compound, two
coats of drywall topcoat complete for
finished item of work as per Idia Gypsum Ltd
specification.

UNIT -1 sqm
A) Material requirement as per India Gypsum

12.5 mm Gypboard
1219 mm x 1829 mm size Boards sqm 1.03
Ceiling Angle
25 mm x 10 mm x 0.55 mm RM 0.64
Connecting Clips Nos 1.84
Ceiling Section
51.5 mm x 26 mm x 10.5 mm x 0.55 mm thick RM 2.30

Intermediate Channel
45 mmx 15 mm x 15 mm x 0.9 mm RM 0.84
Perimeter Channel
20 mm x 27 mm x 30 mm(web) of 0.55 mm RM 0.40
thick
Rawl Plug Nos 0.64
Soffit Cleats Nos 0.64
Drywall Screws - 25 mm Nos 18.00
Jointing Compound Kgs 0.55
Jointing Paper Tape RM 1.46
Drywall Top Coat Lits 0.15
B) LABOUR CHARGES
1st Class Carpenter day 0.40
2nd Class Carpenter day 0.40

73
STANDARD DATA BOOK – BUILDING WORK ITEMS

1st Class Painter day 0.08


2nd Class Painter day 0.08
Power Saw Cutter - Hand Operated - day 0.04
Operator
Power Drill - Hand Operated - Operator day 0.08
Unskilled Mazdoor day 0.24
C) Machinery
Power Saw Cutter - Hand Operated - Hire Hrs 0.32
charges
Power Drill - Hand Operated - Hire Charges Hrs 0.64

Scaffolding charges 1%
BASIC COST per 1 sqm
Gyp Board Fine Line Grid false ceiling
BLD-CSTN- 155 Supplying and fixing Gyp Board Fine Line Grid
10-32 false ceiling (GS-FLC-4.6 as per India Gypsum)
in size 600 mm x 600 mm using 12.5 mm
thick/ 9.5 mm thick Gyp Board sheet tiles of
size 595 mm x 595 mm or 595 mm x 1195
mm conforming to IS 2095 - 1982 fixing to
Gyp steel precoated GI wall angle of size 25
mm x 25 mm x of 0.70 mm thick along the
perimeter of ceiling screw fixed to brick
work/ partition at 610 mm c/c and
suspending the frame work using precoated
GI Tee section (24 mm x 38 mm x 0.7 mm)
from soffit at 1220 mm c/c fixed with GI
Soffit Cleat, rawl plugs and steel expansion
fasteners & connecting clip to the GI T
section with 4 mm dia GI Rod with galvanised
spring steel level clip of PVC unversal holding
clips system at 1200 mm c/c and fixing the
12.5 mm / 9.5 mm Gypboard Sheet tiles of
size 595 mm x 595 mm or 595 mm x 1195
mm and finishing two coats of drywall
topcoat complete for finished item of work
as per Idia Gypsum Ltd specification.

UNIT -1 sqm
A) Material requirement as per India Gypsum

12.5 mm / 9.5 mm - Gypboard Tiles


Either - 595 mm x 595 mm - sqm 1.00
Or - 595 mm x 1195 mm -
GI Angle - Precoated
25 mm x 25 mm x 0.7 mm RM 0.40
GI - Precoated - T Section - 3600 mm long
24 mm x 38 mm x 0.7 mm thick RM 1.60
GI - Precoated - T Section - 600 mm long
24 mm x 38 mm x 0.7 mm thick RM 1.60
GI Rod - 4 mm Dia
Connecting Rod RM 1.28
Rawl Plug Nos 1.28

74
STANDARD DATA BOOK – BUILDING WORK ITEMS

Soffit Cleats Nos 1.28


Unversal Holding Clips Nos 5.36
Drywall Top Coat Lits 0.15
B) LABOUR CHARGES
1st Class Carpenter day 0.40
2nd Class Carpenter day 0.40
1st Class Painter day 0.08
2nd Class Painter day 0.08
Power Saw Cutter - Hand Operated - day 0.04
Operator
Power Drill - Hand Operated - Operator day 0.04
Unskilled Mazdoor day 0.24
C) Machinery
Power Saw Cutter - Hand Operated - Hire Hrs 0.32
charges
Power Drill - Hand Operated - Hire Charges Hrs 0.32

Scaffolding charges 1%
BASIC COST per 1 sqm
Armstrong False ceiling
BLD-CSTN- 156 Providing and fixing in true horizontal level
10-33 600 mm x 600 mm 15 mm thick Arm strong
false ceiling system manufactured by M/s
Arm strong world Industries using hot dipped
Galvanised Steel section exposed surface
with pre-coated capping, main Tee of size 24
x 32 mm at every 1200 mm c/c maximum
and rotary stiched cross tee of size 24 x 27
mm at evry 600 mm c/c and sub-cross tee of
size 24 mm x 25 mm at 1200 mm c/c and wall
angle of size 19 x 19 mm fixed to periphery of
the wall and the above grid is suspended at
every 1200 mm c/c in both directions using
2.0 mm thick pre-straightened GI Wire laying
fine fissured butt edge ceiling tiles of 15 mm
thick mineral fiber Board manufactured by
M/s Arm Strong World Industries Ltd., having
RH 99% and for finished of size 600 x 600 mm
including Cost &conveyance of all materials
and labour charges such as cutting , fixing of
standing of frame work exposing roof making
complete for finished item of work

UNIT 1 sqm
A) Material requirement
15 mm - Armstrong Mineral Fiber sheet 600 x sqm 1.00
600
Hotdipped GI Angle - Precoated - Grid
19 mm x 19 mm RM 0.40
Polyster painted GI - T Section - 1200 mm
(1) 24 x 32 mm and (2) 24 x 25 mm (sub-cross RM 1.60
Tee)

75
STANDARD DATA BOOK – BUILDING WORK ITEMS

Polyster painted GI - T Section - 300 mm


24 mm x 27 mm RM 1.60
GI Rod - prestraightened - 2.0 mm dia
Connecting Rod RM 1.28
6 mm Nylon Rawl Plug Nos 1.28
B) LABOUR CHARGES
PER UNIT 1 sqm
1st Class Carpenter day 0.40
2nd Class Carpenter day 0.40
1st Class Painter day 0.08
2nd Class Painter day 0.08
Power Saw Cutter - Hand Operated - day 0.04
Operator
Power Drill - Hand Operated - Operator day 0.04
Unskilled Mazdoor day 0.24
C) Machinery
Power Saw Cutter - Hand Operated - Hire Hrs 0.32
charges
Power Drill - Hand Operated - Hire Charges Hrs 0.32

Scaffolding charges 1%
BASIC COST per 1 sqm
Thermocole False ceiling
BLD-CSTN- 157 Providing and fixing Thermocole False ceiling
10-34 in true horizontal level 600 mm x 600 mm
using 15 mm/ 19 mm thick Thermocole
sheet anodised Aluminium Tee sections of
size 24.50 mm x 24.0 mm x 2.4 mm in grid
with cross tee of size 24 x 24.5 mm at every
600 mm c/c and anodised aluminium wall
angle of size 24 x 24 mm fixed to periphery of
the wall and the above grid is suspended at
every 1200 mm c/c in both directions using
2.0 mm thick GI Wire for finished of size 600
x 600 mm including Cost &conveyance of all
materials and labour charges such as cutting ,
fixing of standing of frame work exposing
roof making complete for finished item of
work

UNIT 1 sqm
A) Material requirement
15 mm/ 19 mm Thermocole sheet 600 x 600 sqm 1.00

Alumninium Angle
24 mm x 24 mm RM 0.40
Anodised Aluminium T Section
(1) 24 x 24.5 x 2.4 mm mm RM 3.20
GI Rod - prestraightened - 2.0 mm dia
Connecting Rod Nos 1.28
Rawl Plugs Nos 1.28
B) LABOUR CHARGES
1st Class Carpenter day 0.36

76
STANDARD DATA BOOK – BUILDING WORK ITEMS

2nd Class Carpenter day 0.36


1st Class Painter day 0.00
2nd Class Painter day 0.00
Power Saw Cutter - Hand Operated - day 0.02
Operator
Power Drill - Hand Operated - Operator day 0.04
Unskilled Mazdoor day 0.20
C) Machinery
Power Saw Cutter - Hand Operated - Hire Hrs 0.16
charges
Power Drill - Hand Operated - Hire Charges Hrs 0.32

Scaffolding charges 1%
BASIC COST per 1 sqm
BLD-CSTN- WHITE WASHING, COLOUR WASHING &
11 DISTEMPERING
BLD-CSTN- 158 White washing one coat with lime of
11-1 approved quality to give an even shade after
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials

Unit: 10 sqm
A. MATERIALS :
Fine screened shell lime cum 0.005
Gum, conjee water, or prickly pear juice L.S
including necessary fire wood
B. LABOUR
Brick Layers day 0.11
Mazdoor (unskilled) day 0.22
Sundries including brushes etc., LS
Total cost for 10 sqm
BLD-CSTN- 159 White washing two coats with lime of
11-2 approved quality to give an even shade after
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials

Unit: 10 sqm
A. MATERIALS :
Fine screened shell lime cum 0.007
Gum, conjee water, or prickly pear juice L.S
including necessary fire wood
B. LABOUR
Brick Layers day 0.160

77
STANDARD DATA BOOK – BUILDING WORK ITEMS

Mazdoor (unskilled) day 0.32


Sundries including brushes etc., LS
Total cost for 10 sqm
BLD-CSTN- 160 White washing three coats with lime of
11-3 approved quality to give an even shade after
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials

Unit: 10 sqm
A. MATERIALS :
Fine screened shell lime cum 0.009
Gum, conjee water, or prickly pear juice L.S
including necessary fire wood
B. LABOUR
White washer day -
Brick Layers day 0.220
Man Mazdoor day -
Women mazdoor day -
Mazdoor (unskilled) day 0.43
Sundries including brushes, ladders etc., LS
Total cost for 10 sqm
BLD-CSTN- 161 White washing one coat with whiting of with White Cement Grade
11-4 approved quality to give an even shade after II
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials

Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement cum / 1.20
kg
Gum, conjee water, or prickly pear juice
including necessary fire wood
B. LABOUR
Brick Layers / Painter day 0.11
Mazdoor (unskilled) day 0.22
Sundries including brushes, ladders, etc., 0.50%
Total cost for 10 sqm

78
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 162 White washing two coats with whiting of


11-5 approved quality to give an even shade after
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials

Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement cum / 2.00
kg
Gum, conjee water, or prickly pear juice L.S
including necessary fire wood
B. LABOUR
Brick Layers / Painter day 0.210
Mazdoor (unskilled) day 0.320
Sundries including brushes, ladders, etc., 1.00%
Total cost for 10 sqm
BLD-CSTN- 163 White washing three coats with whiting of
11-6 approved quality to give an even shade after
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials

Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement cum / 2.800
kg
Gum, conjee water, or prickly pear juice
including necessary fire wood
B. LABOUR
Brick Layers / Painter day 0.300
Mazdoor (unskilled) day 0.430
Total cost for 10 sqm
BLD-CSTN- 164 Colour Washing, One Coat
11-7
Unit: 10 sqm
Rate for "White Washing" one coat 10 1.000
sqm
Add: For Colours, etc., (50 percent of above
rate)
Total
BLD-CSTN- 165 Colour Washing, Two Coats
11-8
Unit: 10 sqm

79
STANDARD DATA BOOK – BUILDING WORK ITEMS

Rate for "White Washing" two coats 10 1.000


sqm
Add: For Colours, etc., (50 percent of above
rate)
Total
BLD-CSTN- 166 Distempering, 2 Coats with Water Bound
11-9 Distemper
Unit: 10 sqm
A. MATERIALS :
Distemper kg 1.340
B. LABOUR
Painter day 0.500
Mazdoor (unskilled) day 1.300
Sundries including brushes, ladders, etc., 1.000%
Total cost for 10 sqm
BLD-CSTN- 167 Distempering, 2 Coats with Oil Bound
11-10 Distemper
Unit: 10 sqm
A. MATERIALS :
Distemper kg 1.700
B. LABOUR
Painter day 1.200
Sundries including brushes, ladders, etc., 1.000%
Total cost for 10 sqm
BLD-CSTN- PAINTING & VARNISHING
12
BLD-CSTN- 168 Painting to new walls with 2 coats of ready
12-1 mixed oil bound wahsable distemper of
approved brand and shade over a base coat
of appropriate primer of approved brand,
making 3 coats in all to give an even shade
after thourughly brushing the surface to
remove all dirt and remains of loose
powdered materials, including cost and
conveyance of all materials to work site and
all operational, incidental, labour charges etc.
complete for finished item of work as per SS
911 for internal walls

PRIMARY COAT:
Cost of Primer Lts 0.50
Painter I st class Nos 0.08
Pianter Iind class Nos 0.19
Cost of washable Oil Bound Distemper Lts 1.70
1st class painter Nos 0.36
II class painter Nos 0.84
Total cost
BLD-CSTN- 169 Painting, Priming Coat on New Plastered
12-2 Surface
Unit: 10 sqm
A. MATERIALS :
Cement Primer kg 1.00
B. LABOUR

80
STANDARD DATA BOOK – BUILDING WORK ITEMS

Painter day 0.700


Sundries including brushes, soaps, putty etc., 0.500%

Total cost for 10 sqm


BLD-CSTN- 170 Painting Walls with Snowcem or other equal
12-3 and approved Water Proof Cement Paint
over Priming Coat, One Coat (All Colours)
Unit: 10 sqm
A. MATERIALS :
Cement Paint at 5 sqm., per kg kg 2.000
B. LABOUR
Painter day 0.300
Mazdoor (unskilled) day 1.500
Sundries including brushes, etc., 1.000%
Total cost for 10 sqm
BLD-CSTN- 171 Painting Walls with Snowcem or other equal
12-4 and approved Water Proof Cement Paint
over Priming Coat, 2 Coats (All Colours)
Unit: 10 sqm
A. MATERIALS :
Cement Paint at 3 sqm., per kg kg 3.500
B. LABOUR
Painter day 0.500
Mazdoor (unskilled) day 1.500
Sundries including brushes, etc., 1.000%
Total cost for 10 sqm
BLD-CSTN- 172 Painting to new walls with 2 coats of water
12-5 proof cement paint of apporved brand and
shade over a base coat of approved cement
primer grade I making making 3 coats in all to
give an even shade after thourughly brushing
the surface to remove all dirt and remains of
loose powdered materials, including cost and
conveyance of all materials to work site and
all operational, incidental, labour charges etc.
complete for finished item of work as per SS
912 for internal walls

Cost of Cement Primer kg 1.00


Ist class painter day 0.21
2nd class painter day 0.49
Cost of water proof cement Paint of kg 3.50
approved quality
1st class painter day 0.15
2nd class painter day 0.35
Mazdoor (unskilled) day 1.50
Total cost
BLD-CSTN- 173 Painting, Priming Coat on New Wood Work
12-6
Unit: 10 sqm
A. MATERIALS :

81
STANDARD DATA BOOK – BUILDING WORK ITEMS

Wood Primer L 0.700


B. LABOUR
Painter day 0.700
Sundries including brushes, soap, putty etc., 1.000%

Total cost for 10 sqm


BLD-CSTN- 174 Painting, Priming Coat on New Iron Work
12-7
Unit: 10 sqm
A. MATERIALS :
Red Oxide Primer L 0.70
B. LABOUR
Painter day 0.70
Sundries including brushes, soap, putty etc.,

Total cost for 10 sqm


BLD-CSTN- 175 Varnishing to Wood Work, One Coat
12-8
Unit: 10 sqm
A. MATERIALS :
Varnish L 0.800
Linseed Oil - boiled L 0.600
B. LABOUR
Painter day 0.700
Man Mazdoor day 0.700
Sundries including brushes,fuel, size etc.,
Total cost for 10 sqm
BLD-CSTN- 176 Varnishing to Wood Work, Two Coats
12-9
Unit: 10 sqm
A. MATERIALS :
Varnish L 1.200
Linseed Oil - boiled L 1.100
B. LABOUR
Painter day 1.100
Man Mazdoor day 1.100
Sundries including brushes,fuel, size etc.,
Total cost for 10 sqm
BLD-CSTN- 177 Painting with Ready mixed oil paint (all
12-10 colours)
i. One Coat - New Wood Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint kg 1.600
B. LABOUR
Painter day 0.700
Sundries including brushes, soap, putty etc., LS

Total cost for 10 sqm


178 Two Coats - New Wood Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint kg 2.800

82
STANDARD DATA BOOK – BUILDING WORK ITEMS

B. LABOUR
Painter day 1.200
Sundries including brushes, soap, putty etc., LS

Total cost for 10 sqm


179 One Coat - Old Wood Work & New Iron Work
:
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint kg 1.500
B. LABOUR
Painter day 0.700
Sundries including brushes, soap, putty etc., LS

Total cost for 10 sqm


180 Two Coats - Old Wood Work & New Iron
Work:
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint kg 2.4.
B. LABOUR
Painter day 1.200
Sundries including brushes, soap, putty etc., LS
Total cost for 10 sqm
181 One Coat - Old Iron Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint kg 1.200
B. LABOUR
Painter day 0.700
Sundries including brushes, soap, putty etc., LS
Total cost for 10 sqm
182 Two Coats - Old Iron Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint kg 2.100
B. LABOUR
Painter day 1.100
Sundries including brushes, soap, putty etc., LS
Total cost for 10 sqm
183 Three Coats - Old Iron Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint kg 3.400
B. LABOUR
Painter day 1.500
Sundries including brushes, soap, putty etc., LS
Total cost for 10 sqm
184 Three Coats - New Wood Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint kg 3.900

83
STANDARD DATA BOOK – BUILDING WORK ITEMS

B. LABOUR
Painter day 1.600
Sundries including brushes, soap, putty etc., LS

Total cost for 10 sqm


BLD-CSTN- 185 Painting with :
12-11
i. Plastic Emulsion paint Grade I - One Coat
for New Wood Work, Old Wood Work & New
Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per L 0.500
British Paints (I) Ltd.
B. LABOUR
Painter day 0.700
Sundries including brushes, soap, putty etc.,

Total cost for 10 sqm


186 Plastic Emulsion paints - One Coat for Old
Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per L 0.400
British Paints (I) Ltd.
B. LABOUR
Painter day 0.700
Sundries including brushes, soap, putty etc.,

Total cost for 10 sqm


187 Plastic Emulsion paints - Two Coats for New
Wood Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per L 0.900
British Paints (I) Ltd.
B. LABOUR
Painter day 1.200
Sundries including brushes, soap, putty etc.,

Total cost for 10 sqm


188 Plastic Emulsion paints - Two Coats for Old
Wood Work & New Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per L 0.800
British Paints (I) Ltd.
B. LABOUR
Painter day 1.200
Sundries including brushes, soap, putty etc.,

Total cost for 10 sqm


189 Plastic Emulsion paints - Two Coats for New
Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per L 0.800
British Paints (I) Ltd.

84
STANDARD DATA BOOK – BUILDING WORK ITEMS

B. LABOUR
Painter day 1.100
Sundries including brushes, soap, putty etc.,

Total cost for 10 sqm


190 Plastic Emulsion paints - Two Coats for Old
Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per L 0.700
British Paints (I) Ltd.
B. LABOUR
Painter day 1.100
Sundries including brushes, soap, putty etc.,

Total cost for 10 sqm


191 Plastic Emulsion paints - Three Coats for
New Wood Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per L 1.200
British Paints (I) Ltd.
B. LABOUR
Painter day 1.600
Sundries including brushes, soap, putty etc.,

Total cost for 10 sqm


192 Plastic Emulsion paints - Three Coats for Old
Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per L 1.100
British Paints (I) Ltd.
B. LABOUR
Painter day 1.500
Sundries including brushes, soap, putty etc.,

Total cost for 10 sqm


BLD-CSTN- 193 Painting with Synthetic Enamel paints - One
12-12 Coat - for New Wood Work, Old Wood Work
& New Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as L 0.700
per British Paints (I) Ltd.
B. LABOUR
Painter day 0.700
Sundries including brushes, soap, putty etc.,

Total cost for 10 sqm


194 Painting with Synthetic Enamel paints - One
Coat - For Old Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as L 0.500
per British Paints (I) Ltd.
B. LABOUR
Painter day 0.700

85
STANDARD DATA BOOK – BUILDING WORK ITEMS

Sundries including brushes, soap, putty etc.,

Total cost for 10 sqm


195 Painting with Synthetic Enamel paints - Two
Coats - for New Wood Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as L 1.200
per British Paints (I) Ltd.
B. LABOUR
Painter day 1.200
Sundries including brushes, soap, putty etc.,

Total cost for 10 sqm


196 Painting with Synthetic Enamel paints - Two
Coats - For Old Wood Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as L 1.100
per British Paints (I) Ltd.
B. LABOUR
Painter day 1.200
Sundries including brushes, soap, putty etc.,

Total cost for 10 sqm


197 Painting with Synthetic Enamel paints - Two
Coats - For New Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as L 1.100
per British Paints (I) Ltd.
B. LABOUR
Painter day 1.100
Sundries including brushes, soap, putty etc.,

Total cost for 10 sqm


198 Painting with Synthetic Enamel paints - Two
Coats - For Old Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as L 0.900
per British Paints (I) Ltd.
B. LABOUR
Painter day 1.100
Sundries including brushes, soap, putty etc.,

Total cost for 10 sqm


199 Painting with Synthetic Enamel paints - Three
Coats - for New Wood Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as L 1.700
per British Paints (I) Ltd.
B. LABOUR
Painter day 1.600
Sundries including brushes, soap, putty etc.,

Total cost for 10 sqm

86
STANDARD DATA BOOK – BUILDING WORK ITEMS

200 Painting with Synthetic Enamel paints - Three


Coats - For Old Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as L 1.600
per British Paints (I) Ltd.
B. LABOUR
Painter day 1.500
Sundries including brushes, soap, putty etc.,

Total cost for 10 sqm


BLD-CSTN- 201 Polishing on wood work with readymade wax
12-13 polish of approved brand and manufacture

New Work :
A. MATERIALS :
Readymade wax polish kg 0.500
B. LABOUR
Painter day 0.800
Helper day 0.800
Sundries including brushes, soap, cloth etc., LS

Total cost for 10 sqm


BLD-CSTN- 202 Melamine polishing on wood work (one coat)
12-14
New Work :
A. MATERIALS :
Melamine polish L 0.650
B. LABOUR
Painter day 0.800
Healper day 0.800
Sundries for Spraying Machine etc., LS
Total cost for 10 sqm
BLD-CSTN- 203 French Spirit polishing Two or more coats on
12-15 new works including a coat of wood filler.
A. MATERIALS :
Shellac kg 0.228
Spirit L 1.630
B. LABOUR
Painter day 3.200
Sundries such as pigment, terpentaine, sand LS
paper, putty, wood filler, white woolen cloth,
linseed oil, cotton etc.,
Total cost for 10 sqm
BLD-CSTN- WOOD WORK, ALUMINUM DOORS,
13 WINDOWS, VENTILATORS Etc.,
BLD-CSTN- 204 Best Teak Wood wrought and put up to 2
13-1 meters (Schedule Item No 286)
Unit = 1 cum
Materials :—
Teak wood large scantlings upto 2 m cum 1.000
Labour :—
Carpenter day 17.700
Man Mazdoor day 8.800

87
STANDARD DATA BOOK – BUILDING WORK ITEMS

Sundries including nails, screws etc., LS


Cost per cum
BLD-CSTN- 205 Best Teak Wood wrought and put up over 2
13-2 metres and below 3 metres in length
(Schedule Item No 287)
Unit = 1 cum
Materials :—
Teak wood large scantlings over 2 m and cum 1.000
below 3 m in length
Labour :—
Carpenter day 17.700
Man Mazdoor day 8.800
Sundries including nails, screws etc., LS
Cost per cum
BLD-CSTN- 206 Best Teak Wood wrought and put up in large
13-3 scantling of over 3 metres in length (Schedule
Item No 288)
Unit = 1 cum
Materials :—
Teak wood large scantlings over 2 m and cum 1.000
below 3 m in length
Labour :—
Carpenter day 17.700
Man Mazdoor day 8.800
Sundries including nails, screws etc., LS
Cost per cum
BLD-CSTN- 207 Best Teak Wood wrought and put up for
13-4 trusses including straps and all iron work
(Schedule Item No 289)
Unit = 1 cum
Materials :—
Teak wood large scantlings cum 1.000
Iron Work (average) kg 112.000
Labour :—
Carpenter day 26.500
Man Mazdoor day 8.800
Sundries including nails, screws etc., LS
Cost per cum
BLD-CSTN- 208 Fully Panelled doors - External or Internal -
13-5 Moulded panels (Schedule Item No 290)
Single Shutter
800 x 2000 mm
*Teak wood cum 0.083
Labour, wrought and putup in position frame sqm 1.600
& shutters
Sundries inclusive of holdfasts and all wind LS
appliances (Vide relevant standard
specification)
Total for each door
209 900 x 2000 mm
*Teak wood cum 0.088
Labour, wrought and putup in position frame sqm 1.800
& shutters

88
STANDARD DATA BOOK – BUILDING WORK ITEMS

Sundries inclusive of holdfasts and all wind


appliances (Vide relevant standard
specification)
Total for each door
210 1100 x 2000 mm
*Teak wood cum 0.109
Labour, wrought and putup in position frame sqm 2.200
& shutters
Sundries inclusive of holdfasts and all wind LS
appliances (Vide relevant standard
specification)
Total for each door
211 1200 x 2100 mm
*Teak wood cum 0.123
Labour, wrought and putup in position frame sqm 2.520
& shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard
specification)
Total for each door
212 900 x 2100 mm
*Teak wood cum 0.094
Labour, wrought and putup in position frame sqm 1.890
& shutters
Sundries inclusive of holdfasts and all wind LS
appliances (Vide relevant standard
specification)
Total for each door
213 1500 x 2400 mm
*Teak wood cum 0.159
Labour, wrought and putup in position frame sqm 3.600
& shutters
Sundries inclusive of holdfasts and all wind LS
appliances (Vide relevant standard
specification)
Total for each door
214 Double Shutter
900 x 2000 mm
*Teak wood cum 0.096
Labour, wrought and putup in position frame sqm 1.800
& shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard
specification)
Total for each door
215 1000 x 2000 mm
*Teak wood cum 0.104
Labour, wrought and putup in position frame sqm 2.000
& shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard
specification)
Total for each door

89
STANDARD DATA BOOK – BUILDING WORK ITEMS

216 1300 x 2200 mm


*Teak wood cum 0.134
Labour, wrought and putup in position frame sqm 2.860
& shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard
specification)
Total for each door
217 1400 x 2300 mm
*Teak wood cum 0.147
Labour, wrought and putup in position frame sqm 3.220
& shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard
specification)
Total for each door
* Note : Average rate for respective size
scantlings and rough plank
BLD-CSTN- 218 Fully Panelled doors - Internal Five Ply - Ply-
13-6 wood Panels (Schedule Item No 291)
Single Shutter
800 x 2000 mm
*Teak wood cum 0.068
Five - Ply - Ply - Wood brich sqm 0.720
Labour, wrought and putup in position frame sqm 1.600
& shutters
Sundries inclusive of holdfasts and all wind LS
appliances (Vide relevant standard
specification)
Total for each door
219 900 x 2000 mm
*Teak wood cum 0.071
Five - Ply - Ply - Wood brich sqm 0.870
Labour, wrought and putup in position frame sqm 1.800
& shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard
specification)
Total for each door
220 1200 x 2100 mm
*Teak wood cum 0.100
Five - Ply - Ply - Wood brich sqm 1.160
Labour, wrought and putup in position frame sqm 2.520
& shutters
Sundries inclusive of holdfasts and all wind LS
appliances (Vide relevant standard
specification)
Total for each door
221 1300 x 2200 mm
*Teak wood cum 0.106
Five - Ply - Ply - Wood brich sqm 1.390
Labour, wrought and putup in position frame sqm 2.860
& shutters

90
STANDARD DATA BOOK – BUILDING WORK ITEMS

Sundries inclusive of holdfasts and all wind


appliances (Vide relevant standard
specification)
Total for each door
222 900 x 2100 mm
*Teak wood cum 0.077
Five - Ply - Ply - Wood brich sqm 0.880
Labour, wrought and putup in position frame sqm 1.890
& shutters
Sundries inclusive of holdfasts and all wind LS
appliances (Vide relevant standard
specification)
Total for each door
223 1000 x 2100 mm
*Teak wood cum 0.091
Five - Ply - Ply - Wood brich sqm 0.880
Labour, wrought and putup in position frame sqm 2.100
& shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard
specification)
Total for each door
224 Double Shutter
900 x 2000 mm
*Teak wood cum 0.082
Five - Ply - Ply - Wood brich sqm 0.710
Labour, wrought and putup in position frame sqm 1.800
& shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard
specification)
Total for each door
225 1000 x 2000 mm
*Teak wood cum 0.088
Five - Ply - Ply - Wood brich sqm 0.820
Labour, wrought and putup in position frame sqm 2.000
& shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard
specification)
Total for each door
226 1100 x 2000 mm
*Teak wood cum 0.090
Five - Ply - Ply - Wood brich sqm 0.940
Labour, wrought and putup in position frame sqm 2.200
& shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard
specification)
Total for each door
227 1400 x 2300 mm
*Teak wood cum 0.123
Five - Ply - Ply - Wood brich sqm 1.900

91
STANDARD DATA BOOK – BUILDING WORK ITEMS

Labour, wrought and putup in position frame sqm 3.600


& shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard
specification)
Total for each door
228 1500 x 2400 mm
*Teak wood cum 0.130
Five - Ply - Ply - Wood brich sqm 1.280
Labour, wrought and putup in position frame sqm 3.600
& shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard
specification)
Total for each door
* Note : Average rate for respective size
scantlings and rough plank
BLD-CSTN- 229 Furniture - Iron - for External doors (Schedule
13-7 Item 292)
Top Tower bolts (Ave : Size) Nos 2
Bottom Tower bolts 150mm long Nos 2
Parliament hings with screws Nos 6
Oxidised aldrop with bolts Nos 1
Wind cleats with hings Nos 2
(Same for all doors)
BLD-CSTN- 230 Furniture - Iron - Internal doors (Schedule
13-8 Item 293)
Top Tower bolts (Ave : Size) Nos 1
Bottom Tower bolts 150mm long Nos 2
Butt hings with screws Nos 6
Wind cleats with hings Nos 2
(Same for all doors)
BLD-CSTN- 231 Glazed and Panelled doors (Schedule Item
13-9 No. 294)
Single Shutter
800 x 2000 mm
*Teak wood cum 0.072
Glass sqm 0.470
Labour, wrought and putup in position frame sqm 1.600
& shutters
Sundries inclusive of putty, brads, hold fasts LS
and all wind appliances (Vide relevant
standard specification)
Total for each door
232 900 x 2000 mm
*Teak wood cum 0.076
Glass sqm 0.560
Labour, wrought and putup in position frame sqm 1.800
& shutters
Sundries inclusive of putty, brads, hold fasts LS
and all wind appliances (Vide relevant
standard specification)
Total for each door

92
STANDARD DATA BOOK – BUILDING WORK ITEMS

233 1200 x 2100 mm


*Teak wood cum 0.106
Glass sqm 0.760
Labour, wrought and putup in position frame sqm 2.520
& shutters
Sundries inclusive of putty, brads, hold fasts LS
and all wind appliances (Vide relevant
standard specification)
Total for each door
234 1300 x 2200 mm
*Teak wood cum 0.115
Glass sqm 0.870
Labour, wrought and putup in position frame sqm 2.860
& shutters
Sundries inclusive of putty, brads, hold fasts LS
and all wind appliances (Vide relevant
standard specification)
Total for each door
235 Double Shutter
900 x 2000 mm
*Teak wood cum 0.087
Glass sqm 0.420
Labour, wrought and putup in position frame sqm 1.800
& shutters
Sundries inclusive of putty, brads, hold fasts LS
and all wind appliances (Vide relevant
standard specification)
Total for each door
236 1000 x 2000 mm
*Teak wood cum 0.092
Glass sqm 0.510
Labour, wrought and putup in position frame sqm 2.000
& shutters
Sundries inclusive of putty, brads, hold fasts LS
and all wind appliances (Vide relevant
standard specification)
Total for each door
237 1100 x 2000 mm
*Teak wood cum 0.096
Glass sqm 0.600
Labour, wrought and putup in position frame sqm 2.200
& shutters
Sundries inclusive of putty, brads, hold fasts LS
and all wind appliances (Vide relevant
standard specification)
Total for each door
238 1400 x 2300 mm
*Teak wood cum 0.123
Glass sqm 1.060
Labour, wrought and putup in position frame sqm 3.220
& shutters

93
STANDARD DATA BOOK – BUILDING WORK ITEMS

Sundries inclusive of putty, brads, hold fasts LS


and all wind appliances (Vide relevant
standard specification)
Total for each door
239 1500 x 2400 mm
*Teak wood cum 0.130
Glass sqm 1.280
Labour, wrought and putup in position frame sqm 3.600
& shutters
Sundries inclusive of putty, brads, hold fasts LS
and all wind appliances (Vide relevant
standard specification)
Total for each door
* Note : Average rate for respective size
scantlings and rough planks.
BLD-CSTN- 240 Furniture - Same as for Fully Panelled Doors
13-10 External (Schedule Item No. 295)
Total for each door
BLD-CSTN- 241 Framed and Planked Doors (Schedule Item
13-11 No. 296)
1000 x 2000 mm
*Teak wood cum 0.107
Labour, wrought and putup in position frame sqm 2.000
& shutters
Sundries inclusive of putty, brads, hold fasts LS
and wind appliances and screws for planks
(Vide standard specification)
Total for each door
242 1200 x 2100 mm
*Teak wood cum 0.127
Labour, wrought and putup in position frame sqm 2.520
& shutters
Sundries inclusive of putty, brads, hold fasts LS
and wind appliances and screws for planks
(Vide standard specification)
Total for each door
* Note : Average rate for respective size
scantlings and rough planks.
BLD-CSTN- 243 Country wood Framed and Planked Doors
13-12 (Schedule Item No. 297)
Single Shutter :
1000 x 2000 mm
Country wood cum 0.107
Labour, wrought and putup in position frame sqm 2.000
& shutters
Sundries inclusive of putty, brads, hold fasts LS
and wind appliances and screws for planks
(Vide standard specification)
Total for each door
244 1200 x 2100 mm
Country wood cum 0.127
Labour, wrought and putup in position frame sqm 2.520
& shutters

94
STANDARD DATA BOOK – BUILDING WORK ITEMS

Sundries inclusive of putty, brads, hold fasts LS


and wind appliances and screws for planks
(Vide standard specification)
Total for each door
BLD-CSTN- 245 Furniture - 6 Butt Hings - 1 Top and 2 Bottom
13-13 Tower Bolts and One Wrought steel safety
Hasp L.S. (Schedule Item No. 298)

Each Door
BLD-CSTN- 246 Ledged Braced and Planked Doors (Schedule
13-14 Item No. 299)
Single Shutter :
800 x 2000 mm
*Teak wood cum 0.083
Labour, wrought and putup in position frame sqm 1.600
& shutters
Sundries inclusive of hold fasts and wind LS
appliances and nails for planks (Vide standard
specification)
** Furniture - 3 Nos T - hinges - Vide SS for LS
size - 2 Nos Chain and slopes country make.

Total for each door


247 1000 x 2100 mm
*Teak wood cum 0.100
Labour, wrought and putup in position frame sqm 2.100
& shutters
Sundries inclusive of hold fasts and wind LS
appliances and nails for planks (Vide standard
specification)
** Furniture - 3 Nos T - hinges - Vide SS for LS
size - 2 Nos Chain and slopes country make.

Total for each door


Note : * Average rate for respective size
scantlings and rough planks.
** Note that for this type of door the
furniture will be supplied and fixed by the
contractor.
BLD-CSTN- 248 * Country wood Ledged Braced and Planked
13-15 Doors (Schedule Item No. 300)
800 x 2000 mm
Country wood cum 0.083
Labour, wrought and putup in position frame sqm 1.600
& shutters
Sundries inclusive of hold fasts and wind LS
appliances and nails for planks (Vide standard
specification)
** Furniture - 3 Nos T - hinges - Vide SS for LS
size - 2 Nos Chain and slopes country make.

Total for each door


249 1000 x 2100 mm

95
STANDARD DATA BOOK – BUILDING WORK ITEMS

Country wood cum 0.100


Labour, wrought and putup in position frame sqm 2.100
& shutters
Sundries inclusive of hold fasts and wind LS
appliances and nails for planks (Vide standard
specification)
** Furniture - 3 Nos T - hinges - Vide SS for LS
size - 2 Nos Chain and slopes country make.

Total for each door


** Note that for this type of door the
furniture will be supplied and fixed by the
contractor.
Note : * Class of Country wood to be defined
in relevent schedule item.
BLD-CSTN- 250 Flush type Doors with 35mm Thick Flush
13-16 Shutters with Bondwood solied Block Board
Type Faced on Both the sides with
Commercial Type Plywood (Schedule Item
No. 301.)
Single Shutter :
900 x 2000 mm
*Teak wood cum 0.035
Flush Shutter 35mm thick (Vide relevant sqm 1.530
standard specification)
Labour, wrought and putup in position frame sqm 1.800
& shutters
Sundries inclusive of hold fasts and all wind
appliances (Vide standard specification)
Total for each door
251 1000 x 2100 mm
*Teak wood cum 0.037
Flush Shutter 35mm thick (Vide relevant sqm 1.820
standard specification)
Labour, wrought and putup in position frame sqm 2.100
& shutters
Sundries inclusive of hold fasts and all wind
appliances (Vide standard specification)

Total for each door


*Note : Average rate for respective size
scantlings.
BLD-CSTN- 252 Windows Glazed (Schedule Item No. 302)
13-17
Single Shutter :
600 x 1200 mm
*Teak wood cum 0.028
Glass sqm 0.390
Labour, wrought and putup in position frame sqm 0.720
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)

96
STANDARD DATA BOOK – BUILDING WORK ITEMS

Total for each window


253 800 x 1200 mm
*Teak wood cum 0.037
Glass sqm 0.500
Labour, wrought and putup in position frame sqm 0.960
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)
Total for each window
254 Double Shutter :
1000 x 1200 mm
*Teak wood cum 0.041
Glass sqm 0.700
Labour, wrought and putup in position frame sqm 1.200
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)
Total for each window
255 1200 x 1200 mm
*Teak wood cum 0.061
Glass sqm 0.710
Labour, wrought and putup in position frame sqm 1.440
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)
Total for each window
256 1500 x 1200 mm (3 Pannels)
*Teak wood cum 0.072
Glass sqm 0.920
Labour, wrought and putup in position frame sqm 1.800
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)
Total for each window
257 1000 x 1700 mm (2 Pannels)
*Teak wood cum 0.059
Glass sqm 0.970
Labour, wrought and putup in position frame sqm 1.700
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)
Total for each window
*Note : Average rate for respective size scantlings.
BLD-CSTN- 258 Furniture for Double Leaf Windows Glazed
13-18 With Top Lights (Schedule Item No. 303)
Banel Bolts 100 mm long each 2
Top tower bolts 150 mm long each 2
Bottom bolts 150 mm long each 2

97
STANDARD DATA BOOK – BUILDING WORK ITEMS

Parliament hinges each 4


BLD-CSTN- 259 Furniture for Double Leaf Windows Glazed LS
13-19 without Top Lights (Schedule Item No. 304)
Top tower bolts 150 mm long each 2
Bottom bolts 150 mm long each 2
Parliament hinges each 4
Same for all such windows
BLD-CSTN- 260 Furniture for Single Leaf Windows Glazed LS
13-20 without Top Lights (Schedule Item No. 305)
Top tower bolts 150 mm long each 1
Bottom tower bolts 150 mm long each 1
Parliament hinges each 2
Same for all such windows
BLD-CSTN- 261 Windows Panelled (Schedule Item No. 306)
13-21
Single Shutter
600 x 1200 mm
*Teak wood cum 0.039
Labour, wrought and putup in position frame sqm 0.720
& shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window
262 700 x 1200 mm
**Teak wood cum 0.043
Labour, wrought and putup in position frame sqm 0.840
& shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window
263 Double Shutter
800 x 1200 mm
*Teak wood cum 0.051
Labour, wrought and putup in position frame sqm 0.960
& shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window
264 1000 x 12000 mm
*Teak wood cum 0.059
Labour, wrought and putup in position frame sqm 1.200
& shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window
265 1200 x 1200 mm
*Teak wood cum 0.081
Labour, wrought and putup in position frame sqm 1.440
& shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window

98
STANDARD DATA BOOK – BUILDING WORK ITEMS

*Note : Average rate for respective size


scantlings.
266 900 x 1200 mm
**Teak wood cum 0.056
Labour, wrought and putup in position frame sqm 1.080
& shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window
**Note : Average rate for respective size
scantlings and rough planks.
BLD-CSTN- 267 Windows Panelled & Glazed (Schedule Item
13-22 No. 307)
Single Shutter
600 x 1200 mm
**Teak wood cum 0.036
Glass sqm 0.070
Labour, wrought and putup in position frame sqm 0.720
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)
Total for each window
268 Double Shutter
900 x 1200 mm
**Teak wood cum 0.052
Glass sqm 0.100
Labour, wrought and putup in position frame sqm 1.080
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)
Total for each window
269 1200 x 1200 mm
**Teak wood cum 0.077
Glass sqm 0.120
Labour, wrought and putup in position frame sqm 1.440
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)
Total for each window
270 1500 x 1200 mm (3 Pannels)
**Teak wood cum 0.094
Glass sqm 0.150
Labour, wrought and putup in position frame sqm 1.800
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)
Total for each window
**Note : Average rate for respective size
scantlings and rough planks.

99
STANDARD DATA BOOK – BUILDING WORK ITEMS

271 Furniture for Windows Panelled : Single Leaf


with half Shutters (Schedule Item No. 308)

Cabin hooks and eyes 200 mm long each 2


Butt hinges 75 mm size each 4
Top tower bolts 150 mm long each 1
Bottom bolts 150 mm long each 1
Same for all such windows
BLD-CSTN- 272 Furniture for Windows Panelled : Double Leaf
13-23 with half Shutters (Schedule Item No. 309)

Cabin hooks and eyes 200 mm long each 4


Butt hinges 75 mm size each 8
Top tower bolts 150 mm long each 2
Bottom bolts 150 mm long each 2
Same for all such windows
BLD-CSTN- 273 Teak Wood Windows - Ledged Braced and
13-24 Planked (Schedule Item No. 310)
600 x 1200 mm (half Shutters)
*Teak wood cum 0.034
Labour, wrought and putup in position frame sqm 0.720
& shutters
Sundries inclusive of all furniture and fitting LS
in accordance with relevant standard
specification
Total for each window
274 800 x 1200 mm (half Shutters)
*Teak wood cum 0.048
Labour, wrought and putup in position frame sqm 0.960
& shutters
Sundries inclusive of all furniture and fitting LS
in accordance with relevant standard
specification
Total for each window
275 900 x 1200 mm (half Shutters)
*Teak wood cum 0.052
Labour, wrought and putup in position frame sqm 1.080
& shutters
Sundries inclusive of all furniture and fitting LS
in accordance with relevant standard
specification
Total for each window
276 1000 x 1200 mm (half Shutters)
*Teak wood cum 0.052
Labour, wrought and putup in position frame sqm 1.200
& shutters
Sundries inclusive of all furniture and fitting LS
in accordance with relevant standard
specification
Total for each window
*Note : Average rate for respective size
scantlings and rough planks.

100
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 277 Ventilators Glazed - Fixed Double Frame and


13-25 with Wire Netting (Schedule Item No. 312)

800 x 500 mm
*Teak wood cum 0.012
Glass sqm 0.240
Wire netting sqm 0.190
Labour, wrought and putup in position sqm 0.400
Sundries inclusive of putty brads and iron LS
hold fasts where such are necessary say in 30
cm wall.
Total for each Ventilator
278 1000 x 500 mm
*Teak wood cum 0.014
Glass sqm 0.310
Wire netting sqm 0.240
Labour, wrought and putup in position sqm 0.500
Sundries inclusive of putty brads and iron LS
hold fasts where such are necessary say in 30
cm wall.
Total for each Ventilator
279 1200 x 600 mm
*Teak wood cum 0.018
Glass sqm 0.480
Wire netting sqm 0.290
Labour, wrought and putup in position sqm 0.720
Sundries inclusive of putty brads and iron LS
hold fasts where such are necessary say in 30
cm wall.
Total for each Ventilator
*Note : Average rate for respective size
scantlings
BLD-CSTN- 280 Swing Ventilators - Glazed (Schedule Item
13-26 No. 313)
800 x 500 mm
*Teak wood cum 0.021
Glass sqm 0.190
Labour, wrought and putup in position frame sqm 0.400
& shutters
Sundries inclusive of putty brads sash centres LS
brass ring iron cleats and window card - vide
relevant standard specifications.

Total for each Ventilator


281 1000 x 500 mm
*Teak wood cum 0.025
Glass sqm 0.024
Labour, wrought and putup in position frame sqm 0.500
& shutters
Sundries inclusive of putty brads sash centres LS
brass ring iron cleats and window card - vide
relevant standard specifications.
Total for each Ventilator

101
STANDARD DATA BOOK – BUILDING WORK ITEMS

282 1200 x 600 mm


*Teak wood cum 0.030
Glass sqm 0.390
Labour, wrought and putup in position frame sqm 0.720
& shutters
Sundries inclusive of putty brads sash centres LS
brass ring iron cleats and window card - vide
relevant standard specifications.

Total for each Ventilator


*Note : Average rate for respective size
scantlings and rough planks.
Aluminium Fixed Glazing
BLD-CSTN- 283 Supply and fixing of aluminimum fixed
13-27 glazing as per drawing using standard
powder coated/ anodised aluminimum
section of 101.4 x 44.45 x 3.18 mm thick
fitted with 6.0mm thick / 4.0 mm thick plain
glass glazing fitted with suitable Aluminimum
glazing clips and aproved brand silicon
sealant including cost and conveyance of all
materials labour charges for manufacturing
fixing in position using wooden blocks and
sheet metal screw etc. to complete for
finished item of work as approved by
Engineer-in-charge

Unit - 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION Kgs as per design
GLAZING with GLASS sqm as per design
SILICON SEALANT Kgs as per design
RUBBER BEADING RM as per design
B) LABOUR CHARGES
1st Class Carpenter day 0.947
2nd Class Carpenter day 1.158
Power Saw Cutter - Hand Operated - day 0.105
Operator
Power Drill - Hand Operated - Operator day 0.211
Unskilled Mazdoor day 0.632
C) Machinery
Power Saw Cutter - Hand Operated - Hire Hrs 0.842
charges
Power Drill - Hand Operated - Hire Charges Hrs 1.684
Supervision Charges Nos 0.211
Power charges for Motors 1%
BASIC COST per 1 sqm
Aluminimum Partition partly glazed

102
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 284 Supply and fixing of aluminimum Partition


13-28 partly glazed as per drawing using standard
powder coated/ anodised aluminimum
section of 101.4 x 44.45 x 3.18 mm thick
fitted with 12.0mm thick Particle Boards -
prelaminated up to 2.1 M height and balance
height provided with 5.0 mm thick plain glass
glazing fitted with suitable Aluminimum
glazing clips and aproved brand silicon
sealant including cost and conveyance of all
materials labour charges for manufacturing
fixing in position using wooden blocks and
sheet metal screw etc. to complete for
finished item of work as approved by
Engineer-in-charge

Unit - 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION Kgs as per design
PARTICLE BOARD - Prelaminated sqm as per design
GLAZING with GLASS sqm as per design
SILICON SEALANT Kgs as per design
RUBBER BEADING RM as per design
B) LABOUR CHARGES
1st Class Carpenter day 1.042
2nd Class Carpenter day 1.042
Power Saw Cutter - Hand Operated - day 0.104
Operator
Power Drill - Hand Operated - Operator day 0.139
Unskilled Mazdoor day 0.347
C) Machinery
Power Saw Cutter - Hand Operated - Hire Hrs 0.833
charges
Power Drill - Hand Operated - Hire Charges Hrs 1.111

Supervision Charges Nos 0.174


Power charges for Motors 1%
BASIC COST per 1 sqm
BLD-CSTN- 285 Aluminium Anodised Casement windows
13-29
Unit - 1 sqm

103
STANDARD DATA BOOK – BUILDING WORK ITEMS

Supply and fixing Aluminium Anodised


Casement windows as per approved drawing
with aluminium anodised sections of Series C
Jindal Hollow sections and outer frame of
8804 of size 46 x 44 mm, Shutter frame of
8802 of size 44 mm x 46 mm and Mullion
frame of 8803 of size 59 x 38 and glazing
section of 4433 with plain clear float glass 6
mm thick fixed including supply and fixing
aluminium powder coated 1 No.of casement
friction stay hinges for each shutter, 1 Nos.
aluminium handles of 150 mm for each
shutter and all labour charges for fixing the
fixtures with required no.of screws, bolts and
nuts and including labour charges for fixing
the frame in position, fixing shutter to frame
etc. completed for finished item of work

Unit - 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION Kgs as per design
GLAZING with GLASS sqm as per design
SILICON SEALANT Kgs as per design
RUBBER BEADING RM as per design
Alum.Anodised.PC Friction stay casement Each as per design
hinges
Alum.Anodised.PC Handles Each as per design
B) LABOUR CHARGES
1st Class Carpenter day 0.360
2nd Class Carpenter day 1.081
Power Saw Cutter - Hand Operated - day 0.360
Operator
Power Drill - Hand Operated - Operator day 0.360
Unskilled Mazdoor day 1.081
C) Machinery
Power Saw Cutter - Hand Operated - Hire Hrs 2.883
charges
Power Drill - Hand Operated - Hire Charges Hrs 2.883

Supervision Charges Nos 0.360


Power charges for Motors 1%
BASIC COST per 1 sqm
Aluminium Two/ Three Track Sliding
Windows

104
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 286 Supply and fixing Aluminium Anodised Two/


13-30 Three Track Sliding Windows as per approved
drawing with aluminium anodised sections of
Series C Jindal sections and outer frame top
horizontals & both verticals of 8774 of size 62
x 29.5 mm and bottom horizontal - two track
frame of 8773 of size 62 x 29.5 mm, Shutter
frame top, bottom and verticals of 8304 of
size 50 mm x 20 mm and Weather
interlocking frame of 8306 of size 50 x 20
with plain clear float glass 5 mm thick fixed
including supply and fixing aluminium
handles of 100 mm for each shutter, nylon
rollers assembly and all labour charges for
fixing the fixtures with required no.of screws,
bolts and nuts and including labour charges
for fixing the frame in position, fixing shutter
to frame etc. completed for finished item of
work

UNIT 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION Kgs as per design
GLAZING with GLASS sqm as per design
SILICON SEALANT Kgs as per design
RUBBER BEADING RM as per design
Alum.Anodised.PC Handles Each as per design
B) LABOUR CHARGES
1st Class Carpenter day 0.347
2nd Class Carpenter day 1.042
Power Saw Cutter - Hand Operated - day 0.347
Operator
Power Drill - Hand Operated - Operator day 0.347
Unskilled Mazdoor day 1.042
C) Machinery
Power Saw Cutter - Hand Operated - Hire Hrs 2.778
charges
Power Drill - Hand Operated - Hire Charges Hrs 2.778

Supervision Charges Nos 0.347


Power charges for Motors 1%
BASIC COST per 1 sqm
Aluminium Anodised Doors - Single Shutter

105
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 287 Supply and fixing Aluminium Anodised Doors


13-31 - Single Shutter as per approved drawing with
aluminium anodised sections of Jindal
sections and outer frame top horizontals &
both verticals of 2408 of size 101.6 x 44.75 x
3.18 mm Shutter frame top, bottom and
verticals of 4504 of size 44.45 mm x 47.62
mm x 3.18 and Middle lock rail of 4621 of
size 49.91 x 44.45 x 3 mm with plain clear
float glass 5 mm thick fixed including supply
and fixing aluminium handles of 100 mm for
each shutter, floor springs/ hydraulic door
closure assembly and all labour charges for
fixing the fixtures with required no.of screws,
bolts and nuts and including labour charges
for fixing the frame in position, fixing shutter
to frame etc. completed for finished item of
work

UNIT 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION Kgs as per design
GLAZING with GLASS sqm as per design
SILICON SEALANT Kgs as per design
RUBBER BEADING RM as per design
Alum.Anodised.PC Handles Each as per design
Hydraulic Floor Spring/ Door Closure Each as per design
B) LABOUR CHARGES
1st Class Carpenter day 0.417
2nd Class Carpenter day 0.833
Power Saw Cutter - Hand Operated - day 0.417
Operator
Power Drill - Hand Operated - Operator day 0.417
Unskilled Mazdoor day 1.250
C) Machinery
Power Saw Cutter - Hand Operated - Hire Hrs 3.333
charges
Power Drill - Hand Operated - Hire Charges Hrs 3.333

Supervision Charges Nos 0.417


Power charges for Motors 1%
BASIC COST per 1 sqm
BLD-CSTN- DISMANTLING & DEMOLITION
14
BLD-CSTN- 288 Removing white wash or colour wash by steel
14-1 wire brushing and/or scraping; sand papering
and preparing the wall surface smooth
including necessary repairs to scratches
complete
Details of cost for 10 sq.m
Labour :—
White washer / Mason 2nd Class day 0.010
Mazdoor (unskilled) day 0.170

106
STANDARD DATA BOOK – BUILDING WORK ITEMS

Sundries such as sand paper and scraper etc.

Scaffolding
Add for water charges @ 1 %
Add for contractor's profit and overheads
Cost for 10 sq.m.
Cost per sq.m
BLD-CSTN- 289 Removing white wash or colour wash by steel
14-2 wire brushing and/or scraping; sand papering
and preparing the ceiling and/or sloping
roofs surface smooth including necessary
repairs to scratches complete
Deatailed cost for 10 sqm
Rate as per above item 10
sqm
Add 10 % extra for ceiling / sloping roof
Cost per 10 sq.m
Cost per sq.m
BLD-CSTN- 290 Removing white wash or colour wash by steel
14-3 wire brushing and/or scraping; sand papering
and preparing the wall surface smooth
including necessary repairs to scratches
complete for the wall surface spoiled by
smoke soot
Rate as per Item No (203) 10
sqm
For washing the wall surface spoiled by
smoke soot with clear water before sand
papering the surface smooth and including
necessary repairs to the scratches complete

Details of cost for 10 sq.m


Labour :—
Mazdoor (unskilled) day 0.080
Sundries
Add for water charges @ 1 %
Add for contractor's profit and overheads
Cost for 10 sq.m.
Cost per sq.m
BLD-CSTN- 291 Removing white wash or colour wash by steel
14-4 wire brushing and/or scraping; sand papering
and preparing the ceiling and/or sloping
roofs surface smooth including necessary
repairs to scratches complete for the ceiling
surface spoiled by smoke soot

Rate as per Item No (205) 10


sqm
Extra 10% for washing the surface with clean
water on ceiling and/or sloping roofs
Cost per 10 sq.m
Cost per sq.m

107
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 292 Washing and cleaning of decorated wall


14-5 surfaces with soap, soda and water
Details of cost for 10 sq.m
Labour :—
White washer / Mason 2nd Class day 0.010
Mazdoor (unskilled) day 0.170
Sundries such as soap, soda, sand paper and
scaper etc
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
BLD-CSTN- 293 Washing and cleaning of the old plastered
14-6 ceiling and/or sloping roofs with soap, soda
and water
Rate as per Item above
Extra 10% over
Cost per 10 sq.m
Cost per sq.m
BLD-CSTN- 294 Washing and cleaning of oil and grease spots
14-7 on decorated wall surface by suitable
chemical
Details of cost for 10 sq.m
Labour :—
White washer / Mason 2nd Class day 0.010
Mazdoor (unskilled) day 0.170
Sundries, such as chemical etc.
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
BLD-CSTN- 295 Demolishing and disposal of
14-8 unserviceable materials within 100 metres
lead
Lime concrete.
Details of cost for 1 cu.m.
Labour :-
Mazdoor (unskilled) day 1.220
Sundries
Cost per cu m
296 Unreinforced cement concrete upto 15 cm
thicknes
Details of cost for 1 cu.m.
Labour :-
Mazdoor (unskilled) day 2.440
Sundries
Cost per cu m
297 Unreinforced cement concrete more than 15
cm thickness
Details of cost for 1 cu.m.
Labour :-
Mazdoor (unskilled) day 4.880
Sundries
Cost per cu m

108
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 298 Demolition including stacking of serviceable


14-9 materials and disposal of unserviceable
materials within 100 metres lead

R.C.C. work
Details of cost for 1 cu.m.
Labour :-
Mazdoor (unskilled) day 4.320
Sundries
Cost per cu m
299 Brick work:
Details of cost for 1 cu.m.
Labour :-
Mazdoor (unskilled) day 4.090
Sundries
Cost per cu m
BLD-CSTN- 300 Extra over item 14.2.ii for cutting steel bars in
14-10 R.C.C. of R.B. work (sectional area of R.C.C. or
R.B. Work to be measured) Details of cost for
one Sq.m. of sectional area—
Reinforced area considering 1% Labour for
cuttings 0.01 Sq.m. reinforcement
Blacksmith 2nd class day 0.500
Mazdoor (Male) day 0.500
Sundries
Cost per sq m
BLD-CSTN- 301 Dismantling doors, windows and clear storey
14-11 windows, ventilators etc.; (wood or steel)
shutters including chowkhats, architraves,
hold fasts and other attachments etc.,
complete and stacking them within 100
metre lead
Not exceeding 3 sq.m. in area:
Details of cost per each
Labour :-
Mason, II class day 0.100
Mazdoor (male) day 0.200
Blacksmith II class day 0.050
Sundries
Cost per each
302 Exceeding 3 sq.m. in area
Details of cost per each
Labour :-
Mason, II class day 0.130
Mazdoor (male) day 0.270
Blacksmith II class day 0.070
Sundries
Cost per each
BLD-CSTN- MISCELLANEOUS BUILDING ITEMS
15
BLD-CSTN- 303 Providing and fixing aluminium step edging
15-1 'L' shape of size 38 mm x 12 mm x 3 mm
(thick) to stairs

109
STANDARD DATA BOOK – BUILDING WORK ITEMS

Details of cost for 3 metres length


Materials:—
Aluminium step edging 'L' shape 38 x 12 x m 3.150
3mm (thick) = 3.00 metres with 5% wasage
Carriage of materials
Sundries (Wooden plugs, screws and painting
underneath of strips with bitumanistic paint,
etc.,)
Labour :-
Carpenter II class day 0.090
Mason I class day 0.250
Mazdoor (male) day 0.250
Cost for 3 m
Cost per m
BLD-CSTN- 304 Providing and fixing aluminium step edging
15-2 'L' shape of size 57 mm x16 mm x 3 mm
(thick) to stairs
Details of cost for 3 metres length
Materials:—
Aluminium step edging 'L' shape 57 mm x16 m 3.150
mm x 3 mm (thick) with 5% wasage
Carriage of materials
Sundries (Wooden plugs, screws and painting
underneath of strips with bitumanistic paint,
etc.,)
Labour :-
Carpenter II class day 0.090
Mason I class day 0.250
Mazdoor (male) day 0.250
Cost for 3 m
Cost per m
BLD-CSTN- 305 Cutting RCC steps for fixing of aluminium
15-3 step edging and make good to match the
surroundings
Details of cost for 3 metres
Cement Mortar
Labour :-
Mason, II Class day 1.000
Mazdoor (male) day 0.100
Cost for 3 m
Cost per m
BLD-CSTN- 306 Providing and fixing 25 mm bore galvanised
15-4 M.S. tube (light grade) outlet in cement
mortar 1:3(1 cement: 3 fine sand) including
cutting and making good the wall
Details of cost for 10 pipes 12.5 cm long day
i.e., 1.25 metres
Materials:—
Galvanised mild steel tube (light grade) 25 m 1.310
mm nominal bore 10 x 12.5 cm = 1.25 metre
with wastage of 5%
Labour :-
For cutting and fixing in position

110
STANDARD DATA BOOK – BUILDING WORK ITEMS

Assistant fitter day 0.100


Mason. day 0.400
Mazdoor (male). day 0.400
Sundries
Cost for 1.25 m
Cost per m
BLD-CSTN- 307 Providing and fixing 1.80 metre long RCC
15-5 fencing posts with 6 mm bar nibs as per
design in plate No. 22/2/2. (earth work &
concrete to be paid for separately)
Details of cost for 10 pipes 12.5 cm long day
i.e., 1.25 metres
Materials:—
Galvanised mild steel tube (light grade) 40 m 1.310
mm nominal bore 10 x 12.5 cm = 1.25 metre
with wastage of 5%
Labour :-
For cutting and fixing in position
Assistant fitter day 0.100
Mason. day 0.400
Mazdoor (male). day 0.400
Sundries
Cost for 1.25 m
Cost per m
BLD-CSTN- 308 Providing and fixing 1.80 metre long RCC
15-6 fencing posts with 6 mm bar bibs as per
design in plate No. 22/2/2. (earth work &
concrete to be paid for separately)
Details of cost for 10 posts, i.e., 0.336 Cu. m

(Details as per Annexure ' X ' at the end of


this item)
Materials:—
Cement concrete 1:2:4 (1 cement : 2 coarse cum 0.336
sand :4 graded stone aggregate 12.5 mm
nominal size)
(Rate as per item Concrete work)
M.S. reinforcement 6 mm dia bars 10 x kg 26.440
4 x 1.88 = 75.20 metres 10 x 9 x
0.50 = 45.00 metres./ l20.00 m 120.20 m @
0.22 Kg/m=26.44 Kg
(Rate as per item No.5.51 Section Concrete
work)
Centering and shuttering cum 0.336
(Details as per Annexure 'X')
(Rate as per item No.9.1.8. of Section 9 Form
work).
10 mm cement plaster with cement mortar sqm 9.880
1:2 (1 cement: 2 sand)
(Details as per Annexure 'X')
Carriage of R.C.C. posts
6 mm bar bibs
Sundries

111
STANDARD DATA BOOK – BUILDING WORK ITEMS

Labour for fixing posts in line


Mason, 1st Class day 0.120
Mason, 2nd Class day 0.120
Mazdoor (Male) day 0.250
Add Water charges on A @ 1%
Add Contractor's profit and overheads on 'A'
+ 'B' + 'C @ 10%
Cost for 10 posts
Cost per post
Sub Analysis :
Plastering with CM 1:3, 12 mm thick 10 1.000
sqm
Deduct - CM 1:3 cum 0.025
Add - Cement (720-480 x .125) cum 30.000
Rate for 10 sqm
Rate per sqm
Annexure - 'X'
Details of quantities for RCC posts
Concrete quantity
Area of bottom A, =15+12.5/2 x 8.75+1/2 x
22/7 (6.25) = 120.31+61.38=181.69 Sq.m.
Area of top A2= 10+7.5/1 x 6.25 + 1/2 x 22 x
2
(3.75) / 7= 54.69+22.10=76.79 Sq.Cm.
Av A2 = 118.12 Sq. Cm.
Volume = h/3(A, + A2 + VA,A2)
A2+A2+A, A2=0.V03766 Sq.m
Volume = 1.05/3 * 0.03766 = 0.0131810
Cu.m. =0.0132 Cu.m.
Volume of lower square portion
=0.165x0.165x0.75 =0.0204 Cu.m
Total volume = 0.0336 Cu. m
Quantity for 10 posts = 0.336 Cu.m
Quantity of centring & shuttering 0.2770*
1.05=0.2908 Sq.m.
3x0.165x0.75=0.3712
0.165x0.165=0.0272
0.10 x 0.10=0.0100/0.6992 Sq.m..
For ten posts=10 x 0.6992 = 6.992 Sq.m.
Quantity of surface plaster area
12.50+7.60+7.60=27.70 Cm.
xr=3.1416x5=15.71Cm./43.41Cm 0.434 x
1.05=0.4560 Sq.m.
4x0.165x0.75=0.4950
0.165x0.165=0.0272
0.10 x 0.10=0.0100/0.9882 Sq.m. For
10 posts = 10 x 0.9882=9.88 Sq.m.

112
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 309 Supplying and fixing galvanised steel barbed


15-7 wire (IS : 278-1962 Type I) weighing 9.38 Kg
per 100 metres (min.), Straining and fixing to
any type of standard, rails, straining bolts,
including securing with and provision of
galvanised mild steel wire, stapples or steel
pins, etc., as directed (Posts and struts of
wood, concrete, steel, etc.) and straining
bolts shall be paid for separately).

Details of Cost per 100 metres (day line of


wire)
Materials:—
Galvanised steel barbed wire IS type I kg 9.380
weighing 9.38 Kg/100 metre
Carriage of barbed wire.
G.I. staples steel pins or binding wire LS
Labour :-
For fixing & stretching wire
Blacksmith, 1st Class day 0.150
Blacksmith, 2nd Class day 0.150
Mazdoor (male). day 0.300
Sundries.
Add water charges @ 1 %
Cost for 100 metres day line of wire
Rate per m
BLD-CSTN- 310 Broken glass coping as specified on top of
15-8 walls
In cement mortar 1:3 (1 cement: 3 sand)
Details of cost per one Sq.m.
Materials:—
Broken glass. kg 19.500
Cement mortar 1:3(1 cement: 3 sand) cum 0.040
Labour :-
Mason (Skilled) day 0.080
Mazdoor (Male) day 0.160
Scaffolding etc
Add water charges @ 1 %
Cost per Sq.metre
BLD-CSTN- ANTE-TERMITE TREATMENT
16

113
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 311 Providing Antitermite treatment as per IS


16-1 6315 (Part - 2) 2001 (Pre-constructional
chemical treatment measures) along the
internal & external vertical faces of the
columns, plinth beams, basement and top
surface of the basement filling below flooring
bed as per the specified procedure
conforming to IS 6315 (Part-2) 2001 and
other relevant approved specification duly
using Chlorpyriphos/ Lindane emulsifiable
concentrate 20% with 1% concentration @
7.5 Liters/ sqm of the vertical surface & @
5.0 Liters/ sqm of the horizontal surface of
the substructure to a depth of 500 mm
around columns & 300 mm deep around
plinth beams, basements & floor filling area
including excavation channel along the wall &
rodding etc & cost & conveyance of all
materials to the site, cost of labour for
spraying, rodding etc complete for finished
item of work as per the approval of the
Engineer-in-Charge

Unit = 10 sqm
A) Chlorpyriphos/ Lindane emulsifiable
concentrate of 20%
1 liter : 19 Parts water Therefore: 868.55 L Lit 4.100
/20
Add 12%wastage Liters 0.41
Total Quantity 4.51
B) Add Water Charges @ 1% 1%
C) Labour Charges
Man Mazdoor day 3.0
Sprayer day 0.22
D) Hire charges
Sprayer, drilling machine etc 10%
sundries & contingencies 3%
Water charges & electricity 1.50%
Add OH & CP
BASIC COST per 1 sqm
BLD-CSTN- CENTERING, FORM WORK etc.
17
BLD-CSTN- 312 Providing traditional centering, shuttering
17-1 and scaffolding using Casurina balli props and
bracings supporting wooden brackets,
wooden wall plates, wooden runners and
steel plate form work as per the approved
plan and other accessories as per the
standard trade practice including hire
charges for ballies, runners, wooden
members and cost and conveyance of all
other consumable accessories, taxes etc
complete for finished item of work

114
STANDARD DATA BOOK – BUILDING WORK ITEMS

UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M
(12'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0" Nos 2.40
Height
Wall Plate Brackets / beam bottom supports Nos 1.44

Wedge Plate fixture Nos 1.44


Runner beams of approximately 4" x 4" size RM 16.00

Steel Plate - form work plates - sqm 1.86


B) LABOUR CHARGES
1st Class Carpenter day 0.16
2nd Class Carpenter day 0.28
Unskilled Mazdoor day 0.48
Supervision Charges day 0.04
Consumables like Rope, Nails, de-shuttering 1%
oil
Tape, cover plates 1%
Tools like Hammers etc., 1%
BASIC COST per 1 sqm
313 Unsupported Roof Height up to - 4.60 M
(15'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0" Nos 4.32
Height
Wall Plate Brackets / beam bottom supports Nos 1.44

Wedge Plate fixture Nos 1.44


Runner beams of approximately 4" x 4" size RM 16.00

Steel Plate - form work plates - sqm 1.86


B) LABOUR CHARGES
1st Class Carpenter Nos 0.20
2nd Class Carpenter Nos 0.36
Unskilled Mazdoor Nos 0.68
Supervision Charges Nos 0.06
Consumables like Rope, Nails, de-shuttering 1%
oil
Tape, cover plates 1%
Tools like Hammers etc., 1%
BASIC COST per 1 sqm
314 Unsupported Roof Height up to - 7.30 M
(24'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0" Nos 5.76
Height
Wall Plate Brackets / beam bottom supports Nos 1.44

Wedge Plate fixture Nos 1.44


Runner beams of approximately 4" x 4" size RM 16.00

115
STANDARD DATA BOOK – BUILDING WORK ITEMS

Steel Plate - form work plates - sqm 1.86


B) LABOUR CHARGES
1st Class Carpenter Nos 0.28
2nd Class Carpenter Nos 0.52
Unskilled Mazdoor Nos 1.08
Supervision Charges Nos 0.08
Consumables like Rope, Nails, de-shuttering 1%
oil
Tape, cover plates 1%
Tools like Hammers etc., 1%
BASIC COST per 1 sqm
BLD-CSTN- 315 Providing rigid Steel centering, shuttering
17-2 and scaffolding using steel pipes, adjustable
Jack screw props, acro spans, couplers, tie
rods, bracings members, supporting brackets,
acro span beams and steel plate/ ply-wood
form work as per the approved shuttering
designs & plan and other accessories as per
the IS Norms and stability calculations
including hire charges for jack pipes, acro
spans, runners, wooden members and cost
and conveyance of all other consumable
accessories, taxes etc complete for finished
item of work

UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M
(12'0")
A) MATERIAL REQUIREMENT
Jack Screw Adjsutable Props - 50 mm dia B
Class Pipes
for vertical props placed @ 3'0" c/c in
bothways
Approximately 33'-0" x 33'-0" roof area
Span Beams - 2.4 M Long (Acro Spans) -
Approximtely
Wallers, Couplers, Foot Plates
Steel Plate Beam Bottom - form work plates -
9" wide
230 mm wide plate x 80 RM
Beam Sides - form work plates - 15" wide
400 mm wide plate x 80 RM - both sides
Slab Bottom Plates - formwork plates
3'-0" x 4'-0" - 7 Nos
3'-0" x 2'-0" - 2 Nos
1'-0" x 4'-0" - 1 Nos
Slab Sides - 0-6" Height - 40.0 RM
Total Scaffolding Pipes & Centering Plates - Kgs 62.51
Appx -
B) LABOUR CHARGES
1st Class Carpenter day 0.22
2nd Class Carpenter day 0.38
Unskilled Mazdoor day 0.72

116
STANDARD DATA BOOK – BUILDING WORK ITEMS

Supervision Charges day 0.04


Consumables like Rope, Nails, de-shuttering 1%
oil
Tape, cover plates 1%
Tools like Hammers etc., 1%
BASIC COST per 1 sqm
316 Unsupported Roof Height up to - 7.32 M
(24'0")
A) MATERIAL REQUIREMENT
Heavy Frames - 50 mm dia B Class Pipes (HD
Towers)
Span Beams - 2.4 M Long (Acro Spans) -
Approximtely
Wallers, Couplers, Foot Plates
Steel Plate Beam Bottom - form work plates -
9" wide
230 mm wide plate x 80 RM
Beam Sides - form work plates - 15" wide
400 mm wide plate x 80 RM - both sides
Slab Bottom Plates - formwork plates
3'-0" x 4'-0" - 7 Nos
3'-0" x 2'-0" - 2 Nos
1'-0" x 4'-0" - 1 Nos
Slab Sides - 0-6" Height - 40.0 RM
Total Scaffolding Pipes & Centering Plates - Kgs 112.635
Appx -
B) LABOUR CHARGES
1st Class Carpenter day 0.32
2nd Class Carpenter day 0.52
Unskilled Mazdoor day 1.28
Supervision Charges day 0.06
Consumables like Rope, Nails, de-shuttering 1%
oil
Tape, cover plates 1%
Tools like Hammers etc., 1%
BASIC COST per 1 sqm
BLD-CSTN- 317 Providing STAGE SCAFFOLD with staging
17-3 using Casurina balli props and bracings
supporting wooden brackets, wooden stage
scaffold boards including hire charges for
Casurina ballies, wooden baords, scaffolds
etc., and cost and conveyance of all other
consumable accessories, taxes etc complete
for finished item of work for PLAN AREA
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M
(12'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0" Nos 2.40
Height
Scaffold Boards - Bamboo scaffolds - Nos 2.70
Bamboos - 8'0" long
B) LABOUR CHARGES

117
STANDARD DATA BOOK – BUILDING WORK ITEMS

1st Class Carpenter day 0.04


2nd Class Carpenter day 0.30
Unskilled Mazdoor day 0.48
Supervision Charges day 0.04
Consumables like Rope, Nails, de-shuttering 1%
oil
Tape, cover plates 1%
Tools like Hammers etc., 1%
BASIC COST per 1 sqm - PLAN AREA
318 Unsupported Roof Height up to - 4.60 M
(15'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0" Nos 4.32
Height
Scaffold Boards - Bamboo scaffolds - Nos 2.70
Bamboos - 8'0" long
B) LABOUR CHARGES
1st Class Carpenter day 0.08
2nd Class Carpenter day 0.38
Unskilled Mazdoor day 0.68
Supervision Charges day 0.06
Consumables like Rope, Nails, de-shuttering 1%
oil
Tape, cover plates 1%
Tools like Hammers etc., 1%
BASIC COST per 1 sqm - PLAN AREA
319 Unsupported Roof Height up to - 7.30 M
(24'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0" Nos 5.76
Height
Scaffold Boards - Bamboo scaffolds - Nos 2.70
Bamboos - 8'0" long
B) LABOUR CHARGES
1st Class Carpenter day 0.12
2nd Class Carpenter day 0.54
Unskilled Mazdoor day 1.08
Supervision Charges day 0.08
Consumables like Rope, Nails, de-shuttering 1%
oil
Tape, cover plates 1%
Tools like Hammers etc., 1%
BASIC COST per 1 sqm - PLAN AREA
BLD-CSTN- 320 Providing ACCESS SCAFFOLD using Casurina
17-4 balli props and bracings supporting wooden
brackets, wooden stage scaffold boards
including hire charges for Casurina ballies,
wooden baords, scaffolds etc., and cost and
conveyance of all other consumable
accessories, taxes etc complete for finished
item of work for ELEVATION AREA

UNIT 1 sqm

118
STANDARD DATA BOOK – BUILDING WORK ITEMS

Up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0" Nos 1.74
Height
Scaffold Boards - Bamboo scaffolds - Nos 0.72
Bamboos - 8'0" long
B) LABOUR CHARGES
1st Class Carpenter day 0.07
2nd Class Carpenter day 0.11
Unskilled Mazdoor day 0.2
Supervision Charges day 0.04
Consumables like Rope, Nails, de-shuttering 1%
oil
Tape, cover plates 1%
Tools like Hammers etc., 1%
BASIC COST per 1 sqm - VERTICAL ELEVATION
AREA
BLD-CSTN- 321 Providing STAGE SCAFFOLD using Steel
17-5 Scaffolding Pipe Frames made of 40 mmd ia
MS Pipes and bracings with scaffold boards
including hire charges for MS Pipe Frames
scaffolds boards etc., and cost and
conveyance of all other consumable
accessories, taxes etc complete for finished
item of work for PLAN AREA
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M
(12'0")
A) MATERIAL REQUIREMENT
Jack Screw Adjsutable Props - 50 mm dia B
Class Pipes
for vertical props placed @ 3'0" c/c in
bothways
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx - Kgs 39.26
B) LABOUR CHARGES
1st Class Carpenter day 0.04
2nd Class Carpenter day 0.34
Unskilled Mazdoor day 0.60
Supervision Charges day 0.04
Consumables like Rope, Nails, de-shuttering 1%
oil
Tape, cover plates 1%
Tools like Hammers etc., 1%
BASIC COST per 1 sqm - PLAN AREA
322 Unsupported Roof Height up to - 7.32 M
(24'0")
A) MATERIAL REQUIREMENT
Heavy Frames - 50 mm dia B Class Pipes (HD
Towers)
Lock Pins

119
STANDARD DATA BOOK – BUILDING WORK ITEMS

LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx - Kgs 112.635
B) LABOUR CHARGES
1st Class Carpenter day 0.12
2nd Class Carpenter day 0.58
Unskilled Mazdoor day 1.20
Supervision Charges day 0.08
Consumables like Rope, Nails, de-shuttering 1%
oil
Tape, cover plates 1%
Tools like Hammers etc., 1%
BASIC COST per 1 sqm - PLAN AREA
BLD-CSTN- 323 Providing ACCESS SCAFFOLD using Steel
17-6 Scaffolding Pipe Frames made of 40 mmd ia
MS Pipes and bracings with scaffold boards
including hire charges for MS Pipe Frames
scaffolds boards etc., and cost and
conveyance of all other consumable
accessories, taxes etc complete for finished
item of work for ELEVATION AREA
UNIT 1 sqm
Up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
MS Pipe Scaffold Frames - 1.20 x 1.50 M
Approximately 27.3 M Long x 3.66 M High
MS Pipe Bracing structure - 1.5 x 2.25 M
Scaffold Board
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx - Kgs 19.7496
B) LABOUR CHARGES
1st Class Carpenter day 0.07
2nd Class Carpenter day 0.11
Unskilled Mazdoor day 0.24
Supervision Charges day 0.04
Consumables like Rope, Nails, de-shuttering 1%
oil
Tape, cover plates 1%
Tools like Hammers etc., 1%
BASIC COST per 1 sqm - VERTICAL ELEVATION
AREA
324 Up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
MS Pipe Scaffold Frames - 1.20 x 1.50 M
Approximately 27.3 M Long x 3.66 M High
MS Pipe Bracing structure - 1.5 x 2.25 M
Scaffold Board
Lock Pins
LD Foot Plates
LD Couplers

120
STANDARD DATA BOOK – BUILDING WORK ITEMS

Total Scaffolding Pipes - Appx - Kgs 19.14


B) LABOUR CHARGES
1st Class Carpenter day 0.12
2nd Class Carpenter day 0.22
Unskilled Mazdoor day 0.44
Supervision Charges day 0.04
Consumables like Rope, Nails, de-shuttering 1%
oil
Tape, cover plates 1%
Tools like Hammers etc., 1%
BASIC COST per 1 sqm - VERTICAL ELEVATION
AREA
BLD-CSTN- 325 Fixing steel barricading with MS Angle Iron
17-7 Pegs and GI Pipes with nuts & bolts duly
excavating pits and its removal after the
function is over including transporting of the
entire barricading materials from the
Divisional stores to the barricading site duly
engaging labour to load, transport and
unload the materials at barricading site & as
per the schedule given by the departmental
authorities and loading back into the trucks,
unloading at Divisional stores, accounting for
the received materials, labour for loading,
unloading, fixing, handling etc, complete for
finished item of work

A) MATERIAL REQUIREMENT
a. MS Iron Angle Posts using ISA 65x65x6 mm
- 1.5 M long - 329 Nos in 1000 RM length -
3015 Kgs
b. GI Pipes of 32 mm dia Nominal Bore
medium grade 2000 RM in 1000 RM length -
6300 Kgs
c. Nuts & Bolts - 329 posts x 4 Nos = 1316
Nos in a length of 1000 RM - 130 Kgs
Total Barricading Weight - Appx 9445 Kgs
(if departmental material is used no hire
charges shall be calculated)
B) LABOUR CHARGES
a. for materials loading & carriage to work
spot
1 Day ( 8 Hrs) - Men Mazdoor 16 Numbers
1 Night - (2 Days - 16 Hrs) 16 + 16 Numbers
b. for removal, unloading & return to stores
back
1 Day ( 8 Hrs) - Men Mazdoor 16 Numbers
Total 64 Numbers day 64.00
c. for fixing the barricading materials
1 Day ( 8 Hrs) - Men Mazdoor 16 Numbers
½ Night - (1 Day - 8 Hrs) 16 Numbers
Total 32 Numbers day 32.00
BASIC COST per 1000 RM

121
STANDARD DATA BOOK – BUILDING WORK ITEMS

BLD-CSTN- 326 Providing barricading arrangement with


17-8 casurina ballies as per the design duly
excavating pits and its removal after the
function is over including hire charges of the
barricading materials as per the schedule
given by the departmental authorities
complete for finished item of work
2 - TIER (2 Nos Horizontals- 6'-0" long - 1 No
Vertical -4'-0" High)
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - (50 Nos-4 Nos 85
RM & 55 Nos-2 RM = 200+110=310 RM/3.66
= 85 Nos, if 12'-0" long ballies are used)
B) LABOUR CHARGES
Unskilled Mazdoor day 12
Consumables like Rope, Nails 1%
Conveyance, loading & unloading etc 1%
Tools like Hammers etc., 1%
BASIC COST per 100 RM
BLD-CSTN- 327 3 - TIER (3 Nos Horizontals- 6'-0" long - 1 No
17-9 Vertical -4'-0" High)
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - (75 Nos-4 Nos 130
RM & 55 Nos-2 RM = 300+110=410 RM/3.66
= 112 Nos, if 12'-0" long ballies are used)
B) LABOUR CHARGES
Unskilled Mazdoor day 12.5
Consumables like Rope, Nails 1%
Conveyance, loading & unloading etc 1%
Tools like Hammers etc., 1%
BASIC COST per 100 RM

BLD-CSTN- 328 Providing and laying cinder concrete in


17-10 cement cinder mix (1:15) prop. using 12.5
mm nominal size cinder laid in layers and
compacted as directed for filling sunken
floors including cost and conveyance of all
materials, water to work site, seigniorage
charges and all operational, incidental, labour
charges, such as mixing cement & cinder etc.
complete for finished item of work.

A) MATERIAL REQUIREMENT
Cost of Cinder cum 1.00
Cement Kgs 95.00
B) LABOUR CHARGES
st
Mason 1 class day 0.10
Mazdoor (unskilled) day 2.36

122
STANDARD DATA BOOK – BUILDING WORK ITEMS

HIRE & LIFT CHARGES - for all Scaffolding Materials


a Casurina Ballies, Bamboos, Wooden Reapers, Runners, Wood Posts, Wall Plates etc., (As per relevant data item)
Cost of Scaffolding materials = Rs. A
Scrap value of Scaffolding materials = Rs. B (Usually B = A * 10%)
Number of uses of Scaffolding materials = U
(Rs. A - Rs. B)
Therefore, Hire Charges of scaffolding Materials: U

b Steel scaffolding pipes, jack Props, wallers, Foot plates, brackets, steel Centering Plates,etc., (As per relevant data item)
Cost of Scaffolding materials = Rs. A
Scrap value of Scaffolding materials = Rs. B (Usually B = A * 10%)
Period of Hire of Scaffolding materials, in years = C
Life of Scaffolding materials, in years = D
[(Rs. A - Rs. B)*C]
Therefore, Hire Charges of scaffolding Materials: D

1 RATE ANALYSIS FOR HIRE CHARGES OF CENTRING & SCAFFOLDING MATERIALS FOR ALL R.C.C. STRUCTURAL MEMBERS - ANY HEIGHT
H Hire Charges of Steel scaffolding: a/365 (OR) Wooden scaffolding: b/10 Rs.
L Labour Charges Rs.

Hire Labour Sub- Duty Factor Centring


Unit of Measurement
Sl NAME OF THE STRUCTURE COMPONENT Qty Unit Charges Charges Total C1 Charges
H L (H + L) C1 (c)*(g)*(h)
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j)
1 FOOTINGS 3.880 sqm per 1 cum of concrete
member
2 PEDESTALS 6.170 sqm per 1 cum of concrete
member
3 PLINTH BEAMS 9.350 sqm per 1 cum of concrete
member
4 LINTELS 7.940 sqm per 1 cum of concrete
member
5 CHAJJAS - SUNSHADES 1.220 sqm per 1 sqm of concrete
member
6 COLUMNS 11.150 sqm per 1 cum of concrete

123
STANDARD DATA BOOK – BUILDING WORK ITEMS

member
7 BEAMS 9.350 sqm per 1 cum of concrete
member
8 SLABS - Up to 150 mm thick 1.050 sqm per 1 sqm of concrete
member
9 SLABS - above 150 mm - Up to 300 mm thick 1.090 sqm per 1 sqm of concrete
member
10 SLABS - above 300 mm thick 1.140 sqm per 1 sqm of concrete
member
11 WAFFLE(GRID)SLABS(Rib Beams with Slabs) 3.850 sqm per 1 sqm of concrete
member
12 PERGOLA SLABS (Only Rib Beams) 2.700 sqm per 1 sqm of concrete
member
13 ARCHE BEAMS - up to 1.5 M Span 10.630 sqm per 1 cum of concrete
member
14 ARCHE BEAMS - above 1.5 M Span 10.780 sqm per 1 cum of concrete
member
15 DOME SLABS 17.190 sqm per 1 cum of concrete
member
16 HELICAL STAIRCASES 1.310 sqm per 1 sqm of concrete
member

124
STANDARD DATA BOOK – BUILDING WORK ITEMS

2 RATE ANALYSIS FOR HIRE CHARGES SCAFFOLDING MATERIALS FOR BRICK & STONE MASONRY

H Hire Charges of Steel scaffolding: a/365 (OR) Wooden scaffolding: b/10 - as per Access Scaffold items Rs.
L Labour Charges - as per Access Scaffolds items Rs.

Hire Duty
SCAFFOLDING CHARGES FOR BRICK / STONE Labour Charges Lift Charges Scaffolding Charges
Sl Qty Unit Charges Factor C1
MASONRY
H L (f) * (g) C1 [(e)+(h)]*(i)
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j)
1 1st Floor 1.00 sqm 100%
2 2nd Floor 1.00 sqm 150%
3 3rd Floor 1.00 sqm 200%
4 4th Floor 1.00 sqm 250%
5 5th Floor 1.00 sqm 300%
6 6th Floor 1.00 sqm 350%
7 7th Floor 1.00 sqm 400%
8 8th Floor 1.00 sqm 450%
9 9th Floor 1.00 sqm 500%
10 10th Floor 1.00 sqm 550%
11 11th Floor 1.00 sqm 600%
12 12th Floor 1.00 sqm 650%
13 13th Floor 1.00 sqm 700%
14 14th Floor 1.00 sqm 750%
15 15th Floor 1.00 sqm 800%
16 .... ... ... ...

125
STANDARD DATA BOOK – BUILDING WORK ITEMS

3 RATE ANALYSIS FOR HIRE CHARGES OF SCAFFOLDING MATERIALS FOR WALL PLASTERINGS, RCM WORKS - ANY THICK

H Hire Charges of Steel scaffolding: a/365 (OR) Wooden scaffolding: b/10 - as per Access Scaffold items Rs.

L Labour Charges - as per Access Scaffolds Rs.


items

Hire Duty
SCAFFOLDING CHARGES FOR BRICK / STONE Labour Charges Lift Charges Scaffolding Charges
Sl Qty Unit Charges Factor C1
MASONRY
H L (f) * (g) C1 [(e)+(h)]*(i)
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j)
1 1st Floor 10.00 sqm 100%
2 2nd Floor 10.00 sqm 150%
3 3rd Floor 10.00 sqm 200%
4 4th Floor 10.00 sqm 250%
5 5th Floor 10.00 sqm 300%
6 6th Floor 10.00 sqm 350%
7 7th Floor 10.00 sqm 400%
8 8th Floor 10.00 sqm 450%
9 9th Floor 10.00 sqm 500%
10 10th Floor 10.00 sqm 550%
11 11th Floor 10.00 sqm 600%
12 12th Floor 10.00 sqm 650%
13 13th Floor 10.00 sqm 700%
14 14th Floor 10.00 sqm 750%
15 15th Floor 10.00 sqm 800%
16 .... ... ... ...

126
STANDARD DATA BOOK – BUILDING WORK ITEMS

4 RATE ANALYSIS FOR HIRE CHARGES OF SCAFFOLDING MATERIALS FOR CEILING PLASTERINGS - ANY THICK

H Hire Charges of Steel scaffolding: a/365 (OR) Wooden scaffolding: b/10 - as per Stage Scaffold items Rs.
L Labour Charges - as per Stage Scaffolds items Rs.
Hire Duty
SCAFFOLDING CHARGES FOR BRICK / STONE Labour Charges Lift Charges Scaffolding Charges
Sl Qty Unit Charges Factor C1
MASONRY
H L (f) * (g) C1 [(e)+(h)]*(i)
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j)
1 1st Floor 10.00 sqm 100%
2 2nd Floor 10.00 sqm 150%
3 3rd Floor 10.00 sqm 200%
4 4th Floor 10.00 sqm 250%
5 5th Floor 10.00 sqm 300%
6 6th Floor 10.00 sqm 350%
7 7th Floor 10.00 sqm 400%
8 8th Floor 10.00 sqm 450%
9 9th Floor 10.00 sqm 500%
10 10th Floor 10.00 sqm 550%
11 11th Floor 10.00 sqm 600%
12 12th Floor 10.00 sqm 650%
13 13th Floor 10.00 sqm 700%
14 14th Floor 10.00 sqm 750%
15 15th Floor 10.00 sqm 800%
16 .... ... ... ...

127
STANDARD DATA BOOK – BUILDING WORK ITEMS

Note
1 For Material Lift Charges & Labour rate for scaffolding above 7.32 M - increase @ 50% on labour component for each upper
floor on First Floor Rate (7.32 M)
2 For Hire Charges of scaffolding Materials following ratesmay be allowed:
a Number of uses of Scaffolding materials (C )
b Wooden Materials - No of Uses - 10 Times (C)
c Period of Hire of Steel Scaffolding materials, in years =
1.64 (C )
d Life of Steel Forms & Scaffolding Material - 3
Years (D)
e Duty Factor - Steel Scaffolding C1 0.500
f Duty Factor - Wooden Scaffolding C1 0.333
3 Add Area Allowances as applicable on labour
charges

128
STANDARD DATA BOOK – BUILDING WORK ITEMS

5 RATE ANALYSIS FOR HIRE CHARGES OF BARRICADING MATERIALS

a Casurina Ballies (As per relevant data item)


Cost of Barricading materials = Rs. A
Scrap value of Barricading materials = Rs. B (Usually B = A * 10%)
Number of uses of Barricading materials = U
(Rs. A - Rs. B)
Therefore, Hire Charges of Barricading Materials: U

b Steel Barricading G.I. Pipes, Mild Steel IS Angles (As per relevant data item)
Cost of Barricading materials = Rs. A
Scrap value of Barricading materials = Rs. B (Usually B = A * 10%)
Period of Hire of Barricading materials, in years = C
Life of Barricading materials, in years = D
[(Rs. A - Rs. B)*C]
Therefore, Hire Charges of Barricading Materials: D

H Hire Charges of Steel Barricading: a/365 (OR) Wooden Barricading: b/10 - as per Barricading Item Rs.
L Labour Charges: as per Barricading work Rs.
data items

No of
Hire Duty MaterialHire Labour
Days of Barricading Charges
Sl NAME OF THE STRUCTURE COMPONENT Qty Unit Charges Factor charges Charges
Hire
H R C1 (e*f*g) L (h) + (i)
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j)
1 STEEL BARRICADING 1000.00 RM
WOODEN BARRICADING
3 2 - TIER 100.00 RM
4 3 - TIER 100.00 RM

129
STANDARD DATA BOOK – BUILDING WORK ITEMS

Note
1 25% extra over the corresponding labour rates in respect of the work to be done during night time subject to issue of
certificate accordingly by the concerned estimate sanctioning authority for providing in the data and by concerned
Executive Engineer in charge of the work for payment. The night time allowance is applicable only to the works done under
Greater Hyderabad Municipal Corporation limits only
2 For Hire Charges of Barricading Materials following ratesmay be allowed:
a Number of uses of woodenBarricading
materials (U )
b Wooden Materials - No of Uses - 10 Times (U)
c Period of Hire of Steel Barricading materials, in years =
1.64 (C )
d Life of Steel Forms & Barricading Material - 3
Years (D)
e Duty Factor - Steel Barricading C1 0.500
f Duty Factor - Wooden Barricading C1 0.333
3 Add Area Allowances as applicable on labour
charges

130
STANDARD DATA BOOK – BUILDING WORK ITEMS

LIFT CHARGES FOR ALL ITEMS OF WORKS

6 LIFT CHARGES - for all RCC Items

1. For Lift Charges of Labour, increase @ 10% on labour charges for each upper floor on Ground Floor Rate
2. For Lift Charges of Materials only, for lifting Concrete above 6.1 M (2nd floor onwards) Winch/ Lift hire charges may be
allowed at following rates:

for each additional


Basic Rate for 2nd floor (3.66 M) over
Description of Structure
Floor (7.32 M) and above 2nd
floor (7.32 M)
a. FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth) Nil Nil
b. COLUMNS, LINTELS, WATER TANKS, RCC WALLS 1.333 Hrs 10%
c. RCC SLABS, BEAMS 0.267 Hrs 10%

8 LIFT CHARGES - for Brick Masonry, all Plastering items, all Flooring items, HYSD Steel fabrication, impervious coats, RCM Works

1 For Lift Charges of Labour, increase @ 10% on labour charges of respective item for each upper floor on Ground Floor Rate
2 Add Area Allowances as applicable on labour
charges

9 LIFT CHARGES - for Scaffolding Works


1 For Lift Charges of Labour, increase @ 50% on labour charges of respective item for each upper floor on Ground Floor Rate
2 Add Area Allowances as applicable on labour
charges

131
STANDARD DATA BOOK – LEAD CHARGES

LEAD/LIFT/LOADING & UNLOADING CHARGES


Amount
Unit Quantity Rate Rs.
Rs.

COM-LDLFT-1 DATA FOR LEAD CHARGES BY HEAD


LOAD :
Earth / Sand / Gravel / Murrum /
Lime / Surki / Coarse aggregate /
Rubble stone / Size stone / Cut
stone
1 LEAD UP TO 100 m
A) LABOUR
Mazdoor day 1
Cost for 7 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM

2 LEAD UP TO 150 m
A) LABOUR
Mazdoor day 2
Cost for 7 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM

Cement/ HYSD Steel/ Structural


steel
3 LEAD UP TO 100 m
A) LABOUR
Mazdoor day 1
Cost for 12 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT

4 LEAD UP TO 150 m
A) LABOUR
Mazdoor day 2
Cost for 12 MT =
Contractor's profit and overhead
charges
RATE PER 1 CUM

PCC slab / Shahabad stone slab /


CC block / Laterite stone / BS slab /
Wood
5 LEAD UP TO 100 m
A) LABOUR
Mazdoor day 1
Cost for 5.5 cum =
Contractor's profit and overhead
charges

132
STANDARD DATA BOOK – LEAD CHARGES

RATE PER 1 CUM

6 LEAD UP TO 150 m
A) LABOUR
Mazdoor day 2
Cost for 5.5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
COM-LDLFT-2 (Lead) Conveyance charges for machinery
per kilometer for transporting materials
by tippers and trucks excluding loading,
unloading and hire charges of machinery

Earth / Sand / Gravel / Murrum /


Lime / Surki /Coarse aggregate /
Rubble stone / Size stone / Cut
stone
7 LEAD UP TO 1 KM
A) HIRE CHARGES
Tipper charges Hr 0.15
Fuel Charges Hr 0.15
Crew charges Hr 0.15
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM

8 LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Tipper charges Hr 0.21
Fuel Charges Hr 0.21
Crew charges Hr 0.21
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM

9 LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Tipper charges Hr 0.28
Fuel Charges Hr 0.28
Crew charges Hr 0.28
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM

10 LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Tipper charges Hr 0.34
Fuel Charges Hr 0.34
Crew charges Hr 0.34

133
STANDARD DATA BOOK – LEAD CHARGES

Cost for 5 cum =


Contractor's profit and overhead
charges
RATE PER 1 CUM

11 LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Tipper charges Hr 0.40
Fuel Charges Hr 0.40
Crew charges Hr 0.40
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM

12 LEAD UPTO 5 to 30 KM/ EVERY


KM
A) HIRE CHARGES
Tipper charges Hr 0.06
Fuel Charges Hr 0.06
Crew charges Hr 0.06
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM

13 LEAD BEYOND 30 KM/ EVERY KM


A) HIRE CHARGES
Tipper charges Hr 0.05
Fuel Charges Hr 0.05
Crew charges Hr 0.05
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM

Cement/ Steel/ Pipes/ RCC poles/


AC & GI sheets/ Packed materials
14 LEAD UP TO 1 KM
A) HIRE CHARGES
Tipper charges Hr 0.15
Fuel Charges Hr 0.15
Crew charges Hr 0.15
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT

15 LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Tipper charges Hr 0.21
Fuel Charges Hr 0.21

134
STANDARD DATA BOOK – LEAD CHARGES

Crew charges Hr 0.21


Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT

16 LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Tipper charges Hr 0.28
Fuel Charges Hr 0.28
Crew charges Hr 0.28
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT

17 LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Tipper charges Hr 0.34
Fuel Charges Hr 0.34
Crew charges Hr 0.34
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT

18 LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Tipper charges Hr 0.40
Fuel Charges Hr 0.40
Crew charges Hr 0.40
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT

19 LEAD UPTO 5 to 30 KM/ EVERY


KM
A) HIRE CHARGES
Tipper charges Hr 0.06
Fuel Charges Hr 0.06
Crew charges Hr 0.06
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT

20 LEAD BEYOND 30 KM/ EVERY KM


A) HIRE CHARGES
Tipper charges Hr 0.05
Fuel Charges Hr 0.05
Crew charges Hr 0.05

135
STANDARD DATA BOOK – LEAD CHARGES

Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT

PCC slabs/ Shahabad slabs/ BS


slabs/ CC & Laterite blocks/ Wood
21 LEAD UP TO 1 KM
A) HIRE CHARGES
Tipper charges Hr 0.15
Fuel Charges Hr 0.15
Crew charges Hr 0.15
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM

22 LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Tipper charges Hr 0.21
Fuel Charges Hr 0.21
Crew charges Hr 0.21
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM

23 LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Tipper charges Hr 0.28
Fuel Charges Hr 0.28
Crew charges Hr 0.28
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM

24 LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Tipper charges Hr 0.34
Fuel Charges Hr 0.34
Crew charges Hr 0.34
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM

25 LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Tipper charges Hr 0.40
Fuel Charges Hr 0.40
Crew charges Hr 0.40

136
STANDARD DATA BOOK – LEAD CHARGES

Cost for 3.4 CUM =


Contractor's profit and overhead
charges
RATE PER 1 CUM

26 LEAD UPTO 5 to 30 KM/ EVERY


KM
A) HIRE CHARGES
Tipper charges Hr 0.06
Fuel Charges Hr 0.06
Crew charges Hr 0.06
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM

27 LEAD BEYOND 30 KM/ EVERY KM


A) HIRE CHARGES
Tipper charges Hr 0.05
Fuel Charges Hr 0.05
Crew charges Hr 0.05
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM

WATER
28 LEAD UP TO 1 KM
A) HIRE CHARGES
Water Tanker Charges Hr 0.15
Fuel Charges Hr 0.15
Crew charges Hr 0.15
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres

29 LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Water Tanker Charges Hr 0.21
Fuel Charges Hr 0.21
Crew charges Hr 0.21
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres

30 LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Water Tanker Charges Hr 0.28
Fuel Charges Hr 0.28
Crew charges Hr 0.28

137
STANDARD DATA BOOK – LEAD CHARGES

Cost for 8000 Litres =


Contractor's profit and overhead
charges
RATE PER 1000 Litres

31 LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Water Tanker Charges Hr 0.34
Fuel Charges Hr 0.34
Crew charges Hr 0.34
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres

32 LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Water Tanker Charges Hr 0.40
Fuel Charges Hr 0.40
Crew charges Hr 0.40
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres

33 LEAD UPTO 5 to 30 KM/ EVERY


KM
A) HIRE CHARGES
Water Tanker Charges Hr 0.06
Fuel Charges Hr 0.06
Crew charges Hr 0.06
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres

34 LEAD BEYOND 30 KM/ EVERY KM


A) HIRE CHARGES
Water Tanker Charges Hr 0.05
Fuel Charges Hr 0.05
Crew charges Hr 0.05
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres

BRICKS
35 LEAD UP TO 1 KM
A) HIRE CHARGES
Truck 10 T Charges Hr 0.15
Fuel Charges Hr 0.15
Crew charges Hr 0.15

138
STANDARD DATA BOOK – LEAD CHARGES

Cost for 3000 Nos =


Contractor's profit and overhead
charges
RATE PER 1000 Nos

36 LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Truck 10 T Charges Hr 0.21
Fuel Charges Hr 0.21
Crew charges Hr 0.21
Cost for 3000 Nos =
Contractor's profit and overhead
charges
RATE PER 1000 Nos

37 LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Truck 10 T Charges Hr 0.28
Fuel Charges Hr 0.28
Crew charges Hr 0.28
Cost for 3000 Nos =
Contractor's profit and overhead
charges
RATE PER 1000 Nos

38 LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Truck 10 T Charges Hr 0.34
Fuel Charges Hr 0.34
Crew charges Hr 0.34
Cost for 3000 Nos =
Contractor's profit and overhead
charges
RATE PER 1000 Nos

39 LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Truck 10 T Charges Hr 0.40
Fuel Charges Hr 0.40
Crew charges Hr 0.40
Cost for 3000 Nos =
Contractor's profit and overhead
charges
RATE PER 1000 Nos

40 LEAD UPTO 5 to 30 KM/ EVERY


KM
A) HIRE CHARGES
Truck 10 T Charges Hr 0.06
Fuel Charges Hr 0.06
Crew charges Hr 0.06
Cost for 3000 Nos =

139
STANDARD DATA BOOK – LEAD CHARGES

Contractor's profit and overhead


charges
RATE PER 1000 Nos

41 LEAD BEYOND 30 KM/ EVERY KM


A) HIRE CHARGES
Truck 10 T Charges Hr 0.05
Fuel Charges Hr 0.05
Crew charges Hr 0.05
Cost for 3000 Nos =
Contractor's profit and overhead
charges
RATE PER 1000 Nos

COM-LDLFT-3 LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks
are not added)

42 LOADING
Loading of Lime, Aggregate, Stone
Boulder, Brick Aggregate, Kankar,
Building Rubbish, Building Rubbish,
Crushed Slag, Stone for Masonry
Work by manual means including a
lead upto 30 m

Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor day 0.02
Mazdoor day 0.50
Contractor's profit and overhead
charges
RATE PER 1 CUM

43 UNLOADING
50% of the loading charges i.e.,
RATE PER 1 CUM

44 LOADING
Loading of Earth, Sand, Murrum,
Manure, Fly-Ash, by manual means
including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor day 0.01
Mazdoor day 0.25
Contractor's profit and overhead
charges
RATE PER 1 CUM

45 UNLOADING
50% of the loading charges i.e.,

140
STANDARD DATA BOOK – LEAD CHARGES

RATE PER 1 CUM

46 LOADING
Loading of Bricks-1000 Nos
(Regular sizes - 225x140x70 mm)
by manual means including a lead
upto 30 m
Unit = 1000 Nos
Taking output = 2000 Nos
A) LABOUR
Head Mazdoor day 0.01
Mazdoor day 0.25
Contractor's profit and overhead
charges
RATE PER 1000 Nos

47 UNLOADING & STACKING


100% of the loading charges i.e.,
RATE PER 1000 Nos

48 LOADING
Loading of Cement by manual
means including a lead upto 30 m
Unit = 1 MT
Taking output = 10 MT
A) LABOUR
Head Mazdoor day 0.06
Mazdoor day 1.50
Contractor's profit and overhead
charges
RATE PER 1 MT

49 UNLOADING & STACKING


100% of the loading charges i.e.,
RATE PER 1 MT

50 LOADING
Loading of Structural Steel, Steel
Bars by manual means including a
lead upto 30 m
Unit = 1 MT
Taking output = 10 MT
A) LABOUR
Head Mazdoor day 0.07
Mazdoor day 1.80
Contractor's profit and overhead
charges
RATE PER 1 MT

51 UNLOADING & STACKING


100% of the loading charges i.e.,
RATE PER 1 MT

141
STANDARD DATA BOOK – LEAD CHARGES

COM-LDLFT-4 LOADING AND UNLOADING CHARGES BY MANUAL MEANS (Including idle hire charges
of trucks )

52 LOADING
Loading of Lime, Aggregate, Stone
Boulder, Brick Aggregate, Kankar,
Building Rubbish, Building Rubbish,
Crushed Slag, Stone for Masonry
Work by manual means including a
lead upto 30 m
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor day 0.02
Mazdoor day 0.50
B) MACHINERY
TRUCK - 10 T Hour 0.50
Contractor's profit and overhead
charges
RATE PER 1 CUM

53 UNLOADING
50% of the loading charges i.e.,
RATE PER 1 CUM

54 LOADING
Loading of Earth, Sand, Murrum,
Manure, Fly-Ash, by manual means
including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor day 0.01
Mazdoor day 0.25
B) MACHINERY
TRUCK - 10 T Hour 0.500
Contractor's profit and overhead
charges
RATE PER 1 CUM

55 UNLOADING
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor day 0.005
Mazdoor day 0.125
B) MACHINERY
TRUCK - 10 T Hour 0.166
Contractor's profit and overhead
charges
RATE PER 1 CUM

142
STANDARD DATA BOOK – LEAD CHARGES

56 LOADING
Loading of Bricks-1000 Nos
(Regular sizes - 225x140x70 mm)
by manual means including a lead
upto 30 m
Unit = 1000 Nos
Taking output = 2000 Nos
A) LABOUR
Head Mazdoor day 0.01
Mazdoor day 0.25
B) MACHINERY
TRUCK - 10 T Hour 0.33
Contractor's profit and overhead
charges
RATE PER 1000 Nos

57 UNLOADING & STACKING


Unit = 1000 Nos
Taking output = 2000 Nos
A) LABOUR
Head Mazdoor day 0.06
Mazdoor day 1.50
B) MACHINERY
TRUCK - 10 T Hour 1.00
Contractor's profit and overhead
charges
RATE PER 1000 Nos

58 LOADING
Loading of Cement by manual
means including a lead upto 30 m

Unit = 1 MT
Taking output = 10 MT
A) LABOUR
Head Mazdoor day 0.06
Mazdoor day 1.50
B) MACHINERY
TRUCK - 10 T Hour 1.00
Contractor's profit and overhead
charges
RATE PER 1 MT

59 UNLOADING & STACKING


Unit = 1 MT
Taking output = 10 MT
A) LABOUR
Head Mazdoor day 0.07
Mazdoor day 1.80
B) MACHINERY
TRUCK - 10 T Hour 1.00

143
STANDARD DATA BOOK – LEAD CHARGES

Contractor's profit and overhead


charges
RATE PER 1 MT

60 LOADING
Loading of Structural Steel, Steel
Bars by manual means including a
lead upto 30 m
Unit = 1 MT
Taking output = 10 MT
A) LABOUR
Head Mazdoor day 0.07
Mazdoor day 1.80
B) MACHINERY
TRUCK - 10 T Hour 1.00
Contractor's profit and overhead
charges
RATE PER 1 MT

61 UNLOADING & STACKING


100% of the loading charges i.e.,
RATE PER 1 MT

COM-LDLFT-5 LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire
charges of trucks)

62 LOADING
Loading of Lime, Aggregate, Stone
Boulder, Brick Aggregate, Kankar,
Building Rubbish, Building Rubbish,
Crushed Slag, Stone by mechanical
means including a lead upto 30 m
placing a tipper at loading point ,
loading with front end loader
excluding time for haulage and
return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading Min 1.00
point
ii) Loading by front end loader 1 Min 7.33
cum bucket capacity
@ 45 / 25 cum per hour
iii) Manoevouring, reversing, Min -
dumping and turning
for return
iv) Waiting time, unforeseen Min 2.00
contingencies, etc.
Total Min 10.33
A) MACHIENRY
Tipper 10 t capacity hour 0.17

144
STANDARD DATA BOOK – LEAD CHARGES

Front end-loader 1 cum bucket hour 0.12


capacity @ 45 cum
per hour
Cost for 5.5 cum =
b) contractor's profit and
overhead charges
Rate per cum = (a+b)/5.5

63 Loading of Earth, Sand, Murrum,


Gravel, Manure, Fly-Ash, by
mechanical means including a lead
upto 30 m placing a tipper at
loading point , loading with front
end loader excluding time for
haulage and return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading Min 1.00
point
ii) Loading by front end loader 1 Min 3.30
cum bucket capacity
@ 45 / 25 cum per hour
iii) Waiting time, unforeseen Min 2.00
contingencies, etc.
Total Min 6.30
A) MACHINERY
Tipper 10 t capacity hour 0.11
Front end-loader 1 cum bucket hour 0.06
capacity @ 45 cum
per hour
Cost for 5.5 cum =
b) contractor's profit and
overhead charges
Rate per cum = (a+b)/5.5

64 UNLOADING
Unloading of Earth, Sand,
Murrum, Gravel, Manure, Fly-Ash,
Lime, Aggregate, Stone Boulder,
Brick Aggregate, Kankar, Building
Rubbish, Building Rubbish, Crushed
Slag, Stone by mechanical means
including a lead upto 30 m placing
a tipper at loading point , loading
with front end loader excluding
time for haulage and return trip

Placing tipper at unloading point,


excluding time
for haulage and return trip.
Taking output = 5.5 cum
Time required for

145
STANDARD DATA BOOK – LEAD CHARGES

i) Positioning of tipper at loading Min 1.00


point
ii) Loading by front end loader 1 Min 2.00
cum bucket capacity
@ 45 / 25 cum per hour
iii) Waiting time, unforeseen Min 2.00
contingencies, etc.
Total 5.00
A) MACHINERY hour 0.08
Tipper 10 t capacity
Cost for 5.5 cum =
b) contractor's profit and
overhead charges
Rate per cum = (a+b)/5.5

COM-LDLFT-6 LIFT CHARGES FOR MATERIALS BY HEAD LOAD

65 LIFT UPTO 3.00 M


FOR CATEGORY : Earth / Sand /
Gravel / Murrum / Lime / Surki /
Coarse aggregate /
This is the initial lift and forms
integral part of the activities in the
basic rate of work item.
Lift charges are admissible only
lifting effort beyond initial lift
specified in the work item.

66 ADDITIONAL LIFT CHARGES FOR


each 1 METER LIFT BEYOND 3 M
INITIAL LIFT

For additional lift of 1m beyond


initial lift of 3 m
one meter lift is taken equivalent
to 6 meters lead
average speed of conveyance by 60 M/
head load minute
Round trip cycle time for 1.00 m
considering 50 min/ hr working
1 x6x 60 / 50 / 60 ) min 0.12
No. of trips per day for lift 1.0 m 4000
above 3 m ( 8 x 60 / 0..12)
Quantity of material by head load cum 0.015
Quantity of material by head load cum 60
per day ( 4000x 0.015 )
Deploy 1 mazdoor for every
additional lift of 1.0 m beyond
initial lift.
A) LABOUR
Mazdoor day 1.00
b) contractor's profit and
overhead charges

146
STANDARD DATA BOOK – LEAD CHARGES

Rate per cum = (a+b)/60

67 LIFT UPTO 3.00 M


FOR CATEGORY : Cement Bag/
Reinforcement Steel/ Structural
Steel sections
This is the initial lift and forms
integral part of the activities in the
basic rate of work item.
Lift charges are admissible only
lifting effort beyond initial lift
specified in the work item.

68 ADDITIONAL LIFT CHARGES FOR


each 1 METER LIFT BEYOND 3 M
INITIAL LIFT

For additional lift of 1m beyond


initial lift of 3 m
one meter lift is taken equivalent
to 6 meters lead
average speed of conveyance by 25 M/
head load Minute
Round trip cycle time for 1.00 m
considering 50 min/ hr working
1 x6x 60 / 50 / 25 ) min 0.29
No. of trips per day foradditional 1655
lift 1.0 m above 3 m ( 8 x 60 / 0.29)

Quantity of material by head load kgs 50

Quantity of material by head load tons 83


per day ( 1655x50x 0.015 )
Deploy 1 mazdoor for every
additional lift of 1.5 m beyond
initial lift.or2/3 mazdoor
A) LABOUR
Mazdoor day 1.00
b) contractor's profit and
overhead charges
Rate per cum = (a+b)/83

69 LIFT UPTO 3.00 M


FOR CATEGORY : PCC slab /
Shahabad stone slab / CC block /
Laterite stone / BS slab / Wood
FOR CATEGORY : Cement Bag/
Reinforcement Steel/ Structural
Steel sections
This is the initial lift and forms
integral part of the activities in the
basic rate of work item.

147
STANDARD DATA BOOK – LEAD CHARGES

Lift charges are admissible only


lifting effort beyond initial lift
specified in the work item.
For additional lift of 1m beyond
initial lift of 3 m
one meter lift is taken equivalent
to 6 meters lead
average speed of conveyance by 25 M/
head load Minute
Round trip cycle time for 1.00 m
considering 50 min/ hr working
1 x6x 60 / 50 / 40 ) min 0.18
No. of trips per day for lift 1.0 m (8 2667
x 60 / 0.18 )
Quantity of material by head load cum 0.017
Quantity of material by head load cum 45
per day ( 1667x 0.018 )
Deploy 1 mazdoor for every
additional lift of 1.5 m beyond
initial lift.or2/3 mazdoor
A) LABOUR
Mazdoor day 1.00
b) contractor's profit and
overhead charges
Rate per cum = (a+b)/45

148
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS - PREAMBLE

STANDARD DATA ELECTRICAL ITEMS FOR BUILDINGS


PREAMBLE

The Standard Data for Electrical Works are prepared based on the relevant BIS
Specifications in conjunction with National Electric Code. Similarly the method of execution
shall be as per the provisions contained in IE Rules and National Electric Code.
The following are the Chapters.
CHAPTER 1 : CONDUIT LAYING
This chapter contains conduit laying i.e. M.S. Conduit, PVC Pipe and PVC Casing and
Capping. The MS Conduit shall be finished with stone enameled surface. The MS Conduit
accessories shall be threaded type only. The conduit shall be joined by means of screwed
couplers and screwed accessories only.
The PVC Pipe should confirm with relevant IS Specifications. PVC casing and capping
is meant of emergency and additional points only.
For LAN / Telephone / Computer Separate Conduit should be laid.
CHAPTER 2 : WIRING
This unit comprises of copper wiring for light points and fan points. Further,
electrical accessories such as Plug Sockets, Batten Holders, Call Bells etc., are provided in this
chapter.
The PVC insulated and flexible copper wires shall be Fire – Retardant and confirm to
IS 694. The colour code for wires shall be followed strictly for the entire installation as
follows :
R – Red
Y – Yellow For Phases
B – Blue
B – Black --- For Neutral
G – Green --- For Earth
All Switch boards for neutral conduit wiring shall be fabricated with CRCA Sheet
Steel from 1.6 mm (16 SWG) thick with 7 – tank process and powder coating or Hot dip
galvanized boxes.
The mounting height of boards (Bottom of Box) shall be as follows :
a) All Switch Boards : 1.32 m from FFL (Finished Floor Level)
b) 16 A Power Plugs
and Metal Sockets : Sill Level of the Window
c) 16 A Power Plugs
and Metal Sockets in Kitchen : Above 30 cm on Platform
d) MCB Distribution Board : 2 m from FFL
The entire installation shall be tested for
(i) Installation Resistance
(ii) Earth Continuity

149
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS - PREAMBLE

CHAPTER 3 : RUN OF MAINS


This chapter contains run of mains and circuit mains from Main Distribution Board to
Sub-distribution Boards and Sub-distribution Boards to Switch Boards. All the cables shall
confirm to IS : 694 and if fire retardant.

CHAPTER 4 : SWITCH GEAR & MCB DISTRIBUTION BOARD


This chapter contains of Switch Disconnection Fuse (SDF), On-Load Change Over
Switches (OLCOS), Moulded Case Circuit Breakers (MCCB), Distribution Boards (DB),
Miniature Circuit Breakers (MCB), Isolators, Residual Current Circuit Breakers (RCCB), Earth
Leakage Circuit Breakers (ELCB). The following are the relevant I.S. Specifications for the
Switchgear.
(i) SDF --- IS : 13947 (Part – 3) – 1993
(ii) OLCOS --- IS : 13947 (Part – 3) – 1993
(iii) MCCB --- IS : 13947 (Part – 2) – 1993
(iv) MCB --- IS : 8828 : 96
(v) Isolator --- IS : 13947 (Part – 3) – 1993
(vi) RCCB / ELCB --- IS : 12640 - 1 : 2000
(vii) DISTRIBUTION BOARD IS : 13032
The Distribution Board shall have vermin, dust and rust proof as per IP – 20 and IP –
42 protections.
An earth leakage circuit breaker of sufficient rating earth leakage shall be provided
on the low voltage side to detect the leakage in x-ray installation, as per Rule 73 (ee) of IE
Rules.
CHAPTER 5 : EARTHING
This chapter comprises of GI Pipe earthing, Copper Plate earthing, Earth Lead &
Earth Strip.
The earthing should be provided for all power consuming devices as per IS
Specifications. Copper Plate earthing shall be provided for sophisticated electronic
equipment.
The Earthing Work shall confirm to the IS : 732.
CHAPTER 6 : SERVICE MAINS & LTOH LINES
Weather Proof Single Core (WPSC) and Weather Proof Twin Core (WPTC) Service
Cables are provided in this chapter. Accessories for LTOH Lines, PSCC Poles are also covered
under this chapter.
The supports for overhead lines shall be of adequate strength confirming in all
respects to Rule 76 of IE Rules. The insulators shall confirm to IS : 1445. The OH Conductor
(AAAC) shall confirm with IS : 398.
CHAPTER 7 : STREET LIGHT LUMINARIES
In this chapter, Florescent Luminaire, MV Luminaire, SV Luminaire, Metal Halide
Luminaire, Post Top Luminaire, Well Glass Luminaire and Flood Light Luminaire are covered.

150
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS - PREAMBLE

Provision of SV/ MV / MH Lamps shall be restricted to Non-residential buildings and


residential buildings where security is involved such as residences of Hon’ble Judges, Hon’ble
Ministers, IAS / IPS Bungalows, IBs, Guest Houses and Security Lighting keeping in view of
the increase in current consumption charges.
CHAPTER 8 : INTERNAL LUMINAIRE
This chapter is meant for Internal Illumination. General Luminaire, Fluorescent
Luminaire, Industrial Luminaire, Mirror Optic Fittings, T-5 Luminaire, CFL / Halogen Down
Lights are covered under this chapter. It is suggested to provide compact Fluorescent Lamps
/ T- 5 Lamps where minimum lux level is required so as to conserve the electrical energy.

CHAPTER 9 : AC AND REFRIGERATION , FANS


Window type, Split type AC Units, Refrigerators, Ceiling fans and exhaust fans are
covered under this chapter.
The Air-condition Units shall confirm to IS : 1391, Refrigerators shall confirm to IS :
1476 and ceiling fans shall confirm IS : 374.
CHAPTER 10 : WATER HEATERS
This chapter comprises of Water Heaters and their accessories and repairs.
The Water Heater shall confirm to IS : 2082. Effective earthing shall be provided to
Water Heaters.
CHAPTER 11 : WATER PUMPS
In this chapter, Mono Block Pumps, Jet Pumps, Submersible Pumps (Bore well type
& Open well type) along with their accessories are covered.
Data for pump sets are prepared excluding the suction and delivery pipes. The pump
sets shall confirm to IS : 9079 and other relevant specifications where ever exist. For the
items covered under Civil SSR, rates have to be carried from Civil SSR.
CHAPTER 12 : BUS BARS
CHAPTER 13 : SWAGED POLES
DIFFERENT SIZES OF Swaged Poles as per IS : 2713 / 1980 are proposed in this
chapter with necessary brackets, garden posts and accessories.
The classification of roads and recommended assignment of MS Poles shall be as per
Part – 5, out door installation of National Electric Code.
CHAPTER 14 : CONTROL PANEL & METERING EQUIPMENT
The Control Panel Board shall be :
(i) Of the metal enclosed, indoor, floor mounted, free standing type.
(ii) Made up of the requisite vertical sections when compiled together shall
form continuous dead front switch boards.
(iii) Provide dust and damp protection, the degree of the protection being not
less than IP – 51.
(iv) Readily extendable on both sides by the addition of vertical sections after
removal of end covers.
The height of the panel board should not be more than 2400 mm. The depth of the
panel should be adequate to cater proper cable termination.

151
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS - PREAMBLE

All the Steel Work used in the construction of the panel boards should have
undergone a rigorous metal treatment process i.e. 7- tank process.

CHAPTER 15 : CABLES / CABLE GLANDS / LUGS


In this chapter, Armoured under ground cables with their accessories are provided.
The armoured cables shall confirm with IS : 1554 and XLPE cables shall confirm with
IS : 7098.
Manufacturer test report shall be submitted for tests on cables in accordance with
BIS specifications. Cables shall be tested after installation and before commissioning by the
using 1100 volts meggar and the following reading shall be obtained.
a) Continuity of all conductors
b) Insulation Resistance
(i) Between conductors
(ii) All conductors and ground.
Cable glands shall be provided wherever the armoured cables are connected to
Distribution boards. Cable laying and terminations shall confirm to IS : 1255. Earthing of
cable glands shall confirm to IS : 3043.
Cables if laid underground shall be at a depth of not less than 600 mm in a trench.
Sand filling shall be provided at the bottom of trench before laying the cable. Bricks shall be
provided on either side of the laid cable. Sand filling shall be done to cover the cable laid.
Bricks shall be provided on top. Earth filling shall be done. Cable identification tags to be
provided at every 8 m length of cable laid.
GI Pipe / RCC Hume Pipe / Double Corrugated PVC / HDPE Pipe shall be provided for
cable protection to with stand wear and tear of Vehicular Traffic at road crossings.
Cables shall bent to a radius of 20 times diameter of the cable with a minimum of 10
times the diameter at restricted space.
Ladder or perforated type cable trays shall be provided if cable laid inside the
buildings and shall be properly clamped to the trays by plated MS Saddles at proper
intervals.

CHAPTER 16 : TEMPORARY ILLUMINATION


This chapter provides Hire charges for temporary lighting arrangements. Data are
worked out based on the observed data. However, statutory service charges or VAT shall be
added to the data at prevailing rate of percentages

CHAPTER 17 : GENERATORS AND TRANSFORMERS


The Alternator shall confirm with IS : 13364 of 1992 and Diesel Engine shall confirm
with IS : 10001 and IS 10002. Transforms, substation equipment, substation maintenance
and protective gear data are provided in this chapter.
The transformers shall be designed, manufactured and tested as per IS : 2026. For LT
bulk supply, only Core Self Protected (CSP) type aluminum wound distribution transformers

152
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS - PREAMBLE

of 63 KVA / 100 KVA shall be proposed. Where HT supply is required, only copper wound
distribution transformers are to be proposed.
The lightening arrestors shall confirm to IS : 3070 and the protection against the
lightening shall be in accordance with Rule 92 of IE Rules.

CHAPTER 18 : REPAIRS TO MOTORS & REWINDING


All the miscellaneous repairs to motors & fans are covered under this chapter.

153
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Standard Data - Electrical Items For Buildings


Specifica
Quant Rate Amou
Index-code tion No. Description Unit Remarks
ity Rs. nt Rs.
1 2 3 4 5 6 7
BLD-ELEC-1 Conduit Laying
BLD-ELEC-1 1 MS / PVC / Trunks Coduit Laying
BLD-ELEC-1- 1.1 M.S.CONDUIT (Surface)
1
1.1.1 Supply and Fixing of 20mm dia 16 SWG Note for
(ISI Mark) MS Surface conduit pipe duly All Items
threading at Joints with all required for
accessories fixing on T.W. Separators Coduit
with chromium plated base saddles Laying
and No.18 SWG MS box for light, fan
and separate plug points including cost
of Cement, all materials, accessories
and all labour charges etc., complete.
Taking Output = 100 M
a) Material
20mm dia 16 SWG MS conduit 100 M 1
T.W seperators 100 Nos 2
30mm Screws No.8 100 Nos 2
Rawal Plugs 100 Nos 2
12mm Screws 100 Nos 4
20mm Saddles MS 100 Nos 2
20mm 1,2,3 & 4 way Junction box Dozen 1
20mm dia HG bends Dozen 1
200mm x 250mm sheet metal deep Each 3
box
Cement (As per civil SSR) kg 12.5
b) Labour charges :
Skilled Electrician day 3
Semi skilled Electrician day 3
Helpers day 3
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
1.1.2 Supply and Fixing of 25mm dia 16 SWG
(ISI MARK) MS Surface pipe duly
threading at Joints with all required
accessories fixing on T.W. Seperators
with chromium plated base saddles
and No.18 SWG MS box for run of
mains including cost of Cement, all
materials, accessories and all labour
charges etc., complete.
Taking Output = 100 M
a) Material
25mm dia 16 SWG MS conduit 100 M 1
T.W seperators 100 Nos 1.5
38mm Screws No.8 100 Nos 1.5
Rawal Plugs 100 Nos 1.5

154
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

12mm Screws 100 Nos 3


25mm Saddles MS 100 Nos 1.5
25mm 1,2,3 & 4 way Junction box Dozen 0.5
25mm dia HG bends Dozen 1
Cement (As per civil SSR) kg 12.5
b) Labour charges :
Skilled Electrician day 3
Semi skilled Electrician day 3
Helpers day 3
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
1.1.3 Supply and Fixing of 32mm dia 16 SWG
(ISI MARK) MS Surface pipe duly
threading at Joints with all required
accessories fixing on T.W. Seperators
with chromium plated base saddles
and No.18 SWG MS box for run of
mains including cost of Cement, all
materials, accessories and all labour
charges etc., complete.
Unit = 1Metre
Taking Output = 100 M
a) Material
32mm dia 16 SWG MS conduit 100 M 1
T.W seperators 100 Nos 1.5
38mm Screws No.8 100 Nos 1.5
Rawal Plugs 100 Nos 1.5
12mm Screws 100 Nos 3
32mm Saddles MS 100 Nos 1.5
32mm 1,2,3 & 4 way Junction box Dozen 0.5
32mm dia HG bends Dozen 1
Cement (As per civil SSR) kg 12.5
b) Labour charges :
Skilled Electrician day 3
Semi skilled Electrician day 3
Helpers day 3
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
BLD-ELEC-1- 1.2 MS Conduit Concealed
2
1.2.1 Supply and Fixing of 20mm dia 16 SWG
(ISI Mark) MS concealed conduit, duly
threadig at Joints, on wall with
required accessories including
chiselling the wall for light, Fan and
separate plug point including
necessary sheet metal deep boxes,
masonsary work and all labour charges
etc. complete.
Taking Output = 100 M
a) Material

155
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

20mm dia 16 SWG MS conduit pipe 100 M 1


U' Nails 100 Nos 2
200mm x 250mm sheet metal deep Each 3
box
20mm HG bends Dozen 1
Cement kg 12.5
b) Labour charges :
Skilled Electrician day 3
Semi skilled Electrician day 3
Helpers day 3
Mason Ist class day 3
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
1.2.2 Supply and Fixing of 25mm dia 16 SWG
(ISI MARK) MS concealed conduit, duly
threadig at Joints in Slab and on wall
with required accessories including
chiselling the wall and necessary
Masonary and all labour charges etc.
complete for run of mains.
Taking Output = 100 M
a) Material
25mm dia 16 SWG MS conduit pipe 100 M 1
U' Nails 100 Nos 2
25 mm Deep Junction Box Dozen 1
25mm HG bends Dozen 1
Cement kg 50
b) Labour charges :
Skilled Electrician day 3
Semi skilled Electrician day 3
Helpers day 3
Mason Ist class day 3
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
1.2.3 Supply and Fixing of 32mm dia 16 SWG
(ISI Mark) MS concealed conduit, duly
threadig at Joints in Slab and on wall
with required accessories including
chiselling the wall and necessary
Masonary and all labour charges etc.
complete for run of mains.
Taking Output = 100 M
a) Material
32mm dia 16 SWG MS conduit pipe 100 M 1
U' Nails 100 Nos 2
32 mm Deep Junction Box Dozen 1
32mm HG bends Dozen 1
Cement kg 50
b) Labour charges :
Skilled Electrician day 3
Semi skilled Electrician day 3

156
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Helpers day 3
Mason Ist class day 3
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
NOTE : For Laying MS Concealed Conduit pipe in roof
Slab, deduct the Cost of Cement and U' Nails.
BLD-ELEC-1- 1.3 P.V.C. Conduit (Surface)
3
1.3.1 Supply and Fixing of 20mm dia 1.5mm
thick surface P.V.C. pipe (ISI MARK)
with all accessories fixing on chromium
plated metallic base saddles and
decolam board for switches for Light,
Fan and separate plug point including
all labour charges etc., complete.
Taking Output = 100 M
a) Material
20mm dia 1.5mm thick PVC pipe 100 M 1
Rawl Plugs 100 Nos 2
35mm Screws 100 Nos 2
Chromium Plated saddles with base Each 200
20mm 1,2,3, & 4 way Junction boxes Each 12
20mm PVC Bends Each 12
8" x10" Decolam Board Each 3
Cement kg 25
b) Labour charges :
Skilled Electrician day 2
Semi skilled Electrician day 2
Helpers day 2
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
1.3.2 Supply and Fixing of 25mm dia 1.5mm
thick surface P.V.C. pipe (ISI MARK)
with all accessories fixing on chromium
plated metallic base saddles including
all labour charges etc., complete for
run of mains.
Taking Output = 100 M
a) Material
25mm dia 1.5mm thick PVC pipe 100 M 1
Rawl Plugs 100 Nos 2
35mm Screws 100 Nos 2
Chromium Plated saddles with base Each 200
25mm 1,2,3, & 4 way Junction boxes Each 12
25mm PVC Bends Each 12
Cement kg 25
b) Labour charges :
Skilled Electrician day 2
Semi skilled Electrician day 2
Helpers day 2
Sundries

157
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

C) Cost for 100 RM


Rate per Metre = C/100
1.3.3 Supply and Fixing of 32mm dia 2mm
thick surface P.V.C. pipe (ISI Mark) with
all accessories fixing on chromium
plated metallic base saddles including
all labour charges etc., complete for
run of mains
Taking Output = 100 M
a) Material
32mm dia 1.5mm thick PVC pipe 100 M 1
Rawl Plugs 100 Nos 2
35mm Screws 100 Nos 2
Chromium Plated saddles with base Each 200
32mm 1,2,3, & 4 way Junction boxes Each 12
32mm PVC Bends Each 12
Cement kg 25
b) Labour charges :
Skilled Electrician day 2
Semi skilled Electrician day 2
Helpers day 2
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
1.3.4 Supply and Fixing of 40mm dia 2mm
thick surface P.V.C. pipe (ISI MARK)
with all accessories fixing on chromium
plated metallic base saddles including
all labour charges etc., complete for
run of mains.
Taking Output = 100 M
a) Material
40mm dia 1.5mm thick PVC pipe 100 M 1
Rawl Plugs 100 Nos 2
35mm Screws 100 Nos 2
Chromium Plated saddles with base Each 200
40mm 1,2,3, & 4 way Junction boxes Each 12
40mm PVC Bends Each 12
Cement kg 25
b) Labour charges :
Skilled Electrician day 2
Semi skilled Electrician day 2
Helpers day 2
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
1.3.5 Supply and Fixing of 50mm dia 2mm
thick surface P.V.C. pipe (ISI MARK)
with all accessories fixing on chromium
plated metallic base saddles including
all labour charges etc., complete for
run of mains.
Taking Output = 100 M

158
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

a) Material
50mm dia 1.5mm thick PVC pipe 100 M 1
Rawl Plugs 100 Nos 2
35mm Screws 100 Nos 2
Chromium Plated saddles with base Each 200
50mm 1,2,3, & 4 way Junction boxes Each 12
50mm PVC Bends Each 12
Cement kg 25
b) Labour charges :
Skilled Electrician day 2
Semi skilled Electrician day 2
Helpers day 2
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
BLD-ELEC-1- 1.4 P.V.C. Conduit (Concealed)
4
1.4.1 (a) Supply and Fixing of 20mm dia 2mm
thick P.V.C. pipe (ISI MARK) concealed
in wall with all required accessories
including masonary work for light, fan
and separate plug point with well
seasoned wooden deep box including
all labour charges etc., complete.
Taking Output = 100 M
a) Material
20mm dia 2mm thick PVC pipe 100 M 1
U' Links 100 Nos 2
10" x 8" Wooden deep box Each 3
20mm dia 1,2,3 & 4 way deep Junction Each 12
Box
20mm PVC bends Each 12
Cement kg 50
b) Labour charges :
Skilled Electrician day 2
Semi skilled Electrician day 2
Helpers day 2
Mason Ist class day 2
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
(b) Supply and Fixing of 20mm dia 1.5mm
thick P.V.C. pipe (ISI MARK) concealed
in wall with all required accessories
including masonary work for light, fan
and separate plug point with well
seasoned wooden deep box including
all labour charges etc., complete.
Taking Output = 100 M
a) Material
20mm dia 1.5mm thick PVC pipe 100 M 1
U' Links 100 Nos 2
10" x 8" Wooden deep box Each 3

159
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

20mm dia 1,2,3 & 4 way deep Junction Each 12


Box
20mm PVC bends Each 12
Cement kg 50
b) Labour charges :
Skilled Electrician day 2
Semi skilled Electrician day 2
Helpers day 2
Mason Ist class day 2
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
1.4.2 Supply and Fixing of 25mm dia 2mm
(a) thick PVC pipe (ISI MARK) concealed in
wall with all required accessories
including masonary work and labour
charges etc., complete.
Taking Output = 100 M
a) Material
25mm dia 2mm thick PVC pipe 100 M 1
U' Links 100 Nos 2
25mm dia 1,2,3 & 4 way deep Junction Each 12
Box
25mm PVC bends Each 12
Cement kg 50
b) Labour charges :
Skilled Electrician day 2
Semi skilled Electrician day 2
Helpers day 2
Mason Ist class day 2
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
(b) Supply and Fixing of 25mm dia 1.5mm
thick PVC pipe (ISI MARK) concealed in
wall with all required accessories
including masonary work and labour
charges etc., complete.
Taking Output = 100 M
a) Material
25mm dia 1.5mm thick PVC pipe 100 M 1
U' Links 100 Nos 2
25mm dia 1,2,3 & 4 way deep Junction Each 12
Box
25mm PVC bends Each 12
Cement kg 50
b) Labour charges :
Skilled Electrician day 2
Semi skilled Electrician day 2
Helpers day 2
Mason Ist class day 2
Sundries
C) Cost for 100 RM

160
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Rate per Metre = C/100


Supply and Fixing of 25mm dia 2mm
thick PVC pipe (ISI MARK) concealed in
Roof Slabs with all required accessories
including masonary work and labour
charges etc., complete.
Taking Output = 100 M
a) Material
25mm dia 2mm thick PVC pipe 100 M 1
25mm dia 1,2,3 & 4 way deep Junction Each 12
Box
25mm PVC bends Each 12
b) Labour charges :
Skilled Electrician day 2
Semi skilled Electrician day 2
Helpers day 2
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : 1. If 25mm dia PVC / MS pipes are used for
light / fan point, add the cost of sheet metal / well
seasoned wooden board / box.
BLD-ELEC-1- 1.5 P.V.C. Casing and Caping
5
1.5.1 Supply and Laying of P.V.C casing and
caping (ISI MARK) with double locking
arrangments with groover trunking of
size not below 12.5mm height
19/20mm size with all accessories, duly
sealed at points and erected on Wall /
Ceiling including cost of all materials
and labour charges complete.
Taking Output = 100 M
a) Material
19mm / 20mm x 12.5 mm height 100 M 1
Casing and Caping
b) Labour charges :
Skilled Electrician day 1
Semi skilled Electrician day 1
Helpers day 2
Sundries such as screws, Rawal Plugs, LS
Gutting, Cement, Sand and Rounding
off.
C) Cost for 100 RM
Rate per Metre = C/100
1.5.2 Supply and Laying of P.V.C casing and
caping (ISI MARK) with double locking
arrangments with groover trunking of
size not below 12.5mm height 25mm
size with all accessories, duly sealed at
points and erected on Wall / Ceiling
including cost of all materials and
labour charges complete.

161
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Taking Output = 100 M


a) Material
25mm x 12.5 mm height Casing and 100 M 1
Caping
b) Labour charges :
Skilled Electrician day 1
Semi skilled Electrician day 1
Helpers day 2
Sundries such as screws, Rawal Plugs, LS
Gutting, Cement, Sand and Rounding
off.
C) Cost for 100 RM
Rate per Metre = C/100
1.5.3 Supply and Laying of P.V.C casing and
caping (ISI MARK) with double locking
arrangments with groover trunking of
size not below 12.5mm height
31/32mm size with all accessories, duly
sealed at points and erected on Wall /
Ceiling including cost of all materials
and labour charges complete.
Taking Output = 100 M
a) Material
30 / 32mm x 12.5 mm height Casing 100 M 1
and Caping
b) Labour charges :
Skilled Electrician day 1
Semi skilled Electrician day 1
Helpers day 2
Sundries such as screws, Rawal Plugs, LS
Gutting, Cement, Sand and Rounding
off.
C) Cost for 100 RM
Rate per Metre = C/100
1.5.4 Supply and Laying of P.V.C casing and
caping (ISI MARK) with double locking
arrangments with groover trunking of
size not below 12.5mm height 38/40
size with all accessories, duly sealed at
points and erected on Wall / Ceiling
including cost of all materials and
labour charges complete.
Taking Output = 100 M
a) Material
38 / 40mm x 12.5 mm height Casing 100 M 1
and Caping
b) Labour charges :
Skilled Electrician day 1
Semi skilled Electrician day 1
Helpers day 2
Sundries such as screws, Rawal Plugs, LS
Gutting, Cement, Sand and Rounding
off.

162
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

C) Cost for 100 RM


Rate per Metre = C/100
BLD-ELEC-2 2 Wiring Note for
2.1 Copper Wiring All Items
BLD-ELEC-2-
for
1
Wiring
2.1.1 Wiring with 2 runs of 14/0.3mm (1.0 The R&B
Sq.mm) Fire Retardant (FR) P.V.C. Departm
insulated flexible copper cable (ISI ent
MARK) in existing pipe with 6A switch, Proposed
Ceiling rose and 3mm thick hylam Labour,
sheet covering to switch control box for both
including all labour charges etc., piping &
complete for light, bell, fan and wiring
exhaust fan points in Non-Residential consideri
Buildings ng 40%
Taking Output = 6 Points Labour,
a) Material for Wire
draw.
Keeping
this, the
labour is
proposed
for
wiring
100 RM.
14/0.3mm PVC FR flexible copper wire 100 M 1
6A Switch @16/each each 6
6A 2 way Ceiling Rose@17/each each 6
25 x 20 cms (10" x8") Hylam sheet sqm 0.05
3mm thick
b) Labour charges :
Skilled Electrician day 0.6
Semi skilled Electrician day 1.2
Helpers day 0.6
C) Cost for 6 Points
Rate per Point = C/6
2.1.2 Wiring with 2 runs of 14/0.3mm (1.0
Sq.mm) P.V.C. insulated F.R flexible
copper cable (ISI MARK) in existing
pipe with 6A switch, Ceiling rose and
3mm thick hylam sheet covering to
switch control box including all labour
charges etc., complete for light, bell,
fan and exhaust fan points in
Residential Buildings.
Taking Output = 7 Points
a) Material
14/0.3mm PVC FR flexible copper wire 100 M 1
6A Switch @16/each each 7
6A 2 way Ceiling Rose@17/each each 7
25 x 20 cms (10" x8") Hylam sheet sqm 0.05
3mm thick
b) Labour charges :

163
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Skilled Electrician day 0.7


Semi skilled Electrician day 1.4
Helpers day 0.7
C) Cost for 7 Points
Rate per Points = C/7
2.1.3 Wiring with 2 of 14/0.3mm (1.0
Sq.mm) P.V.C. insulated F.R. flexible
copper cable (ISI MARK) in existing
pipe with 6A switch control and 3/2 pin
sockets fixing on separate board
including all labour charges etc.,
complete.
Taking Output = 15 Points
a) Material
14/0.3mm PVC FR flexible copper wire 100 M 1
6A switches @16/each each 15
6A 3 pin / 2 Pin Socket each 15
b) Labour charges :
Skilled Electrician day 1.5
Semi skilled Electrician day 1.5
Helpers day 1.5
C) Cost for 15 Points
Rate per Points = C/15
2.1.4 Supply and fixing of 6A 3 pin wall plug
socket with 6A switch control on a
common switch board with earth
continuity including wire leads, earth
connections along with all labour
charges etc., complete.
Taking Output = each
a) Material
6A 3 pin / 2 pin Socket each 1
6A switch each 1
b) Labour charges :
Skilled Electrician day 0.067
Helpers day 0.067
Rate per each
Note : Labour Charges proposed for 1point
considering 15 per day
2.1.5 Supply and fixing of 16A 3pin / 6A 3pin
plug socket with indicator lamp and
16Amps fuse unit and 16 Amps switch
control (5 in one) on decolam sheet
covered board including earth
connection and all labour charges etc.,
complete on wall.
Taking Output = each
a) Material
20 x 15 cms (8" x6") Decolam sheet each 1
covered board
16A 3 pin / 6A 3pin Plug socket with each 1
indicator lamp, fuse unit (5 in 1)
b) Labour charges :

164
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Skilled Electrician day 0.1


Helpers day 0.1
Rate per each
Note : Labour Charges proposed for 1point
considering 10 per day
2.1.6 Supply and Fixing of 16A 3pin and 6A
3pin plug socket with indicator lamp
and 16A fuse unit and 16A switch
control (5 in 1) duly recessed in wall
with wooden deep box of 6" x8" x2
1/2" size covered with hylam sheet
including earth connections and all
labour charges etc., complete.
Taking Output = each
a) Material
20 x 15 cms (8" x6") Wooden deep box each 1
21.6 x 16.6 cms (8.5 x 6.5") 3mm thick each 1
hylam sheet
16A 3 pin / 6A 3pin plug socket (5 in 1) each 1
b) Labour charges :
Skilled Electrician day 0.1
Semi Skilled Electrician day 0.1
Helpers day 0.1
Rate per each
Note : Labour Charges proposed for 10 jobs per day
2.1.7 Supply and fixing of batten holder /
slanting holder in lieu of ceiling rose of
light point complete with all
connections and all labour charges
with 40W bulb (for new installation).
Taking Output = each
a) Material
PVC batten holder each 1
40W bulb each 1
b) Labour charges :
Skilled Electrician day 0.05
Helpers day 0.05
Rate per each
Note : 1. The Cost of Ceiling Rose may be deducted in
view of holder.
2. Labour Charges proposed for 20 jobs per day
2.1.8 Supply and fixing of batten holder /
angle holder on existing block, but
without bulb including all connections
etc., complete (For replacement).
Taking Output = each
a) Material
PVC batten holder each 1
Less : Cost of ceiling Rose
b) Labour charges :
Skilled Electrician day 0.05
Helpers day 0.05
Rate per each

165
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

NOTE : Labour Charges proposed for 20 jobs per day


2.1.9 Supply and fixing of 0.5mtr length
angle iron upright of size
40mmx40mmx6mm with eye bolt and
shackle insulator with accessories and
all labour charges etc., complete.
Taking Output = each
a) Material
40x40x6mm angle iron Kg 5
Eye bolt. each 1
Shackle Insulator each 1
b) Labour charges :
Semi Skilled Electrician day 0.125
Mason 2nd class day 0.125
Welder 2nd Class day 0.125
Rate per each
NOTE : Labour Charges proposed for 8 jobs per day
2.1.10 Supply and fixing of bed light
transformer with M.C. holders
including giving connections and cost
of all accessories and all labour charges
etc., complete with bulb.
Taking Output = each
a) Material
Bed light transformer each 1
M.C.holder each 1
6V bulb each 1
b) Labour charges :
Skilled Electrician day 0.05
Helpers day 0.05
Rate per each
NOTE : Labour Charges proposed for 20 jobs per day
2.1.11 Supply and fixing of night lamp fixed at
30 cms height from floor level with 100
x 178 x 20 mm (4"x7"x3/4") wooden
deep box, acrylic cover and batten
holder including cost of all accessories
and labour charges etc., complete with
bulb.
Taking Output = each
a) Material
100 x 178 (4"x7") wooden deep box each 1
Acrylic cover each 1
Batten holder each 1
Zero watt bulb each 1
b) Labour charges :
Skilled Electrician day 0.05
Helpers day 0.05
Rate per each
NOTE : Labour Charges proposed for 20 jobs per day

166
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

2.1.12 Supply and fixing of buzzer / Calling


bell on 100 x 100 mm (4"x4") decolam
block including giving connections, cost
of all accessories and labour charges
etc., complete.
Taking Output = each
a) Material
Buzzer each 1
100 x 100 mm (4"x4") decolam block each 1
b) Labour charges :
Skilled Electrician day 0.062
Helpers day 0.062
Rate per each
NOTE : Labour Charges proposed for 16 jobs per day
2.1.13 Supply and fixing of ding dong bell on
100 x 178 mm (4"x7") decolam block
including giving connections cost of all
accessories and all labour charges etc.,
complete.
Taking Output = each
a) Material
Ding Dong bell each 1
100 x 178 mm (4"x7") Decolam block each 1
b) Labour charges :
Skilled Electrician day 0.062
Helpers day 0.062
Rate per each
NOTE : Labour Charges proposed for 16 jobs per day
2.1.14 Supply and fixing of Electronic musical
bell on 150 x 200 mm (6"x8") decolam
block including giving connections cost
of all accessories and all labour charges
etc., complete.
Taking Output = each
a) Material
Electronic Musical bell Nos 1
150 x 200 mm (6"x8") Decolam block Nos 1
b) Labour charges :
Skilled Electrician day 0.062
Helpers day 0.062
Rate per each
NOTE : Labour Charges proposed for 16 jobs per day
BLD-ELEC-3 3 RUN OF MAINS
BLD-ELEC-3- 3.1 Wiring with F.R P.V.C. insulated
1 flexible copper cable
3.1.1 Supply and run of 2 of 14/0.3mm (1.0
Sq.mm) F.R P.V.C. insulated flexible
copper cable in existing pipe for mains
inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
14/0.3mm FR PVC copper wire 100 M 2

167
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

b) Labour charges :
Skilled Electrician day 0.67
Semi Skilled Electrician day 2
Helpers day 0.67
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
3.1.2 Supply and run of 1 of 14 /0.3mm (1.0
Sq.mm) FR P.V.C. insulated flexible
copper cable in existing pipe for earth
continuity including all labour charges
etc., complete.
Taking Output = 100 M
a) Material
14/0.3mm FR PVC copper wire 100 M 1
b) Labour charges :
Skilled Electrician day 0.34
Semi Skilled Electrician day 1
Helpers day 0.34
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
3.1.3 Supply and run of 2 of 22/0.3mm (1.5
Sq.mm) F.R P.V.C. insulated flexible
copper cable in existing pipe for mains
inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
22/0.3mm FR PVC copper wire 100 M 2
b) Labour charges :
Skilled Electrician day 0.67
Semi Skilled Electrician day 2
Helpers day 0.67
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
3.1.4 Supply and run of 2 of 36/0.3mm (2.5
Sq.mm) F.R P.V.C. insulated flexible
copper cable in existing pipe for mains
inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
36/0.3mm (2.5 sqmm) FR PVC copper 100 M 2
wire
b) Labour charges :
Skilled Electrician day 0.67
Semi Skilled Electrician day 2
Helpers day 0.67

168
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
3.1.4 (a) Supply and run of 1 of 36/0.3mm (2.5
Sq.mm) F.R P.V.C. insulated flexible
copper cable in existing pipe for earth
continuity inlcuding all labour charges
etc., complete.
Taking Output = 100 M
a) Material
36/0.3mm (2.5 sqmm) FR PVC copper 100 M 1
wire
b) Labour charges :
Skilled Electrician day 0.34
Semi Skilled Electrician day 1
Helpers day 0.34
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
3.1.5 Supply and run of 2 of 56/0.3mm (4
Sq.mm) FR P.V.C. insulated flexible
copper cable in existing pipe for mains
inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
56 /0.3mm (4 sqmm)FR PVC flexible 100 M 2
copper wire.
b) Labour charges :
Skilled Electrician day 1
Semi Skilled Electrician day 3
Helpers day 1
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 100 M / day
3.1.6 Supply and run of 2 of 84/0.3mm (6.0
Sq.mm) FR P.V.C. insulated flexible
copper cable in existing pipe for mains
inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
84 /0.3mm (6 Sq.mm) FR PVC flexible 100 M 2
copper wire.
b) Labour charges :
Skilled Electrician day 1
Semi Skilled Electrician day 3
Helpers day 1
Sundries
C) Cost for 100 RM

169
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Rate per Metre = C/100


Note : Labour Charges considered for 100 M / day
3.3.7 Supply and run of 2 of 140 /0.3mm (10
Sq.mm) F.R PVC insulated flexible
copper cable in existing pipe for mains
including all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
140/0.3 (10 Sq.mm) FR PVC flexible 100 M 2
copper wire
b) Labour charges :
Skilled Electrician day 1
Semi Skilled Electrician day 3
Helpers day 1
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 100 M / day
3.3.8 Supply and run of 2 of 126 /0.4mm (16
Sq.mm) F.R PVC insulated flexible
copper cable in existing pipe for mains
including all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
126/0.4mm (16 Sq.mm) FR PVC flexible 100 M 2
copper wire
b) Labour charges :
Skilled Electrician day 1
Semi Skilled Electrician day 3
Helpers day 1
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 100 M / day
4 SWITCH GEAR & MCB DISTRIBUTION
BLD-ELEC-4
BOARDS.
4.1 Panel Mounting Cubical type SDF
4.1.1 Supply and erection of Panel mounting
cubical type 30 / 32A TPN 415V, 50 Hz.
switch disconnector fuse unit complete
with front drive mechanism with door
inter lock, padlocking arrangement
etc., complete with fuse links on
existing control panel.
Taking Output = each
a) Material
30 / 32A TPN 415V, 50 Hz. switchs each 1
Disconnector fuse unit with HRC fuses.
b) Labour charges :
Skilled Electrician day 0.167
Semi Skilled Electrician day 0.167

170
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Helpers day 0.333


Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
4.1.2 Supply and erection of Panel mounting
cubical type 60 / 63A TPN 415V, 50 Hz.
switch disconnector fuse unit complete
with front drive mechanism with door
inter lock, padlocking arrangement
etc., complete with fuse links on
existing control panel.
Taking Output = each
a) Material
60 / 63A TPN 415V, 50 Hz. switchs each 1
Disconnector fuse unit with HRC fuses.
b) Labour charges :
Skilled Electrician day 0.167
Semi Skilled Electrician day 0.167
Helpers day 0.333
Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
4.1.3 Supply and erection of Panel mounting
cubical type 125A TPN 415V, 50 Hz.
switch disconnector fuse unit complete
with front drive mechanism with door
inter lock, padlocking arrangement
etc., complete with fuse links on
existing control panel.
Taking Output = each
a) Material
125A TPN 415V, 50 Hz. switchs each 1
Disconnector fuse unit with HRC fuses.
b) Labour charges :
Skilled Electrician day 0.167
Semi Skilled Electrician day 0.167
Helpers day 0.333
Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
4.1.4 Supply and erection of Panel mounting
cubical type 200A TPN 415V, 50 Hz.
switch disconnector fuse unit complete
with front drive mechanism with door
inter lock, padlocking arrangement
etc., complete with fuse links on
existing control panel.
Taking Output = each
a) Material
200A TPN 415V, 50 Hz. switchs each 1
Disconnector fuse unit with HRC fuses.
b) Labour charges :
Skilled Electrician day 0.2

171
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Semi Skilled Electrician day 0.4


Helpers day 0.4
Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 5 jobs / day
4.1.5 Supply and erection of Panel mounting
cubical type 250A TPN 415V, 50 Hz.
switch disconnector fuse unit complete
with front drive mechanism with door
inter lock, padlocking arrangement
etc., complete with fuse links on
existing control panel.
Taking Output = each
a) Material
250A TPN 415V, 50 Hz. switchs each 1
Disconnector fuse unit with HRC fuses.
b) Labour charges :
Skilled Electrician day 0.2
Semi Skilled Electrician day 0.4
Helpers day 0.4
Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 5 jobs / day
4.1.6 Supply and erection of Panel mounting
cubical type 400A TPN 415V, 50 Hz.
switch disconnector fuse unit complete
with front drive mechanism with door
inter lock, padlocking arrangement
etc., complete with fuse links on
existing control panel.
Taking Output = each
a) Material
400A TPN 415V, 50 Hz. switchs each 1
Disconnector fuse unit with HRC fuses.
b) Labour charges :
Skilled Electrician day 0.25
Semi Skilled Electrician day 0.5
Helpers day 0.5
Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 4 jobs / day
4.1.7 Supply and erection of Panel mounting
cubical type 630A TPN 415V, 50 Hz.
switch disconnector fuse unit complete
with front drive mechanism with door
inter lock, padlocking arrangement
etc., complete with fuse links on
existing control panel.
Taking Output = each
a) Material
630A TPN 415V, 50 Hz. switchs each 1
Disconnector fuse unit with HRC fuses.
b) Labour charges :

172
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Skilled Electrician day 0.25


Semi Skilled Electrician day 0.5
Helpers day 0.5
Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 4 jobs / day
4.2 Panel Mounting Cubical type, 4pole
BLD-ELEC-4-
onload change over switch confirming
2
to IS 13947-3-1993.
4.2.1 Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 60 / 63A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
60 / 63A, 4 Pole, 415V, 50 Hz. On load each 1
cubical type C.O.S
b) Labour charges :
Skilled Electrician day 0.167
Semi Skilled Electrician day 0.167
Helpers day 0.333
Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
4.2.2 Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 125A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
125A, 4 Pole, 415V, 50 Hz. On load each 1
cubical type C.O.S
b) Labour charges :
Skilled Electrician day 0.167
Semi Skilled Electrician day 0.167
Helpers day 0.333
Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
4.2.3 Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 200A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
200A, 4 Pole, 415V, 50 Hz. On load each 1
cubical type C.O.S
b) Labour charges :
Skilled Electrician day 0.2
Semi Skilled Electrician day 0.4

173
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Helpers day 0.4


Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 5 jobs / day
4.2.4 Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 250A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
250A, 4 Pole, 415V, 50 Hz. On load each 1
cubical type C.O.S
b) Labour charges :
Skilled Electrician day 0.2
Semi Skilled Electrician day 0.4
Helpers day 0.4
Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 5 jobs / day
4.2.5 Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 400A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
400A, 4 Pole, 415V, 50 Hz. On load each 1
cubical type C.O.S
b) Labour charges :
Skilled Electrician day 0.25
Semi Skilled Electrician day 0.5
Helpers day 0.5
Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 4 jobs / day
4.2.6 Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 630A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
630A, 4 Pole, 415V, 50 Hz. On load each 1
cubical type C.O.S
b) Labour charges :
Skilled Electrician day 0.25
Semi Skilled Electrician day 0.5
Helpers day 0.5
Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 4 jobs / day

174
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

4.2.7 Supply and erection of Panel mounting


cubical type L.T heavy duty ON LOAD
change over switch of 800A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
800A, 4 Pole, 415V, 50 Hz. On load each 1
cubical type C.O.S
b) Labour charges :
Skilled Electrician day 1
Semi Skilled Electrician day 1
Helpers day 1
Sundries such as hardware etc., LS
Rate per each
4.2.8 Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 1060A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
1060A, 4 Pole, 415V, 50 Hz. On load each 1
cubical type C.O.S
b) Labour charges :
Skilled Electrician day 1
Semi Skilled Electrician day 1
Helpers day 1
Sundries such as hardware etc., LS
Rate per each
BLD-ELEC-4- 4.3 Panel Mounting Moulded Case Circute
3 Breakers (MCCBs)
4.3.1 Supply and erection of Panel mounting
60 / 63A, 3 Pole, 10 /16kA, MCCB with
thermal magnetic setting /
Microprocessor based release
arrangement with all connections etc.,
complete on existing panel.
Taking Output = each
a) Material
60 / 63A, 3 Pole, 10 / 16kA, MCCB. each 1
b) Labour charges :
Skilled Electrician day 0.167
Semi Skilled Electrician day 0.167
Helpers day 0.333
Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 6 jobs / day

175
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

4.3.2 Supply and erection of Panel mounting


60 / 63A, 4 Pole, 10 / 16kA, MCCB with
thermal magnetic setting /
Microprocessor based release
arrangement with all connections etc.,
complete on existing panel.
Taking Output = each
a) Material
Cost of 60 / 63A, 4 Pole Panel each 1
mounting 10 / 16 kA, MCCB
b) Labour charges :
Skilled Electrician day 0.167
Semi Skilled Electrician day 0.167
Helpers day 0.333
Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
4.3.3 Supply and erection of Panel mounting
125A, 3 Pole, 25kA, MCCB with thermal
magnetic setting / Microprocessor
based release arrangement with all
connections etc., complete on existing
panel.
Taking Output = each
a) Material
Cost of 125A, 3 Pole, 25 kA panel each 1
mounting MCCB.
b) Labour charges :
Skilled Electrician day 0.167
Semi Skilled Electrician day 0.167
Helpers day 0.333
Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
4.3.4 Supply and erection of Panel mounting
125A, 4 Pole, 25kA, MCCB with thermal
magnetic setting / Microprocessor
based release arrangement with all
connections etc., complete on existing
panel.
Taking Output = each
a) Material
Cost of 125A, 4 Pole, 25 kA panel each 1
mounting MCCB.
b) Labour charges :
Skilled Electrician day 0.167
Semi Skilled Electrician day 0.167
Helpers day 0.333
Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 6 jobs / day

176
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

4.3.5 Supply and erection of Panel mounting


250A, 4 Pole, 35 / 36kA, MCCB with
thermal magnetic setting /
Microprocessor based release
arrangement with all connections etc.,
complete on existing panel.
Taking Output = each
a) Material
250A, 4 Pole, 36/35kA panel mounting each 1
MCCB
b) Labour charges :
Skilled Electrician day 0.2
Semi Skilled Electrician day 0.4
Helpers day 0.4
Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 5 jobs / day
4.3.6 Supply and erection of Panel mounting
400A, 4 Pole, 35 /36kA, MCCB with
thermal magnetic setting /
Microprocessor based release
arrangement with all connections etc.,
complete on existing panel.
Taking Output = each
a) Material
400A, 4 Pole, 36/35kA panel mounting each 1
MCCB
b) Labour charges :
Skilled Electrician day 0.2
Semi Skilled Electrician day 0.4
Helpers day 0.4
Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 5 jobs / day
BLD-ELEC-4- 4.4 DISTRIBUTION BOARDS
4
4.4.1 Supply and fixing SPN Distribution
board with IP-20 protection suitable
for single phase Earth Leakage Circute
Braker (ELCB) / Residual Current
Circute Braker (RCCB) / Double Pole
(DP) Isolator as incomer and 10kA SP
MCBs as out going including internal
connections and labour charges for
surface / flush mounting etc.,
complete.
A 40A DP Isolator / RCCB / ELCB - 1 No
for incomer, 6-32A SP MCBs - 4Nos
for outgoing.
Taking Output = each
a) Material
SPN 4way D.B with IP-20 Protection each 1
suitable for single phase ECCB / RCCB/
DP Isolator.

177
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

40A D.P.Isolator / ECCB / RCCB each 1


10 kA - 6-32A range SP MCBs each 4
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 0.5
Helpers day 1
Sundries such as hardware, cement LS
etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
B 40A DP Isolator / RCCB / ELCB - 1 No
for incomer, 6-32A SP MCBs - 6Nos
for outgoing.
Taking Output = each
a) Material
SPN 8way D.B with IP-20 Protection each 1
suitable for single phase ECCB / RCCB/
DP Isolator.
40A D.P.Isolator / ECCB / RCCB each 1
10 kA - 6-32A range SP MCBs each 6
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 0.5
Helpers day 1
Sundries such as hardware, cement LS
etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
C 40A DP Isolator / RCCB / ELCB - 1 No
for incomer, 6-32A SP MCBs - 8Nos
for outgoing.
Taking Output = each
a) Material
SPN 12 way D.B with IP-20 Protection each 1
suitable for single phase ECCB / RCCB/
DP Isolator.
40A D.P.Isolator / ECCB / RCCB each 1
10 kA - 6-32A range SP MCBs each 8
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 0.5
Helpers day 1
Sundries such as hardware, cement LS
etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
4.4.2 Supply and fixing SPN Distribution
board with IP-42 protection (Metal
Door) suitable for single phase ELCB /
RCCB/DP Isolator as incomer and 10kA
SP MCBs as outing going including
internal connection and labour charges
for surface / flush mounting etc.,

178
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

complete.

A 40A DP Isolator/ RCCB / ELCB - 1 No


for incomer, 6-32A SP MCBs - 4Nos
for outgoing.
Taking Output = each
a) Material
SPN 4 way D.B with IP-42 Protection each 1
(MD) suitable for single phase ECCB /
RCCB/ DP Isolator.
40A D.P.Isolator / ECCB / RCCB each 1
10 kA - 6-32A range SP MCBs each 4
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 0.5
Helpers day 1
Sundries such as hardware, cement LS
etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
B 40A DP Isolator / RCCB / ELCB - 1 No
for incomer, 6-32A SP MCBs - 6Nos
for outgoing.
Taking Output = each
a) Material
SPN 8 way D.B with IP-42 Protection each 1
(MD) suitable for single phase ECCB /
RCCB/ DP Isolator.
40A D.P.Isolator / ECCB / RCCB each 1
10 kA - 6-32A range SP MCBs each 6
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 0.5
Helpers day 1
Sundries such as hardware, cement LS
etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
C 40A DP Isolator/ RCCB / ELCB - 1 No
for incomer, 6-32A SP MCBs - 8 Nos
for outgoing.
Taking Output = each
a) Material
SPN 12 way D.B with IP-42 Protection each 1
(MD) suitable for single phase ECCB /
RCCB/ DP Isolator.
40A D.P.Isolator / ECCB / RCCB each 1
10 kA - 6-32A range SP MCBs each 8

179
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 0.5
Helpers day 1
Sundries such as hardware, cement LS
etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
4.4.3 Supply and fixing TPN Distribution
board with IP-20 protection suitable
for 3 phase ELCB / RCCB / FP Isolator as
incomer and 10kA SP MCBs as outing
going including internal connection
and labour charges for surface / flush
mounting etc., complete.
A 40A FP Isolator/ RCCB / ELCB - 1 No
for incomer, 10kA-6-32A SP
MCBs - 12Nos for outgoing.
Taking Output = each
a) Material
4way TPN, D.B with IP-20 Protection each 1
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.
40A, 4 Pole Isolator / ELCB / RCCB each 1
10kA - 6-32A range SP MCBs each 12
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 1
Helpers day 1
Sundries such as TW Plugs, Screws LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
B 63A FP Isolator - 1 No for incomer,
10kA- 6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
4way TPN, D.B with IP-20 Protection each 1
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.
63A, 4 Pole Isolator / ELCB / RCCB each 1
10kA - 6-32A range SP MCBs each 12
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 1
Helpers day 1
Sundries such as TW Plugs, Screws LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
C 80A FP Isolator - 1 No for incomer,
10kA- 6-32A SP MCBs - 18Nos for

180
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

outgoing.

Taking Output = each


a) Material
6 way TPN, D.B with IP-20 Protection each 1
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.
80A, 4 Pole Isolator / ELCB / RCCB each 1
10kA - 6-32A range SP MCBs each 18
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 1
Helpers day 1
Sundries such as TW Plugs, Screws LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
4.4.4 Supply and fixing TPN Distribution
board with IP-42 protection (Metal
Door) suitable for 3 phase ELCB / RCCB
/ FP Isolator as incomer and 10kA SP
MCBs as outing going including internal
connection and labour charges for
surface / flush mounting etc.,
complete.
A 40A FP Isolator - 1 No for incomer,
10kA-6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
4way TPN, D.B with IP-42 Protection each 1
(MD) suitable for 3 phase ELCB / RCCB/
FP Isolator as incommer.
40A, 4 Pole Isolator / ELCB / RCCB each 1
10kA - 6-32A range SP MCBs each 12
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 1
Helpers day 1
Sundries such as TW Plugs, Screws LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
B 63A FP Isolator - 1 No for incomer,
10kA-6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
4way TPN, D.B with IP-42 Protection each 1
(MD) suitable for 3 phase ELCB / RCCB/
FP Isolator as incommer.
63A, 4 Pole Isolator / ELCB / RCCB each 1
10kA - 6-32A range SP MCBs each 12

181
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 1
Helpers day 1
Sundries such as TW Plugs, Screws LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
C 80A FP Isolator - 1 No for incomer, 6-
32A SP MCBs - 18Nos for outgoing.
Taking Output = each
a) Material
6 way TPN, D.B with IP-42 Protection each 1
(MD) suitable for 3 phase ELCB / RCCB/
FP Isolator as incommer.
80A, 4 Pole Isolator / ELCB / RCCB each 1
10kA - 6-32A range SP MCBs each 18
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 1
Helpers day 1
Sundries such as TW Plugs, Screws LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
4.4.5 Supply and fixing TPN - Vertical type
Distribution board with IP - 20
Protection suitable for 3 phase ELCB /
RCCB / FP Isolator as incomer and 10
kA TP / SP MCBs as outing going
including internal connection and
labour charges for surface / flush
mounting etc., complete.
A Incomer : 63A FP Isolator / ELCB /
RCCB
Outgoing : 32A TP MCBs 2 Nos and
6-32A SP MCBs 6 Nos
a) Material
4way TPN - Vertical type DB with IP-20 Nos 1
protection suitable for 3 Phase ELCB /
RCCB / 4 Pole Isolator as in commer
and TP / SP MCBs as outgoing with
Bus-bar arrangment etc.,
63Apms, 4 Pole Isolator / ELCB / RCCB Nos 1
32A TP MCBs Nos 2
10kA -6-32A SP MCBs Nos 6
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 1
Helpers day 1
Sundries, suchas T.W plugs, Screws, LS
Cement etc,
Rate per each

182
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Note : Labour Charges considered for 2 jobs / day


B Incomer : 80A FP Isolator / ELCB /
RCCB
Outgoing : 32A TP MCBs 4 Nos and
6-32A SP MCBs 12Nos
a) Material
8way TPN - Vertical type DB with IP-20 Nos 1
protection suitable for 3 Phase ELCB /
RCCB / 4 Pole Isolator as in commer
and TP / SP MCBs as outgoing with
Bus-bar arrangment etc.,
80 Apms, 4 Pole Isolator / ELCB / RCCB Nos 1
32A TP MCBs Nos 4
10kA -6-32A SP MCBs Nos 8
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 1
Helpers day 1
Sundries, suchas T.W plugs, Screws, LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
4.4.6 Supply and fixing TPN - Vertical type
Distribution board with IP - 42
Protection (Metal Door) suitable for 3
phase ELCB / RCCB / FP Isolator as
incomer and 10 kA TP / SP MCBs as
outing going including internal
connection and labour charges for
surface / flush mounting etc.,
complete.
A Incomer : 63A FP Isolator/ ELCB /
RCCB
Outgoing : 32A TP MCBs 2 Nos and
6-32A SP MCBs 6 Nos
a) Material
4way TPN - Vertical type DB with IP-42 Nos 1
(Metal Door) protection suitable for 3
Phase ELCB / RCCB / 4 Pole Isolator as
in commer and TP / SP MCBs as
outgoing with Bus-bar arrangment etc.,
63Apms, 4 Pole Isolator / ELCB / RCCB Nos 1
32A TP MCBs Nos 2
10kA -6-32A SP MCBs Nos 6
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 1
Helpers day 1
Sundries, suchas T.W plugs, Screws, LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
B Incomer : 80A FP Isolator/ ELCB /
RCCB

183
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Outgoing : 32A TP MCBs 4 Nos and


6-32A SP MCBs 12 Nos
a) Material
8way TPN - Vertical type DB with IP-42 Nos 1
(MD) protection suitable for 3 Phase
ELCB / RCCB / 4 Pole Isolator as in
commer and TP / SP MCBs as outgoing
with Bus-bar arrangment etc.,
80 Apms, 4 Pole Isolator / ELCB / RCCB Nos 1
32A TP MCBs Nos 4
10kA -6-32A SP MCBs Nos 8
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 1
Helpers day 1
Sundries, suchas T.W plugs, Screws, LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
4.4.7 Supply and fixing 7 Segment, TPN
Distribution board with IP-42
Protection (Metal door) with phase
segregation and separation between
incoming and outgoing suitable for 3
Phase ELCB / RCCB / FP Isolator as
incomer and DP Isolator / RCCB for
phase control with 10kA SP MCCB as
outgoing including internal connection
and labour charges for surface / flush
mounting etc., complete.
A Incomer : 63A FP Isolator/ ELCB
/ RCCB
Phase Control : 40A DP Isolator 3
Nos
Outgoing : 10kA 6-32A SP
MCBs 12 Nos
a) Material
7 Segment, TPN Distribution 4Way DB Nos 1
with IP-42 (Metal Door) protection
with phase segregation and seperation
between incomming an outgoing.
63A, 4 Pole Isolator / ELCB / RCCB . Nos 1
40A DP Isolator Nos 3
6-32 Amps range SP MCBs. Nos 12
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 1
Helpers day 1
Sundries such as T.W. Plugs, Screws, LS
Cement etc.,
Rate per each
Note : Labour Charges considered for 2 jobs / day
B Incomer : 80A FP Isolator/ ELCB
/ RCCB

184
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Phase Control : 63A DP Isolator 3


Nos
Outgoing : 10kA-6-32A SP
MCBs 24 Nos
a) Material
7 Segment, TPN Distribution 8 Way DB Nos 1
with IP-42 (Metal Door) protection
with phase segregation and seperation
between incomming an outgoing.
80A, 4 Pole Isolator / ELCB / RCCB . Nos 1
63A DP Isolator Nos 3
6-32 Amps range SP MCBs. Nos 12
b) Labour charges :
Skilled Electrician day 1
Semi Skilled Electrician day 1
Helpers day 1
Sundries such as T.W. Plugs, Screws, LS
Cement etc.,
Rate per each
Note : Labour Charges considered for 2 jobs / day
4.4.8 Supply and fixing TPN - Vertical type
Distribution board with IP -42
Protection (Metal Door) with 125A,
4Pole 25 kA MCCB as incomer with
4Nos 32A TP MCBs and 12 Nos. 10 kA
SPMCBs as outgoing including internal
connection and labour charges for
surface / flush mounting etc.,
complete.
a) Material
8 Way TPN Vertical DB with IP -42 Nos 1
(Metal door) protection suitable for
125A, 4 Pole, 16kA MCCB as incomer.
125 Amps, 4 Pole , 25 kA MCCB Nos 1
10 kA, 32A TP MCBs: Nos 4
10kA, 6 to 32A SP MCBs: Rs.119 / Each Nos 12
b) Labour charges :
Skilled Electrician day 1
Semi Skilled Electrician day 1
Helpers day 1
Sundries such as T.W. Plugs, Screws, LS
Cement etc.,
Rate per each
Note : 1. Labour Charges considered for 2 jobs / day
2. If the Distribution Boards from Item No. 4.4.1 to
4.4.8 proposed for concealing, add the following:
a 1No. Semi skilled mason
b 1/4 bag cement
4.4.9 Supply and fixing Distribution board
with 20A single phase plug and Socket,
in sheet steel enclosure with
10/16/20A SP MCB including internal
connection and labour charges for
surface / flush mounting etc., complete

185
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

a) Material
1 Phase Distribution board with 20A Nos 1
plug and socket.
10/16/20A SP MCB Nos 1
b) Labour charges :
Skilled Electrician Nos 0.25
Semi skilled Electrician Nos 0.25
Helpers Nos 0.25
Sundries such as Cement, Sand, T.W. LS
Plugs, Screws etc.,
Rate per each
Note : 1. Labour Charges considered for 4 jobs / day
2. For concealing, add the following:
a 1No. Semi skilled mason
b 1/4 bag cement
4.4.10 Supply and fixing Distribution board
with 20A 3 phase plug and Socket, in
sheet steel enclosure with 16/20A TP
MCB including internal connection and
labour charges for surface / flush
mounting etc., complete.
a) Material
Distribution board with 3 Ph. 20A Plug Each 1
and Socket .
32A TP MCB, 10 kA Each 1
b) Labour charges :
Skilled Electrician Nos 0.33
Semi skilled Electrician Nos 0.33
Helpers Nos 0.33
Sundries such as Cement, T.W. Plugs,
Screws etc.,
Rate per each
Note : 1. Labour Charges considered for 3 jobs / day
2. For concealing, add the following:
a 1No. Semi skilled mason
b 1/4 bag cement
BLD-ELEC-5 5 EARTHING
BLD-ELEC-5- 5.1 EARTHING
1
5.1.1 Providing independent earthling by
excavating a trench to a depth of 2.1 M
in all soils, as per size specified in the
Data, using 40mm dia 'B' class GI pipe
of 2.5 Mtrs length with necessary
accessories with hume pipe ring duly
providing staggered holes including
filling with equal proportion of Salt and
Charcoal in layers and all labour
charges etc., complete for small
quarters.
a) Material

186
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Earth Work Excavation of Hard gravel cum 0.85


Soil with small boulder for trench 1st
step of size 1.5 x 0.6 x 0.9 m (5'x2'x3')
Excavation of Hard disteggrated rocks cum 0.9
and boulders for trench 2nd Step of
size 1.2 x 0.6 x 1.2 m (Civil SSR)
(4'x2'x4')
25% extra for narrow trench & pit and
back filling with Sand, Coke, Salt etc.,
and leveling
40mm dia 'B' Class G.I pipe Mtr 2.5
25 x 6 mm (1"X 1/4") G.I Flat duly Each 1
drilled 12mm holes (4 Nos) of 200 mm
(8") length
Drilling of 16 Nos through holes of Each 16
12mm dia to G.I pipe
G.I Nuts, Bolts an Washers Set 4
18" dia hume pipe ring Each 1
Hard Coke Kg 40
Salt Kg 20
b) labour charges for fixing pipe ring Each
and connections
Semi skilled Electrician Nos 0.5
Helpers Nos 0.5
Sundries
Rate per each
5.1.2 Providing independent earthing for
Important equipment with 40mm dia
'B' class 2.5m long G.I pipe and 19mm
dia 'B' class G.I pipe of 0.3mtr. long
connected with reducer providing G.I
funnel with mesh enclosed in
C.C.Chamber of 400m x 400m x
400mm with R.C.C. Slab cover duly
providing staggered holes filling with
salt and charcoal from the bottom of
the pipe giving earth connection from
electrode through G.I strip of 25 x
6mm x 200mm length with all
accessories and labour charges
complete, as per IS specifications
732/1982 (Part II)
a) Material
Earth work excavation of hard gravel cum 1.27
soil with small boulders for trench 1st
step of size 1.5 x 0.9 x 0.9 m (5'x3'x3')
Earth work hard disintegrated rock and cum 1.87
boulders for trench 2nd Step of size 1.2
x 0.9 x 1.65 m (Civil SSR-16) (4'x3'x5.5')
25% extra for trenches and narrow Pit,
back filling and blending.
Laying C.C bed in Cement mortar with cum 0.9
1: 2:4 with 20 mm HBG Stone Metal
(Civil SSR).

187
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Masonary through with brick Masonry cum 0.23


with CM 1:3
Cement plastering inside through with sqm 2.09
1:3 Cement mortar, 12 mm thick (Civil
SSR).
40mm dia G.I pipe Class 'B' (Civil SSR) Mtr 2.5
19mm dia G.I pipe Mtr 0.3
40mm x 19mm reducer Each 1
G.I Funel covered with wire mesh Each 1
25mm x 6mm x 200 mm length G.I Each 1
Strip (Flat) with 4 Nos. Holes of 12mm
dia.
Drilling of staggered holes of 12mm Each 16
dia to G.I pipe.
G.I Bolts, Nuts and Washers. Set 4
Hard Coke. kg 4
Salt. kg 20
Cost Iron cover 400 mm x 400mm x L.S
50mm.
b) labour charges for fixing pipe
Skilled Electrician Nos 1
Sundries such as Lugs and Saddles
Rate per each
5.1.3 Providing independent earthing for
Sophisticated Electronic equipment
with 600mm x 600mm x 3.15mm thick
copper plate rigidly fixed to 40mm dia
G.I Pipe of 0.3mtr. length connected
with reducer providing G.I funnel with
wiremesh as per National Electric Code
including C.C.Chamber of size 400m x
400m x 400mm covered with R.C.C.
Slab filling with salt and charcoal
giving earth connection from electrode
G.I strip of 25mm x 6mm x 200mm
length with all accessories and labour
charges complete as per IS
specification 732/1982 (Part II).
a) Material
Earth work excavation of hard gravel cum 1.27
soil with small boulders for trench 1st
step of size 1.5 x 0.9 x 0.9 m (5'x3'x3')
Earth work hard disintegrated rock and cum 1.87
boulders for trench 2nd Step of size 1.2
x 0.9 x 1.65 m (Civil SSR-16) (4'x3'x5.5')
25% extra for trenches and narrow Pit,
back filling and blending.
Laying C.C bed in Cement mortar with cum 0.9
1: 2:4 with 20 mm HBG Stone Metal
(Civil SSR).
Masonary through with brick Masonry cum 0.23
with CM 1:3
Cement plastering inside through with sqm 2.09
1:3 Cement mortar, 12 mm thick (Civil

188
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

SSR).

40mm dia G.I pipe Class 'B' (Civil SSR) Mtr 2.5
19mm dia G.I pipe Mtr 0.3
40mm x 19mm reducer Each 1
G.I Funel covered with wire mesh Each 1
25mm x 6mm x 200 mm length G.I Each 1
Strip (Flat) with 4 Nos. Holes of 12mm
dia.
600mm x600mm x 3.15mm thick kg 10.00
copper plate
Drilling of staggered holes of 12mm Each 16
dia to G.I pipe.
G.I Bolts, Nuts and Washers. Set 4
Hard Coke. kg 4
Salt. kg 20
Cost Iron cover 400 mm x 400mm x L.S
50mm.
b) labour charges for fixing pipe
Skilled Electrician Nos 1
Sundries such as Lugs and Saddles
Rate per each
BLD-ELEC-5- 5.2 G.I Wire and Strip
2
5.2.1 Supply and Run of No.8 SWG G.I wire
including cost of all accessories and
labour charges etc., complete.
a) Material
No.8 SWG G.I wire 100 M Length 10.4
(0.104 Kg / Mtr) Kg
U' Nails 100Nos 1.5
b) labour charges
Helpers day 2
Sundries.
C) Cost for 100 M
Rate per mtr c/100
5.2.2 Supply and Run of No.10 SWG G.I wire
including cost of all accessories and
labour charges etc., complete.
a) Material
No.10 SWG G.I wire 100 M Length 6.7
(0.067 Kg / Mtr) Kg
U' Nails 100Nos 1.5
b) labour charges
Helpers day 2
Sundries.
C) Cost for 100 M
Rate per mtr c/100
5.2.3 Supply and Run of No.12 SWG G.I wire
including cost of all accessories and
labour charges etc., complete.
a) Material

189
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

No.12 SWG G.I wire 100 M Length 4.4


(0.044 Kg / Mtr) Kg
U' Nails 100Nos 1.5
b) labour charges
Helpers day 2
Sundries.
C) Cost for 100 M
Rate per mtr c/100
5.2.4 Supply and Run of No.14 SWG G.I wire
including cost of all accessories and
labour charges etc., complete.
a) Material
No.14 SWG G.I wire 100 M Length 2.6
(0.026 Kg / Mtr) Kg
U' Nails 100Nos 1.5
b) labour charges
Helpers day 2
Sundries.
C) Cost for 100 M
Rate per mtr c/100
5.2.5 Supply and Run of 25mm x 6mm G.I
Strip including cost of all accessories
and labour charges etc., complete.
a) Material
25mm x 6mm G.I Strip 100 M Length kg 118
(1.18 Kg / Mtr)
b) labour charges
Skilled Electrician Nos 2
Helper Nos 2
Sundries such as T&P.
C) Cost for 100 M
Rate per mtr c/100
5.2.6 Supply and Run of 40mm x 6mm G.I
Strip including cost of all accessories
and labour charges etc., complete
a) Material
40mm x 6mm G.I Strip 100 M Length kg 188
(1.88 Kg / Mtr)
b) labour charges
Skilled Electrician Nos 2
Helper Nos 2
Sundries such as T&P.
C) Cost for 100 M
Rate per mtr c/100
5.2.7 Supply and Run of 50mm x 6mm G.I
Strip including cost of all accessories
and labour charges etc., complete.
a) Material
50mm x 6mm G.I Strip 100 M Length kg 236
(2.36 Kg / Mtr)
b) labour charges
Skilled Electrician Nos 2
Helper Nos 2

190
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Sundries such as T&P.


C) Cost for 100 M
Rate per mtr c/100
BLD-ELEC-5- 5.3 Copper wire and Strip
3
5.3.1 Supply and Run of Zero gauge copper
wire including cost of all accessories
and labour charges etc., complete
a) Material
O' SWG Copper wire (0.455 Kg/Mtr.) Kg 45.5
100 M Length
b) labour charges
Skilled Electrician Nos 1
Semi skilled Electrician Nos 1
Helper Nos 1
Sundries such as T&P and rounding off
C) Cost for 100 M
Rate per mtr c/100
5.3.2 Supply and Run of No. 8 SWG copper
wire including cost of all accessories
and labour charges etc., complete.
a) Material
8 SWG Copper wire (0.1155 Kg/Mtr.) Kg 11.55
100 M Length
b) labour charges
Skilled Electrician Nos 1
Semi skilled Electrician Nos 1
Helper Nos 1
Sundries such as T&P and rounding off
C) Cost for 100 M
Rate per mtr c/100
5.3.3 Supply and Run of No. 14 SWG copper
wire including cost of all accessories
and labour charges etc., complete
a) Material
14 SWG Copper wire (0.028 Kg/Mtr.) Kg 2.8
100 M Length
b) labour charges
Skilled Electrician Nos 1
Semi skilled Electrician Nos 1
Helper Nos 1
Sundries such as T&P and rounding off
C) Cost for 100 M
Rate per mtr c/100
5.3.4 Supply and Run of 25mm x 3mm
copper strip including cost of all
accessories and labour charges etc.,
complete.
a) Material
25mmx 3mm Copper strip (0.663 Kg / Kg 66.3
Mtr) 100 M Length
b) labour charges
Skilled Electrician Nos 2

191
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Helper Nos 2
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
5.3.5 Supply and Run of 32mm x 6mm LS
copper strip including cost of all
accessories and labour charges etc.,
complete.
a) Material
32mmx 6mm Copper strip (1.697 Kg / Kg 169.7
Mtr) 100 M Length
b) labour charges
Skilled Electrician Nos 2
Helper Nos 2
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
BLD-ELEC-6 6 SERVICE MAINS & LTOH Lines
BLD-ELEC-6- 6.1 WPSC (Weather Prrof Single Core)
1 (PVC Cleats)
6.1.1 Supply and Run of 2 of 2.5 Sq.mm
WPSC (Whether Proof Single Core)
Aluminium cable along with No.10
SWG G.I bearer wire through PVC
cleats with all accessories including
labour charges etc., complete for
service mains.
a) Material
2.5 Sq.mm WPSC Aluminium cable 100 M 2
No.10 SWG G.I wire. (0.026 Kg / Mtr) kg 6.7
Length 100 RM
PVC Cleats 100 Nos 1
b) labour charges
Skilled Electrician day 1
Semi skilled day 1
Helper day 1
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
6.1.2 Supply and Run of 2 of 6 Sq.mm WPSC
Aluminium cable along with No.10
SWG G.I bearer wire through PVC
cleats with all accessories including
labour charges etc., complete for
service mains.
a) Material
6 Sq.mm WPSC Aluminium cable 100 M 2
No.10 SWG G.I wire. (0.026 Kg / Mtr) kg 6.7
Length 100 RM
PVC Cleats 100 Nos 1
b) labour charges
Skilled Electrician day 1
Semi skilled day 1

192
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Helper day 1
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
6.1.3 Supply and Run of 2 of 10 Sq.mm
WPSC Aluminium cable along with
No.10 SWG G.I bearer wire through
PVC cleats with all accessories
including labour charges etc., complete
for service mains.
a) Material
10 Sq.mm WPSC Aluminium cable 100 M 2
No.10 SWG G.I wire. (0.026 Kg / Mtr kg 6.7
)Length 100 RM
PVC Cleats 100 Nos 1
b) labour charges
Skilled Electrician day 1
Semi skilled day 1
Helper day 1
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
6.1.4 Supply and Run of 4 of 6 Sq.mm WPSC
Aluminium cable along with No.10
SWG G.I bearer wire on both sides
through PVC cleats with all accessories
including labour charges etc., complete
for service mains.
a) Material
6 Sq.mm WPSC Aluminium cable 100 M 4
No.10 SWG GI Wire (6.7kg x 2) Length kg 13.4
200 RM
Binding wire kg 0.25
PVC Cleats / Separters 4 W. 100 Nos 1
b) labour charges
Skilled Electrician day 2
Semi skilled day 2
Helper day 2
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
6.1.5 Supply and Run of 4 of 10 Sq.mm
WPSC Aluminium cable along with
No.10 SWG G.I bearer wire on both
sides through PVC cleats with all
accessories including labour charges
etc., complete for service mains.
a) Material
10 Sq.mm WPSC Aluminium cable 100 M 4

193
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

No.10 SWG GI Wire (6.7kg x 2) Length kg 13.4


200 RM
Binding wire kg 0.25
PVC Cleats / Separters 4 W. 100 Nos 1
b) labour charges
Skilled Electrician day 2
Semi skilled day 2
Helper day 2
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
6.1.6 Supply and Run of 4 of 16 Sq.mm
WPSC Aluminium cable along with
No.10 SWG G.I bearer wire through
PVC cleats with all accessories
including labour charges etc., complete
for service mains.
a) Material
16 Sq.mm WPSC Aluminium cable 100 M 4
No.10 SWG GI Wire (6.7kg x 2) Length kg 13.4
200 RM
Binding wire kg 0.25
PVC Cleats / Separters 4 W. 100 Nos 1
b) labour charges
Skilled Electrician day 2
Semi skilled day 2
Helper day 2
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
BLD-ELEC-6- 6.2 WPTC (Weather Prrof Twin Core)
2 Cable
6.2.1 Supply and Run of 1 of 6 Sq.mm WPTC
Aluminium cable along with No.10
SWG G.I bearer wire through PVC
cleats with all accessories including
labour charges etc., complete.
a) Material
6 Sq.mm (7/18) wptc Aluminium cable 100 M 1
No.10 G.I wire. Length 100 RM kg 6.7
Insulation tapes each 2
Aluminium link clips box 2
b) labour charges
Skilled Electrician day 1
Semi skilled day 1
Helper day 1
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100

194
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

6.2.2 Supply and Run of 1 of 10 Sq.mm


WPTC Aluminium cable along with
No.10 SWG G.I bearer wire through
PVC cleats with all accessories
including labour charges etc.,
complete.
a) Material
10 Sq.mm (7/18) wptc Aluminium 100 M 1
cable
No.10 G.I wire. Length 100 RM kg 6.7
Insulation tapes each 2
Aluminium link clips box 2
b) labour charges
Skilled Electrician day 1
Semi skilled day 1
Helper day 1
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
6.2.3 Supply and Run of 2 of 6 Sq.mm WPTC
Aluminium cable along with No.10
SWG G.I bearer wire through PVC
cleats with all accessories including
labour charges etc., complete.
a) Material
6 Sq.mm (7/18) wptc Aluminium cable 100 M 2
No.10 G.I wire. Length 100 RM kg 6.7
PVC insulation tapes each 4
Link clips box 2
b) labour charges
Skilled Electrician day 1
Semi skilled day 1
Helper day 1
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
6.2.4 Supply and Run of 2 of 10 Sq.mm
WPTC Aluminium cable along with
No.10 SWG G.I bearer wire through
PVC cleats with all accessories
including labour charges etc., complete
a) Material
10 Sq.mm (7/18) wptc Aluminium 100 M 2
cable
No.10 G.I wire. Length 100 RM kg 6.7
PVC insulation tapes each 4
Link clips box 2
b) labour charges
Skilled Electrician day 1
Semi skilled day 1
Helper day 1
Sundries and rounding off
C) Cost for 100 M

195
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Rate per mtr c/100


6.2.5 Supply and Run of 2 of 16 Sq.mm
WPTC Aluminium cable along with
No.10 SWG G.I bearer wire through
PVC cleats with all accessories
including labour charges etc.,
complete.
a) Material
16 Sq.mm (7/18) wptc Aluminium 100 M 2
cable
No.10 G.I wire. Length 100 RM kg 6.7
PVC insulation tapes each 4
Link clips box 2
b) labour charges
Skilled Electrician day 1
Semi skilled day 1
Helper day 1
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
BLD-ELEC-6- 6.3 L.T.O.H. Lines
3
6.3.1 Supply and fixing of 3 phase, 4 wire
angle iron cross arm with 3 Nos shackle
/ pin insulators for phases and C.I
knob for neutral including cost and
conveyance of all materials.
a) Material
Angle Iron 38 x 38 x 6 mm kg 4.27
(1.5"x1.5"x1/4")
Drilling Holes each 6
M.S Clamp 25mm x 6mm with bolts each 1
and nuts
Pin insulators 100 x 80 mm (4"x3 1/2") each 3
C.I Nob each 1
Cutting of angle Iron and Welding LS
including cost of flat Iron etc.,
b) labour charges
Skilled Electrician day 0.125
Semi skilled day 0.125
Rate per Each
Note : 1. Labour Charges considered for 8 jobs / day
6.3.2 Supply and fixing of single phase, 2
wire angle iron cross arm with 1 Nos
shackle / pin insulators for phases and
C.I knob for neutral including cost and
conveyance of all materials.
a) Material
Angle Iron 38 x 38 x 6 mm kg 2.13
(1.5"x1.5"x1/4" (0.61 mt))
Drilling Holes each 4
M.S Clamp 25mm x 6mm with bolts each 1
and nuts

196
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Pin insulators 100 x 80 mm (4"x3 1/2") each 1


C.I Knob each 1
Cutting of angle Iron and Welding LS
including cost of flat Iron sundires.
b) labour charges
Skilled Electrician day 0.1
Semi skilled day 0.1
Rate per Each
Note : 1. Labour Charges considered for 10 jobs / day
6.3.3 Supply and fixing of stayset with 7/8
SWG (10to 15m long) guy insulator
with concreting 1:3:6 incluidng
excavation of pit and back filling
including cost and conveyance of all
materials and labolur charges etc.,
complete.
a) Material
Stay rod of 16mm dia (7/8 SWG) each 1
1560mm length with bolts and nuts
with switch plate.
Stay tight set (Jum Bracket 300mm) pair 1
Stay wire 7/20 weighing 4kgs each 1
Cement Concrete 1:3:6 (As per Civil cum 0.142
SSR)
Excavation of pit and back filling 1.5 x cum 0.675
0.75 x 0.6 m (5'x2.5'x2')
Stay clamp with bolts and nuts set 1
L.T guy insulator each 1
b) labour charges
Skilled Electrician. day 0.5
Man Mazdoor day 1
Rate per Each
Note : 1. Labour Charges considered for 2 jobs / day
6.3.4 Supply and fixing of over head line
horizontal type safety device with
angle iron cross arm of size 50 x 50 x 6
mm, 1.52m length projection from
pole with 38 x 38 x 6 mm (1 1/2"x1
1/2" x 1/4") angle iron arm including
G.I wire for earth continuity and cost
of all accessories labour charges etc.,
complete.
a) Material
50 x 50 x 6 mm (2"x2"x1/4") Angle Iron kg 5.32
of 1.52 Mtr length
38 x 38 x 6 mm (1.5"x1.5"x1/4") Angle kg 1.57
Iron of 0.45 Mtr
Special Flat Iron Clamp 25x6mm with each 1
bolts and nuts
No.8 SWG G.I wire 8m Length kg 0.8
b) labour charges
Skilled Electrician day 0.25
Semi skilled day 0.25

197
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Helper day 0.5


Sundires such as bolts, nuts including
soldering.
Rate per Each
Note : 1. Labour Charges considered for 4 jobs / day
6.3.5 OH Conductors
6.3.5 (a) Supply and erecting 7/2.00 AAAC (All
Aluminium Annealed Conductor) /
Squirrel (20 Sq.mm) conductor for
Overhead line with stringing, binding
and suitable size of clamps for
Jumpering etc., complete
a) Material
7/2.0 AAAC (Squirrel) km 1
7/2.0 AAAC for binding and Jumpering. km 0.1
Aluminium Clamps each 10
b) labour charges
Skilled Electrician day 2
Helper day 8
For special T&P LS
Sundires and rounding off
Rate per km
6.3.5 (b) Supply and erecting 7/2.50 AAAC /
Weasel (34 Sq.mm) conductor for
Overhead line with stringing, binding
and suitable size of clamps for
Jumpering etc., complete.
a) Material
7/2.5 AAAC / Weasel (34 Sq.mm) km 1
7/2.5 AAAC for binding and Jumpering. km 0.1
Aluminium Clamps each 10
b) labour charges
Skilled Electrician day 2
Helper day 8
For special T&P LS
Sundires and rounding off
Rate per km
6.3.5 (c) Supply and erecting 7/3.15 AAAC /
Rabbit (55 Sq.mm) conductor for
Overhead line with stringing, binding
and suitable size of clamps for
Jumpering etc., complete.
a) Material
7/3.15 AAAC / Rabbit (55 Sq.mm) km 1
7/3.15 AAAC for binding and km 0.1
Jumpering.
Aluminium Clamps each 10
b) labour charges
Skilled Electrician day 2
Helper day 8
For special T&P LS
Sundires and rounding off
Rate per km

198
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

6.3.6 Supply and erecting of fibre / PVC


spacers for L.T Overhead line of 3 to 5
conductors.
a) Material
PVC spacer suitable for 3 to 5 each 1
conductos.
b) labour charges
Helper day 0.2
Special T&P. LS
Rate per km
Note : 1. Labour Charges considered for 5 jobs / day
6.3.7 Excavation of hard rock or Bituminous
road (BT) by chiselling for preparing pit
for poles / stay / earth plates / laying
pipes, including clearing the site by
removing debris and making the site to
original position.
a) Material
Cutting B.T road surface (As per Civil cum 1
SSR)
Excavation of WBM under B.T cum 1

Note : Rate shall be as per Civil SSR


6.3.8 (a) Brick Masonry in CM (1:6) with
country Bricks traditional size 23 x 11
x 7 cms
Unit = 1cum
a) Material
Bricks traditional size 23 x 11 x 7 cms Nos 512
2nd class
Cement Mortar 1:6 cum 0.20
b) labour charges
st
Mason 1 class day 0.24
nd
Mason 2 class day 0.56
Mazdoor (unskilled) day 1.88
Scaffolding charges
Add 25% extra on labour for isolated
work
Rate per cum
6.3.8 (b) Plastering with CM (1:5), 12 mm thick

Unit = 10 sqm
a) Material
Cement Mortor (1:5) cum 0.15
b) labour charges
st
Mason 1 class day 0.6
Mazdoor (unskilled) day 0.96
Rate per cum
6.3.8 (c) CRS Masonry in CM (1:6) 2nd Sort

Unit = 1cum
a) Material

199
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Coursed Rubble Stone cum 0.94


Bond Stones 7Nos 0.24 x 0.24 x 0.39 = cum 0.16
0.16cum
Cement Mortar 1:6 cum 0.32
b) labour charges
st
Mason 1 class day 0.45
nd
Mason 2 class day 1.05
Mazdoor (unskilled) day 2.32
Add 25% extra on labour for isolated
work
Rate per cum
6.3.9 (a) Supply Transportation and unloading
the 9.1mtr long PSCC poles with 300kg
working load at site in good condition
for H.T. / L.T. lines support including
cost and conveyance of all materials
and labour charges etc., complete.
a) Material
9.1 Mtr PSCC pole of 300 Kg working each 1
load
Transportation Charges @ 5% of Cost
Helper for Unloading day 0.5
Rate per each
Note : 1. Unloading Charges considered for 12 jobs /
6 Helpers / day
6.3.9 (b) Supply Transportation and unloading
the 9.1mtr long PSCC poles with 280kg
working load at site in good condition
for H.T. / L.T. lines support including
cost and conveyance of all materials
and labour charges etc., complete.
a) Material
9.1 Mtr PSCC pole of 280 Kg working each 1
load
Transportation Charges @ 5% of Cost
Helper for Unloading day 0.5
Rate per each
Note : 1. Unloading Charges considered for 12 jobs /
6 Helpers / day
6.3.9 (c) Supply Transportation and unloading
the 8.0mtr long PSCC poles with 200kg
working load at site in good condition
for H.T. / L.T. lines support including
cost and conveyance of all materials
and labour charges etc., complete.
a) Material
8 Mtr PSCC pole of 200 Kg working each 1
load
Transportation Charges @ 5% of Cost
Helper for Unloading day 0.5
Rate per each
Note : 1. Unloading Charges considered for 12 jobs /
6 Helpers / day

200
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

6.3.9 (d) Supply, Transportation and unloading


the 8.0mtr long PSCC poles with 140kg
working load at site in good condition
for H.T. / L.T. lines support including
cost and conveyance of all materials
and labour charges etc., complete.
a) Material
8 Mtr PSCC pole of 140 Kg working each 1
load
Transportation Charges @ 5% of Cost
Helper for Unloading day 0.5
Rate per each
Note : 1. Unloading Charges considered for 12 jobs /
6 Helpers / day
6.3.10 Supply Transportation and unloading
(a) the RS Joist of 9.0 mtr long 175mm x
85mm size at site in good condition for
H.T. / L.T. lines support including cost
and conveyance of all materials and
labour charges etc., complete.
a) Material
175mm x 85mm, 9.0 Mtr long R.S.Joist kg 176.4
(1mt = 19.6 Kg)
Transportation Charges @ 5% of Cost
Helper for Unloading day 0.33
Rate per each
Note : 1. Unloading Charges considered for 20 jobs /
6 Helpers / day
6.3.10 Supply Transportation and unloading
(b) the RS Joist of 8.0 mtr long 150mm x
75mm size at site in good condition for
H.T. / L.T. lines support including cost
and conveyance of all materials and
labour charges etc., complete.
a) Material
150mm x 75mm, 8.0 Mtr long R.S.Joist kg 120
(1mt = 15.0 Kg)
Transportation Charges @ 5% of Cost
Helper for Unloading day 0.33
Rate per each
Note : 1. Unloading Charges considered for 20 jobs /
6 Helpers / day
BLD-ELEC-7 7 STREET LIGHT LUMINARIES
BLD-ELEC-7- 7.1 FLOURESCENT LUMINAIRE
1
7.1.1 Supply of 1x40W weatherproof
flourescent streetlight fitting
comprising canopy of sheet Aluminium
in stove enamel finish with copper /
VPIT ballast, capacitor, tube and
starter etc., complete.
a) Material
1x40W WP flourscent street light each 1
fitting.

201
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Lamp cost of 40W each 1


Sundries and rounding off
Rate per each
7.1.2 Supply of 2x11W CFL (Compacted
Flourescent Lamp), Street light fitting
with all standard accessories and 2 Nos
11W CFL, Lamp etc., complete.
a) Material
2x11W CFL street light fitting. each 1
Cost of 11W CFL each 1
Sundries and rounding off
Rate per each
7.1.3 Supply of 1x18W CFL, Street light
fitting with all standard accessories
and 1 No 18W CFL lamp etc., complete.
a) Material
1x18W CFL street light flourscent each 1
fitting.
Lamp cost of 1x18W CFL each 1
Sundries and rounding off
Rate per each
BLD-ELEC-7- 7.2 Mercury Vapour (M.V.) LUMINAIRE
2
7.2.1 Supply of single piece die cast
Aluminium body with 80W mercury
vapour luminaire with copper wound
ballast and capacitor including 80W
M.V.Lamp etc., complete.
a) Material
80W MV Lamp fitting single piece die each 1
cast Aluminium body with copper
wound ballast and capacitor
80W MV lamp each 1
Sundries and rounding off
Rate per each
7.2.2 Supply of single piece die cast
Aluminium body with 125W M.V.
luminaire with copper wound ballast
and capacitor including 125W HPMV
lamp etc., complete.
a) Material
125W MV Lamp fitting single piece die each 1
cast Aluminium body with copper
wound ballast and capacitor
125W MV lamp each 1
Sundries and rounding off
Rate per each
BLD-ELEC-7- 7.3 High Pressure Sodium Vapour (S.V.)
3 LUMINAIRE

202
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

7.3.1 Supply of Integral street light luminaire


of 70W HPSV lamp fitting comprises of
single piece die cast Aluminium body
with copper wound ballast and
capacitor, Ignitor, with pot optics
including 70W HPSV lamp etc.,
complete.
a) Material
70W HPSV Lamp fitting single piece die each 1
cast Aluminium body with copper
wound ballast and capacitor, Ignitor,
with pot optics
70W HPSV lamp each 1
Sundries and rounding off
Rate per each
7.3.2 Supply of Integral street light luminaire
of 150W HPSV lamp fitting comprises
of single piece die cast Aluminium
body with copper wound ballast and
capacitor, Ignitor, with pot optics
including 150W HPSV lamp etc.,
complete.
a) Material
150W HPSV Lamp fitting single piece each 1
die cast Aluminium body with copper
wound ballast and capacitor, Ignitor,
with pot optics
156W HPSV lamp each 1
Sundries and rounding off
Rate per each
7.3.3 Supply of Integral street light luminaire
of 250W HPSV lamp fitting comprises
of single piece die cast Aluminium
body with copper wound ballast and
capacitor, Ignitor, with pot optics
including 250W HPSV lamp etc.,
complete.
a) Material
250W HPSV Lamp fitting single piece each 1
die cast Aluminium body with copper
wound ballast and capacitor, Ignitor,
with pot optics
250W HPSV lamp each 1
Sundries and rounding off
Rate per each
BLD-ELEC-7- 7.4 METAL HALIDE LUMINAIRE
4
7.4.1 Supply of Integral street light luminaire
of 70W MH lamp fitting comprises of
single piece die cast Aluminium body
with copper wound ballast and
capacitor, Ignitor, with pot optics
including 70W MH lamp etc.,
complete
a) Material

203
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

70W MH Lamp fitting single piece die each 1


cast Aluminium body with copper
wound ballast and capacitor, Ignitor,
with pot optics
70W MH lamp each 1
Sundries and rounding off
Rate per each
7.4.2 Supply of Integral street light luminaire
of 150W MH lamp fitting comprises of
single piece die cast Aluminium body
with copper wound ballast and
capacitor, Ignitor, with pot optics
including 150W MH lamp etc.,
complete.
a) Material
150W MH Lamp fitting single piece die each 1
cast Aluminium body with copper
wound ballast and capacitor, Ignitor,
with pot optics
150W MH lamp each 1
Sundries and rounding off
Rate per each
7.4.3 Supply of Integral street light luminaire
of 250W MH lamp fitting comprises of
single piece die cast Aluminium body
with copper wound ballast and
capacitor, Ignitor, with pot optics
including 250W MH lamp etc.,
complete.
a) Material
250W MH Lamp fitting single piece die each 1
cast Aluminium body with copper
wound ballast and capacitor, Ignitor,
with pot optics
250W MH lamp each 1
Sundries and rounding off
Rate per each
7.4.4 Supply of integral street light luminaire
of 250W MH with IP-65 protection,
POT optics comprises of single piece
die cast Aluminium body with copper
wound ballast and capacitor with
250W MH lamp etc., complete.
a) Material
250W IP-65 MH Lamp fitting single each 1
piece die cast Aluminium body with
copper wound ballast and capacitor
Lamp cost of 250W MH lamp each 1
Sundries and rounding off
Rate per each
BLD-ELEC-7- 7.5 POST TOP LUMINAIRE
5

204
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

7.5.1 Supply of post top luminaire of


mushroom type with clear acrylic cover
and comprises of control gear capsule
die cast Aluminium alloy with VPIT /
copper ballast suitable for 9/11/13W
CFL with lamp etc., complete.
a) Material
1X9/11/13W CFL Lamp fitting each 1
1X9/11/13W CFL Lamp each 1
Sundries and rounding off
Rate per each
7.5.2 Supply of 125W HPMV integral post
top luminaire with Aluminium canopy
and acrylic diffuser with all standard
accessories and 125W HPMV lamp
etc., complete.
a) Material
125W HPMV post top Lamp fitting each 1
Cost of 125W HPMV post top LAMP each 1
Sundries and rounding off
Rate per each
7.5.3 Supply of 70W HPSV integral post top
luminaire with Aluminium canopy and
acrylic diffuser with all standard
accessories and 70W HPSV lamp etc.,
complete.
a) Material
70W HPSV post top Lamp fitting each 1
Cost of 70W HPSV post top lamp each 1
Sundries and rounding off
Rate per each
7.5.4 Supply of diamond / sphere type 80W
HPMV post top lantern luminaire with
all standard accessories including 80W
M.V. lamp etc., complete
a) Material
80W HPMV post top diamond / sphere each 1
type Lamp fitting
80W HPMV post top diamond / sphere each 1
type Lamp
Sundries and rounding off
Rate per each
7.5.6 Supply of diamond / sphere type 125W
HPMV post top lantern luminaire with
all standard accessories including
125W M.V. lamp etc., complete.
a) Material
125W HPMV post top Lamp fitting each 1
125W HPMV post top Lamp each 1
Sundries and rounding off
Rate per each

205
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

7.5.7 Supply of diamond / sphere type 70W


HPSV post top lantern luminaire with
all standard accessories including 70W
S.V. lamp etc., complete.
a) Material
70W HPSV diamond / sphere post top each 1
Lamp fitting
70W HPSV diamond / sphere post top each 1
Lamp
Sundries and rounding off
Rate per each
BLD-ELEC-7- 7.6 Well Glass Luminaires
6
7.6.1 Supply of 80W M.V integral wellglass
luminaries with all standard
accessories and 80W MV lamp etc.,
complete.
a) Material
80W MV wellglass luminaries each 1
80W MV wellglass luminaries lamp each 1
Sundries and rounding off
Rate per each
7.6.2 Supply of 70W S.V. integral wellglass
luminaries with all standard
accessories and 70W S.V. lamp etc.,
complete.
a) Material
70W SV wellglass luminaires each 1
70W SV wellglass luminaries. each 1
Sundries and rounding off
Rate per each
BLD-ELEC-7- 7.7 Flood Light Luminaires
7
7.7.1 Supply of 500W Halogen fitting with
all accessories including 500W Halogen
lamp etc., complete.
a) Material
500W halogen lamp fitting. each 1
500W halogen lamp each 1
Sundries and rounding off
Rate per each
7.7.2 Supply of 1000W Halogen fitting with
all accessories including 1000W
Halogen lamp etc., complete.
a) Material
1000W halogen lamp fitting. each 1
1000W halogen lamp each 1
Sundries and rounding off
Rate per each

206
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

7.7.3 Supply of integral type flood light


metal halide luminaire of 250W
comprising of die cast Aluminium
housing and a heat resistant toughned
glass firmly fixed by means of gasket
and toggles with IP-65 protection
incluidng control gear housing and all
accessories with 250W MH-T lamp etc.,
complete.
a) Material
250W MH flood light fitting each 1
250W MH lamp. each 1
Sundries and rounding off
Rate per each
7.7.4 Supply of integral type flood light
metal halide luminaire of 400W
comprising of die cast Aluminium
housing and a heat resistant toughned
glass firmly fixed by means of gasket
and toggles with IP-65 protection
incluidng control gear housing and all
accessories with 400W MH-T lamp etc.,
complete.
a) Material
400W MH flood light fitting each 1
400W MH flood light lamps each 1
Sundries and rounding off
Rate per each
BLD-ELEC-7- 7.8 Labour Charges
8
7.8.1 Fixing of CFL luminaire (Down lights /
Mirror optic / Ornamental type fitting
with all necessary accessories in false
ceiling / on wall including giving
connections and all labour charges
etc., complete.
a) Material
23/0060 twin core flexible copper M 1
cable
screws with rawal plugs each 2
Aluminium flat / cement and sand etc., LS
labour charges.
b) Labour charges.
Skilled Electrician/carpenter day 0.066
Semi skilled Electrician / Helper day 0.066
Rate per each
Note : Labour Charges considered for15 fixtures / day
.
7.9.2 Fixing of 70W MH down light and
control gear box with necessary
accessories in false ceiling including
giving connections and all labour
charges etc., complete.
a) Material

207
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

23/0060 twin core flexible copper M 1


cable
screws with rawal plugs each 2
Aluminium flat / cement and sand etc., LS
labour charges.
b) Labour charges
Skilled Electrician/carpenter day 0.125
Semi skilled Electrician / Helper day 0.125
Rate per each
Note : Labour Charges considered for 8
fixtures / day .
7.9.3 Fixing of 40W tube light luminaire on
wall / Ceiling with / TW round blocks
with all accessories including giving
connections and all labour charges
etc., complete.
a) Material
23/0060 twin core flexible copper M 1
cable
screws with rawal plugs each 2
T.W round blocks each 2
Cement and sand etc., LS
b) Labour charges
Skilled Electrician/carpenter day 0.1
Semi skilled Electrician / Helper day 0.1
Rate per each
Note : Labour Charges considered for 10 fixtures /
day .
7.9.4 Fixing of 40W tube lights with 1/2 Mtr
conduit suspension arrangements from
ceiling with hooks etc., including giving
connections and all labour charges
etc., complete.
a) Material
20mm dia No.16 gauge conduit pipe . M 1
23/0060 twin core flexible copper each 1
cable
Anchor screws / Hooks / Sockets & each 2
Check
b) Labour charges
Skilled Electrician/carpenter day 0.166
Semi skilled Electrician / Helper day 0.166
Rate per each
Note : Labour Charges considered for 6
fixtures / day .
7.9.5 Fixing of 40W street light luminaire to
the wall with 1.0 Mtr., 25mm dia GI
pipe bracket and anti tilting MS flat
etc., including giving connections and
labour charges etc., complete.
a) Material
25mm dia G.I pipe M 1
23/0060 twin core flexible copper M 2

208
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

cable
Pipe bending charges LS
M.S flat and welding charges LS
b) Labour charges
Skilled Electrician/carpenter day 0.2
Mason day 0.2
Semi skilled Electrician / Helper day 0.2
Rate per each
Note : Labour Charges considered for 5
fixtures / day .
7.9.6 Fixing of CFL street light luminary with
1.0 Mtr., 25mm dia GI pipe bracket
and anti tilting MS flat etc., including
giving connections and labour charges
etc., complete.
a) Material
25mm dia G.I pipe M 1
23/0060 twin core flexible copper M 2
cable
Pipe bending charges LS
M.S flat and welding charges LS
b) Labour charges
Skilled Electrician/carpenter day 0.125
Mason day 0.125
Helper day 0.125
Rate per each
Note : Labour Charges considered for 8
fixtures / day .
7.9.7 Fixing of mirror optic tube light
luminaire in false ceiling / pop with
necessary arrangment including giving
connections and all labour charges
etc., complete.
a) Material
28/0060 twin core flexible copper M 1
cable
Aluminium flat (as per requirment) LS
b) Labour charges for cutting P.O.P /
false ceiling and Fixing MOT
Skilled Electrician day 0.125
Carpenter day 0.125
Semi skilled Electrician / Helper day 0.125
Rate per each
Note : Labour Charges considered for 8 Nos MOT
lights in a day
7.9.8 Fixing of MV / SV/MH luminaire on
wall with 1.0mt 40mm dia GI pipe
bracket and anti-tilting MS flat, 2.5
Sq.mm flexible copper cable
etc.,including all labour charges for
mason work and giving connections
etc., complete.
a) Material
40mm G.I pipe for Bracket M 1

209
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

2.5 Sq.mm flexible copper cable M 4


Pipe bending charges LS
b) Labour charges for Antitiling MS
flat / welding charges & fixing
Skilled Electrician day 0.25
Carpenter day 0.25
Helper day 0.25
Welder day 0.25
Rate per each
Note : Labour Charges considered for 4Nos MV / SV /
MH in a day
Bldngs_Elec- 8 INTERNAL LUMINAIRE
8
8.1.1 Supply and fixing of single fancy
Bldngs_Elec- bracket with glass shade and bulb of
8-1 approved colour and quality etc., by
field officers
a) Material
Single Fancy bracket each 1
60W Bulb each 1
b) Labour charges
Skilled Electrician day 0.04
Helper day 0.04
Sundires LS
Rate per each
Note : Labour Charges considered for 25Jobs per Day
8.1.2 Supply and fixing of double fancy
bracket with glass shade and bulb of
approved colour and quality etc., by
field officers.
a) Material
Double Fancy bracket each 1
60W Bulb each 2
b) Labour charges
Skilled Electrician day 0.05
Helper day 0.05
Sundires
Rate per each
Note : Labour Charges considered for
20Jobs /Day
8.1.3 Supply and fixing 10" ceiling fittings
with glass doom and bulb apporved by
dept., officers including giving
connection etc., complete.
a) Material
10" Ceiling fitting with glass doom each 1
60W Bulb each 1
b) Labour charges
Skilled Electrician day 0.05
Helper day 0.05
Sundires
Rate per each

210
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Note : Labour Charges considered for


20 Jobs / Day
8.1.4 Supply and fixing of Bulk head fitting
with cast Aluminium enamel painted
body with water tight, clear glass with
wire guard hinged with lock and key
arrangements etc., complete with
lamp.
a) Material
Bulkhead fitting each 1
60W Bulb each 1
b) Labour charges
Skilled Electrician day 0.083
Helper day 0.083
Sundires such as TW block / screws,
cement etc.,
Rate per each
Note : Labour Charges considered for
12 Jobs / Day
Bldngs_Elec- 8.2 Flourescent Luminaire
8-2
8.2.1 Supply and transportation of 1x11 W
mirror light with all standard
accessories diffuser and 1No 11W CFL
lamp etc., complete
a) Material
1x11W M.O. fitting each 1
Cost of C.F.L. each 1
Sundries and rounding off
Rate per each
8.2.2 Supply and Transportation of
1x36/40W box type tube light
luminaire with copper / VPIT Choke,
condensor, starters etc., and 1No
36/40W tube etc., complete.
a) Material
1x40/36 box type T.L fitting each 1
36/40 Tube each 1
Sundries and rounding off
Rate per each
8.2.3 Supply and transportation of
2x36/40W box type tube light
luminaire with 2Nos copper / VPIT
chokes, starters, with condensor and
2Nos 36/40W tube etc., complete.
a) Material
2x40/36 box type T.L fitting each 1
36/40 FTL each 2
Sundries and rounding off
Rate per each
8.2.4 Supply and Transportation of 1x40W
patty type tube light luminaire with
copper choke, starter etc., including
1No 40W tube etc., complete.

211
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

a) Material
1x40 patty type T.L. fitting each 1
40W FTL each 1
Sundires and rounding off
Rate per each
Bldngs_Elec- 8.3 INDUSTRIAL luminaire
8-3
8.3.1 Supply and Transportation of white
vitreous 1x36 / 40W industrial box
type luminaire with Copper / VPIT
Choke, Condensor, Starters etc., with
reflector including 1No 40W tube etc.,
complete.
a) Material
1x36/40W Industrial box type T.L. each 1
fitting
36/40W FTL each 1
Sundries and rounding off
Rate per each
8.3.2 Supply and Transportation of white
vitreous 2x36 / 40W industrial box
type luminaire with 2Nos Copper /
VPIT Choke, Condensor, Starters
etc.,complete with reflector including
2Nos 40W tube etc., complete.
a) Material
2x36/40W Industrial box type T.L. each 1
fitting
36/40W FTL each 2
Sundries and rounding off
Rate per each
Bldngs_Elec- 8.4 MIRROR OPTIC luminaire
8-4
8.4.1 Supply and Transportation of 2x36 /
40W surface mounting mirror optic
luminaire with powder coated CRCA
sheet steel housing with Aluminium
mirror reflectors with VPIT chokes,
Starters, Condensor etc., complete
with 2Nos 36/40W tubes
etc.,complete.
a) Material
2x36/40 Surface M.O.L fitting each 1
40/36 FTL each 2
Sundries and rounding off
Rate per each
8.4.2 Supply and transportation of
2x36/40W recessed mounting mirror
optic (darklite) luminaire with powder
coated CRCA sheet steel housing with
Aluminium mirror reflector with VPIT
Chokes, Starter, Condensor etc.,
complete with 2Nos 36/40W tubes
etc., complete.

212
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

a) Material
2x36/40 Recessed M.O. L fitting each 1
36/40 FTL each 2
Sundries and rounding off
Rate per each
8.4.3 Supply and transportation of 2x11W
surface mounting mirror optic
luminaire with powder coated CRCA
sheet steel housing with Aluminium
mirror refector with VPIT Chokes and
2Nos 11W CFL lamps etc., complete.
a) Material
2x11W CFL surface M.O.L fitting each 1
11W CFL each 2
Sundries and rounding off
Rate per each
8.4.4 Supply and transportation of 2x11W
Recessed type luminaire with powder
coated CRCA sheet steel housing with
Aluminium mirror refector with VPIT
Chokes and 2Nos 11W CFL lamps etc.,
complete.
a) Material
2x11W CFL recessed M.O.L fitting each 1
11W cfl each 2
Sundries and rounding off
Rate per each
8.4.5 Supply and transportation of 2x36w
CFL paralite louvre (P5) recessed low
glare mirror optic luminaire comprising
bright anodised Aluminium reflector
with VPIT Chokes and 36w CFL lamps.
a) Material
2x36 CFL PS paralite Louvars fitting each 1
36w CFL each 2
Sundries and rounding off
Rate per each
8.4.6 Supply and transportation of 3x36w
CFL paralite louvre (P5) recessed low
glare mirror optic luminaire comprising
bright anodised Aluminium reflector
with VPIT Chokes and 3x36w CFL
lamps.
a) Material
3x36 CFL PS paralite Louvars fitting each 1
36w CFL each 3
Sundries and rounding off
Rate per each
Bldngs_Elec- 8.5 T- 5 Luminaires.
8-5

213
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

8.5.1 Supply and transportation of 1X28W


surface pendant mounting T- 5
extruded Aluminium with Aluminium
reflector luminaire with all standard
accessories and connections etc.,
complete with 1 No. 28 W tube
a) Material
1x28w pendant T5 lugs fitting each 1
28w T5 FTL each 1
Sundries and rounding off
Rate per each
8.5.2 Supply and transportation of 2X28W
recessed With 2 Nos. pendant
mounting low glare T- 5 mirror optic
luminaire with electronic Ballasts etc.,
complete 28w tubes.
a) Material
2x28w T5 M.O. fitting each 1
28w T5 FTL each 2
Sundries and rounding off
Rate per each
Bldngs_Elec- 8.6 C.F.L. Down Lights
8-6
8.6.1 Supply and transportation of recessed
mounting 1x13W CFL down light with
all standard accessories with 1No. 13W
CFL lamp (D type) etc., complete.
a) Material
1x13W CFL Down light fitting each 1
13W CFL each 1
Sundries and rounding off
Rate per each
8.6.2 Supply and transportation of recessed
mounting 2x13W CFL down light with
all standard accessories with 2No. 13W
CFL lamp etc., complete.
a) Material
2x13W CFL Down light fitting each 1
13W CFL each 2
Sundries and rounding off
Rate per each
8.6.3 Supply and transportation of recessed
mounting 1x18W CFL down light with
all standard accessories with 1No. 18W
CFL lamp etc., complete.
a) Material
1x18W CFL Down light fitting each 1
18W CFL each 1
Sundries and rounding off
Rate per each

214
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

8.6.4 Supply and transportation of recessed


mounting 2x18W CFL down light with
all standard accessories with 2No. 18W
CFL lamp etc., complete.
a) Material
2x18W CFL Down light fitting each 1
18W CFL each 2
Sundries and rounding off
Rate per each
8.6.5 Supply and Transportation recess
mounting 70W metal hallide down
lighter with control gear and 1No 70W
M.H lamp etc., complete.
a) Material
70W M.H down light fitting each 1
70W M.H lamp each 1
Sundries and rounding off
Rate per each
8.6.6 Supply and Transportation of Ceiling /
Wall mounted Circular 1x13W
luminaire with decorative acrylic
diffuser and 1 No. 13W CFL lamp
(circular type) etc., complete.
a) Material
1x13W Circular CFL fitting each 1
13W CFL each 1
Sundries and rounding off
Rate per each
8.6.7 Supply and Transportation of Ceiling /
Wall mounted Circular 2x13W
luminaire with decorative acrylic
diffuser and 2 No. 13W CFL lamp
(circular type) etc., complete.
a) Material
2x13W Circular CFL fitting each 1
13W CFL each 2
Sundries and rounding off
Rate per each
Bldngs_Elec- 8.7 HALOGEN DOWN LIGHTERS
8-7
8.7.1 Supply and Transportation of recess
mounting 12v, 50w adjustable halogen
down light with white / colour Shade
including transformer and 1No 50w
halogen lamp etc., complete.
a) Material
50w Halogen recessed mounting each 1
50w Halogen bulb each 1
Sundries and rounding off
Rate per each

215
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

8.7.2 Supply and Transportation of recess


mounting 12v, 50w Zoom type halogen
down light with white / colour Shade
including transformer and 1No 50w
halogen lamp etc., complete.
a) Material
50w Halogen zoom type down light. each 1
50w Halogen bulb each 1
Sundries and rounding off
Rate per each
Bldngs_Elec- 9 AIR CONDITIONING & REFRIGERATION
9
Bldngs_Elec- 9.1 Air-Conditioners
9-1
9.1.1(a) Supply and Transportation of Window
mounted type, Room Air-Conditioner
1.5 Ton confirming to IS : 1391,
Suitable for operation on 230V + 10%
50 Hz.., Single phase, A.C. Supply
capable for performing Cooling,
Dehumidifying, Air Circulating, Filtering
and Ventilation etc., complete.
a) Material
1.5 Ton A.C Unit
ADD : Duties & Taxes as applicable
Transportation on Material 2%
Rate per each
9.1.1(b) Supply and Transportation of Window
mounted type, Room Air-Conditioner
2.0 Ton confirming to IS : 1391,
Suitable for operation on 230V + 10%
50 Hz.., Single phase, A.C. Supply
capable for performing Cooling,
Dehumidifying, Air Circulating, Filtering
and Ventilation etc., complete.
a) Material
2.0 Ton A.C Unit
ADD : Duties & Taxes as applicable
Transportation on Material 2%
Rate per each
9.1.2 (a) Supply and Transportation of 1.5 Ton
Split type Air-Conditiner, fitted with
Hermetically sealed compressor,
Operating on refrigerant R-22 / Non -
CFC High wall mounting confirming to
IS : 1391, suitable for operation on
230V, 50 Hz.., Single phase, A.C Supply
capable of performing Cooling,
Dehumidifying, Air Circulating, Filtering
with cooling and condensing units,
with 5 Mtr of required size of copper
piping duly insulated and 3 core copper
flexible chord of required length etc.,
complete.
a) Material

216
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

1.5 Ton Split A.C Unit ABS (Plastic


Cabin)
ADD : Duties & Taxes as applicable
Transportation on Material 2%
Rate per Each
9.1.2 (b) Supply and Transportation of 2.0 Ton
Split type Air-Conditiner, fitted with
Hermetically sealed compressor,
Operating on refrigerant R-22 / Non -
CFC High wall mounting confirming to
IS : 1391, suitable for operation on
230V, 50 Hz.., Single phase, A.C Supply
capable of performing Cooling,
Dehumidifying, Air Circulating, Filtering
with cooling and condensing units,
with 5 Mtr of required size of copper
piping duly insulated and 3 core copper
flexible chord of required length etc.,
complete.
a) Material
2.0 Ton Split ABS Plastic Cabin A.C Unit
ADD : Duties & Taxes as applicable
Transportation on Material 2%
Rate per Each
9.1.3 Installation Charges for 1/0 / 1.5 / 2.0
Ton Window type room Air-
Conditioner with insulating foam,
testing and commissioning etc.,
complete.
a) Material
Installation Charges of Window type
A.C.Unit. (as per observed Data)
Rate per Each
9.1.4 Installation Charges for 1.5 / 2.0 Ton
Split Air-Conditioner with foam,
insulation for copper pipings
connected for the Indoor and outdoor
unit including testing and
commissioning etc., complete.
a) Material
Installation Charges of 1/5 / 2.0 Ton
Split A.C.Unit. (As per observed Data )
Rate per Each
9.1.5 Supply, Fabrication and installation of
well seasoned T.W. frame of size 685 x
483 mm (27" x 19") ( with section size
of 75 x 100 mm (3" x 4" T.W.)) for 1.0 /
1.5 / 2.0 Ton Window A.C.Unit duly
making necessary provision in the wall
/ Window with cost and conveyance of
all materials etc., complete
a) Material
Well seasoned wooden frame for cum 0.018
Window A.C Units

217
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

b) Labour charges for fabrication &


Fixing
Carpenter day 0.5
Mason day 0.5
Helper day 0.5
Making necessary provision in wall / LS
window with Hardware
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
9.1.6 Supply, Fabrication and installation of
38 x 38 x 6 mm (1.5" x 1 1/2" x 1/4")
M.S. angle Iron frame suitable for
condensing Unit for Split A.C including
2 Coats of Red oxide the followed by 2
coats enamel paint etc., complete.
a) Material
38 x 38 x 6 mm (1.5" x 1 /12" x 1/4") kg 10.5
angle iron frame, 13 M length (1 Mtr =
3.5 Kgs)
Fabrication charges including Painting kg 10.5
b) Labour charges for Fixing
Carpenter day 0.25
Mason day 0.25
Helper day 0.25
Sundires such as cement etc. LS
Rate per Each
Note : Labour is Considered for 4 jobs
/ day
9.1.7 Supply and Installation of copper
tubing between indoor and outdoor
unit for split Air-Conditioner including
foaming etc., complete.
a) Material
Copper tubing between indoor and
outdoor units inlcuding foaming
b) Labour charges for cutting,
bending, welding etc.,
Welder day 0.04
Helper day 0.04
Rate per Metre
Note : Labour is Considered for 25 M /
day
Bldngs_Elec- 9.2 REPAIRS TO AIR - CONDITIONERS
9-2
9.2.1 Replacement of defective compressor
by supply of 1.0 / 1.5 Ton brand new
sealed compressor ISI Mark
a) Material
Supply of brand new.1/ 1.5 Ton each 1
compressor ISI Mark
b) Labour charges
Skilled Electrician day 0.5

218
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Helper day 0.5


Transportation on Material 2%
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
9.2.2 Replacement of defective compressor
by supply of 2.0 Ton brand new sealed
compressor ISI Mark
a) Material
Supply of brand new 2.0 Ton each 1
compressor by brand new ISI Mark
b) Labour charges
Skilled Electrician day 0.5
Helper day 0.5
Transportation on Material 2%
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
9.2.3 Replacement of old and Unserviceable
Fan Motor by supply and Installation of
new 1/6th H.P multi speed Fan Motor
suitable for 1.0 / 1.5 / 2.0 Ton Window
A.C.Unit.
a) Material
Supply of 1/6th H.P multispeed Fan each 1
Motor for 1.0 / 1.5 / 2.0 T A.C.Unit.
b) Labour charges
Skilled Electrician day 0.5
Helper day 0.5
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
9.2.5 Replacement of Unserviceable fan
motor capacitor 6 mfd by new
capacitor for A.C machine of 1.0 1.5 /
Ton Capacity.
a) Material
6 MFD motor capacitor each 1
b) Labour charges for removing old
one & fixing
Semi skilled Electrician day 0.2
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
9.2.6 Replacement of Unserviceable
Thermostat switch by supply and
installation of new thermostat switch
suitable for 1.0 / 1.5 / 2.0 Ton
A.C.Unit.
a) Material
Thermostat switch for 1.0 / 1.5 / 2.0 each 1
Ton A.C.Unit.

219
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

b) Labour charges for removing old


one & fixing
Semi skilled Electrician day 0.2
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
9.2.7 Replacement of Unserviceable starting
capacitor of 80 to 120 mfd. By new
approved make capacitor suitable for
compressor motor of 1.0 / 1.5 Ton A.C.
Unit.
a) Material
Starting capacitor of 80 to 120 mfd. each 1
b) Labour charges for removing old
one & fixing
Semi skilled Electrician day 0.2
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
9.2.8 Replacement of unserviceable running
capacitor of 36 mfd by new approved
make capacitor suitable for
compressor motor of 1.0 / 1.5 Ton
A.C.Unit.
a) Material
Running capacitor 36 mfd each 1
b) Labour charges for removing old
one & fixing
Semi skilled Electrician day 0.2
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
9.2.9 Replacement of Unserviceable relay by
new approved make having pickup
voltage 220 Volts and dropout voltage
120 Volts suitable for 1.0 / 1.50 Ton
A.C. Unit.
a) Material
Relay having pickup 220V and dropout each 1
voltage 120V
b) Labour charges for removing old
one & fixing
Semi skilled Electrician day 0.2
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
9.2.10 Replacement of Unserviceable filter
and capillary tube by supply and
installation of new filter and capillary
tube including welding et., complete
for 1.0 / 1.5 / 2.0 Ton A.C.Unit.
a) Material

220
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Filter and capillary tube for 1.0 / each 1


1.5/2.0 Ton A.C.Unit
b) Labour charges for removing old
one & fixing
Semi skilled Electrician day 0.2
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
9.2.11 Replacement of Unserviceable air filter
by new air filter suitable for 1.50 Ton
A.C.Unit P.V.C. / NYLON for Window
A.C.
a) Material
PVC / Nylon Air Filter for Window type each 1
A.C.Unit.
b) Labour charges for removing old
one & fixing
Semi skilled Electrician day 0.2
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
9.2.11(a) Replacement of Unserviceable air filter
by new air filter suitable for 1.50 Ton
A.C.Unit P.V.C. / NYLON for Split A.C.
a) Material
PVC / Nylon Air Filter for Split type each 1
A.C.Unit.
b) Labour charges for removing old
one & fixing
Semi skilled Electrician day 0.2
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Bldngs_Elec- 9.3 Refrigerators
9-3
9.3.1 Supply Refrigerator domestic type
approved make 165 to 310 Ltrs.
Storage capacity, suitable for operation
on 230 /250 Volts 50 Hz.. complete
with automatic temparture control
confirming to IS specifications No.
1476 / 79 with one year guarantee for
seale unit in refrigeration system
including cost and conveyance of all
materials and labour charges etc.,
complete.
a) Material
----- capacity refrigerator cost each 1
Transportation @ 2% of Unit Cost 2%
Loading, Unloading & Instalation @ 2% 2%
of Unit Cost
Rate per Each
Bldngs_Elec- 9.6 Stabilizers
9-4

221
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

9.6.1 Supply and erecting fully automatic


line voltage stabilizer for operation on
input voltage 200 to 250V. rated for
0.5 KVA maximum load and time delay
model with Volt meter, selector
switch, 6A / 16A flush type, 5 pin
socket for out put and with 3 core
flexible chord and 3 pin 6/16A plug top
suitable for refrigerator for continuous
operation including cost and
conveyance of all mateials and all
labour charges etc., complete.
a) Material
0.5 KVA Stabilizer each 1
b) Labour Charges
Semi skilled Electrician day 0.044
Helper day 0.044
Transportation Charges on Unit Cost 2%
Rate per Each
Note : Labour is Considered for 23
jobs / day
9.6.2 Supply and erecting fully automatic
line voltage stabilizer for operation on
input voltage 200 to 250V. rated for 1
KVA maximum load and time delay
model with Volt meter, selector
switch, 6A / 16A flush type, 5 pin
socket for out put and with 3 core
flexible chord and 3 pin 6/16A plug top
suitable for refrigerator for continuous
operation including cost and
conveyance of all mateials and all
labour charges etc., complete.
a) Material
1 KVA Stabilizer each 1
b) Labour Charges
Semi skilled Electrician day 0.044
Helper day 0.044
Transportation Charges on Unit Cost 2%
Rate per Each
Note : Labour is Considered for 23
jobs / day
9.6.3 Supply and erecting fully automatic
line voltage stabilizer for operation on
input voltage 200 to 250V. rated for 3
KVA / 4 KVA / 5 KVA maximum load
and time delay model with Volt meter,
selector switch, 6A / 16A flush type, 5
pin socket for out put and with 3 core
flexible chord and 3 pin 6/16A plug top
suitable for refrigerator for continuous
operation including cost and
conveyance of all mateials and all
labour charges etc., complete.

222
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

a) Material
3 KVA / 4 KVA / 5 KVA Stabilizer each 1
b) Labour Charges
Skilled Electrician day 0.1
Helper day 0.1
Transportation Charges on Unit Cost 2%
Rate per Each
Note : Labour is Considered for 10
jobs / day
Bldngs_Elec- 9.7 Fans
9-5
9.7.2 Supply of 900 mm (36") / 1200 mm
(48") / 1400 mm (56") sweep 230V, A.C
50 Hz.Ceiling fan with 3 Blades and
double ball bearings with all standard
accessories.
a) Material
900 mm (36") / 1200 mm (48") / 1400 each 1
mm (56") Ceiling Fan
Transportation Charges on Unit Cost 1%
Rate per Each
9.7.7 Supply and erecting wall mounting fan
400mm (16") / 450 mm (18") sweep
A.C. 50Hz.. 1350 r.p.m oscillating type
with regulator.
a) Material
400mm (16") / 450 mm (18") wall each 1
mounting Fan
b) Labour Charges
Semi Skilled Electrician day 0.1
Helper day 0.1
Rate per Each
Note : Labour is Considered for 10
jobs / day
9.7.10 Supply of pedastal fan (16") 400mm,
250 Volts, 50Hz. oscillating type
complete with all standard accessories.
a) Material
400mm (16") Pedastal Fan each 1
Transportation Charges on Unit Cost 2%
Rate per Each
9.7.16 EXHAUST FANS
Supply of fresh air exhaust fan of light
duty 250V A.C.50Hz.. 225 mm (9") /
300mm size (12") 1350 R.P.M Metallic
body plastic blades, wire mesh, etc.,
complete.
a) Material
225 mm (9") / 300mm (12") L.D. each 1
Exhaust Fan
Transportation Charges on Unit Cost 1%
Rate per Each

223
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

9.7.18 Supply of fresh air exhaust fan of


Heavy duty 250V A.C.50Hz.. 300mm
size (12") / 375 mm (15") 900 R.P.M
etc., complete.
a) Material
300mm (12") / 375 mm (15") H.D. each 1
Exhaust Fan
Transportation Charges on Unit Cost 1%
Rate per Each
9.7.24 Supply and erecting fan hook of
12/15mm dia M.S. rod / bar grouted in
RCC slab with making the slab as
original.
a) Material
12/15mm plain M.S rod for Fan hook each 1
Cement, Sand and Rounding off LS
b) Labour charges for grouting in RCC
slab, Fixing of Fan hook with
masonary work.
Mason day 0.166
Helper day 0.166
Rate per Each
Note : Labour is Considered for 6 jobs
/ day
9.7.25 Supply and erecting 19/20mm steel
tube down rod of one meter length
with bolts & nuts duly painted with
matching colour of fan complete
a) Material
19/20mm steel tube down rod with M 1
bolts & nuts for fan with maching
colour.
b) Labour charges for Fixing
Helper day 0.1
Rate per Each
Note : Labour is Considered for 10
jobs / day
9.7.26 Supply and erecting resistance type
regulator for ceiling fans
900/1200/1400mm sweep complete
erected on existing board.
a) Material
Resistance type Regulator M 1
b) Labour charges.
Semi skilled Electrician day 0.1
Rate per Each
Note : Labour is Considered for 10
jobs / day
9.7.33 Cleaning of Ceiling fan in existing
position .
Labour charges for cleaning greasing /
oilingoverhauling
Helper day 0.2

224
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Rate per Each


Note : Labour is Considered for 10 jobs / day by 2
helpers
9.7.34 Removing the ceiling fan and refixing
after overhauling and greasing the
bearings and replacement of wire
leads etc complete
a) Material
23/0060 twin core wire M 1
b) Labour charges.
Removing and refixing of ceiling fan
after overhauling
Semi skilled Electrician day 0.166
Helper day 0.166
sundries LS
Rate per Each
Note : Labour is Considered for 6 jobs
/ day
9.7.35 Labour Charges
Labour charges for Fixing of Ceiling fan
and regulator including transportation
and giving connections with twin core
wire etc., complete.
a) Material
23/0060 Twin Core wire M 1
Unforseen item works, such as painting LS
to down rod, screws etc.,
b) Labour charges.
Skilled Electrician day 0.125
Helper day 0.125
Rate per Each
Note : Labour is Considered for 8 fans
/ day
9.7.36 Labour charges for fixing of Exhaust fan
in wall with necessary connections and
masonary work of making hole,
finishing etc., complete
a) Material
23/0060 Twin flat wire M 1
Cement kg 25
b) Labour charges.
Skilled Electrician day 0.25
Helper day 0.25
Mason day 0.25
Sundries such as Sand, Bolt, Nuts etc., LS
Rate per Each
Note :1. Labour is Considered for 6
jobs / day
2. Cost of louver shutter may be added
if required.
3. If hole is already made available,
labour charges of Mason shall be
deleted.

225
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Bldngs_Elec- 10 WATER HEATERS


10
10.1.2 Supply and Transportation of stove
enamelled storage / pressure type
vertical / Horizontal water heater with
copper tank 25 / 35 / 50 Ltrs. Capacity
with non return valve on inlet side and
dead weight pressure reducing valve
Bldngs_Elec- on outlet side 230/ 250V, single phase
10-1 2000 watts heating element,
thermostat control, fusible plug, pilot
lamp etc., erected and tested complete
with ISI specifications etc., including all
materials, transportation, and labour
charges complete.
a) Material
25 / 35 / 50 Ltrs. Water Heater each 1
Transportation Charges on Unit Cost 2%
Rate per Each
10.1.5 Labour charges for erection of storage
water heater with 2Nos Nylon / PVC /
Metalic hose pipe etc., on wall duly
making necessary fixing arrangments
including connections etc., complete.
a) Material
Flexible Nylon / PVC / Metallic hose each 2
pipe
50 / 100 mm (2" / 4") long bolt and nut each 4
with washers
Towards wooden plugs, cement etc., LS
b) Labour charges.
Skilled Electrician day 0.25
Helper day 0.5
Semi skilled Mason day 0.25
Rate per Each
Note : Labour is Considered for 4 jobs
/ day
Bldngs_Elec- 10.2 INSTANT WATER HEATERS
10-2
10.2.1 Supply and erecting ISI Mark 3KW
Instant Water heater with multiple
safety system, rust free ABS plastic
body, 230V, 50Hz.., A.C. supply with
inlet and outlet connections with pvc/
nylon / metallic hose pipe, thermostat
control and thermal cutoff with 3 core
P.V.C. flexible wire leads duly tested
including cost of all materials and all
labour charges etc., complete.
a) Material
3KW Instant Water Heater each 1
Transportation Charges on Unit Cost 2%
Hose pipe PVC/ Nylon each 2

226
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

T.W getting Bolt / Nuts, Cement, Sand LS


etc.
b) Labour charges.
Skilled Electrician day 0.25
Helper day 0.25
Rate per Each
Note : Labour is Considered for 4 jobs
/ day
Bldngs_Elec- 10.4 REPAIRS TO WATER HEATERS.
10-3
10.4.1 Replacement of unserviceable heating
element by new one for 1.5 / 2.0 / 3.0
Kw water heater
a) Material
2/3 KW heating Element each 1
b) Labour charges.
Skilled Electrician day 0.2
Sundries and rounding off LS
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
10.4.2 Replacement of Unserviceable
thermostat by new thermostat with
range 30 to 90 C. adjustable and
suitable for 25 to 50 Ltrs. Capacity.
a) Material
Thermostat range 30-90 Degree each 1
suitable for 25 to 50 Ltrs.
b) Labour charges.
Skilled Electrician day 0.2
Sundries and rounding off LS
Rate per Each
10.4.5 Replacing unserviceable pressure
release valve by new water heater of
15 to 50 Ltrs.capacity.
a) Material
Pressure release valve for 25 to 50 Ltrs each 1
water heater
b) Labour charges.
Skilled Electrician day 0.2
Sundries and rounding off LS
Rate per Each
Bldngs_Elec- 11 WATER PUMPS
11
Bldngs_Elec- 11.1 Mono-Block Pumps
11-1

227
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.1.1 Supply and erecting approved make


centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 230V,
Single phase, 50Hz.. 1440 RPM
A.C.Supply of 0.5HP exculding suction /
delivery pipe with nuts duly grouted on
existing C.C foundation and bolts,
spring washers of requisite size for
monoblock motor and pump (IS :
9079).
a) Material
0.5HP, 230V, single phase A.C 50Hz. each 1
1440 RPM with all accessories.
Including all taxes
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 0.5
Helper day 1
Plumber day 0.5
Sundries and rounding off LS
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
11.1.2 Supply and erecting approved make
centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 230V,
Single phase, 50Hz.. 1440 RPM
A.C.Supply of 1HP exculding suction /
delivery pipe with nuts duly grouted on
existing C.C foundation and bolts,
spring washers of requisite size for
monoblock motor and pump (IS :
9079).
a) Material
1 HP, 230V, single phase A.C 50Hz. each 1
1440 RPM with all accessories.
Including all taxes
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 0.5
Helper day 1

228
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Plumber day 0.5


Sundries and rounding off LS
Rate per Each
11.1.3 Supply and erecting approved make
centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 230V,
Single phase, 50Hz.. 1440 RPM
A.C.Supply of 1.5 HP exculding suction
/ delivery pipe with nuts duly grouted
on existing C.C foundation and bolts,
spring washers of requisite size for
monoblock motor and pump (IS :
9079).
a) Material
1.5 HP, 230V, single phase A.C 50Hz. each 1
1440 RPM with all accessories.
Including all taxes
Transportation Charges on Unit Cost 2%
b) Labour charges.
Skilled Fitter day 0.5
Helper day 1
Plumber day 0.5
Sundries and rounding off LS
Rate per Each
11.1.4 Supply and erecting approved make
centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 230V,
Single phase, 50Hz.. 1440 RPM
A.C.Supply of 2.0 HP exculding suction
/ delivery pipe with nuts duly grouted
on existing C.C foundation and bolts,
spring washers of requisite size for
monoblock motor and pump (IS :
9079).
a) Material
2 HP, 230V, single phase A.C 50Hz. each 1
1440 RPM with all accessories.
Including all taxes
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 0.5
Helper day 1
Plumber day 0.5

229
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Sundries and rounding off LS


Rate per Each
11.1.5 Supply and erecting approved make
centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 415V, 3
phase, 50Hz.. 2880 RPM A.C.Supply of
3.0HP exculding suction / delivery pipe
with nuts duly grouted on existing C.C
foundation and bolts, spring washers
of requisite size for monoblock motor
and pump (IS : 9079).
a) Material
3 phase, 3 HP, 415V, 50Hz., 2880 RPM each 1
centrifugal Water pump with all taxes
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 1
Plumber day 1
Sundries and rounding off LS
Rate per Each
11.1.6 Supply and erecting approved make
centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 415V, 3
phase, 50Hz.. 2880 RPM A.C.Supply of
5HP exculding suction / delivery pipe
with nuts duly grouted on existing C.C
foundation and bolts, spring washers
of requisite size for monoblock motor
and pump (IS : 9079).
a) Material
3 phase, 5 HP, 415V, 50Hz., 2880 RPM each 1
centrifugal Water pump with all taxes
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 1
Plumber day 1
Sundries and rounding off LS
Rate per Each

230
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.1.7 Supply and erecting approved make


centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 415V, 3
phase, 50Hz.. 2880 RPM A.C.Supply of
7.5HP exculding suction / delivery pipe
with nuts duly grouted on existing C.C
foundation and bolts, spring washers
of requisite size for monoblock motor
and pump (IS : 9079).
a) Material
3 phase, 7.5 HP, 415V, 50Hz., 2880 each 1
RPM centrifugal mono block pump
with all taxes
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 1
Plumber day 1
Sundries and rounding off LS
Rate per Each
11.1.8 Supply and erecting approved make
centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 415V, 3
phase, 50Hz.. 2880 RPM A.C.Supply of
10HP exculding suction / delivery pipe
with nuts duly grouted on existing C.C
foundation and bolts, spring washers
of requisite size for monoblock motor
and pump (IS : 9079).
a) Material
3 phase, 10 HP, 415V, 50Hz., 2880 RPM each 1
centrifugal mono block pump with all
taxes
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 1
Plumber day 1
Sundries and rounding off LS
Rate per Each

231
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.1.9 Supply and erecting approved make


centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 415V, 3
phase, 50Hz.. 2880 RPM A.C.Supply of
15HP exculding suction / delivery pipe
with nuts duly grouted on existing C.C
foundation and bolts, spring washers
of requisite size for monoblock motor
and pump (IS : 9079).
a) Material
3 phase, 15 HP, 415V, 50Hz., 2880 RPM each 1
centrifugal Water pump with all taxes
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 3
Plumber day 1
Sundries and rounding off LS
Rate per Each
Bldngs_Elec- 11.2 EJECTO PUMPS
11-2
11.2.1 Supply and erecting Ejecto type water
pump single phase, 0.5HP single stage
with brass venturi and having suction
pipe 40mm dia, pressure pipe 32mm
dia and delivery pipe 32mm dia, with
maximum discharge head of 80 feet
including transportation of all
materials and labour charges etc.,
complete.
a) Material
0.5 HP, single phase, 230V, 50Hz. each 1
Ejecto type pump set. Including all
taxes
M.S clamps suitable for 40mmx32mm each 2
pipes with nuts and bolts.
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Electrician day 0.5
Helper day 1
Fitter day 0.5
Sundries and rouding off LS
Rate per Each
Note : Labour is Considered for 2 jobs
/ day

232
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.2.2 Supply and erecting Ejecto type water


pump single phase, 1.0HP single stage
with brass venturi and having suction
pipe 40mm dia, pressure pipe 32mm
dia and delivery pipe 32mm dia, with
maximum discharge head of 80feet
including transportation of all
materials and labour charges etc.,
complete.
a) Material
1.0 HP, single phase, 230V, 50Hz. each 1
Ejecto type pump set. Including all
taxes
M.S clamps suitable for 40mmx32mm each 2
pipes with nuts and bolts.
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Electrician day 0.5
Helper day 1
Fitter day 0.5
Sundries and rouding off LS
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
11.2.3 Supply and erecting Ejecto type water
pump single phase, 1.5HP single stage
with brass venturi and having suction
pipe 40mm dia, pressure pipe 32mm
dia and delivery pipe 32mm dia, with
maximum discharge head of 80 feet
including transportation of all
materials and labour charges etc.,
complete.
a) Material
1.5 HP, single phase, 230V, 50Hz. each 1
Ejecto type pump set. Including all
taxes
M.S clamps suitable for 40mmx32mm each 2
pipes with nuts and bolts.
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Electrician day 0.5
Helper day 1
Fitter day 0.5
Sundries and rouding off LS
Rate per Each
Note : Labour is Considered for 2 jobs
/ day

233
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.2.4 Supply and erecting Ejecto type water


pump single phase, 2.0HP single stage
with brass venturi and having suction
pipe 40mm dia, pressure pipe 32mm
dia and delivery pipe 32mm dia, with
maximum discharge head of 80 feet
including transportation of all
materials and labour charges etc.,
complete.
a) Material
2.0 HP, single phase, 230V, 50Hz. each 1
Ejecto type pump set. Including all
taxes
M.S clamps suitable for 40mmx32mm each 2
pipes with nuts and bolts.
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Electrician day 0.5
Helper day 1
Fitter day 0.5
Sundries and rouding off LS
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
11.2.6 Supply and erecting Ejecto type water
pump 3 phase, 3 HP single stage with
brass venturi and having suction pipe,
pressure pipe and delivery pipe, with
maximum discharge head of 80 feet ,
including transportation, and all
materials all labour charges etc.,
complete.
a) Material
3.0 HP, single phase, 230V, 50Hz. each 1
Ejecto type pump set. Including all
taxes
M.S clamps suitable for 40mmx32mm each 2
pipes with nuts and bolts.
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Electrician day 0.5
Helper day 1
Fitter day 0.5
Sundries and rouding off LS
Rate per Each
Note : Labour is Considered for 2 jobs
/ day

234
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.2.7 Supply and erecting Ejecto type water


pump 3 phase, 5 HP single stage with
brass venturi and having suction pipe,
pressure pipe and delivery pipe, with
maximum discharge head of 80',
including transportation, and all
materials all labour charges etc.,
complete.
a) Material
3Ph, 5 HP 415V, 50Hz. Ejecto pump set each 1
with all taxes
M.S clamps suitable for Air and each 2
delivery pipes with nuts and bolts.
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 0.5
Helper day 1.5
Plumber day 0.5
Sundries and rouding off LS
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Bldngs_Elec- 11.3 SUBMERSIBLE PUMPS (Bore well type)
11-3
11.3.1 Supply and erecting, ISI mark
(a) submersible 1.0 HP,Single Phase
18stages pumpset suitable for 106 /
156mm dia borewell with high quality
water resistant and dynamically
balanced bronze impeller with
stainless steel shaft sleeves, pump
coupling and pivot of Single phase
250V, 50Hz.. A.C. power supply copper
winding with water proof insulation
and high precision strength not to be
effected by chemical in water and
suitable bronze bearings with nut and
bolts etc., with necessary H-type
clamp of suitable size and strength.
a) Material
1HP, Single Phase 18 stage each 1
submerisible pump set including all
taxes
Special M.S. clamps with bolts and nuts each 2
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 0.5
Helper day 1
Plumber day 0.5
Sundries and rouding off LS

235
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Rate per Each


Note : Labour is Considered for 2 jobs
/ day
11.3.1 Supply and erecting, ISI mark
(b) submersible 1.5 HP, Single Phase 20
stages pumpset suitable for 106 /
156mm dia borewell with high quality
water resistant and dynamically
balanced bronze impeller with
stainless steel shaft sleeves, pump
coupling and pivot of Single phase
250V , 50Hz.. A.C. power supply copper
winding with water proof insulation
and high precision strength not to be
effected by chemical in water and
suitable bronze bearings with nut and
bolts etc., with necessary H-type
clamp of suitable size and strength.
a) Material
1.5HP, Single Phase 20 stage each 1
submerisible pump set including all
taxes
Special M.S. clamps with bolts and nuts each 2
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 0.5
Helper day 1
Plumber day 0.5
Sundries and rouding off LS
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
11.3.1 (c) Supply and erecting, ISI mark
submersible 2.0 HP, Single Phase 30
stages pumpset suitable for 106 /
156mm dia borewell with high quality
water resistant and dynamically
balanced bronze impeller with
stainless steel shaft sleeves, pump
coupling and pivot of Single phase
250V , 50Hz.. A.C. power supply copper
winding with water proof insulation
and high precision strength not to be
effected by chemical in water and
suitable bronze bearings with nut and
bolts etc., with necessary H-type
clamp of suitable size and strength.
a) Material
2HP, Single Phase 30 stage each 1
submerisible pump set including all
taxes
Special M.S. clamps with bolts and nuts each 2
Transportation Charges on Unit Cost 2%

236
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

b) Labour charges for erection of


pump set including pipe connection
for suction & delivery
Skilled Fitter day 0.5
Helper day 1
Plumber day 0.5
Sundries and rouding off LS
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
11.3.2 Supply and erecting, ISI mark
submersible 2.0 HP, 3 Phase, 3 stages
pumpset suitable for 156mm dia
borewell with high quality water
resistant and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V , 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
2HP, 3 Ph 3 stage submerisible pump each 1
set including all taxes
Special M.S. clamps with bolts and nuts each 2
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 2
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.3 Supply and erecting, ISI mark
submersible 3.0 HP,3 Phase, 4 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V , 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.

237
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

a) Material
3HP, 3 Ph 4 stage submerisible pump each 1
set. Including all taxes
Special M.S. clamps with bolts and nuts each 2
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 2
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.4 Supply and erecting, ISI mark
submersible 3 HP, 3 Phase, 6 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V , 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
3HP, 3 Ph 6 stage submerisible pump each 1
set. Including all taxes
Special M.S. clamps with bolts and nuts each 2
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 2
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each

238
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.3.5 Supply and erecting, ISI mark


submersible 3 HP, 3 Phase, 8 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V , 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
3HP, 3 Ph 6 stage submerisible pump each 1
set. Including all taxes
Special M.S. clamps with bolts and nuts each 2
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 2
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.6 Supply and erecting, ISI mark
submersible 3 HP, 3 Phase, 9 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V , 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
3HP, 3 Ph 6 stage submerisible pump each 1
set Including all taxes
Special M.S. clamps with bolts and nuts each 2
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 2

239
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.7 Supply and erecting, ISI mark
submersible 4 HP, 3 Phase, 6 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V, 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
4HP, 3 Ph 6 stage submerisible pump each 1
set including all taxes
Special M.S. clamps with bolts and nuts each 2
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 2
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.8 Supply and erecting, ISI mark
submersible 4 HP, 3 Phase, 12 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V, 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
4HP, 3 Ph 12 stages submerisible pump each 1
set Including all taxes
Special M.S. clamps with bolts and nuts each 2
Transportation Charges on Unit Cost 2%

240
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

b) Labour charges for erection of


pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 2
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.10 Supply and erecting, ISI mark
submersible 5 HP, 3 Phase, 8 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V, 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
Cost of 3 Ph, 5 HP, 8 St. S.M pumpset each 1
Special Clamps with Bolts & Nuts each 2
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 2
Helper day 3
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.11 Supply and erecting, ISI mark
submersible 5 HP, 3 Phase, 13 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V , 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material

241
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Cost of 3 Ph, 5 HP, 8 St. S.M pumpset each 1


Special Clamps with Bolts & Nuts each 2
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 2
Helper day 3
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.12 Supply and erecting, ISI mark
submersible 7.5 HP,3 Phase, 6 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V, 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
3 Ph, 7.5 HP, 6 St. S.M pumpset each 1
Special Clamps with Bolts & Nuts each 2
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 2
Helper day 3
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each

242
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.3.13 Supply and erecting, ISI mark


submersible 7.5 HP, 3 Phase, 12 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V , 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
3 Ph, 7.5 HP, 12 St. S.M pumpset each 1
Special Clamps with Bolts & Nuts each 2
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 2
Helper day 3
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.15 Supply and erecting, ISI mark
submersible 10 HP,3 Phase, 12 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V, 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
Cost of 3 Ph,10 H.P 12St. S.M pumpset each 1
Special Clamps with Bolts & Nuts each 2
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 2
Helper day 3
Plumber day 1

243
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Hire charges of tripod with winch 50%


of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.16 Supply and erecting, ISI mark
submersible 10 HP,3 Phase,16 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V, 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
Cost of 3 Ph,10 H.P 16 St. S.M pumpset each 1
Special Clamps with Bolts & Nuts each 2
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 2
Helper day 3
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.17 Supply and erecting, ISI mark
submersible 15 HP, 3 Phase, 15 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V, 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
Cost of 3 Ph,15 H.P 15 St. S.M pumpset each 1
Special Clamps with Bolts & Nuts each 2
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery

244
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Skilled Fitter day 2


Helper day 4
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each
Bldngs_Elec- 11.4 SUB MERSIBLE PUMPS (OPEN WELL)
11-4
11.4.1 Supply and erecting ISI make
submersible pumpset suitable for
erection in open well with water
resistant dynamically balanced
impeller with stainless steel shaft
sleeves, pump coupling and pivot with
squirrel cage Induction Motor of 3
phase, 415V, 50Hz.., A.C.Supply, heavy
copper windings with water proof
insulation and high precision strength
not to be effected by chemicals in
water with suitable bronze bearings, 3
HP pump erected with necessary H-
type clamps of suitable size and
strength including cost of all materials,
Transportation and labour charges
etc., complete.
a) Material
3 Ph, 3HP Submersible motor each 1
Special clamps with nut and bolis each 2
MS Girders across the open well to
support delivery pipe clamps (as per
requirement)
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 2
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each

245
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.4.2 Supply and erecting ISI make


submersible pumpset suitable for
erection in open well with water
resistant dynamically balanced
impeller with stainless steel shaft
sleeves, pump coupling and pivot with
squirrel cage Induction Motor of 3
phase, 415V, 50Hz.., A.C.Supply, heavy
copper windings with water proof
insulation and high precision strength
not to be effected by chemicals in
water with suitable bronze bearings, 5
HP pump erected with necessary H-
type clamps of suitable size and
strength including cost of all materials,
Transportation and labour charges
etc., complete.
a) Material
3 Ph, 5HP Submersible motor each 1
Special clamps with nut and bolis each 2
MS Girders across the open well to
support delivery pipe clamps (as per
requirement)
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 2
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each
11.4.3 Supply and erecting ISI make
submersible pumpset suitable for
erection in open well with water
resistant dynamically balanced
impeller with stainless steel shaft
sleeves, pump coupling and pivot with
squirrel cage Induction Motor of 3
phase, 415V, 50Hz.., A.C.Supply, heavy
copper windings with water proof
insulation and high precision strength
not to be effected by chemicals in
water with suitable bronze bearings,
7.5 HP pump erected with necessary
H-type clamps of suitable size and
strength including cost of all materials,
Transportation and labour charges
etc., complete.
a) Material
3 Ph, 7.5HP Submersible motor each 1
Special clamps with nut and bolis each 2

246
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

MS Girders across the open well to


support delivery pipe clamps (as per
requirement)
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 2
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each
11.4.4 Supply and erecting ISI make
submersible pumpset suitable for
erection in open well with water
resistant dynamically balanced
impeller with stainless steel shaft
sleeves, pump coupling and pivot with
squirrel cage Induction Motor of 3
phase, 415V, 50Hz.., A.C.Supply, heavy
copper windings with water proof
insulation and high precision strength
not to be effected by chemicals in
water with suitable bronze bearings,
10 HP pump erected with necessary H-
type clamps of suitable size and
strength including cost of all materials,
Transportation and labour charges
etc., complete.
a) Material
3 Ph, 10 HP Submersible motor each 1
Special clamps with nut and bolis each 2
MS Girders across the open well to
support delivery pipe clamps (as per
requirement)
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 3
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each
Note:- Above rates of pumpsets are exculding
suction & delivery pipes
Bldngs_Elec- 11.5 ACCESSORIES
11-5

247
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.5.1 Providing cement concrete with 1:2:4


foundation for pump and motor with
required size and length of foundation
bolts and nuts including cost and
conveyance of all materials and labour
charges etc., complete.
a) Material
Rate as per Civil SSR, since it is a Civil
item.
11.5.2 Supplying and erecting D.O.L Starter
250V, Single phase, 50Hz. With SS
enclouser comprising of contactor
with bi-metalic relay with necessary
push buttons, transportation and all
labour charges etc., complete .
a) Material
D.O.L. Starter 1Ph, 250V each 1
b) Labour charges for fixing and giving
connections.
Skilled Electrician day 0.33
Helper day 0.33
Sunries such, as bolts, nuts and
rounding off
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
11.5.2(a) Supplying and erecting D.O.L Starter
400V, 3 phase, 50Hz. enclosed with no
volt coil and overload protection with
necessary materials, transportation
and all labour charges etc., complete
suitable upto 3/4/5 HP.
a) Material
D.O.L. Starter 3Ph, 415V upto 3/4/5HP each 1
b) Labour charges for fixing and giving
connections.
Skilled Electrician day 0.33
Helper day 0.33
Sunries such, as bolts, nuts and
rounding off
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
11.5.3 Supply and fixing of approved make
semi automatic hand operated 3ph,
415V star - delta started suitable from
7.5 HP upto 15 HP motor totally
enclosed with over load protection and
No-volt relay etc., to complete
including Transportation and all labour
charges.
a) Material

248
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Semi automatic 3Ph, Induction motor each 1


with enclosure (Including of all taxes
with Transportation)
b) Labour charges for fixing and giving
connections.
Skilled Electrician day 0.5
Helper day 0.5
Sunries such, as bolts, nuts and
rounding off
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
11.5.4 Supply and fixing of approved make
semi automatic hand operated 3ph,
415V star - delta started suitable upto
15 to 25 HP motor totally enclosed
with over load protection and No-volt
relay etc., to complete including
Transportation and all labour charges.
a) Material
Deduct
Cost of semi Automatic star - Delta each 1
starter
Semi automatic 3Ph, Induction motor each 1
with enclosure (Including of all taxes
with Transportation)
b) Labour charges.
Skilled Electrician day 0.5
Helper day 0.5
Sunries such, as bolts, nuts and
rounding off
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
11.5.5 Supply and fixing of approved make
automatic operated 3ph, 415V star -
delta started suitable 10 to 12.5 HP
automatic star delta starter motor
totally enclosed with over load
protection and No-volt relay to
complete including Transportation and
all labour charges .
a) Material
Cost of semi Automatic star - Delta each 1
starter
Semi automatic 3Ph, Induction motor each 1
with enclosure (Including of all taxes
with Transportation)
b) Labour charges.
Skilled Electrician day 0.5
Helper day 0.5
Sunries such, as bolts, nuts and
rounding off
Rate per Each

249
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Note : Labour is Considered for 2 jobs


/ day
11.5.6 Supply and fixing of approved make
semi automatic hand operated 3ph,
415V star - delta started suitable for 15
HP fully automatic star delta motor
totally enclosed with over load
protection and No-volt relay to
complete including Transportation and
all labour charges.
a) Material
Cost of semi Automatic star - Delta each 1
starter
Semi automatic 3Ph, Induction motor each 1
with enclosure (Including of all taxes
with Transportation)
b) Labour charges.
Skilled Electrician day 0.5
Helper day 0.5
Sunries such, as bolts, nuts and
rounding off
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
11.5.7 Supply and erecting directly operated
single phasing preventer connected to
A.C. supply upto 45A range with
guarantee to operate on single phase
for one Year.
a) Material
Single phase parameter upto 45A each 1
(Including all taxes and Transportation)
b) Labour charges.
Skilled Electrician day 0.2
Helper day 0.2
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Bldngs_Elec- 12 Bus Bars
12
For details, Please see after Chapter
20.
Bldngs_Elec- 13 SWAGED POLES (Confirming to IS
13 2713 / 1980).
13.1 Fabrication, supply and transportation
of swaged poles up to site confirming
to IS 2713 / 1980 specifications. The
Bldngs_Elec- pole should be painted with primary
13-1 coat of red oxide and black bituminous
paint up to ground level with base
plate, including cost of all materials
etc., complete.
a) Material
Cost of swaged pole

250
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Add: Labour for handling


Transportation charges, loading
unloading as per Common SSR taking
250Km as average load considering
fabrication point at hyd and
Visakhapatnam.
Transportation charges upto 250Km
Breakup.
P.No. 156 of Common SSR (Civil)
Upto 20 Km
163.80 / Tonne
Upto 50 Km 3.40 x 10
Upto 80 Km 2.80 x 50
Beyond 106 Km 2.20 x 156
Loading 15.50 /
Tonne
Unloading 12.00 /
Tonne
Stacking 7.00 /
Tonne
Rate per Kg

D A T A F O R M . S S W A G E D P O L E S C O N F I R M I N G TO I.S : 2713 /1980

Data Specification of pole Overall Length of Sections


Planting
No. length of pole. In Mtrs.
depth in
as per IS 2713 / 1980 Botto Mid
mtrs. Top
m dle
1 2
4 5a 5b 5c
3
13.1.1 410 SP.2 7 Mtrs. 1.25 4.00 1.50 1.50
13.1.2 410 SP.3 7 Mtrs. 1.25 4.00 1.50 1.50
13.1.3 410 SP.5 7.5 Mtrs. 1.25 4.50 1.50 1.50
13.1.4 410 SP.6 7.5 Mtrs. 1.25 4.50 1.50 1.50
13.1.5 410 SP.11 8 Mtrs. 1.50 4.50 1.75 1.75
13.1.6 410 SP.12 8 Mtrs. 1.50 4.50 1.75 1.75
13.1.7 410 SP.26 9 Mtrs. 1.50 5.00 2.00 2.00
13.1.8 410 SP.27 9 Mtrs. 1.50 5.00 2.00 2.00
13.1.9 410 SP.41 10 Mtrs. 1.80 5.20 2.40 2.40
13.1.10 410 SP.42 10 Mtrs. 1.80 5.20 2.40 2.40
13.1.11 410 SP.50 11 Mtrs. 1.80 5.60 2.70 2.70
13.1.12 410 SP.51 11 Mtrs. 1.80 5.60 2.70 2.70
13.1.13 410 SP.59 12 Mtrs. 2.00 5.80 3.10 3.10
13.1.14 410 SP.60 12 Mtrs. 2.00 5.80 3.10 3.10
13.1.15 410 SP.73 14.5 Mtrs. 2.00 6.50 4.00 4.00
13.1.16 410 SP.74 14.5 Mtrs. 2.00 6.50 4.00 4.00
13.1.17 410 SP.77 16 Mtrs. 2.30 7.00 4.50 4.50
13.1.18 410 SP.78 16 Mtrs. 2.30 7.00 4.50 4.50
O.D and thickness Weight of Weight of Total Rate Total
Pole in Kgs Base plate weigh / Kg cost
of sections in Kgs. t in inclu of
Bottom Kgs. ding pole
Middle Tran

251
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Top spor
tatio
n
and
Fabr
icati
on
6a 6b 6c 7 8 9 10 11
114.3x4.5 88.9x4.05 76.1x3.25 73 5 78
114.3x5.4 88.9x4.85 76.1x3.25 85 5 90
114.3x4.5 88.9x4.05 76.1x3.25 79 5 84
114.3x5.4 88.9x4.85 76.1x3.25 93 5 98
114.3x4.5 88.9x4.05 76.1x3.25 83 5 88
114.3x5.4 88.9x4.85 76.1x3.25 97 5 102
114.3x45 88.9x4.05 76.1x3.25 92 5 97
114.3x5.4 88.9x4.85 76.1x3.25 108 5 113
139.7x4.85 114.3x4.5 88.9x3.25 135 5 140
139.7x5.4 114.3x4.5 88.9x3.25 144 5 149
139.7x4.85 114.3x4.5 88.9x3.25 147 5 152
139.7x5.4 114.3x4.5 88.9x3.25 164 5 169
165.1x4.85 139.7x4.5 114.3x3.65 197 5 202
165.1x5.4 139.7x4.5 114.3x3.65 208 5 213
193.7x5.4 165.1x4.85 139.7x4.50 312 10 322
193.7x5.9 165.1x5.4 139.7x4.50 336 10 346
193.7x5.4 165.1x4.85 139.7x4.50 341 10 351
193.7x5.9 165.1x5.4 139.7x4.50 367 10 377

Bldngs_Elec- 13.2 Garden Posts


13-2
13.2.1 Fabrication and Supply of M.S. Poles
for garden posts with 'B' class 4mtrs
long 60.25mm outer dia with base
plate and suitable pole cap including
cost and conveyance of all material
including fixing of luminaire and labour
charges etc., complete.
a) Material
4Mtrs 'B' Class M.S. pipe of 60.25mm Kg 24.8
dia with base plate and suitable pole
cap
Rate per Each
13.2.2 Fabrication and Supply of M.S. Poles
for garden posts with 'B' class 6 mtrs
long 60.25mm outer dia with base
plate and suitable pole cap including
cost and conveyance of all material
including fixing of luminaire and labour
charges etc., complete.
a) Material
6Mtrs 'B' Class M.S. pipe of 60.25mm Kg 37.2
dia with base plate and suitable pole
cap
Rate per Each
Bldngs_Elec- 13.3 Brackets

252
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

13-3
13.3.1 Supply and fixing of 50mm dia 0.5 mtrs
single arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
0.5Mtr length 50mm 'B' class pipe. Kg 2.55
45cm length , 10cm dia and cap. Kg 5.4
Painting with red oxid and enamel job 1
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician day 0.2
Fitter day 0.2
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
13.3.2 Supply and fixing of 50mm dia 0.5 mtrs
double arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire
a) Material
2 x 0.5Mtr length 50mm 'B' class pipe. Kg 5.1
45cm length , 10cm dia and cap. Kg 5.4
Painting with red oxid and enamel job 1
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician day 0.33
Fitter day 0.33
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
13.3.3 Supply and fixing of 50mm dia 0.5 mtrs
triple arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
3 x 0.5Mtr length 50mm 'B' class pipe. Kg 7.65
45cm length , 10cm dia and cap. Kg 5.4
Painting with red oxid and enamel job 1
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician day 0.5
Fitter day 0.5
Rate per Each

253
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Note : Labour is Considered for 2 jobs


/ day
13.3.4 Supply and fixing of 50mm dia 1 mtrs
single arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire
a) Material
1Mtr length 50mm 'B' class M.S pipe. Kg 5.1
45cm length , 10cm dia and cap. Kg 5.4
Painting with red oxid and anamel job 1
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician day 0.2
Fitter day 0.2
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
13.3.5 Supply and fixing of 50mm dia 1 mtrs
double arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
2 x 1Mtr length 50mm 'B' class M.S Kg 10.2
pipe.
45cm length , 10cm dia and cap. Kg 5.4
Painting with red oxid and anamel job 1
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician day 0.33
Helper day 0.33
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
13.3.6 Supply and fixing of 50mm dia 1 mtrs
triple arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
3 x 1Mtr length 50mm 'B' class M.S Kg 15.3
pipe.
45cm length , 10cm dia and cap. Kg 5.4
Painting with red oxid and anamel job 1
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician day 0.5

254
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Helper day 0.5


Rate per Each
Note : Labour is Considered for 2 jobs
/ day
13.3.7 Supply and fixing of 50mm dia 1.5 mtrs
single arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
1.5 Mtr length 50mm 'B' class M.S Kg 7.65
pipe.
45cm length , 10cm dia and cap. Kg 5.4
Painting with red oxid and anamel job 1
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician day 0.2
Helper day 0.2
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
13.3.8 Supply and fixing of 50mm dia 1.5 mtrs
double arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
2 x 1.5Mtr length 50mm 'B' class M.S Kg 15.3
pipe.
45cm length , 10cm dia and cap. Kg 5.4
Painting with red oxid and anamel job 1
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician day 0.33
Helper day 0.33
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
13.3.9 Supply and fixing of 50mm dia 1.5 mtrs
triple arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
3 x 1.5Mtr length 50mm 'B' class M.S Kg 22.95
pipe.
45cm length , 10cm dia and cap. Kg 5.4
Painting with red oxid and anamel job 1
paint.

255
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

b) Labour charges for fixing with Spl. T


&P
Skilled Electrician day 0.5
Helper day 0.5
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
13.3.10 Supply and fixing of 50mm dia 1.5 mtrs
curved single arm M.S. pipe bracket
with sleeve and fasteners with
necessary angle including painting etc.,
complete on existing pole including
fixing of luminaire.
a) Material
1.5 Mtr length 50mm 'B' class M.S Kg 7.65
pipe.
45cm length , 10cm dia and cap. Kg 5.4
Painting with red oxid and anamel job 1
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician day 0.2
Helper day 0.2
For Moulding & making Suitable curve job 1
on length
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
13.3.11 Supply and fixing of 50mm dia 1.5 mtrs
curved double arm M.S. pipe bracket
with sleeve and fasteners with
necessary angle including painting etc.,
complete on existing pole including
fixing of luminaire.
a) Material
2 x 1.5 Mtr length 50mm 'B' class M.S Kg 15.3
pipe.
45cm length , 10cm dia and cap. Kg 5.4
Painting with red oxid and anamel job 1
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician day 0.33
Helper day 0.33
For Moulding & making Suitable curve job 1
on length
Rate per Each
Note : Labour is Considered for 3 jobs
/ day

256
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

13.3.12 Supply and fixing of 50mm dia 1.5 mtrs


curved triple arm M.S. pipe bracket
with sleeve and fasteners with
necessary angle including painting etc.,
complete on existing pole including
fixing of luminaire.
a) Material
3 x 1.5 Mtr length 50mm 'B' class M.S Kg 22.95
pipe.
45cm length , 10cm dia and cap. Kg 5.4
Painting with red oxid and anamel job 1
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician day 0.5
Helper day 0.5
For Moulding & making Suitable curve job 1
on length
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Bldngs_Elec- 13.4 Erection Charges for Swaged Poles
13-4
13.4.1 Erection charges for 7 mtrs. to 8 mts
long swaged pole including excavation
of pit, coil earthing, hire charges of
special T&P painting of Pole CC 1:3:6
upto ground and 1:2:4 for Couping
work, including labour and
transportation charges etc., complete
a) Material
Pit excavation 156 Cmx cum 0.54
60Cmx60cm.(Civil SSR)
C.C.work for pit 1:3:6 (Civil SSR) cum 0.54
Couping 1:2:4 (Civil SSR) cum 0.054
Painting with red oxid and enamel M 6.2
paint.
Coil earthing each 1
b) Labour charges
Skilled Electrician day 0.33
Helper day 2.67
Mason day 0.33
Hire charges for Spl.T&P 40% on labour
cost
Rate per Each
Note : Labour is Considered for 3 jobs
/ day

257
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

13.4.2(a) Erection charges for 9 mtrs to 11 mtrs


long swaged pole including excavation
of pit, coil earthing, hire charges of
special T&P painting of Pole CC 1:3:6
upto ground and 1:2:4 for Couping
work, including labour and
transportation charges etc., complete.
a) Material
Pit excavation 156 Cmx cum 0.72
60Cmx60cm.(Civil SSR)
C.C.work for pit 1:3:6 (Civil SSR) cum 0.72
Couping 1:2:4 (Civil SSR) cum 0.054
Painting with red oxid and enamel M 8.35
paint.
Coil earthing each 1
b) Labour charges
Skilled Electrician day 0.33
Helper day 2.67
Mason day 0.33
Hire charges for Spl.T&P 40% on labour
cost
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
13.4.2(b) Erection charges for 12 Mts to 14Mts
long swaged pole including excavation
of pit, coil earthing, hire charges of
special T&P (Crane)painting of Pole CC
1:3:6 upto ground and 1:2:4 for
Couping work, including labour and
transportation charges etc., complete.
a) Material
Pit excavation 2.0x1.0x1.0Mtr cum 2
1:3:6 CC Work cum 2
couping 1:2:4 cum 0.054
Painting with red oxid and alluminum M 12
paint.
Coil earthing each 1
b) Labour charges
Skilled Electrician day 0.5
Helper day 4
Mason day 0.5
Hire charges for Spl.T&P 20% on labour
cost
Rate per Each
Note : Labour is Considered for 2 jobs
/ day

258
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

13.4.3 Erection charges for 16Mts long


swaged pole including excavation of
pit, coil earthing, hire charges of
special T&P (Crane)painting of Pole CC
1:3:6 upto ground and 1:2:4 for
Couping work, including labour and
transportation charges etc., complete.
a) Material
Pit excavation 2.30x1.0x1.0Mtr cum 2.3
1:3:6 CC Work cum 2.3
couping 1:2:4 cum 0.054
Painting with red oxid and alluminum M 14
paint.
Coil earthing each 1
b) Labour charges
Skilled Electrician day 0.5
Helper day 4
Mason day 0.5
Hire charges for Spl.T&P 20% on labour
cost
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
13.4.4 Erection charges for 7to 9Mts long
swaged pole on bridge kerb portion (
R.C.C. work with V.C.C. M.15 concrete
with 3 Nos 25x6 mm MS Special clamps
bolts with nuts and locking nuts
etc.including cost and con veyance of
all material and all labour charges etc.
complete with painting.
a) Material
Painting with red oxid and enamel M 6.2
paint.
Coil earthing each 1
3 Nos, 25 x 6 mm MS Special Clamps of Kg 3.54
1 M Length each @ 1.18 Kg
VCC M 15 Concrete 0.5 x 0.3 x 0.9 cum 0.135
b) Labour charges
Skilled Electrician day 0.33
Helper day 2.67
Mason day 0.33
Fanrication of clamps kgs 3.54
Hire charges for Spl.T&P 20% on labour
cost
Rate per Each
Note : Labour is Considered for 3 jobs
/ day

259
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

13.4.5 Erection charges for 4 Mtrs. Long MS /


GI Garden post including excavation of
pit, concreting 1:3:6 and painting
including cost and conveyance of all
materials including fixing of luminaire
and labour charges etc., complete.
a) Material
Pit excavation (0.4x0.4x1.0 mtr) cum 0.16
Painting with red oxide and enamel M 2.5
paint.
1:3:6 C.C work. cum 0.16
b) Labour charges
Mason day 0.2
Helper day 0.4
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
13.4.6 Erection charges for 6Mtrs. Long MS /
GI Garden post including excavation of
pit, concreting 1:3:6 and painting
including cost and conveyance of all
materials including fixing of luminaire
and labour charges etc., complete.
a) Material
Pit excavation ( 0.45x0.45x1.25) cum 0.25
1: 3: 6 C.C. work cum 0.25
Painting with red oxide and enamel M 4.75
paint
b) Labour charges
Mason day 0.2
Helper day 0.4
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
13.4.7 Fabrication, supply and fixing of
luminaire carriage, made with 50mm
dia M.S. 'B' class pipe, moulded to 6
feet dia ring wheel, and 40mm dia M.S
support pieces on 4 sides inside the
wheel and necessary size of M.S pole
cap for fixing the ring wheel on the
156mm dia M.S. pole for fixing
floodlight and gear box with suitable
nut & bolts and painted with Red
Oxide and Aluminium paint including
cost & conveyance of all materials etc.,
complete.
a) Material
50mm 'B' class MS pipe of 5.7mts Kg 29.07
(1Mt=5.106Kgs)
40mm 'B' glass pipe MS pipe of 3.6Mtr Kg 13
(1Mt=3.61Kgs)
200mm MS pipe for pole cap.C-Class Kg 13
(heavy) 0.3Mts (1Mt=31Kgs)

260
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Special bolts and nuts 6" length. each 12


Painting with red oxide and enamel Job 1
paint etc.,
b) Labour charges
Fitter day 0.5
Helper day 4
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Bldngs_Elec- 13.5 Accessories
13-5
13.5.1 Supply and fixing of 300mm x 260mm x
140mm No.16 gauge CRCA sheet box
with hinged door and locking
arrangements and din channel for
fixing 2Nos MCBs duly powder coated
with matching colour of poles including
fixing with necessary arrangments etc.,
complete.
a) Material
300x260x140mm 16 guage CRCA box sqm 0.35
finished of item(as per 14.1.2)
Sundries as rounding off
Rate per Each
13.5.2 Supply and fixing of 300mm x 180mm x
140mm No.16 gauge CRCA sheet box
with hinged door and locking
arrangements and din channel for
fixing 2Nos MCBs duly powder coated
with matching colour of poles including
fixing with necessary arrangments etc.,
complete.
a) Material
300x180x140mm 16 guage CRCA sheet sqm 0.29
box as per 14.1.2
Sundries as rounding off
Rate per Each
13.5.3 Supply and fixing of 1 No.10A SP MCB
in existing M.S. box with Din channel,
4way 63A connector including cost &
conveyance of all materials and labour
charges etc., complete.
a) Material
10A SP MCB each 1
4Way connector. each 1
b) Labour charges
Skilled Electrician day 0.066
Rate per Each
Note : Labour is Considered for 15
jobs / day

261
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

13.5.4 Supply and fixing of 2 Nos 10A SP


MCBs in existing M.S box with Din
channel, 4way 63A connector including
cost & conveyance of all materials and
labour charges etc., complete.
a) Material
10A SP MCB each 2
4Way connector. each 1
b) Labour charges
Skilled Electrician day 0.066
Sundries such as screws, tape
Rate per Each
Bldngs_Elec- 14 CONTROL PANEL AND METERING
14 EQUIPMENT
Bldngs_Elec- 14.1
14-1 CONTROL PANEL
14.1.1 Supply, Transportation, fabrication and
erection of following guage CRCA sheet
steel enclosure for power control
cubicle panel / boxes etc., including
cutting, bending drilling, welding and
reveting etc., complete with cleaning
with 7 tank process and painting with
powder coating including cost and
conveyance of all materials and labour
charges.
1) 14 SWG CRCA sheet steel enclosure
a) Material
14 SWG (2mm) CRCA sheet - 1 sft (Wt kg 1.56
of 8 x 4 feet sheet, 50Kg)
Transportation charges on Material 2%
cost
Fabrication including cutting, bending, 30%
drilling and Dust proof arrnagments
etc.,
Cleaning of cubicals in seven tank 40%
process
Painting with powder coating. 40%
Erection charges 30%
Sundires such as hardware etc.,
Rate per sft
Rate per sqm
14.1.2 16 SWG CRCA sheet steel enclosure
a) Material
16 SWG (2mm) CRCA sheet - 1sft (Wt kg 1.218
of 8 x 4 feet sheet, 39Kg)
Transportation charges 2%
Fabrication including cutting, bending, 30%
drilling and Dust proof arrnagments
etc.,
Cleaning of cubicals in seven tank 40%
process
Painting with powder coating. 40%
Erection charges 30%

262
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Sundires such as hardware etc.,


Rate per sft
Rate per sqm
14.1.3 18 SWG CRCA sheet steel enclosure
a) Material
18 SWG (2mm) CRCA sheet - 1 sft (Wt kg 0.937
of 8 x 4 feet sheet, 30Kg)
Transportation charges 2%
Fabrication including cutting, bending, 30%
drilling and Dust proof arrnagments
etc.,
Cleaning of cubicals in seven tank 40%
process
Painting with powder coating. 40%
Erection charges 30%
Sundires such as hardware etc.,
Rate per sft
Rate per sqm
Bldngs_Elec- 14.2 METERING EQUIPMENT
14-2
14.2.1 Supply and erection of 0-500V volt
meter of size 96x96mm on exisiting
box / panel board including
connections etc., complete.
a) Material
0-500 Voltmeter Analog / Degital each 1
inclusive of all Taxes.
b) Labour charges for fixing &
Connections
Skilled Electrician day 0.2
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
14.2.2 Supply and erection of 0-100 / 200 /
400 / 600 /1000 - 5A CT Ammeter of
size 96x96mm on existing box / panel
board including connections etc.,
complete.
a) Material
96 x 96mm size Ammeter Analog / each 1
Degital inclusive of all Taxes
b) Labour charges for fixing and
connections.
Skilled Electrician day 0.2
Rate per Each
14.2.3 Supply and erection of frequency
meter of size 96x96mm on existing
box / panel board including
connections etc., complete.
a) Material
Frequency meter Analog / Degital each 1
inclusive of all Taxes.

263
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

b) Labour charges for fixing and


connections.
Skilled Electrician day 0.2
Rate per Each
14.2.4 Supply and erection of power factor
meter, 3 phase, 4 wire balanced or
unbalanced load 5A, 415V of size
96x96mm on existing box / panel
board including connections etc.,
complete.
a) Material
Power Factor meter Analog / Degital each 1
inclusive of all Taxes.
b) Labour charges for fixing and
connections.
Skilled Electrician day 0.2
Rate per Each
14.2.5 Supply and erection of L.T. 3phase
multifunction energy meter with 3
lines LCD display of size 96x96mm for
measuring all the parameters (voltage
/ Current / Power / frequency / power
factor / KW / KWH / KVAR/ KVARH) on
existing box panel board including
connections etc., complete.
a) Material
L.T. 3 Ph. Multifunction energy meter each 1
Analog / Degital inclusive of all Taxes.
b) Labour charges for fixing and
connections.
Skilled Electrician day 0.33
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
14.2.6 Supply and erection of selector switch
for voltmeter / Ammeter on the
existing box / panel including
connections etc., complete.
a) Material
Selector switch for Ammeter / each 1
Voltmeter.
b) Labour charges for fixing and
connections.
Skilled Electrician day 0.2
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
14.2.7 Supply and erection of LED indicator
lamps on the existing box / panel
board.
a) Material
LED indicator lamp Analog each 1
b) Labour charges for fixing and
connections.

264
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Skilled Electrician day 0.1


Rate per Each
Note : Labour is Considered for 10
jobs / day
14.2.8 Supply and erection of LT current
transformer with bar primary 100/5A
to 1000 / 5A ratio in the existing box /
panel including connections etc.,
complete.
a) Material
L.T. C.T with bar primary 100 / 5A to each 1
1000 / 5A
b) Labour charges for fixing and
connections.
Skilled Electrician day 0.1
Rate per Each
Note : Labour is Considered for 10
jobs / day
14.2.9 Supply and fixing of single phase
energy Meter,240V AC,50 HZ as per
IS13010 with 2.5-5 /5-10/10-20 Amps
range with 200% over load capacity
complete with connections etc.,
complete on the existing board.
a) Material
cost of single phase energy meter each 1
b) Labour charges for fixing and
connections.
Skilled Electrician day 0.33
sunderies
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
14.2.10 Supply and fixing of three phase
energy Meter,415V AC,50 HZ as per
IS13010 with 2.5-5 /5-10/10-20 Amps
range with 200% over load capacity
complete with connections etc.,
complete on the existing board.
a) Material
Cost of three phase energy meter each 1
b) Labour charges for fixing and
connections.
Skilled Electrician day 0.33
sunderies
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
Bldngs_Elec- 15
15 CABLES / CABLE GLANDS / LUGS
Bldngs_Elec- 15.3 CABLE GLANDS
15-1

265
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

15.3.1 Supply and Fixing of heavy duty flange


type brass cable glands for 2 to 4 core,
2.5 Sq.mm to 6 Sq.mm PVC armoured
cable with brass washers complete.
a) Material
Brass cable gland for 2-4 core, 2.5 each 1
Sqmm to 6 Sq.mm armoured cable
b) Labour charges for fixing glands.
Semi skilled Electrician day 0.066
Sundireis and Rounding off
Rate per Each
Note : Labour is Considered for 15
jobs / day
15.3.2 Supply and Fixing of heavy duty flange
type brass cable glands for 2 to 4 core,
10 Sq.mm PVC armoured cable with
brass washers complete.
a) Material
Brass cable gland for 2-4 core, 10 each 1
Sqmm armoured cable
b) Labour charges for fixing glands.
Semi skilled Electrician day 0.066
Sundireis and Rounding off
Rate per Each
Note : Labour is Considered for 15
jobs / day
15.3.3 Supply and Fixing of heavy duty flange
type brass cable glands for 4 core, 16
Sq.mm / 3.5 core 25Sq.mm PVC
armoured cable with brass washers
complete.
a) Material
Brass cable gland suitabtle for 4core each 1
16 Sq.mm / 3.5 core 25 Sq.mm
armoured cable
b) Labour charges for fixing glands.
Skilled Electrician day 0.066
Sundireis and Rounding off
Rate per Each
15.3.4 Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core, 35
Sq.mm / 3.0 core 50Sq.mm PVC
armoured cable with brass washers
complete.
a) Material
Brass cable gland suitabtle for 3.5core each 1
35 Sq.mm / 3 core 50 Sq.mm
armoured cable
b) Labour charges for fixing glands.
Skilled Electrician day 0.066
Sundireis and Rounding off
Rate per Each

266
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Note : Labour is Considered for 15


jobs / day
15.3.5 Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core, 50
Sq.mm PVC armoured cable with
brass washers complete.
a) Material
Brass cable gland suitabtle for 3.5core each 1
50 Sq.mm armoured cable
b) Labour charges for fixing glands.
Skilled Electrician day 0.066
Sundireis and Rounding off
Rate per Each
Note : Labour is Considered for 15
jobs / day
15.3.6 Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core, 70
Sq.mm PVC armoured cable with brass
washers complete.
a) Material
Brass cable gland suitabtle for 3.5core each 1
70Sq.mm armoured cable
b) Labour charges for fixing glands.
Skilled Electrician day 0.066
Helper day 0.066
Sundireis and Rounding off
Rate per Each
Note : Labour is Considered for 15
jobs / day
15.3.7 Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core, 95
Sq.mm PVC armoured cable with
brass washers complete.
a) Material
Brass cable gland suitabtle for 3.5core each 1
95 Sq.mm armoured cable
b) Labour charges for fixing glands.
Skilled Electrician day 0.066
Helper day 0.066
Sundireis and Rounding off
Rate per Each
Note : Labour is Considered for 15
jobs / day
15.3.8 Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core,
120 Sq.mm PVC armoured cable with
brass washers complete.
a) Material
Brass cable gland suitabtle for 3.5core each 1
120 Sq.mm armoured cable
b) Labour charges for fixing glands.
Skilled Electrician day 0.066
Helper day 0.066

267
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Sundireis and Rounding off


Rate per Each
Note : Labour is Considered for 15
jobs / day
15.3.9 Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core,
150 Sq.mm PVC armoured cable with
brass washers complete.
a) Material
Brass cable gland suitabtle for 3.5core each 1
150 Sq.mm armoured cable
b) Labour charges for fixing glands.
Skilled Electrician day 0.083
Helper day 0.083
Sundireis and Rounding off
Rate per Each
Note : Labour is Considered for 12
jobs / day
15.3.10 Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core,
185 Sq.mm PVC armoured cable with
brass washers complete.
a) Material
Brass cable gland suitabtle for 3.5core each 1
185 Sq.mm armoured cable
b) Labour charges for fixing glands.
Skilled Electrician day 0.083
Helper day 0.083
Sundireis and Rounding off
Rate per Each
Note : Labour is Considered for 12
jobs / day
15.3.11 Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core,
240 Sq.mm PVC armoured cable with
brass washers complete.
a) Material
Brass cable gland suitabtle for 3.5core each 1
240 Sq.mm armoured cable
b) Labour charges for fixing glands.
Skilled Electrician day 0.083
Helper day 0.083
Sundireis and Rounding off
Rate per Each
Note : Labour is Considered for 12
jobs / day
15.3.12 Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core,
300 Sq.mm PVC armoured cable with
brass washers complete.
a) Material
Brass cable gland suitabtle for 3.5core each 1
300 Sq.mm armoured cable

268
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

b) Labour charges for fixing glands.


Skilled Electrician day 0.1
Helper day 0.1
Sundries, such as insulated tape.
Rate per Each
Note : Labour is Considered for 10
jobs / day
15.3.13 Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core,
400 Sq.mm PVC armoured cable with
brass washers complete.
a) Material
Brass cable gland suitabtle for 3.5core each 1
400 Sq.mm armoured cable
b) Labour charges for fixing glands.
Skilled Electrician day 0.1
Helper day 0.1
Sundries, such as insulated tape.
Rate per Each
Note : Labour is Considered for 10
jobs / day
Bldngs_Elec- 15.4
15-2 CABLE LUGS:
15.4.1 Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable upto 16 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs upto 16 Sq.mm. each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.01
Helper day 0.01
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 100
jobs / day
15.4.2 Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 25 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs upto 25 Sq.mm. each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.01
Helper day 0.01
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 100
jobs / day

269
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

15.4.3 Supply and fixing of crimping type


copper lugs confirming to I.S
specifications for cable of 35 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs up to 35 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.013
Helper day 0.013
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 75
jobs / day
15.4.4 Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 50 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs upto 50 Sq.mm. each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.013
Helper day 0.013
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 75
jobs / day
15.4.5 Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 70Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs upto 70 Sq.mm. each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.013
Helper day 0.013
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 75
jobs / day
15.4.6 Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 95 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs up to 95 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.016
Helper day 0.016
Sundries such as bolts and nuts.
Rate per Each

270
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Note : Labour is Considered for 60


jobs / day
15.4.7 Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 120 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs up to 120 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.02
Helper day 0.02
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 50
jobs / day
15.4.8 Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 150 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs up to 150 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.033
Helper day 0.033
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 30
jobs / day
15.4.9 Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 185 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs up to 185 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.033
Helper day 0.033
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 30
jobs / day
15.4.11 Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 240 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs up to 240 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.04
Helper day 0.04

271
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Sundries such as bolts and nuts.


Rate per Each
Note : Labour is Considered for 25
jobs / day
15.4.12 Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 300 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs up to 300 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.05
Helper day 0.05
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 20
jobs / day
15.4.13 Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 400 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs up to 400 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.062
Helper day 0.062
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 16
jobs / day
15.4.14 Supply and fixing of crimping type
Aluminium lugs confirming to I.S
specifications for cables upto 16
Sq.mm including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 16 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.01
Helper day 0.01
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 100
jobs / day
15.4.15 Supply and fixing of crimping type
Aluminium lugs confirming to I.S
specifications for cable of 25 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 25 sqmm each 1

272
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

b) Labour charges for crimping


Semi Skilled Electrician day 0.01
Helper day 0.01
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 100
jobs / day
15.4.16 Supply and fixing of crimping type
Aluminium lugs confirming to I.S
specifications for cable of 35 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 35 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.013
Helper day 0.013
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 75
jobs / day
15.4.17 Supply and fixing of crimping type
Aluminium lugs confirming to I.S
specifications for cable of 50 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 50 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.013
Helper day 0.013
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 75
jobs / day
15.4.18 Supply and fixing of crimping type
aluminium lugs confirming to I.S
specifications for cable of 70 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 70 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.013
Helper day 0.013
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 75
jobs / day

273
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

15.4.19 Supply and fixing of crimping type


aluminium lugs confirming to I.S
specifications for cable of 95 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 95 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.016
Helper day 0.016
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 60
jobs / day
15.4.20 Supply and fixing of crimping type
aluminium lugs confirming to I.S
specifications for cable of 120 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 120 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.02
Helper day 0.02
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 50
jobs / day
15.4.21 Supply and fixing of crimping type
aluminium lugs confirming to I.S
specifications for cable of 150 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 150 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.04
Helper day 0.04
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 25
jobs / day
15.4.22 Supply and fixing of crimping type
aluminium lugs confirming to I.S
specifications for cable of 185 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 185 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.04
Helper day 0.04
Sundries such as bolts and nuts.

274
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Rate per Each


Note : Labour is Considered for 25
jobs / day
15.4.24 Supply and fixing of crimping type
aluminium lugs confirming to I.S
specifications for cable of 240 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 240 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.04
Helper day 0.04
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 25
jobs / day
15.4.25 Supply and fixing of crimping type
aluminium lugs confirming to I.S
specifications for cable of 300 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 300 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.05
Helper day 0.05
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 20
jobs / day
15.4.26 Supply and fixing of crimping type
aluminium lugs confirming to I.S
specifications for cable of 400 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 400 sqmm each 1
b) Labour charges for crimping
Semi Skilled Electrician day 0.062
Helper day 0.062
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 16
jobs / day
Bldngs_Elec- 15.5 CABLE JOINTS
15-3

275
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

15.5.1 Providing and erecting epoxy staight


through joint out door / indoor for L.T,
PVC Armoured cable 1100V grade
complete with ferrule, bushings,
accessories and suitable clamps duly
erected and connected to the supply
for the following multi core cables
including cost and conveyance of
materials and all labour charges etc.,
complete.
(a) 2.5 Sq.mm to 16 Sq.mm
a) Material
Epoxy straight joint 2.5 to 16 Sq.mm each 1
with accessories
b) Labour charges
Skilled Electrician day 0.5
Helper day 0.5
Sundries
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
(b) 25 Sq.mm to 50 Sq.mm
a) Material
Epoxy straight joint 25 to 50 Sq.mm each 1
with accessories
b) Labour charges
Semi Skilled Electrician day 0.5
Helper day 0.5
Sundries
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
(c ) 70 Sq.mm to 95 Sq.mm
a) Material
Epoxy straight joint 70 to 95 Sq.mm each 1
with accessories
b) Labour charges
Semi Skilled Electrician day 0.5
Helper day 0.5
Sundries
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
(d) 120 Sq.mm to 185 Sq.mm
a) Material
Epoxy straight joint 120 to 185 Sq.mm each 1
with accessories
b) Labour charges
Semi Skilled Electrician day 0.5
Helper day 0.5
Sundries
Rate per Each

276
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Note : Labour is Considered for 2 jobs


/ day
(e) 240 Sq.mm
a) Material
Epoxy straight joint 240 Sq.mm with each 1
accessories
b) Labour charges
Skilled Electrician day 1
Helper day 1
Sundries
Rate per Each
(f) 300 Sq.mm
a) Material
Epoxy straight joint 300 Sq.mm with each 1
accessories
b) Labour charges
Skilled Electrician day 1
Helper day 1
Sundries
Rate per Each
(g) 400 Sq.mm
a) Material
Epoxy straight joint 400 Sq.mm with each 1
accessories
b) Labour charges
Skilled Electrician day 1
Helper day 1
Sundries
Rate per Each
15.6 Labour Charges Laying of Cable
Bldngs_Elec-
including cost of all Materials other
15-4
than Cable
15.6.1 Earth work excavation of Trench in
hard ground soil, laying of U.G cables
upto 50 Sq,mm on sand cushion
covering the cable with bricks and back
filling of Trench duly providing route
indicator embedded in C.C including
cost and conveyance of materials and
labour charges etc., complete.
a) Material
Excavation of earth 100 x 0.3 X 0.9 m cum 27
Cost of bricks (Civil SSR) 1000 Nos 0.92

Cost of sand (Civil SSR) cum 6


Cement (Civil SSR) Kg 25
Cost of cable route indicator each 12
Transportation charges of bricks and LS
sand
b) Labour charges for laying cable.
Man Mazdoor for spreading the sand each 2.5
and back filling the excavated soil.
Skilled Electrician day 1

277
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Helper day 2
Man Mazdoor for concreting and day 2
embedding of cable way indicators
Sundires and Rounding off
Rate per 100mts
Note : Labour Charges Considered for
100 Mts / day
15.6.2 Earth work excavation of Trench in
hard ground soil, laying of U.G cables
from 70 sqmm to 400 Sq,mm on sand
cushion covering the cable with bricks
and back filling of Trench duly
providing route indicator embedded in
C.C including cost and conveyance of
materials and labour charges etc.,
complete.
a) Material
Excavation of earth 100 x 0.3 X 0.9 m cum 27
Cost of bricks (Civil SSR) 1000 Nos 0.92

Cost of sand (Civil SSR) cum 6


Cement (Civil SSR) Kg 25
Cost of cable route indicator each 12
Transportation charges of bricks and LS
sand
b) Labour charges for laying cable.
Man Mazdoor for spreading the sand each 2.5
and back filling the excavated soil.
Skilled Electrician day 1.6
Helper day 3.3
Man Mazdoor for concreting and day 2
embedding of cable way indicators
Sundires and Rounding off
Rate per 60mts
Note :1. Labour Charges Considered for 60 Mts / day
2. Cables shall be at a depth of not less than 600 mm in a trench. Sand filling
shall be provided at the bottom of trench before laying the cable. Bricks shall
be provided on either side of the laid cable. Sand filling shall be done to
cover the cable laid. bricks shall be provided onthe Top. earth filling shall be
done. cable identificaiton tags to be provided at every 8 mtrs length of cable
laid.
3. Only the cost of cables may be added for finished item.
15.6.3 Labour charges for run of U.G cable on
wall / existing pipe with necessary
fixing arrangments such as saddles,
clamps,wooden separators etc., (as
directed by departmental official) with
No.10 SWG G.I wire for eath
connections for the cables.
a) Material
Wooden separators each 200
saddles of required size 100 nos 2
12mm screws 100 nos 4
No.10 SWG GI wire kg 7

278
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

b) Labour charges
Skilled Electrician day 1
Helper day 4
Sundires such as Cement, Sand etc.,
Rate per Each
Note : Labour Charges Considered for
100 Mts / day
15.6.4 Supply and laying of one number
double walled corrugated (DWC) HDPE
pipe of following sizes having
corrugation on the outer wall and plain
surface inner wall confirming to IS :
14930 Part - I and II complete with
necessary HDPE fittings for protection
of 1.1 KV grade U.G cable directly in
ground at a depth of 60Cms including
excavation and refilling the trench as
required.
a) 50mm outer dia nominal size
b) 78mm outer dia nominal size
c) 90mm outer dia nominal size
d) 120mm outer dia nominal size
a) Material
Double wall corrugated HDPE pipe RM 6
confirming to IS : 14930.
Snap-fit coupler each 1
Excavation of earth work & Refilling for cum 0.18
a size of 1.0x0.3x0.6Mtr.
Rate per Metre
Bldngs_Elec- 16
16 TEMPORARY ILLUMINATION
data shown seperately at the end.
Bldngs_Elec- 17
17 GENERATORS AND TRANSFORMERS
Supply, Transportation, erection and commissioning of following specifications
Bldngs_Elec- of D.G. Set consists of Engine and alternator which are directly coupled by
17-1 means of flexible cooping with guard and mounted on a common base plate of
Robust construction and complete with control panel having IP 53 protection.
A Alternator : KIRLOSKAR / STAMFORD / CROMPTON on D.G.S & D approved
make. The alternator of the output rating shall be 1 Ph / 3 Ph, 240V / 415V, 50
Hz., A.C., 0.8 P.f lagging at 1500 RPM. The alternator is self excited, self
regulated, screen protected drip proof and shall confirm to IS : 13364 of 1992
with regulation of + 5% from no load to full load. degree of protections shall be
IP 21.
B Diesel Engine : KIRLOSKAR / GREAVES / CUMMINS / ASHOK LEY LAND or
DGS&D approved. Diesel Engine start, developing suitable BHP output at 1500
RPM with class A2 Governing so as to enable the alternator to give required
KVA continuous output at 0.8 P.F. lagging at NTP conditions. the Diesel Engine
will be capable of providing 10% O/L for 1 Hr for every 11 HRs of continuous
running at full load. The Diesel Engine shall confirm to IS 10001 or IS 10002.
C Control Panel : Control Panel shall be fabricated with 16 SWG CRCA sheet steel.
The control panel shall be totally enclosed, dust and vermin proof, floor
mounted / wall mounted type and shall be comprising the following
instruments and component.
1. Voltmeter with selector switch 2. Ammeter with Selector

279
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Switch
3. MCCB / MCB incomer of suitable rating 4. P.F. Meter and frequency
Meter
5. Indication Lamp Set 6. KWH Meter of required
rating
7. Instrument and control fuses.
ACOUSTIC ENCLOSURE
Supply & providing & installation of acoustic enclosure (sound proof enclosure
cum container) for the above Genset with the following specification.
Construction : The panel of acoustic enclosure shall consists of self supporting
frame work put together with help of fasteners, which is for assembling and
dismantling. The vertical and Horizontal structure 8is to be fabricated with
14/16 SWG CRCA sheet and should be fixed on heavy duty MS Channel which
will form the base frame of the acoustic enclosure. the paneling of ht container
is to be carried out using 18 SWG CRCA sheets. the enclosure should be self
supporting type and does not require any grouting or separate foundation. But
it should be the independent of the DG set and to placed around the DG set.
The frame work shall also have provision for fitting hinged / sliding doors to
open either sides of the enclosure.
17.1 Generating Sets
17.1.3 Supply, Transportation, erection of 3
(a) Ph Air-Cooled 20KVA, D.G.Set with
alternator, Diesel Engine, Control panel
etc., as per specifications mentioned
above.
a) Material
20KVA Air Cooled, 3Ph, 451V, 50Hz., each 1
D.G.Set.
Erection and commissioning charges @ 10%
10% of the cost of the set.
Transportation at 2% on unit cost 2%
Sundires and Rounding off
Rate per Each
17.1.3 Supply, Transportation, erection of 3
(b) Ph Air-Cooled 20KVA, D.G.Set with
alternator, Diesel Engine, Control panel
etc., with acoustic enclosure as per
specifications mentioned above.
a) Material
20KVA Air Cooled, 3Ph, 451V, 50Hz., each 1
D.G.Set
cost of acoustic enclosure each 1
Erection and commissioning charges :
the 10%
cost of the DG set.
cost 5%
of acoustic enclosure
Transportation at 2% on unit cost 2%
Sundires and Rounding off
Rate per Each

280
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.1.3 (c) Supply, Transportation, erection of 3


Ph Air-Cooled 25KVA, D.G.Set with
alternator, Diesel Engine, Control panel
etc., as per specifications mentioned
above.
a) Material
3Ph, 415V, 50Hz., 25 KVA Air Cooled each 1
D.G.Set
Erection and commissioning charges @ 10%
10% of the cost of the set.
Transportation at 2% on unit cost 2%
Sundires and Rounding off
Rate per Each
17.1.3 Supply, Transportation , erection of 3
(d) Ph Air-Cooled 25KVA, D.G.Set with
alternator, Diesel Engine, Control panel
etc., with acoustic enclosure as per
specifications mentioned above.
a) Material
3Ph, 415V, 50Hz., 25 KVA Air Cooled each 1
D.G.Set
Cost of Acoustic enclosure each 1
Erection and commissioning charges :
the 10%
cost of the DG set.
cost 5%
of acoustic enclosure
Transportation at 2% on unit cost 2%
Sundires and Rounding off
Rate per Each
17.1.3 Supply, Transportation, erection of 3
(e) Ph Air-Cooled 40KVA, D.G.Set with
alternator, Diesel Engine, Control panel
etc., as per specifications mentioned
above.
a) Material
40KVA, 3Ph,415V,D.G.Set each 1
Erection and commissioning charges @ 10%
10% of the cost of the set.
Transportation at 2% on unit cost 2%
Sundires and Rounding off
Rate per Each
17.1.3 (f) Supply, Transportation, erection of 3
Ph Air-Cooled 40KVA, D.G.Set with
alternator, Diesel Engine, Control panel
etc., with acoustic enclosure as per
specifications mentioned above.
a) Material
40KVA, 3Ph,415V,D.G.Set each 1
Cost of Acoustic enclosure each 1
Erection and commissioning charges :
the 10%
cost of the DG set.

281
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

cost 5%
of acoustic enclosure
Transportation at 2% 2%
Sundires and Rounding off
Rate per Each
17.1.3 Supply, Transportation , erection of 3
(g) Phase Water cooled / Air Cooled
63KVA, D.G.Set with alternator, Diesel
Engine, Control panel etc., as per
specifications mentioned above.
a) Material
63KVA, 3Ph, 415V, D.G Set each 1
Erection and commissioning charges @ 10%
10% of the cost of the set.
Transportation at 2% 2%
Sundires and Rounding off
Rate per Each
17.1.3 Supply, Transportation , erection of 3
(h) Phase Water Cooled / Air-Cooled
63KVA, D.G.Set with alternator, Diesel
Engine, Control panel etc., with
acoustic enclosure as per specifications
mentioned above.
a) Material
63KVA, 3Ph, 415V, D.G Set each 1
Cost of Acoustic enclosure each 1
Erection and commissioning charges :
the 10%
cost of the DG set.
cost 5%
of acoustic enclosure
Transportation at 2% 2%
Sundires and Rounding off
Rate per Each
17.1.3 (i) Supply, Transportation , erection of 3
Phase Water cooled 125 KVA, D.G.Set
with alternator, Diesel Engine, Control
panel etc., as per specifications
mentioned above.
a) Material
125KVA, Water Cooled, 3Ph, 415V each 1
D.G.Set.
Erection and commissioning charges @ 10%
10% of the cost of the set.
Transportation at 2% 2%
Sundires and Rounding off
Rate per Each
17.1.3 (j) Supply, Transportation, erection of 3
Phase Water-Cooled 125KVA, D.G.Set
with alternator, Diesel Engine, Control
panel etc., with acoustic enclosure as
per specifications mentioned above.
a) Material

282
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

125KVA, Water Cooled, 3Ph, 415V each 1


D.G.Set.
Cost of Acoustic enclosure each 1
Erection and commissioning charges :
the 10%
cost of the DG set.
cost 5%
of acoustic enclosure
Transportation at 2% 2%
Sundires and Rounding off
Rate per Each
Bldngs_Elec- 17.2 Transformers
17-2
17.2.1 Supply, transportation, erection and
commissioning of following
specifications of 3 Phase, 50 Hz., Oil
immersed and naturally cooled, out
door / Indoor type copper wound
transformer connected delta on H.V.
side and star on L.V side with
additional neutral brought out on load
side, rating 11000 / 433 volts with HV
tapping + 2.5% cotinuously rated for
full load and temparature rise not
exceeding 450 C by thermometer in oil
and 500 C by the resistance of the
winding after continuous run on full
load rating complete with the
following standard mounting.
(a) 63 KVA, 3Ph, aluminium wound
Tansformer, CSP type (Core Self
Protection)
a) Material
each 1
63KVA Aluminium wound CSP type
Transformer
Transportation including loading and 2%
unloading
(b) Labour charges for erection and 10%
commissioning.
Rate per Each
(b) 100 KVA, 3Ph, aluminium wound
Tansformer, CSP type
a) Material
each 1
100 KVA Aluminium wound CSP type
Transformer
Transportation including loading and 2%
unloading
(b) Labour charges for erection and 10%
commissioning.
Rate per Each
(c ) 100 KVA, 3Ph, copper wound
Tansformer

283
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

a) Material
each 1
100 KVA Copper wound Transformer
Transportation including loading and 2%
unloading
(b) Labour charges for erection and 10%
commissioning.
Rate per Each
(d ) 160 KVA, 3Ph, copper wound
Tansformer
a) Material
each 1
160 KVA Copper wound Transformer
Transportation including loading and 2%
unloading
(b) Labour charges for erection and 10%
commissioning.
Rate per Each
(e) 200 KVA, 3Ph, copper wound
Tansformer
a) Material
each 1
200 KVA Copper wound Transformer
Transportation including loading and 2%
unloading
(b) Labour charges for erection and 10%
commissioning.
Rate per Each
(f) 250 KVA, 3Ph, copper wound
Tansformer
a) Material
each 1
250 KVA Copper wound Transformer
Transportation including loading and 2%
unloading
(b) Labour charges for erection and 10%
commissioning.
Rate per Each
(g) 315 KVA, 3Ph, copper wound
Tansformer
a) Material
each 1
315 KVA Copper wound Transformer
Transportation including loading and 2%
unloading
(b) Labour charges for erection and 10%
commissioning.
Rate per Each
(h) 500 KVA, 3Ph, copper wound
Tansformer
a) Material
each 1
500 KVA Copper wound Transformer

284
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Transportation including loading and 2%


unloading
(b) Labour charges for erection and 10%
commissioning.
Rate per Each
(i) 630 KVA, 3Ph, copper wound
Tansformer
a) Material
each 1
630 KVA Copper wound Transformer
Transportation including loading and 2%
unloading
(b) Labour charges for erection and 10%
commissioning.
Rate per Each
(j) 1000 KVA, 3Ph, copper wound
Tansformer
a) Material
each 1
1000 KVA Copper wound Transformer
Transportation including loading and 2%
unloading
(b) Labour charges for erection and 10%
commissioning.
Rate per Each
Bldngs_Elec- 17.3 CIRCUIT BREAKER
17-3
17.3.7 Supply and errecting Air circuit Breaker
(ACB) manually operated non drawout
type with 6 way secondary isolating
contacts necessary micro switches for
over load and short circuit indicator,
door interlocking, shunt release, under
voltage release as well as 10%-20%
earth fault release suitable for
operational voltage 415V, 630A,
erected in position on provided panel
boards in an approved manner with
necessary material complete
a) Material
630A, 415V Fixed type 3 pole ACB each 1
Shunt release each 1
U/V release each 1
Earth fault release each 1
Transportation @ 2% on Unit Cost 2%
b) Labour charges for installation @ 5%
5%
Rate per Each

285
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.3.8 Supply and errecting Air circuit Breaker


(ACB) manually operated non drawout
type with 6 way secondary isolating
contacts necessary micro switches for
over load and short circuit indicator,
door interlocking, shunt release, under
voltage release as well as 10%-20%
earth fault release suitable for
operational voltage 415V, 800A,
erected in position on provided panel
boards in an approved manner with
necessary material complete.
a) Material
800A, 415V Fixed type 3 pole ACB each 1
Shunt release Coil. each 1
U/V release Coil. each 1
Earth fault release each 1
Transportation @ 2% on Unit Cost 2%
b) Labour charges for installation @ 5%
5%
Rate per Each
17.3.9 Supply and errecting Air circuit Breaker
(ACB) manually operated non drawout
type with 6 way secondary isolating
contacts necessary micro switches for
over load and short circuit indicator,
door interlocking, shunt release, under
voltage release as well as 10%-20%
earth fault release suitable for
operational voltage 415V, 1000A,
erected in position on provided panel
boards in an approved manner with
necessary material complete.
a) Material
1000A, 415V, Fixed type 3 pole ACB. each 1
Shunt release each 1
U/V release each 1
Earth fault release each 1
Transportation @ 2% on Unit Cost 2%
b) Labour charges for installation @ 5%
5%
Rate per Each
Bldngs_Elec- 17.4 SUB - STATION EQUIPMENT
17-4
17.4.1 Supply and fixing printed instructions
chart both in English and Telugu and
duly framed with front glass for
treatment of person suffering from
Electric shock.
a) Material
Printed insturction chart both of size each 1
0.9 x 0.6 M in English and Telugu.

286
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Towards making wooden frame with 150%


front glass including cost of material
and labour on unti cost of Item 1.
Rate per Each
17.4.2 Supply of pair of rubber hand gloves
suitable for working 11/22 KV supply.
a) Material
Rubber hand gloves suitable for each 1
working on 11/22 KV supply
Rate per Each Pair
17.4.3 Supply of 11KV, ISI, approved rubber
mat of thickness, required length and
breadth.
a) Material
6mm thick, ISI make Rubber mat each 1
suitable for working on 11/22 KV
Sundries and rounding off
Rate per sqmt
17.4.4 Supply of standard 18"x12"x8" first aid
box with all standard contents.
a) Material
18" x 12" x 8" size First Aid box. each 1
Set of Cotton, band aid cloth Antiseptic set 1
cream etc.,
Rate per Each
17.4.5 Supply of G.I sheet bucket of round
bottom of 13 Ltrs. Capacity with
printed letters and filled with sand and
arranged to existing stand or hook.
a) Material
13 Ltrs. Capacity G.I. bucket. each 1
Painting with 2 coats of red color sqm 0.5
enamell paint on out side.
Cost of sand cum 0.13
Sundires for printing letter etc.,
Rate per Each
17.4.6 Supply of Tranformer oil tested and
having good resistance to high electric
stress di-electric strength 50KV, low
viscocity, low pour point, high flash
point and excellent thermal properties
for efficient heat transfer and cooling
as per IS 335-1972.
a) Material
Transformer Oil having Dielectric L 1
strength of 50 KV
Sundries and rounding off
Rate per Lt

287
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.4.7 Providing floor mounting stand for


keeping 4Nos of bucket 1500mm
length, 900mm height made out of
40x40x6mm angle iron welded with 4
hooks and duly painted with one coat
of red lead and two coats of enamel
paint.
a) Material
1500mm length, 900mm height Floor kg 17.5
mounting stand fabricated with
40x40x6mm angle iron welded with 4
Nos Hooks. (1Mtr = 3.5Kg) (5x3.5Kgs =
17.5Kgs)
Fabrication cost of hooks including 50%
painting (on cost of material)
Sundries and rounding off
Rate per Each
17.4.8 Supply and erecting ABC Powder
(stored pressure type) fire extinguisher
5kg conforming to IS 2171-85 with
necessary clamps made from 50x6mm
MS flat with nuts & bolts grouted in
wall complete.
a) Material
ABC Powder Stored pressure type fire each 1
extengensher of 5 Kg capacity .
50 x6mm M.S Apl. Clamps with bolt & each 1
nut.
(b) Labour charges for erection.
Helper day 0.2
Sundires and Rounding off
Rate per Each
Note : Labour is considered for 5 jobs
/ day
17.4.9 Supply and erecting ABC Powder
(stored pressure type) fire extinguisher
10kg conforming to IS 2171-85 with
necessary clamps made from 50x6mm
MS flat with nuts & bolts grouted in
wall complete.
a) Material
ABC Powder Stored pressure type fire each 1
extengensher of 10 Kg capacity .
50 x6mm M.S Apl. Clamps with bolt & each 1
nut.
(b) Labour charges for erection.
Helper day 0.2
Sundires and Rounding off
Rate per Each
Note : Labour is considered for 5 jobs
/ day

288
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.4.10 Supply and erecting fencing of section


having size 2450 mm in height from
ground level and 1200mm width by
using angle iron size 50x50x6mm
erected in CC foundation 15x15x40cms
deep. The section of the frame shall
be fitted with flat iron supports of size
25x6mm on top, bottom and middle
and chain link jali of 8 SWG G.I to the
angle iron at every distance of 30 cms
by iron studs complete duly painted
with one coat of red oxide and two
coats of aluminium paint.
a) Material
50x50x6mm Angle Iron (1 Mt. = 4.37 kg 20.97
Kg) 4.8 m Length
25x6mm M.S Flat (1 Mt. 1.18 Kg) 3.6 M kg 4.25
length
Chain link Mesh (Civil SSR) sqm 2.4
Fabrication of Frame with angles, Flat kg 25.22
and chain link mesh
C.C.Work M 15 using 20 mm metal (15 cum 0.018
x 15 x 40) x 2 As per Civil SSR
Painting with one coat of red oxide and sqm 5.88
two coat of alluminium paint.
Sundires and Rounding off
Rate per Each
17.4.11 Supply and erecting 50x50x6mm angle
iron as corner support to be fixed
away from the fence support fixed at
the middle of the fencing frame and
the other side in CC foundation of
15x15x40 cms complete duly painted
with one coat of red oxide and two
coats of aluminium paint.
a) Material
50x50x6mm Angle. (1 mt. 4.37 Kg) 2m kg 8.74
Length
C.C.Work M 15 using 20 mm metal (15 cum 0.018
x 15 x 40) x 2 As per Civil SSR
Painting with one coat of red oxide and 10%
two coats of Aluminium paint (on cost
of Item 1)
Sundires and Rounding off
Rate per Each

289
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.4.12 Supply and erecting double leaf hinged


door each 150cms width x 185cms
height using 38.1 mm dia B grade ISI
marked G.I pipe from all four sides
with necessary bends with cross
supports of angle iron 40 x 40 x 6mm
with the door leaf covered with chain
link mesh of No. 8 SWG G.I wire with
necessary flat iron covering all around
frame. The door shall have heavy
latches, and side channels of
100x50x5mm locking arrangement
with lock of medium size with
duplicate keys, the fencing completely
erected with anti corrosive red oxide
paint and two coats of prescribed
enamel paint / silver paint. The
channel iron of size 100x50mm x
2.5Mtr. length shall be provided and
erected at both sides of gate with C.C
work
a) Material
38.1mm dia B Class G.I pipe. RM 14
(1.85 x 4 Nos + 1.5x 4Nos = 13.4 Mt or
say 14 Mtrs.) ( civil SSR)
25x6mm M.S. Flat (1.18 Kgs / Mt) 17 kg 20.06
M length
1000x50mm Channle (1mt = 8.74 Kg) 5 kg 43.7
M length
4 Nos x 2.38M Length, 40 x 40 x 6 mm kg 33.32
M.S. Angle Iron ( 1 Mtr = 3.5 Kg) 9.52
M length
Steel Aldrop with bolts and Nuts. each 1
Chain link mesh of 8 SWg G.I (Civil SSR) sqm 5.55
Medium size lock and Key each 1
Fabrication charges including welding kg 118
etc., complete.
Painting Charges sqm
b) Labour charges for erection 5%
including cost of hinges on items 1-6.
Sundireis and Rounding off
Rate per Each
Bldngs_Elec- 17.5
17-5 SUB-STATION MAINTENANCE
17.5.1 Filteration of transformer oil as per ISS Data
(a) for removal of moisture, carbon slurry shall be
etc. by means of circulating oil arrived
through vaccum pump from heating based on
elements and filters to withstand the observed
dielectric strength of the oil above Data
40KV beyond one minute tested in oil
testing Kit.
On site.
a) Material
Labour charges for filterations at site

290
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Rate per Each


17.5.1 Filteration of transformer oil as per ISS Data
(b) for removal of moisture, carbon slurry shall be
etc. by means of circulating oil arrived
through vaccum pump from heating based on
elements and filters to withstand the observed
dielectric strength of the oil above Data
40KV beyond one minute tested in oil
testing Kit.
At Factory.
a) Material
Labour charges for filterations at site
Rate per Each
17.5.3 Carryout routine maintenance,
servicing and testing of 630A to 1000A
L.T.ACB by cleaning fixed contacts,
moving contacts and arcchutes
including servicing and putting the ACB
in perfect working condition after
detting all relay and ON, OFF
mechanism etc.
a) Material
Removing the existing ACB and
servicing and testing of 630A to 1000A
L.T.ACB.
Clearing of fixed contacts, moving
contacts and arcchutes
Refix the ACB inposition and testing
and commissioning charges.
b) Labour charges for entire job
Skilled Electrician day 3
Semi Skilled Electrician day 3
Helper day 6
Sundries and Rounding
Rate per Each
Note :Job requires 3 days. Keeping this labour
arrived.
17.5.4 Carryout routine maintenance and
servicing of LT.Cubical panel board
having approximately 15 to 22 Nos of
switches by cleaning with power
blower and servicing the contacts,
tightning the connection of incoming
and outgoing cables, and clicking the
operating mechanism for smooth
functioning of switches and putting
them in smooth working condition.
a) Material
Removing all the doors of switches,
busbar chamber and back doors.
Clearing by using power blower.
Tightening all the terminations and
cleaning and servicing the contacts of
switches.

291
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

b) Labour charges for entire job


Skilled Electrician day 2
Semi Skilled Electrician day 1
Helper day 2
Sundries and Rounding
Rate per Each
Note :Job requires 3 days. Keeping this labour
arrived.
Bldngs_Elec- 17.6
17-6 PROTECTIVE GEAR
17.6.1 Supply and erecting approved make
11KV, 5KA metal oxide lightning
arrestors suitable for 11 KV supply with
necessary materials on existing cross
arm.
a) Material
Cost of 11 KV 5KA metal oxide lighting each 1
arrester.
b) Labour charges for erection.
Skilled Electrician day 0.33
Helper day 0.33
Sundries
Rate per Each
Note : Labour is considered for 3 jobs /
day
17.6.3 Supply and erecting porcelain disc type
insulator suitable for 11KV line with
suitable hardware on existing cross
arms.
a) Material
Cost of porcelain disc type insulator each 1
suitable for 11 KV
b) Labour charges for erection.
Skilled Electrician day 0.125
Helper day 0.25
Sundries
Rate per Each
Note : Labour is considered for 8 jobs /
day
17.6.5 Supply and erecting porcelain pin type
insulator suitable for 11KV line with
suitable hardware on existing cross
arms.
a) Material
Cost of porcelain pin type insulator each 1
suitable for 11 KV
b) Labour charges for erection.
Skilled Electrician day 0.125
Helper day 0.25
Sundries
Rate per Each
Note : Labour is considered for 8 jobs /
day

292
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.6.6 Supply and erecting porcelain post


type insulator suitable for 11KV line
with suitable hardware on existing
cross arms.
a) Material
Cost of porcelain post type insulator each 1
suitable for 11 KV
b) Labour charges for erection.
Skilled Electrician day 0.125
Helper day 0.25
Sundries
Rate per Each
Note : Labour is considered for 8 jobs /
day
17.6.8 Supply and fixing of lightning
protective system conforming to IS :
2309 with all standard accessories such
as metal globe finials on the top of the
builiding with 25.4 mm dia 3.0 mtrs.
Length of 'B' class G.I pipe etc.,
complete without down conductors
and earthing
a) Material
Lightning protective system with all each 1
standard accessories such as metallic
globe, finials etc.,
25.4 mm B Class GI Pipe, ISI Mark M 3
b) Labour charges
i) for fixing the System on G.I pipe.
ii) for fixing on top of the building with
C.C work / Clamping arrangement.
Skilled Electrician day 1
Helper day 1
Sundries and Rounding off
Rate per Each
17.6.10 Supply and erecting approved made
11KV, 400A A.B switch with all
standard accessories etc., complelte
with cost and conveyance of all
materials and labour charges.
a) Material
Cost of 11KV, 400A A.B switch wth all each 1
standard accessories.
b) Labour charges for erection.
Skilled Electrician day 1
Semi Skilled Electrician day 1
Helper day 1
Sundries and Rounding off
Rate per Each

293
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.6.11 Supply and erecting approved made


11KV, 200A A.B switch with all
standard accessories etc., complelte
with cost and conveyance of all
materials and labour charges.
a) Material
Cost of 11KV, 200A A.B switch wth all each 1
standard accessories.
b) Labour charges for erection.
Skilled Electrician day 1
Semi Skilled Electrician day 1
Helper day 1
Sundries and Rounding off
Rate per Each
17.6.12 Supply and erecting approved made
11KV, 200A (Tilting) A.B switch with all
standard accessories etc., complelte
with cost and conveyance of all
materials and labour charges.
a) Material
Cost of 11kV, 200A (Tilting) A.B switch each 1
wth all standard accessories.
b) Labour charges for erection.
Skilled Electrician day 1
Semi Skilled Electrician day 1
Helper day 1
Sundries and Rounding off
Rate per Each
17.6.13 Supply and erecting 11KV, H.G (Horn
Gap) fuse set including all standard
accessories etc., complete with cost
and conveyance of all materials and
labour charges.
a) Material
Cost of 11KV, H.G. fuse set wth all each 1
standard accessories.
b) Labour charges for erection.
Skilled Electrician day 1
Helper day 1
Sundries and Rounding off
Rate per Each
17.6.14 Supply and erecting of bank of
metalised polypropylene condensors
with the standard capacities of
2,3,5,7,10,12.5 and 15 KVAR units for
PF correction for operation on 3 phase
50 Cycles 400 / 440V (+10%) with
externally discharging resistances,
earthig terminals etc., complete.
a) Material
Cost of MPP capacitor operation on 3 Kvar 1
Ph. 415V.
b) Labour charges for erection.

294
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Skilled Electrician day 0.04


Helper day 0.08
Sundries and Rounding off
Rate per Kvar
Note : Labour considered for 25 jobs /
day
17.6.15 Supply and erecting of bank of
mixdielectric condensors with the
standard capacities of 2,3,5,7,10,12.5
and 15 KVAR units for PF correction for
operation on 3 phase 50 cycles
400/440V (+10%) with externally
discharging resistances, earthing
terminals etc., complete.
a) Material
Cost of of mixed Dielectric capacitor Kvar 1
operation on 3 Ph. 415V.
b) Labour charges for erection.
Skilled Electrician day 0.04
Helper day 0.08
Sundries and Rounding off
Rate per Kvar
Note : Labour considered for 25 jobs /
day
Bldngs_Elec- 18
18 Repairs to Motors and Rewinding
Datas of 11.6.1 to 11.6.4 are hold good
and be adopted.
18.1.1 Rewinding the motor of the table /
pedestal / cabin fan of all types, and
makes and overhauling including minor
Bldngs_Elec- repairs, testing for the original speed
18-1 and consumption with guarantee for
one year including tansporation from
site and back.
a) Material
Copper enamelled winding wire of fine kg 0.3
quality.
Labour charges towards removing 50%
unserviceable winding wire and
cleaning. (on cost of winding wire)
Labour charges towards rewinding the 100%
coils complete with connections etc.,
complete.(on cost of winding wire)
Sundries such as sleeves cotton tape, 40%
minolex paper, solution etc., with
transportion charges.
Less cost towards old winding wire kg 0.3
Rate per Each

295
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

18.1.2 Rewinding the motor of the ceiling fan


of 1200mm / 1400mm of all types and
makes and over hauling including
minor repairs and testing for original
speed and consumption
a) Material
35 / 36 Copper enamelled winding wire kg 0.2
of fine quality.
Labour charges towards removing 50%
unserviceable winding wire and
cleaning. (on cost of winding wire)
Labour charges towards rewinding the 100%
coils complete with connections etc.,
complete.(on cost of winding wire)
Sundries such as sleeves cotton tape, 40%
minolex paper, solution etc., with
transportion charges.
Less cost towards old winding wire kg 0.2
Rate per Each
18.1.3 Rewinding the motor of the exhaust
fan of light duty 225/300mm of
900/1400 RPM of all types and makes
and over hauling including minor
repairs and testing for original speed
and consumption
a) Material
23 / 24 / 28 Copper enamelled winding kg 0.05
wire of fine quality.
Labour charges towards removing 50%
unserviceable winding wire and
cleaning. (on cost of winding wire)
Labour charges towards rewinding the 100%
coils complete with connections etc.,
complete.(on cost of winding wire)
Sundries such as sleeves cotton tape, 40%
minolex paper, solution etc., with
transportion charges.
Less cost towards old winding wire kg 0.05
Rate per Each
18.1.4 Rewinding the motor of the exhaust
fan of heavy duty 375mm of 900/1400
RPM of all types and makes and over
hauling including minor repairs and
testing for original speed and
consumption
a) Material
23 / 24 / 28 Copper enamelled winding kg 0.45
wire of fine quality.
Labour charges towards removing 50%
unserviceable winding wire and
cleaning. (on cost of winding wire)
Labour charges towards rewinding the 100%
coils complete with connections etc.,
complete.(on cost of winding wire)

296
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Sundries such as sleeves cotton tape, 40%


minolex paper, solution etc., with
transportion charges.
Less cost towards old winding wire kg 0.45
Rate per Each
18.1.5 Rewinding of electric motor upto 1 HP
single phase upto 1400 RPM of all
types and makes with copper wire,
overhauling with minor repairs, testing
for the original speed and no load
consumption .
a) Material
Suitable guage copper winding wire kg 2.7
fine quality
Labour charges towards removing of 5%
old unserviceable winding wire.(on
cost of winding wire)
Labour charges towards rewinding 12%
copper coils complete with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, 2%
minolex paper solution etc., with
transportation.
Less cost towards old winding wire kg 2.7
Rate per Each
18.1.6 Rewinding of electric motor 2 HP single
phase 1400 RPM of all types and
makes with copper wire, overhauling
with minor repairs, testing for the
original speed and no load
consumption.
a) Material
Suitable guage copper winding wire kg 3.2
fine quality
Labour charges towards removing of 5%
old unserviceable winding wire.(on
cost of winding wire)
Labour charges towards rewinding 12%
copper coils complete with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, 2%
minolex paper solution etc., with
transportation.
Less cost towards old winding wire kg 3.2
Rate per Each
18.1.7 Rewinding of electric motor 3 HP
three phase 1400 RPM of all types
and makes with copper wire,
overhauling with minor repairs, testing
for the original speed and no load
consumption .
a) Material
Suitable guage copper winding wire kg 4.5
fine quality

297
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Labour charges towards removing of 5%


old unserviceable winding wire.(on
cost of winding wire)
Labour charges towards rewinding 12%
copper coils complete with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, 2%
minolex paper solution etc., with
transportation.
Less cost towards old winding wire kg 4.5
Rate per Each
18.1.8 Rewinding of electric motor 5 HP three
phase 1400 RPM of all types and
makes with copper wire, overhauling
with minor repairs, testing for the
original speed and no load
consumption .
a) Material
Suitable guage copper winding wire kg 5.7
fine quality
Labour charges towards removing of 5%
old unserviceable winding wire.(on
cost of winding wire)
Labour charges towards rewinding 12%
copper coils complete with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, 2%
minolex paper solution etc., with
transportation.
Less cost towards old winding wire kg 5.7
Rate per Each
18.1.9 Rewinding of electric motor 7.5 HP
three phase 1400 RPM of all types
and makes with copper wire,
overhauling with minor repairs, testing
for the original speed and no load
consumption .
a) Material
Suitable guage copper winding wire kg 6.5
fine quality
Labour charges towards removing of 5%
old unserviceable winding wire.(on
cost of winding wire)
Labour charges towards rewinding 12%
copper coils complete with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, 2%
minolex paper solution etc., with
transportation.
Less cost towards old winding wire kg 6.5
Rate per Each

298
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

18.1.10 Rewinding of electric motor 10 HP


three phase 1400 RPM of all types
and makes with copper wire,
overhauling with minor repairs, testing
for the original speed and no load
consumption .
a) Material
Suitable guage copper winding wire kg 10
fine quality
Labour charges towards removing of 5%
old unserviceable winding wire.(on
cost of winding wire)
Labour charges towards rewinding 12%
copper coils complete with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, 2%
minolex paper solution etc., with
transportation.
Less cost towards old winding wire kg 10
Rate per Each
18.1.11 Rewinding of electric motor 12.50 HP
three phase 1400 RPM of all types
and makes with copper wire,
overhauling with minor repairs, testing
for the original speed and no load
consumption .
a) Material
Suitable guage copper winding wire kg 12
fine quality
Labour charges towards removing of 5%
old unserviceable winding wire.(on
cost of winding wire)
Labour charges towards rewinding 12%
copper coils complete with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, 2%
minolex paper solution etc., with
transportation.
Less cost towards old winding wire kg 12
Rate per Each
18.1.12 Rewinding of electric motor 15 HP
three phase 1400 RPM of all types
and makes with copper wire,
overhauling with minor repairs, testing
for the original speed and no load
consumption .
a) Material
Suitable guage copper winding wire kg 15
fine quality
Labour charges towards removing of 5%
old unserviceable winding wire.(on
cost of winding wire)

299
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Labour charges towards rewinding 12%


copper coils complete with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, 2%
minolex paper solution etc., with
transportation.
Less cost towards old winding wire kg 15
Rate per Each
18.1.13 Rewinding of electric motor 20 HP
three phase 1400 RPM of all types
and makes with copper wire,
overhauling with minor repairs, testing
for the original speed and no load
consumption.
a) Material
Suitable guage copper winding wire kg 18
fine quality
Labour charges towards removing of 5%
old unserviceable winding wire.(on
cost of winding wire)
Labour charges towards rewinding 12%
copper coils complete with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, 2%
minolex paper solution etc., with
transportation.
Less cost towards old winding wire kg 18
Rate per Each
18.1.14 Rewinding of submersible motor upto
15 HP three phase of all types and
makes with copper wire, overhauling
with minor repairs, testing for the
original speed and no load
consumption .
a) Material
PVC insulated copper winding wire of kg 18
suitable guage.
Labour charges towards removing of 10%
old unserviceable winding wire.(on
cost of winding wire)
Labour charges towards rewinding 15%
copper coils complete with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, 5%
minolex paper solution etc., with
transportation.
Less cost for winding wire kg 18
Rate per Each
Bldngs_Elec- 18.2
18-2 Bearings

300
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

18.2.1 Replacing the existing bearing of


approved make for electric motor
single phase / 3 phase AC upto 1 HP of
all types with due alignment of the
shaft and tested.
a) Material
Ball Bearings suitable for 1 HP Motor each 1
inclusive of taxes
Labour charges for removing the 50%
existing unserviceable bearing and
fixing the new ball bearing with special
T&P. (on cost of Ball Bearing)
Transportation and Rounding off
Rate per Each
18.2.2 Replacing the existing bearing of
approved make for electric motor
single phase / 3 phase AC upto 2 to 3
HP of all types with due alignment of
the shaft and tested.
a) Material
Ball Bearings suitable for 2 to 3 HP each 1
Motor inclusive of taxes
Labour charges for removing the 50%
existing unserviceable bearing and
fixing the new ball bearing with special
T&P. (on cost of Ball Bearing)
Transportation and Rounding off
Rate per Each
18.2.3 Replacing the existing bearing of
approved make for electric motor
single phase / 3 phase AC upto 5 to 7.5
HP of all types with due alignment of
the shaft and tested.
a) Material
Ball Bearings suitable for 5 to 7.5 HP each 1
Motor inclusive of taxes
Labour charges for removing the 50%
existing unserviceable bearing and
fixing the new ball bearing with special
T&P. (on cost of Ball Bearing)
Transportation and Rounding off
Rate per Each
18.2.4 Replacing the existing bearing of
approved make for electric motor
single phase / 3 phase AC upto 10 to
12.5 HP of all types with due
alignment of the shaft and tested.
a) Material
Ball Bearings suitable for 5 to 7.5 HP each 1
Motor inclusive of taxes

301
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Labour charges for removing the 50%


existing unserviceable bearing and
fixing the new ball bearing with special
T&P. (on cost of Ball Bearing)
Transportation and Rounding off
Rate per Each
18.2.5 Replacing the existing bearing of
approved make for electric motor
single phase / 3 phase AC upto 15 to
20 HP of all types with due alignment
of the shaft and tested.
a) Material
Ball Bearings suitable for 5 to 7.5 HP each 1
Motor inclusive of taxes
Labour charges for removing the 50%
existing unserviceable bearing and
fixing the new ball bearing with special
T&P. (on cost of Ball Bearing)
Transportation and Rounding off
Rate per Each
18.2.6 Replacing the ball bearing of table /
cabin / pedestal / ceiling / exhaust fan
complete with alignment of shaft and
tested.
a) Material
Ball Bearings suitable for table / cabin / each 1
ceiling / Exhaust Fan inclusive of taxes
Labour charges for removing the 50%
existing unserviceable bearing and
fixing the new ball bearing with special
T&P. (on cost of Ball Bearing)
Transportation and Rounding off
Rate per Each
18.2.7 Replacing the ball bearing of bush /
rubber / ring washers for fan mortar
complete with alignment of shaft and
tested.
a) Material
Cost of GM / Bush / Rubber / Ring each 1
washer etc.,
Labour charges for removing the 50%
existing unserviceable bush/ ring
washer and fixing the new with special
T&P.(on cost of material)
Rounding Off
Rate per Each
18.2.8 Replacing the existing capacitor of
table / cabin / pedestal / ceiling /
exhaust fan complete with wiring.
a) Material
Cost of 2.5 / 3.5 mfd condensor each 1
suitable for ceiling / pedastal Exhaust
Fan

302
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

b) Labour charges for removing and


refixing
Semi Skilled Electrician day 0.1
Rounding Off
Rate per Each
Note : Labour considered for 10 jobs /
day

303
STANDARD DATA-ELECTRICAL ITEMS – BUS BARS

12 BUS BARS

12.1 Copper Bus Bars

12.1.1 Supply and fabrication and erection of following sizes of 4Nos of copper bus bars in the existing sheet steel enclosure with resin cast
insulator supports etc., complete including cost and conveyance of all materials all labour charges.

D.No. Size of each bar No.of 1 Current Weight / Rate per Kg Cost of Cost of Labour charges for Total Rounding
in mm mtr rating in mtr in Kg copper 8Nos. fabrication and Amount off
bars each bar bars Resin cast fixing of insulators mtr
insulator. providing with PVC
@ Rs.35/- heat shrinkable
Each sleeves.

a 20x3 4 Nos 220A 0.529 Kg


b 20x6 4 Nos 300A 1.072

c 25x3 4 Nos 270A 0.663

d 25x6 4 Nos 350A 1.34

e 30x6 4 Nos 400A 1.608

f 40x6 4 Nos 520A 2.144

g 50x6 4 Nos 630A 2.68

h 60x6 4 Nos 760A 3.216

i 75x6 4 Nos 970A 4.02

j 100x6 4 Nos 1380A 5.36

Note : Labour Charges @ 20 % on Copper cost is allowed

304
STANDARD DATA-ELECTRICAL ITEMS – BUS BARS

Aluminum Bus
12.2 Bars

12.2.1 Supply and fabrication and erection of following sizes of 4Nos of aluminum bus bars in the existing sheet steel enclosure with resin
cast insulator supports etc., complete including cost and conveyance of all materials all labour charges.

D.No. Size of each bar No.of 1 Current Weight / Rate per Kg Cost of Cost of Labour charges for Total Rounding
in mm mtr rating in mtr in Kg copper 8Nos. fabrication and Amount off
bars each bar bars Resin cast fixing of insulators mtr
insulator. providing with PVC
@ Rs.35/- heat shrinkable
Each sleeves.

a 20x3 4 Nos 145A 0.161 Kg

b 20x6 4 Nos 195A 0.322

c 25x3 4 Nos 180A 0.201

d 25x6 4 Nos 230A 0.402

e 40x6 4 Nos 350A 0.644

f 50x6 4 Nos 425A 0.805

g 60x6 4 Nos 500A 0.966

h 75x6 4 Nos 680A 1.207

j 100x6 4 Nos 900A 1.61


Note : Labour charges are as per the rates allowed for Copper bus bar since, there is no difference in the requirement of Labour

305
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION

DATA ANALYSIS FOR TEMPORARY ILLUMINATION


Storage
Transport
charges
Interest ation
Mainten @ 1%
@ 12% charges @
Depreciation: ance on Hire
Data Life in on Labour 2% on
Description Capital Cost Capital cost 50% of capital charges
No. days Capital charges capital
/Life in days deprecia cost/N per day
cost/days cost/No.o
tion o.of
in a year f days in a
days in
year
a year
1 2 3 4 5 6 7 8 9 10 11
16 TEMPORARY ILLUMINATION
16.1 Hire charges for Temporary 1000 Nos 1 year i.e 1.Skill
illumination, consisting of 6.2 strip bulbs & 30 60 days electrician
lights (navar patta) complete with Mtrs 7/20 1.Helper
1000 Nos required wire leads duly service wire
erected and dismantled without
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
16.2 Hire charges for Temporary 1000 Nos 1 year i.e 1.Skill
illumination, consisting of 6.2 strip bulbs & 30 60 days electrician
lights (navar patta) complete with Mtrs 7/20 1.1Helper
1000 Nos required wire leads duly service wire
erected and dismantled with
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.

306
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION

16.3 Hire charges for Temporary 1 No tube 3years i.e 0.06 Skill
illumination, consisting of tube light light, 4 Mtrs 3 x 60 = electrician
with patti type 4'-40W complete with 7/20 service 180 days 0.06Helper
required wire leads duly erected and wire
dismantled without scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
16.4 Hire charges for Temporary 1 No tube 3years i.e 0.06 Skill
illumination, consisting of tube light light, 4 Mtrs 3 x 60 = electrician
with patti type 4'-40W complete with 7/20 service 180 days 0.10Helper
required wire leads duly erected and wire
dismantled with scaffolding including
cost and conveyance of all materials
and labour charges etc., complete for
one day.
16.5 a Hire charges for Temporary 1 No 1000W 3years i.e 0.25 Skill
illumination, consisting of flood light Halogen, 30 3 x 60 = electrician
1000W hallogen with lamp complete Mtrs 7/20 180 days 0.25Helper
with required wire leads duly erected service wire
and dismantled without scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
16.5 b Hire charges for Temporary 1 No 500W 3years i.e 0.25 Skill
illumination, consisting of flood light Halogen, 30 3 x 60 = electrician
500W hallogen with lamp complete Mtrs 7/20 180 days 0.25Helper
with required wire leads duly erected service wire
and dismantled without scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.

307
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION

16.5 c Hire charges for Temporary 1 No 250W 3years i.e 0.25 Skill
illumination, consisting of flood light Metal halide, 3 x 60 = electrician
250W metal halide fitting with lamp 30 Mtrs 180 days 0.25Helper
complete with required wire leads 7/20 service
duly erected and dismantled without wire
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
16.5 5 Hire charges for Temporary 1 No 400W 3years i.e 0.25 Skill
illumination, consisting of flood light Metal halide, 3 x 60 = electrician
400W metal halide fitting with lamp 30 Mtrs 180 days 0.25Helper
complete with required wire leads 7/20 service
duly erected and dismantled without wire
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
16.6 a Hire charges for Temporary 1 No 1000W 3years i.e 0.25 Skill
illumination, consisting of flood light Halogen, 30 3 x 60 = electrician
1000W hallogen with lamp complete Mtrs 7/20 180 days 0.30Helper
with required wire leads duly erected service wire
and dismantled with scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
16.6 b Hire charges for Temporary 1 No 500W 3years i.e 0.25 Skill
illumination, consisting of flood light Halogen, 30 3 x 60 = electrician
500W hallogen with lamp complete Mtrs 7/20 180 days 0.30Helper
with required wire leads duly erected service wire
and dismantled with scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.

308
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION

16.6 c Hire charges for Temporary 1 No 250W 3years i.e 0.25 Skill
illumination, consisting of flood light Metal halide, 3 x 60 = electrician
250W metal halide fitting with lamp 30 Mtrs 180 days 0.30Helper
complete with required wire leads 7/20 service
duly erected and dismantled with wire
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
16.6 d Hire charges for Temporary 1 No 400W 3years i.e 0.25 Skill
illumination, consisting of flood light Metal halide, 3 x 60 = electrician
400W metal halide fitting with lamp 30 Mtrs 180 days 0.30
complete with required wire leads 7/20 service Helper
duly erected and dismantled with wire
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
16.7 Hire charges for Temporary 1000 Nos 1 year i.e 0.5 Skill
illumination, consisting of white / bulbs & 30 60 days electrician
colour series light 6.2v complete with Mtrs 7/20 0.5Helper
1000 Nos. with required wire leads service wire
duly erected and dismantled without
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
16.8 Hire charges for Temporary 1000 Nos 1 year i.e 0.5 Skill
illumination, consisting of white / bulbs & 30 60 days electrician
colour series light 6.2v complete with Mtrs 7/20 1.0 Helper
1000 Nos. with required wire leads service wire
duly erected and dismantled with
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.

309
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION

16.9 Hire charges for Providing and fixing Cost of 10 5 years 0.25
rotating machine to give running KW rotating i.e 5 x 30 Helper
effect to strip lights and miniature machine = 150
lights upto a load of 10KW with days
required wire leads duly dismantled
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
16.10 Hire charges for Providing oscillating 18" pedestal 3years i.e 0.10
type pedestal fan 16" / 18" with fan, 30 3 x 40 = Helper
connected wire leads duly dismantled Mtrs 7/20 120 days
including cost and conveyance of all service wire
materials and labour charges etc.,
complete for one day.
16.1 Hire charges for Providing air cooler Air cooler, 3years i.e 0.20 semi-
connected with necessary mains 30 Mtrs 3 x 40 = skilled
switch gear with continues earth lead 7/20 service 120 days electrician
during function duly dismantled wire
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
16.12 Hire charges for Providing 1.5 ton/2.0 Air 8years 1 skilled
ton capacity window air conditioning conditioned, i.e. 8 x 15 electrician,
unit complete with suitable stabilizer stabilizer = 120 2 Helpers,
with temporary frame and fabrication days 1 carpenter
work and required materials achieve
cooling, temperature connected with
necessary mains switch gear with
continues earth lead during function
duly dismantled including cost and
conveyance of all materials and
labour charges etc., complete for one
day.

310
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION

16.1 Hire charges for Providing temporary 16 Amps 5 in 3years i.e 0.05 semi-
plug point with 5 pin 6 Amps/16 Amps one power 3 x 40 = skilled
with necessary mains switch gear with plug, 30 120 days electrician
continues earth lead during function Mtrs 7/20
duly dismantled including cost and service wire
conveyance of all materials and
labour charges etc., complete for one
day.
Note : 1) The rates are for one
glowing/working day.
2) Allow 50% of rate for each day upto
3 days (i.e. 2nd and 3rd day)
3) For each additional day after 3
days, but not exceeding 15 days,
allow 25 % rate of glowing/working
days
4) For more than 15 days allow 10%
per day but total rental charges shall
not exceeded 80% of capital cost of
item.
16.14 a Hire charges for supply and 125 KVA DG 10years 1.Skill
maintaining 125 KVA, 415 voltage, 50 Set, 200 i.e 10 x Electrician
C/s AC generating set with all Amps main 60 = 600
standard accessories such as control switch days
panel, batteries etc complete for one
day excluding cost of fuel.
16.14 b Hire charges for supply and 82.5 KVA DG 10years 1.Skill
maintaining 82.5 KVA, 415 voltage, 50 Set, 200 i.e 10 x Electrician,
C/s AC generating set with all Amps main 60 = 600
standard accessories such as control switch days
panel, batteries etc complete for one
day excluding cost of fuel.

311
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION

16.14 c Hire charges for supply and 62.5 KVA DG 10years 1.Skill
maintaining 62.5 KVA, 415 voltage, 50 Set, 200 i.e 10 x Electrician,
C/s AC generating set with all Amps main 60 = 600
standard accessories such as control switch days
panel, batteries etc complete for one
day excluding cost of fuel.
16.14 d Hire charges for supply and 30 KVA DG 10years 1.Skill
maintaining 30 KVA, 415 voltage, 50 Set, 100 i.e 10 x Electrician,
C/s AC generating set with all Amps main 60 = 600
standard accessories such as control switch days
panel, batteries etc complete for one
day excluding cost of fuel.
16.14 e Hire charges for supply and 5 to 15 KVA 10years 1.Skill
maintaining 5 to 15 KVA, 415 voltage, DG Set, 63 i.e 10 x Electrician,
50 C/s AC generating set with all Amps main 60 = 600
standard accessories such as control switch days
panel, batteries etc complete for one
day excluding cost of fuel.
16.2 Hire charges for supply and 125 KVA DG 10years 1.Skill
maintaining of 125 KVA DG set with Set, acoustic i.e 10 x Electrician,
acoustic enclosure as per IS enclosure, 60 = 600
specification with DCM 4 wheeler 200 Amps days
vehicle with all standard accessories main switch
such as control panel, batteries etc with 4
complete for one day excluding cost wheeler
of fuel. DCM vehicle.
NOTE: 1) The above rates are applicable per one day only.
2) For subsequent days the above rte shall be reduced by 25% after 8th day
reduce the rate by 50%
3) Diesel cost will be paid extra for running hours at the prevailing rates.
4) For test run,. The minimum req2uirement of the fuel shall be born by the
contractor.
5) The D.G.set should be in good condition and the life of set shall not b e beyond
10 years

312
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION

16.16 a Hire charges for supply and 2 of 6 sq mm 3years i.e 0.015


maintaining towards supply and run WPTC cable 3 x 60 = Helper
of 2 of 2.5 sq mm to 6 sq mm 1 mtr 180 days
VIR/WPTC/WPSC cable with necessary
terminations etc., complete for one
day.
16.16 b Hire charges for supply and 2 of 10 sq 3years i.e 0.02
maintaining towards supply and run mm WPTC 3 x 60 = Helper
of 2 of 10 sq mm VIR/WPTC/WPSC cable 1 mtr 180 days
cable with necessary terminations
etc., complete for one day.
16.16 c Hire charges for supply and 35 sq mm x 3years i.e 0.05
maintaining towards supply and run 3 1/2 UG 3 x 60 = Helper
of 35 sq mm x 3 1/2 core UG cable cable 1 mtr 180 days
with necessary terminations etc.,
complete for one day.
16.16 d Hire charges for supply and 50 sq mm x 3years i.e 0.05
maintaining towards supply and run 3 1/2 UG 3 x 60 = Helper
of 50 sq mm x 3 1/2 core UG cable cable 1 mtr 180 days
with necessary terminations etc.,
complete for one day.
16.16 e Hire charges for supply and 95 sq mm x 3years i.e 0.05
maintaining towards supply and run 3 1/2 UG 3 x 60 = Helper
of 95 sq mm x 3 1/2 core UG cable cable 1 mtr 180 days
with necessary terminations etc.,
complete for one day.
16.16 f Hire charges for supply and 120 sq mm x 3years i.e 0.05
maintaining towards supply and run 3 1/2 UG 3 x 60 = Helper
of 120 sq mm x 3 1/2 core UG cable cable 1 mtr 180 days
with necessary terminations etc.,
complete for one day.
16.16 g Hire charges for supply and 185 sq mm x 3years i.e 0.05
maintaining towards supply and run 3 1/2 UG 3 x 60 = Helper
of 185 sq mm x 3 1/2 core UG cable cable 1 mtr 180 days
with necessary terminations etc.,
complete for one day.

313
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION

16.2 Hire charges for providing industrial 250 Amps 10years 0.5 Skilled
type panel board consisting of bus bar bus bar, 250 i.e 10 x electrician,
chamber with 200/250 amps TPN/MCCB, 15 = 150 1 Helper
incoming TP/MCCB as incomers 12 nos 100 days
switch, 12 nos 100 amps fuse unit, Amps fuse
earth wire erected and dismantled all units
accessories etc., complete for
distribution for one day.
16.18 a Hire charges for supply and 100 Amps 10years 0.125
maintaining towards supply and fixing COS/ TPN i.e 10 x Skilled
of 100 amps 4 pole change over 15 = 150 electrician,
switch/TPN switches including days 0.125
erection and dismantled all Helper
accessories etc., complete for one
day.
16.18 b Hire charges for supply and 200 Amps 10years 0.125
maintaining towards supply and fixing COS/ TPN i.e 10 x Skilled
of 200 amps 4 pole change over 15 = 150 electrician,
switch/TPN switches including days 0.125
erection and dismantled all Helper
accessories etc., complete for one
day.
16.18 c Hire charges for supply and 400 Amps 10years 0.2 Skilled
maintaining towards supply and fixing COS/ TPN i.e 10 x electrician,
of 400 amps 4 pole change over 15 = 150 0.2 Helper
switch/TPN switches including days
erection and dismantled all
accessories etc., complete for one
day.

314
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION

16.19 a Hire charges for supply and erection 24 Mtrs 80/ 15years 0.5 fitter,
and dismantle of 4 pole structure of 4 50mm C i.e 15 x 0.5 skilled
of 20' GI pipe of 50/80mm structure class GI pipe, 12 = 180 electrician,
complete necessary cross arms and 50/50 MS days 2 Helpers,
hardware materials for fixing cross arms 54 Cum.
halogen/ metal halide fitting with weight of 72
suitable earthing arrangements Kgs & 1 No.
including cost conveyance of all coil earthing
materials and labour charges for
maintaining one day.
16.19 b Hire charges for supply and erection 36 Mtrs 15years 0.5 fitter,
and dismantle of 4 pole structure of 4 80/50mm C i.e 15 x 0.5 skilled
of 30' GI pipe of 50/80mm structure class GI pipe, 12 = 180 electrician,
complete necessary cross arms and 50/50 MS days 2 Helpers,
hardware materials for fixing cross arms 54 Cum.
halogen/ metal halide fitting with weight of 72
suitable earthing arrangements Kgs & 1
including cost conveyance of all No.coil
materials and labour charges for earthing
maintaining one day.
NOTE: 1) The rates are for one glowing/working day.
2) Allow 50% of rate for each day upto 3 days (i.e. 2nd and 3rd day)
3) For each additional day after 3 days, but not exceeding 15 days, allow 25 % rate
of glowing/working days
4) For more than 15 days allow 10% per day but total rental charges shall not
exceeded 80% of capital cost of item.
Note : Service Tax and VAT as applicable shall be extra
for all Items.

315
STANDARD DATA-ANNEXURE

GOVERNMENT OF ANDHRA PRADESH


ABSTRACT
Irrigation & CAD Department – Adoption of Revision and Updating of Andhra Pradesh Standard data in all
Engineering/Public Works Department and other organisations – Orders – Issued.
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
IRRIGATION & CAD (PW- REFORMS) DEPARTMENT

G.O.Ms. No. 49 Dated: the 2nd March, 2009


Read the following:-

1. G.O.Rt.No.7326 , GA (GPM/AR) Department dated 26.10.2005


2. From the Director General D.O.Letter.No.CGG/AP Standard Data/2006-07, dated
8.12.2006
3. Govt.Memo.No.36710/Reforms/I&CAD(PW) Dept., dated 22.6.2007
4. U.O.Note.No.36710/Reforms/2005, I&CAD (PW) Dpt., dt.29.6.2007
5. Govt.Memo.No.36710/Reforms/2005, I&CAD Dept., dated 10.3.2008
6. From ENC (AW)/IW I&CAD Dept., Letter.No.ENC/IW/P&M/EE.1/DEE.8 /19200-98, dated
21.4.2008

ORDER:
The basic components for preparing any estimate are Standard Specifications, Standard Data,
and Schedule of Rates for construction materials, skilled and un-skilled labour and hire charges of
machinery utilized on works. To get the work done, as per the standard specifications, required
quantities of recommended materials, requirement of specific need based manpower, deployment of
proper utility based machinery and duration of its utilization are to be observed and quantified for
each unit of work, and this is called Standard Data. Thus, the Standard Data gives the details of
various inputs in terms of quantities required for one Unit of any work. Schedule of rates for material,
skilled and unskilled labour are fixed and revised by the Board of Chief Engineers’ once in a year and
these are called Standard Schedule of Rates. When the Standard Schedule of Rates and Hire charges
of machinery are incorporated in the inputs of Standard Data and Standard Schedule of Rates it will
have direct bearing on the preparation of project Estimates and consequent finalization of Tenders.
2. The existing AP Standard Data for various construction items were based on observations made
several decades back mostly by utilizing manpower for execution of all items of works, and
deployment of machinery was at the barest minimum. The advent of latest machinery and their
extensive use has changed the structure and methodology of data formulation and rate structure.
There is a need to revise the present “Standard Data” for all items of worksdealing with Public works.
Realizing the urgency and importance to haverealistic data, Government in the GO.Rt.No.7326 G.A
(GPM & AR) Departmentdated 26-10-2005 constituted a High Level Committee under the
chairmanshipof Special Chief Secretary, General Administration (GPM&AR) Department, to advise on
“Updating and Revising the A.P.Standard Data”. A project for Standard Data (revision) and Schedule of
Rates was conceived and entrusted to the Centre for Good Governance. Keeping in view the strategy,
factors considered and classification of works, a number of High Level Committee meetings and
review meetings were conducted at Centre for Good Governance/ A.P.Secretariat and in the offices of
concerned Engineers-in-Chief I&CAD, Public Health, Panchayati Raj and Roads & Buildings
Departments etc. Their specific views, suggestions and recommendations were taken into account,
besides collecting the data from various sources while finalizing the Draft AP standard Data and
Standard Schedule of Rates. This has been cleared by the Board of Chief Engineers’ and finally by the
High level Committee. The Standard Data has been revised and updated in four parts considering
nature of work, location of work and magnitude of work as indicated below.
1. PART – I : Irrigation & Command Area Development.
2. PART- II : Roads & Bridges.
3. PART-III : Buildings
4. PART-IV : Drinking Water Supply Schemes.
3. The revision of Standard Data and Schedule of Rates in respect of works items of Irrigation
Department has been taken up by the SPIU (Irrigation) and completed as per the C.W.C guidelines and
B.I.S standards and also observations and recommendations made by the High Level Committee. In

316
STANDARD DATA-ANNEXURE

respect of other Departments, MORTH data is adopted for Roads & Bridges, where higher capacity
machinery can be deployed and MORD data is adopted for Roads & Bridges in Rural areas. For other
works data as per MORTH, MORD, and C.P.W.D. etc., is adopted. The comparative estimates have
been prepared by the T.R. &B Dept. , Engineering-in-Chief (Irrigation) and MA & UD Department for
various types of works of a magnitude of Rs.15-20 crores, based upon the earlier data and the newly
revised and proposed data .
4. After detailed deliberations and discussion on the above issue, the Govt. accept the
recommendations of Board of Chief Engineers and High level Committee and accordingly issue the
orders for adoption of the Revised and Updated Standard data in all Engineering/ Public works
Department and other organisations in four parts considering nature of work, location of work and
magnitude of work as indicated below. The four parts of Standard Data booklets are forwarded to
Engineer-in-Chief (AW), who in turn will publish the authenticated version and circulate a copy to all
works Departments.
1. PART – I : Irrigation & Command Area Development.
2. PART- II : Roads & Bridges.
3. PART-III : Buildings
4. PART-IV : Drinking Water Supply Schemes.
5. The Revised Data now approved is to be adopted by all Engineering Departments/ all Public
Works Department and other organisations, duly superseding all the earlier orders issued on the
subject. 6. These orders shall come into force from the date of issue.
7. This order issues with the concurrence of Finance Department vide their
U.O.No.5532/520/Exp.PW.I Dept/08, dated 13-5-2008.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)

RAJIV RANJAN MISHRA


SECRETARY TO GOVERNMENT
To
All the Engineer-in-Chief of Irrigation & CAD Department.
All the Chief Engineers of Irrigation & CAD Department.
The Commissioner, Commissioner of Tenders,
The Engineer-in-Chief, PR &RD Department, Hyderabad.
The Engineer-in-Chief (R&B) Admn.,Dept., Hyderabad.
The Engineer-in-Chief (PH) Hyderabad.
Copy to:
All the Collectors & Dist. Magistrate of Andhra Pradesh
All Sections in Irrign. & CAD (PW/Irrgn.) Dept.
The Accountant General Andhra Pradesh Hyderabad.
The G.A. (Cabinet) Dept. w.r.t. U.O.No.79/2009, dated 17-2-2009.
The G.A. (GPM&AR) Dept.
The Finance (W&P) Dept.
The P.S. to Ministers (PR & RD/ MA &UD/ T.R. & B / Housing )
The P.S. to Prl. Secy. (SKJ)/ P.S. to Secretary (AD)/ P.S. to Secretary (RRM)
The P.S. to Prl. Secretary, Housing/P.S. to Prl. Secy, M.A. & U.D. / P.S. to
Secretary, T.R.& B / P.S. to Prl. Secretary, PR & RD./P.S. to Secretary , Housing.
All the Advisors of Irrgn. & CAD Dept.
SF/SC.
// FORWARDED::BY ORDER//
SECTION OFFICER

317

You might also like