You are on page 1of 3

Rev.

- Date: 03 April 2019


PROJECT: RCCPL MUKUTBAN
1X11.25 MW STG SET
IN 004516

PERFORMANCE GUARANTEES

A. Guarantees subject to Liquidated Damages:

Power Output 11.25 MW

Auxiliary Power Consumption 45 KW

Notes:
 Siemens HMBDs’02 Load point – Page 1 of 2, Dated 29.03.2019 has to be
considered as Performance Guarantee HMBD Load-Point.
 Guaranteed auxiliary power consumption shall include Power consumed by all
continuously running AC motor only. The equipment considered are as follows;
a) Oil Vapour Extraction Fan
b) GSC Exhaust Fan
c) Main Oil Pump

B. Conditions for Performance Guarantee:

1) The guaranteed values will be applicable for new equipment at steady state operating
conditions, deposit-free blading and clean surfaces of the cooling equipment. Steam
quality requirement which mentioned by Siemens needs to be demonstrated by
Purchaser on continuous basis for achieving the above performance of TG set.

2) The Performance Guarantees are only valid if the delivered equipment is permanently
operated according to Siemens instructions for installation, commissioning, operation
and maintenance and if the requirements indicated in “Design/Guarantee conditions”.

3) The turbo-set performance shall be verified in accordance with DIN1943. Test


instruments to be used for the verification of the Performance guarantees shall be plant
operating instruments. The mass flow devices are to be provided by the party
responsible for BOP scope / Purchaser has to meet the requirements of ISO 5167 Part
1 to 4(Whichever is applicable). Calibration protocols shall be provided to all concerned
parties prior to the test. The calculation for verification of the performance will be done
according to DIN1943 and its supplement VDI 2042.

4) Performance guarantees are based on new and clean conditions. The performance test
of the STG shall be conducted within 2 months from first admission of steam to turbine.
If PG Test doesn’t occur within 2 months from first admission of steam to turbine, then
tolerance for ageing as per IEC953-2 shall be considered during performance
guarantee evaluation.

Siemens Limited Page


1 of 3
Performance Guarantee.doc

All copyrights, titles and patents shall remain vested in Siemens AG. We therefore reserve all rights and titles in this document and in the information contained therein.
This document or parts of it may not be reproduced in any form or by any means whether electronically, mechanical or by photocopying, recording or otherwise and may
not be modified, shown or distributed to third parties without prior written permission of Siemens AG.
Rev.- Date: 03 April 2019
PROJECT: RCCPL MUKUTBAN
1X11.25 MW STG SET
IN 004516

5) In case the PG test is not carried out within 6 months after first admission of steam to
turbine, PG test shall be deemed to be completed and the Unit taken over by
Purchaser.

6) Only those parameters in this chapter and its subchapters, which are explicitly
marked as ‘Guarantees subject to Liquidated Damages’ shall be considered as
binding. All other values in this offer and its attachments are classified as non-binding
design criteria and guidance values for information only.

7) Comparison measurement tests (Straight condensing mode- Bleed/ extraction off) will
be done to ensure turbine is free from deposits/ damages. Based on comparison
measurement results, further actions will be decided. In case deposits are found on
turbine flow-path, Purchaser has to ensure flow-path cleaning. In such cases,
performance guarantee will be considered as void however performance trials will be
taken to evaluate the performance of turbine without any contractual/commercial
liability.

8) Siemens scope of supply only contains the operation instrumentation and


measurements shown in the P&IDs. Calibrated and / or additional measuring
equipment for the Performance Test are only included, if they are explicitly mentioned
as part of Siemens scope of supply.
9) Fulfillment of above performance parameters are subjected to the achievement of all
boundary parameters by Purchaser as specified the guarantee load point parameter
table & the guarantee HBD submitted by Siemens. In case on non-achievement of any
parameter necessary correction curve will be considered during evaluation of PG test
values.

10) Performance guarantee test shall be carried out based on the test procedure prepared
by Siemens. All necessary correction curves required for PG test will be prepared by
Siemens. All performance curves will be used to evaluate the above performance
values.

11) The thermodynamic values are calculated according to the Steam table IAWPS IF97 /
IFC 67- Formulation for Industrial Use for the Thermodynamic Properties of Water and
Steam.

12) A test tolerance equal to test measurement uncertainty (due to the installation, test
conditions and instruments errors etc) will be applied to all performance test results
for the demonstration of meeting contractual guarantee requirements. Measurement
uncertainty shall be calculated using the procedures in IEC. The calculated
measuring uncertainty and the deterioration will be taken into account.

Siemens Limited Page


2 of 3
Performance Guarantee.doc

All copyrights, titles and patents shall remain vested in Siemens AG. We therefore reserve all rights and titles in this document and in the information contained therein.
This document or parts of it may not be reproduced in any form or by any means whether electronically, mechanical or by photocopying, recording or otherwise and may
not be modified, shown or distributed to third parties without prior written permission of Siemens AG.
Rev.- Date: 03 April 2019
PROJECT: RCCPL MUKUTBAN
1X11.25 MW STG SET
IN 004516

For performance acceptance, following formula shall be considered.

Pcorrected + tolerance > Pguarantee (Power Guarantee is fulfilled)

P guarantee: Guaranteed Power


P corrected: Corrected Power after applying correction & deterioration factor

13) If the measured value for Auxiliary Consumption is better than the contractually
defined value, an offset of same will be used to compensate STG power output and
vice-versa.

14) All the demonstration parameters which are not subject to liquidity damages will not be
a part of PG test procedure however all such parameters will be demonstrated
separately by Siemens commissioning team.

15) Purchaser has to maintain operational stability such that parameter fluctuations do not
cross DIN1943 limits. High parameter fluctuations results in high random uncertainty. In
case, the parameter deviation is beyond the range of correction curve, new set of
HMBD & Correction curve is recommended for evaluation.

16) In case of common headers for steam, feed water, process steam, return condensate
etc (whichever is applicable), customer has to ensure cycle isolation such that the plant
can be operated as per HMBD conditions on which guarantee values are agreed. In
case it is not possible, the test can be carried out but the overall measurement
uncertainty will increase.

17) The costs for the performance test shall be only included in the contract price, if it is
explicitly mentioned as part of the scope of supply. In case that the performance test
is carried out by a third party, Siemens shall be given the opportunity to check the
test instrument installation, calibration reports & witness the performance test. Such
witnessing personnel shall have full access to the delivered equipment and operating
records during the test activities. The test report shall be made fully available to
Siemens.

18) The legal consequences, if any of the guarantee values are not achieved, are solely
and conclusively defined in the commercial contract document.

Siemens Limited Page


3 of 3
Performance Guarantee.doc

All copyrights, titles and patents shall remain vested in Siemens AG. We therefore reserve all rights and titles in this document and in the information contained therein.
This document or parts of it may not be reproduced in any form or by any means whether electronically, mechanical or by photocopying, recording or otherwise and may
not be modified, shown or distributed to third parties without prior written permission of Siemens AG.