1. Drilling / Welding Fire& Explosion Ensure the all work under proper supervisions & all
workmen pre brief about job & hazards.
Flash Back Ensure that before start of work tank should be
electrically isolated.
Eye injury (U.V. Provide a fire blanket / fire screen & Trained Fire Watch
Rays) on site.
Make sure fire extinguishers (BC type or Black CO 2), hose
Electrical shock pipe & sand buckets are available on Site.
Gas Monitor correctly sited.
Fire Hazard Ensure that welding work should be performed by
certified/qualified welders only.
Ensure that welder is must in dry condition.
Ensure that proper earthing should be provided to all
Elec. equipment & all cables through 30mA MCB`s,
ELCB`S.
Electric connections should be taken by authorized
electrician only.
Ensure that electrical should be in dry condition & use of
PPE`s like Electric shock proof gloves (IS 4770) & safety
shoes.
Only cotton cloth will be allowed to the hot work.
Ensure that rod holder, cables should be in good
Page 1 of 4
condition.
Proper flame proof JBs for extension & connector for
joints with cable hoods should be use.
If cables are crossing the road then ensure proper
protection.
All workmen should be use proper PPE for welding like
asbestos jackets, leather Gloves, goggles/welding mask,
welding shield.
Make sure spark containment is used such as separate
containers use for hot tabs end Pieces of welding rods.
First Aid box should be maintained with proper
medicines.
Do not cut near electrical fittings or lines.
All instructions on Hot Work Permit must be followed.
Ensure Work to be done under close supervision and
stand by electrician.
Ensure sufficient illumination during night work.
2. Civil works and Surface over All excavation work should be planned and method of
Excavation burdens excavation and type of support should be decided
Damage considering the following:
underground o The stability of the ground
utilities o The excavation will not affect adjoining buildings /
Damage above pipelines & other restricted areas
ground utilities o Gas, water, electrical and other public utilities should
Improper be shut-off or disconnected, if necessary.
access / egress o Presence of underground pipes, cable conductors, etc
Traffic movement
near excavation Sites of excavation should be thoroughly inspected :
Exposure to o Daily prior to each shift and after
falling loads interruption in work of more than one day.
Mobile o After an unexpected fall of ground.
equipment o After a heavy rain
Hazardous Excavated earth should not be placed within one meter
atmosphere of the edge of the treanch or depth of trench whichever
Water is greater.
accumulation Don’t allow vehicles to operate too close to excavated
Adjacent area.
structures No load, plant or equipment should be placed or moved
Loose rock or soil near the edge of any excavation
Fall inside Adequately anchored stop blocks and barriers should be
excavation provided to prevent vehicles being driven into the
excavation.