Professional Documents
Culture Documents
Cracks
Contraction joints can limit cracking induced by moisture or temperature change
Vn = Avf fy µ
where Avf and fy are the area and yield strength, respec-
tively, of reinforcing bars assigned to carry shear across
the interface and µ is the coefficient of friction for the
surface. For a deliberately roughened surface with a
roughness amplitude of about 1/4 in. (6 mm), µ is 1.0 or
0.75 for normalweight concrete or all lightweight concrete,
respectively. With this roughness of 1/4 in. (6 mm) and a
µ of 1.0, the joint complies with the shear strength
assumed in design. No more steel is needed than for a
Fig. 1: A contraction joint for an elevated slab. Strips of extruded typical section away from the joint.
polystyrene foam can be used to form a straight joint at the soffit The width of the crack, however, has an effect on this
of a slab. This layer and the wire mesh are then held down by
continuous strips of plywood located above the reinforcing bars µ value. The shorter the distance between contraction
nailed through the foam to the slab formwork. Here, the wire joints, the narrower the crack and the better the shear
mesh is supported at the top by a continuous bar wired to strength. This leads to the need for designers to detail
triangular braces. Before placement, electrical conduit is routed
through the wire mesh contraction joints at appropriate distances. Because
flexural and shear strengths are met with these condi-
tions, however, contraction joints can be located in any
place of the structure.
Walls
According to ACI 224.3R-95,1 contraction joints in walls
should be at a spacing of no more than 25 ft (7.6 m). In
Chile, we use 16 ft (5 m) spacing. It’s advisable to keep all
the reinforcement through the joint. Even though the
stresses will be transmitted through the joint by the
reinforcing bars, the cracks between joints will be thinner
and less visible. The wall will also be more durable.
Elevated slabs
For construction efficiency, the best location for joints
in suspended slabs is at the edge of beams or walls (Fig. 3).
This position of the joint eliminates the need for shores that
Fig. 2: After the concrete at the joint has reached initial set, the
braces, upper support bar, and plywood strips are removed. would be required for an overhanging slab created with a
Generally, the mesh can be abandoned in the concrete. Before joint located at the third point of a slab. It also eliminates
the next section of the slab is placed, the joint surface is painted the need to keep shores in the adjacent span and eases form
with a form release agent to minimize bond and prevent transfer
of tension across the joint as the concrete shrinks movement. It should be noted, however, that ACI 301-103
requires construction joints to be located in the middle
third of a slab span unless permitted otherwise. If construc-
Construction documents tion joints are to be located at the edge of a beam or wall,
General design requirements the engineer would need to explicitly permit joints to be at
Construction joints can be detailed to transfer moment the edge of a slab, and the contractor would need to
and shear. According to ACI 224.3R-95,1 flexural continuity provide proposed joint locations for acceptance.
is achieved by continuing the reinforcement through the The positioning of the joints (cracks) at a predeter-
joint with sufficient embedment length past the joint to mined location allows the cracks to be hidden from sight.
ensure an adequate splice length for the reinforcement. For example, a crack on the edge of the slab can be
By providing continuous reinforcing bars and ensuring covered with a cornice. In walls and slabs, the cracks can
adequate surface roughness at each joint, designers can be located at the edges, in recesses, or under partitions.
Mass concrete
According to ACI 224.3R-95,1 contraction joints in
reinforced mass concrete structures should be spaced at
40 to 60 ft (12 to 18 m). The construction should be in
blocks with no bonding between them, so it’s advisable
to keep the reinforcement going through the joint (Fig. 4
and 5) when continuous reinforcement is indicated by
design requirements. The positioning of the joint should
be in locations where the cracks are less damaging to the
structural performance of the element.
Massive concrete structures such as concrete gravity
dams and massive walls are generally designed so that
Concluding remarks
The detailing of contraction joints—placing joints in
known places—can be an important improvement for:
■■ Design, as the engineer can place cracks where they
have minimal effect on structural performance;
■■ Construction of elevated floors, as productivity can be
Juan Pablo Covarrubias, FACI, is President
improved; and
of Litoral Ingenieria Ltda., Santiago, Chile.
■■ Construction of mass concrete, as large placements
He received his MSc in 1977 and his PhD in
can be avoided.
1987 from the University of Birmingham,
England. He is a member of ACI Committees
References 325, Concrete Pavements; C610, Field
1. ACI Committee 224, “Joints in Concrete Construction,
Technician Certification; and C630,
(ACI 224.3R-95),” American Concrete Institute, Farmington Hills, MI,
Construction Inspector Certification.
1995, 41 pp.