Professional Documents
Culture Documents
The term unlined tunnel is used to describe hydropower tunnels where water is in direct contact with the rock, that
means, only limited parts of the tunnel are lined with concrete or shotcrete to protect against local tunnel collapses
or major rock falls.
The benefit of using unlined tunnels and/or shafts is a significant reduction in construction costs and
construction time. Unlined tunnels and shafts with heads of more than 1000 m function satisfactorily. This has
been made possible by 100 years of development in design, construction and operation, and Norwegian experience
has made an important contribution. Today’s design, construction and operation of unlined pressure tunnels and
shafts are discussed in this paper.
A
This can easily be explained, as the shortest distance from the cone to the surface is only 17 m, which compared with the required 55 m,
is far too short (see Fig. 3).
www.RockMass.net
The design of unlined hydropower tunnels and shafts:100 years of Norwegian experience
from the shaft was observed subsequently, and the powerplant has now been in operation for almost 100 years
[Selmer-Olsen, 19703; Broch, 19824 and 19845].
Fig. 2.
The development of unlined
pressure shafts and tunnels in
Norway [updated from Broch,
19845, 20102].
The failures at Fossmark, and to some degree, also at Askora, showed that the rule-of-thumb was not sufficient
for the design. The lowest principal stresses can sometimes be different from the estimated one. In subsequent years,
the common practice has been to take stress measurements close to the location of the penstock cone, to ensure that
the rock stresses are sufficient. If not, a new location for the cones is found after stress measurements.
The failure at Bjornstokk plant in 2016 took place as a result of unexpected, low vertical stresses (see Fig. 9).
This might have been avoided, had stress measurements been taken. The failure caused two landslides of 5000 m3
and 130 000 m3, at distances of 400 m and 600 m from the tunnel.
Both the rule-of-thumb (in Fig. 5) and the diagram in Fig. 6 are still being used for quick, preliminary estimations.
Table 1: Rates of tunnel watering up and dewatering used in 1.4 Tunnel support
many Norwegian unlined power tunnels and shafts
The main purpose of rock support is to reinforce unstable
Operation Increase/decrease in head ground conditions in the tunnel during excavation, to obtain
per hour per day safe working conditions for the crew (often referred to as
First watering-up 10 m(a) max. 200 m initial or temporary support) and a stable tunnel during the
Later watering-up 15 m(b) max. 300 m tunnel’s operating life (called final or permanent support).
Dewatering 10–15 m (c)
max. 250 m Appropriate rock support in a tunnel may be chosen and
tailored according to the ground conditions encountered
(a)
Stop infilling, min. 2 hours for observations and measurements per
100 m head increase (10kg/cm2).
during construction. This requires follow-up of the
(b)
Stop infilling, min. 2 hours per 150 m head increase. excavation works by experienced engineering geologists.
(c)
Some stops during dewatering to be evaluated for each tunnel. In Norwegian unlined tunnels, the underlying design
philosophy for operation of the plant is that minor rockfalls can be tolerated. As long as rockfalls in local parts of
the tunnel do not develop significantly and increase the head loss, a reasonable number of minor rock falls spread
out along the tunnel will not harm it or disturb operation of the hydro station. If necessary, rockfalls may be removed
during later inspection and maintenance.
Normally a rock trap is located at the downstream end of the headrace tunnel to prevent rock fragments entering
the turbine.
B
As described in the examples in Section 3, some tuffs have been shown to have swelling properties; swelling that is not easily discovered
by normal testing procedures.
References
1. Broch, E., “Designing and excavating underground powerplants”; Water Power & Dam Construction Vol.
34, No.4, 1982.
2. Broch, E., “Tunnels and underground works for hydropower projects, - lessons learned in home country and
from projects worldwide”. Muir Wood Lecture 2010. International Tunnelling and Underground Space
Technology 2010.
3. Selmer-Olsen, R., “Experience with unlined pressure shafts in Norway”. In: Large permanent underground
openings, Oslo, Norway. Universitetsforlaget, Oslo; 1970.
4. Broch, E., “The development of unlined pressure shafts and tunnels in Norway”. In: Rock mechanics: Caverns
and pressure shafts, published by A.A. Balkema; 1982.
5. Broch, E., “Development of Unlined Pressure Shafts and Tunnels in Norway”, Underground Space, Vol. 8,
No. 3; 1984.
6. Brekke, T.L., Bjorlykke, S. and Blindheim, O.T., “Finite element analysis of the Byrte unlined pressure
shaft failure”. In: Large permanent underground openings. Universitetsforlaget, Oslo, Norway; 1970.
7. Bergh-Christensen, J., “Failure of the unlined pressure tunnel at the Askora” (in Norwegian). Annual national
rock construction conference (Fjellsprengningsteknikk - Bergmekanikk), Trondheim, Norway; 1975.
8. Panthi, K. and Basnet, E.C.B., “Review of the major failure cases of unlined pressure shafts/tunnels of
Norwegian projects”; Hydro Nepal, No. 18, January 2016.
9. Vogt, J.H.L., “Pressure tunnels and geology” (in Norwegian) Report No. 93, Norwegian Geological Survey;
1922.
10. NGI, “Overview of Norwegian unlined tunnels and shafts with water pressures more than 100 m, plus a few
with lower pressures”, Norwegian Geotechnical Institute, Internal Report No. 54402 (in Norwegian); 1972.
11. Garshol, K. and Blindheim, T., “Fosmark hydropower plant. Leakage from pressure shaft” (in Norwegian).
Annual national rock construction conference (Fjellsprengningsteknikk - Bergmekanikk); 1988.
12. Bergh-Christensen, J. and Dannevig, N.T., “Engineering geological evaluations of the unlined pressure shaft
at the Mauranger hydropower plant” (in Norwegian). Unpublished report. Geoteam A/S, Oslo, Norway; 1971.
13. Broch, E., “Design of unlined or concrete lined high pressure tunnels in topographical complicated areas”;
Water Power & Dam Construction; Vol. 36, No.11; 1984.
14. Palmström, A. and Buen, B., “Landslides caused by rupture in hydropower tunnel” (in Norwegian); GEO
Magazine; March 2017.
15. Palmström, A. and Schanche, K., “Design features at Tjodan save time and money”; Water Power & Dam
Construction, June 1987.
16. Dahloe, T.S., Bergh-Christensen, J. and Broch, E., “A review of Norwegian high-pressure concrete plugs”.
Proceedings, Hydropower 92, Norway. Published by A.A. Balkema; 1992.
17. Broch, E., “Sharing experience with concrete plugs in high pressure tunnels”, Hydro Review Worldwide, Vol.
7, No. 4; 1999.
18. Palmström, A. and Stille, H., Chapter 8.5.2 in: Rock Engineering, 2nd Edition; ICE publishing, London, UK;
2015.
19. Hope, J., Palmström, A. and Finnerud, K., “Rebuilding of the 70 years old Nore I power plant”,
Proceedings, Hydropower 97, Trondheim, Norway; 1997.
20. Buen, B. and Palmström, A., “Design and supervision unlined hydropower shafts and tunnels with head up
to 590 meters”, Proceedings, Symposium on Rock mechanics: caverns and pressure shafts. Published by A.A.
Balkema, Netherlands; 1982.
21. Palmström, A., “Norwegian design and construction experience of unlined pressure shafts and tunnels”,
Proceedings, Hydropower 87, Oslo, Norway; 1987.
22. Carter, T.G., Castro, S.O., Carvalho, J.L., Hattersley, D., Wood, K., Barone, F.S., Yuen, C.M.K. and
Giraldo, D., “Tunnelling Issues of Chilean Tertiary Volcaniclastic Rocks”, Proceedings, MIR 2010. XIII
Ciclo di conferenze di Meccanica ed Ingegneria delle Rocce, Torino, Italy; November 2010.
Dr Arild Palmström, a Geological Engineer, is retired from RockMass as, Norway. He has worked on numerous
hydropower projects, road tunnels and subsea tunnel projects in Europe, Asia and South America. He has
contributed more than 50 journal articles, and written two handbooks on rock engineering, as well as the textbook
Rock Engineering (2015)
Dr Einar Broch retired as a Professor in Geological Engineering from the Norwegian University of Science and
Technology. He is former President of the International Tunnelling Association (1986-89), and former editor of the
journal Tunnelling and Underground Space Technology where he worked from 1986 to 2011 and has been
involved in hydropower projects in 15 countries
Department of Geoscience and Petroleum, Norwegian University of Science and Technology, Sem Sælands vei 1,
N-7491, Norway