Total Avtaar Singh
Sr.
No
ITEM NAME & SPECIFICATIONS ( Approx) Unit Govt Contract
RATE Amount
M.S. Wire For 8'*4'*3' ( 27 kg) for 24
crates
(2.4m*1.2m*0.91m )
2 648 kg 56.64 36702.72
27*24 crate= 648 kg
For 24 Crates = 62.89 cu m
Weaving Charges per Crate
3 24 Nos 608 14592
( For 24 Crates)
Transportation Charges for
4 Carrying 24 Crates 24 Nos 292 7008
( 2.4m*1.2m*0.91m)
Labour per Crate for Filling
Boulders in 24 crates
5 24 Nos 1150 27600
Total Amount 166,543
CGST9% 14,988.84
SGST 9% 14,988.84
Total Amount 196,520.41
Indent By : Not Provided
Indent Date : ****
COMMERCIAL COMPARATIVE STATEMENT
Macafferi Environment Solution
Avtaar Singh ( Through Punjab Distributor )
Govt Contractor
Qty Unit
Rate /Cu.m
Total of For Gabion Boulder ( 12 Kg to 70 Kg)
2304 Sq feet
(2+3) Box Considered
Fabrication
Galvanised Zinc Coated Gabion
wall
3m*1m*1m/2.7 mm Galvanised
Zinc Coated
Total Cu m = 3*1*1*19= 57 cu m
815 Rs /Cubic
57 Cu.m
metre cost 1 cubic metre= 10 Kg thus 1 crate of
51294.72 3*1*1 = approx 27 to 30 kg
Thus total weight of all 19 crates =
570 Kg
Mesh Type : 10*12
Transportation of 19 Crates
19 Nos
(3m*1m*1m)
Considered( Labour Charge) for
57 CU.M
filling Boulders in 19 crates
Total Amount
Indent By : Not Provided
Indent Date : ****
ment Solution
Distributor )
RATE Amount
35 80,640.00
826 47,082.00
5,000
600 34200
166,922
15,023
15,023
Total Amount 196,968