Project : United Olefins Complex
1.1 Saudi Binladin Project
PROCEDURE FOR
ALIGNMENT OF PIPERACK
FOUNDATIONS
JUPC-456495096.doc / Page 1 of 3
General Construction Offsites
& OSBL
Project : United Olefins Complex
1.1 Saudi Binladin Project
1 PURPOSE
The purpose of this procedure is to outline the method of alignment of piperack
foundations.
2 SCOPE OF WORK
This method statement covers the method of alignment for the piperack
foundations at east west piperack corridor.
3 REFERENCES
Specifications, Standards, Quality Control Procedures and Test Plans.
5 WORK PROCEDURE
1.1 Procedure
JUPC-456495096.doc / Page 2 of 3
General Construction Offsites
& OSBL
Project : United Olefins Complex
1.1 Saudi Binladin Project
Pump the hydraulic jack slowly to push the footings until it touches the
wooden corner stoppers. Check if the face of the foundation is parallel to
the stopper and touches the stopper.
Carry out survey to check the final alignment.
United shall witness the survey to check proper alignment.
4.0 SAFETY
Execution of all the works shall meet with the relevant codes and practice
for Site Health and Safety as detailed in the approved safety plan.
JUPC-456495096.doc / Page 3 of 3