Professional Documents
Culture Documents
Scholars' Mine
International Conference on Case Histories in (1988) - Second International Conference on Case
Geotechnical Engineering Histories in Geotechnical Engineering
Jun 1st
Joseph L. Kauschinger
Tufts University, Medford, Massachusetts
Antonio C. Doria
Novatecna, San Paulo, Brazil
Edward B. Perry
U.S. Army Engineer Waterways Experiment Station, Vicksburg, Mississippi
Recommended Citation
Guatteri, Giorgio; Kauschinger, Joseph L.; Doria, Antonio C.; and Perry, Edward B., "Advances in the Construction and Design of Jet
Grouting Methods in South America" (1988). International Conference on Case Histories in Geotechnical Engineering. 3.
https://scholarsmine.mst.edu/icchge/2icchge/icchge-session5/3
This Article - Conference proceedings is brought to you for free and open access by Scholars' Mine. It has been accepted for inclusion in International
Conference on Case Histories in Geotechnical Engineering by an authorized administrator of Scholars' Mine. This work is protected by U. S. Copyright
Law. Unauthorized use including reproduction for redistribution requires the permission of the copyright holder. For more information, please contact
scholarsmine@mst.edu.
Proceedings: Second International Conference on Case Histories in Geotechnical Engineering, June 1-5, 1988, St. Louis, Mo., Paper No. 5.32
SYNOPSIS: This paper presents a brief historical development of the two most popular jet grouting
methods used in South America, namely, the chemical churning pile method (CCP) and jumbo jet grout-
ing. Advantages and limitations of each procedure are cited. A brief discussion follows covering
the history of CCP jet grouting in South America. Field trials performed to improve the design
methodology and construction of CCP and jumbo jet grouted columns are presented. Finally, three
case histories are presented to illustrate the use of jumbo jet grouting where limited head room
exists, jet grouting in close proximity to pile supported structures, formation of a diaphragm wall
in gravelly soil with boulders. The paper closes with a short discussion of a recent tunnel project
in which horizontal jet grouting is used as the temporary tunnel support.
1037
Second International Conference on Case Histories in Geotechnical Engineering
Missouri University of Science and Technology
http://ICCHGE1984-2013.mst.edu
large injectors (1.8 to 2.4 mm diameter). The 720,0 . _.....,.....""".....'""'~
CCP technique originally proposed by Nakanishi
and later modified by Colla is the CCP jet
grouting method presently used in South Ameri- N.A.
SILTY
ca by Novatecna. 717,0~ CLAY H
JET GROUTING DEVELOPMENTS IN SOUTH AMERICA: TABLE I CCP Jet Grouting Parameters For
Repair of Sanegran Tunnel
CCP jet grouting was first introduced in South
America in 1980 by Novatecna Construction Ltd.
of Sao Paulo, Brasil. Jet grouting was rapidly Pressure (psi) 5300
accepted in Brasil because this technique was Rotation Rate (rpm) 18
better suited to grouting the silty and clayey Injectors
soils of coastal Brasil than conventional diameter (mm) 1.8
methods. Furthermore, the CCP method was ini- number 2
tially utilized in Brasil because of the rela- Lifting Speed (min/m) 4.2
tive simplicity of the rod system used to jet Grout
grout. injection rate (1/min) 63
water : cement ratio 1 to 1
cement consumption (kg/m) 200
The first CCP jet grouting job performed in Average Column Size (m) 0.'15
South America was in July 1980 for the Sao
Paulo water and sanitation department,
(SABESP), and involved the repair of a col- The soil along the 12 km Sanegran Tunnel was
lapsed tunnel crown for the Sanegran Intercep- variable and susceptible to future collapses.
tor Tunnel. The stratigraphy at the site is Therefore, SABESP decided to performed addi-
depicted in Figure 2, and is essentially silty tional jet grouting work. During the two years
clay in the upper 10 meters, underlain by 4 of jet grouting for the Sanegran Tunnel, jet
meters of fine to medium sand with some clay, grouting was utilized at 10 problem sections:
and then 1. 5 meters of fractured gneiss, un- to repair a second tunnel collapse due to lose
derlain by sound gneiss. The water table was
silty 5.8 75 to 80 70
clay The jumbo grout field trials were conducted in
large pits (30 X 6 X 5 meters deep), excavated
sand 2.9 75 to 80 80 in the banks of the Tiete River in the vicin-
ity of the original CCP field trials. During
sand 5.8 85 to 90 120 phase I and II the same soil type was used,
and was typically silty clay, with about 20
to 30% fine sand. The top 1. 5 meters of the
The data obtained during the CCP field trials fill was medium to stiff in consistency and
supports the following observations: was soft below 1.5 m to the bottom of the pit.
The sand used during phase III tests was a
1). Doubling the jet impact time from 14 to 26 fine uniform sand which was placed moist and
seconds does not have a significant influence in a loose state.
upon the size of any CCP column formed. Doubl-
ing the jetting time resulted in 15% to 25%
increase in the diameter of CCP columns. It All jumbo grout columns were formed using a
appears that most of the cutting action of the nozzle pressure of 3000 psi and a single 3. 0
water-cement jet is expended during the first mm injector, as listed in Table IV. The double
two revolutions of the drill pipe. drill rods were rotated at about 18 rpm's, and
the air cone was delivered at 4 m3/min at 100
2). The compressive strength for all soils was psi. The 1: 1 water: cement grout was injected
significantly increased by doubling the jet at about 70 1/min.
impact time, allowing double the weight of
cement to be injected per meter of column. The
increase in strength was double for the organ- Twenty-two jumbo columns were formed during
ic clay and about a 50% increase for the phase I. The only variable changed was the
silty clay and sand. lifting speed, and as indicated in Table IV,
the speeds varied between 1.6 and 3 min./m.
3). The soil type played a significant role in The fastest lifting speed was selected to
determining the size of CCP column formed, insure that at least one full revolution of
and could account for up to 50% of the differ- the drill pipe occurred before moving the jet
ence in the sizes of columns. As the amount of to a higher elevation. Excavation of all 22
clay in the soil increases the columns de- columns revealed nonhomogeneous, poorly ce-
crease in size. As shown in Table III, the mented cylindrical bodies, with measured dia-
smallest columns when formed in the organic meters between 1.8 and 2.0 meters.
clay (0.55 to 0.60 m.), intermediate sized in
silty clay ( 0.65 to 70 m.), and largest in
sand (0.85 to 0.90 m.). The solution to the nonhomogeneity of the
soilcrete body was to either use more than one
4). Finally, soilcrete made by mixing 1 to 1 jet, or jet longer. It was decided to investi-
water:cement grout with sand results in com- gate how extremely long jetting times, using
pressive strengths ( 80 kg/cm2 i about four one injector, influence the size and strength
times greater than comparable grout mixes in of jumbo columns. Therefore, during phase II 6
clay, with the lowest clay strength being columns were formed using two very long lift-
about 20 kg/cm2. ing times, 12 and 18 min/m.
JUMBO GROUT FIELD TRIALS The results from the phase II studies showed
that no significant size increase resulted in
The diversity of applications of jet grouting jetting 4 to 6 times longer at a particular
produced a need for larger diameter columns elevation; phase II columns were still about
than those produced using the CCP process. the same size as the phase I columns. How-
When constructing a continuous wall a large ever, the phase II soilcrete bodies were much
part of the cost is associated with drilling stronger and more homogeneous than phase I.
Grout
injection rate (1/min) 120
water : cement ratio 1 to 1
Compressed Air
pressure (~si) 100
injection rate (m /min) 4
:
HI SNtp,
sun O•x
$QME " &y
_LIII!;OOII!$fWftliJIIMfWS!ii6N!IN!1-----
1114,10-
excavation. For approximately one week the
wall was standing free for a height of 5 me-
ters. Furthermore, excavation of the interior Figure 4 General Plan and Profile of General
soil from the channel revealed a tight, water- Motors Stamping Mill Pit
proof barrier formed by the jumbo grout col-
umns in the wall and plug of the channel. The
channel was then lined with a 15 em. thick, A major concern expressed by GM engineers was
lightly reinforced concrete covering for ero- related to the effect which the high jetting
sion protection. The project finished one pressures would have upon the foundation of an
month ahead of schedule. existing building, which was only two meters
away from the jumbo columns used to support
the surcharge along the north side of the pit,
GENERAL MOTORS STAMPING MILL PIT: upper portion of wall shown in Figure 4a. If
sufficient grout flow was not communicated to
General Motor of Brasil wanted to expand their the surface, then there existed the possibil-
manufacturing capabilities by building ten new ity of building-up very high pore pressures in
auto body stamping mills. The mills were to be the sub-soil. The pore pressure build-up could
placed at the bottom of a long, narrow pit (68 cause distress to the foundation of the adja-
X 9. 7 X 6. 5 meters deep) . GM also required cent building. Therefore, during this project
that the steel plate stock for the stamped all the jumbo columns used to support the
parts be stockpiled along side the pit, which surcharge along the north side of the excava-
would induce a surcharge loading of about 20 tion were pre-jetted with a special bit so
tons;m 2 . The lateral force induced by the that a 10 inch diameter hole would be created,
surcharge would be about twice that imposed by which would assure pressure relief in the
the soil forces. The soil profile at the site borehole. Furthermore, all surcharge support
is shown in Figure 4c, and consisted of fill columns were jetted using relatively low pres-
in the top 2.5 meters, underlain by alternat- sures ( 3500 psi) , and rapid 1 ifting speeds
ing layers of silty clay and sand, with the ( 2. 2 min/m) . Due to the silty nature of the
water table about 2 meters below the bottom of subsoils at the site and need to create large
the jet grout columns. A diaphragm wall with ( 1. 6 meters), strong, soil crete columns pre-
tie backs was rejected as a solution primarily jetting only water was used to form all col-
because the tie backs would have to infringe umns at the GM pit, as listed in Table VII.
upon land which GM wanted to conserve for
future expansion. Therefore, a single row of
unreinforced and unbraced jumbo grout columns There were three different sets of jetting
was used as the earth retention system. How- parameters used to construct the jumbo grout
ever, toe support of the wall was supplied by columns in the GM pit. The single row of wall
Pressure (psi)
wall 5200
toe struts 4000
surcharge support 3500
Rotation Rate 18
Injector Figure 5 Photograph Showing General View of
diameter (mm) 3.4 Excavation For General Motors Pit
number 1
1044
Second International Conference on Case Histories in Geotechnical Engineering
Missouri University of Science and Technology
http://ICCHGE1984-2013.mst.edu
Jet grouting work commenced in November 1986,
utilizing a single Haliburton T10 pump and a
Novatecna rotator-extractor drill rig. A large
single injector (3.8 mm diameter) was used to
.
a
create the jumbo grout columns. This is about
the largest injector that can be used with a
T10 pump and still deliver 140 1/min of grout
at 4000 psi, which were the highest flow rates
and pressures utilized during the formation of
the diaphragm wall for pit P-3921, as listed
in Table VIII. Pit P-3921 had the longest free
cantilevered length of unreinforced wall (6.1
meters), and therefore, required the greatest
compressive and tensile strength. It was de-
cided to inject a relatively large volume of
cement ( 800 kg/meter of column) by injecting
grout at 140 1/min and lifting the jet grout-
ing monitor slowly (7.4 min/meter).
Pressure (psi)
Pit P-3915 3500
Pit P-3921 4000
Bottom Plugs 3500
Rotation Rate 18
Injector
diameter (mm) 3.8
number 1
Grout
injection rate {1/min)
P-3915 130
P-3921 & Bottom Plug 140
1046
Second International Conference on Case Histories in Geotechnical Engineering
Missouri University of Science and Technology
http://ICCHGE1984-2013.mst.edu