Section MUNYATI POWER STATION Effective Date 01/01/2019
Subject STATION OBJECTIVES Page No. Page 1 of 1
INTEGRATED MANAGEMENT SYSTEMS
STATION OBJECTIVES JANUARY-DECEMBER 2019 ZPC Munyati Power Station strives to generate electricity using world class standards for Safety, Health, Environment and Quality management. Munyati Power Station will achieve this through optimal utilisation of resources, application of continual improvement, employee empowerment and participation and management commitment. In pursuance of this goal we are committed:
1. To achieve a Lost Time Injury Frequency Rate of not more
than 2 by 31 December 2019. 2. To generate power in an environmentally sustainable manner and meet monthly sent out targets, and an annual target of 142.35GWH sent out by 31 December 2019. 3. To increase and maintain plant availability from the current 45% to 65% by 31 December 2019. 4. To reduce cost of generation from 30cents/KWh to 18cents/KWh by 31 December 2019. 5. To improve staff satisfaction index from 3.4 to 3.7 by 31 December 2019.
Originated by: Reviewed by : Approved by:
RISK AND QUALITY OFFICER SECTION ENGINEER MAINTENANCE POWER PLANT MANAGER